The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
26. The Deputy Commissioner has also submitted the list of land owners who have been affected by the construction of the Imphal – Ukhrul road in response to the direction given by this Court on 28.11.91. The list shows that there are 22 persons whose paddy fields have been affected by the construction of the said road. It is also admitted by the respondent No. 2 in the affidavit that the construction of the road has had “ indirect effects Admittedly land has been taken away from the owner and fields have been damaged as a result of construction of the ImphalUkhrul road, but till today no steps have been taken for payment of compensation to the land owners.” [7] This order was challenged before the Supreme Court by the State, and it was disposed of by the Supreme Court on 06.12.1994. While setting aside Para 25 & 26 of the High Court’s order above, the Supreme Court confirmed that the compensation should be given to all the persons concerned including the 22 persons whose paddy fields were affected in the course of acquisition and laying of the road. Thereby, an equitable order was passed. After that, the very same petitioner filed MC (C.R.) No. 325 of 1997 (Ref:- C.R. No. 1 of 1991) which was disposed of on 10.07.2007, directing the respondents to pay the compensation expeditiously. [8] Now, the petitioner pleads for the above stated relief, without specifying under what head he is…
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Item No. 30
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
WP(C) No. 719 of 2015
Hundung victim development, through its Convenor, Mr. David
Mahung, aged about 79 yrs, resident of Hundung Village,
Ukhrul District, Manipur.
……. Petitioner
- Versus1. Union of India, represented by Secretary Ministry of Home
Affairs, North Block, New Delhi – 110 001.
2. The Secretary, Ministry of Defence, New Delhi – 110 001
3. The Commander, 25-BRTF, C/o 99 APO.
4. The Officer, Commanding 84 RCC (GREF), C/O 99 APO
5. The State of Manipur through the Chief Secretary, Imphal,
Manipur.
6. The Collector/Deputy Commissioner, Ukhrul District,
Manipur.
...... Respondents
BEFORE
HON’BLE THE CHIEF JUSTICE MR. RAMALINGAM SUDHAKAR
For the petitioner
::
Mr. Mark Khapai, Advocate.
For the respondents
::
Date of Order
::
Mr. S. Samerjeet, CGC
Mr. Shyam Sharma, G.A.
18.09.2018.
ORDER
[1]
Heard Mr. Mark Khapai, learned counsel appearing for the
rpetitioner; Mr. S. Samarjeet, learned CGC for the Union respondents; and
Mr. Shyam Sharma, learned Government Advocate for the State
respondents.
[2]
This Writ Petition is filed by one David Muhung, who is the
Convenor of Hundung Victim Development, of Hundung Village, Ukhrul
District, Manipur.
[3]
Notice was issued on 11.9.2015 and thereafter, the case was
admitted on 27.03.2017. A counter affidavit was filed by respondent No. 6
on 17.12.2015; and respondents No. 1, 2, 3 & 4 filed their affidavit-inopposition on 04.02.2016; and another affidavit-in-opposition was filed by
respondent No. 2, 3 & 4 on 04.08.2016; thereafter, two rejoinder affidavits
were filed by the petitioner on 20.03.2017 to the counter affidavit filed by
the respondent No. 6, and affidavit-in-opposition filed by respondent No. 1,
2, 3 & 4. On 04.09.2017, respondents No. 2, 3 & 4 filed a reply to the
rejoinder filed by the petitioner.
The brief facts of this case are as follows:-
[4]
In Ukhrul hill District, a Mini Cement Factory was to be
established, and certain extent of land was required. This project resulted
in causing damage to properties of Hundung Village. In some cases, their
agricultural land is affected and in some cases, the land which was
adjacent to the road, was damaged, and the accusation resulted in difficulty
to the village people forcing them to file the petition being Civil Rule No.
1331 of 1990/1/91 before the Gauhati High Court, Imphal Bench and Vide
Order dated 02.02.1993, a direction was issued to the competent authority
to pass an order in respect of the land accusation. Consequently, the
District Collector (Land Accusation), Ukhrul, passed an order on 30.03.1993
and made award in respect of:
”1. (A) LAND VALUE
1. (B) APPROACH ROAD TO CEMENT FACTORY: HUNDUNG
1. (C) 2 MT MAGAZINE FOR MINI CEMENT PLANT.
1. (D) LIME STONE QUARRY FOR CEMENT FACTORY.
2. CONSTRUCTION OF IMPHAL - UKHRUL ROAD (GREF ROAD).
(A) Construction of Imphal Ukhrul Road via Hundung was
started in the year 1981 and Commissioned in 1984. Assessment of
land was carried out in connection with the above referred Civil
Rule to ascertained the land owners and the areas affected by this
road construction. An area of 151.85 acres belonging to 76 land
owners were affected. No land acquisition proceeding was initiated
for payment of compensation to the land owners on the ground
that the land on which the road was constructed falls under Govt.
of Khas land. This was found unacceptable to the High Court since
the ownership of land in the Hill villages of Manipur vested in the
villagers and the provisions of land Acquisition should be followed
in acquiring land for public purposes.
In regard to the determination of the market value of the
affected by the Imphal-Ukhrul Roads I have gone through sale
deeds of relevant area and time. Taking all factors in to account for
determining the Market Value, the Compensation is fixed Rs.
25,000/. ( Rupees twenty five thousand ) only per acre plus, 30%
solatium with interest 15% as indicated in detail on ANNEXUREC/1
Further, compensation for damage caused by the
Construction of Imphal-Ukhrul Road in respect of 22 (twenty two)
paddy land owners is also awarded as per assessment made by the
concerned Department as shown in detail at ANNEXURE C/2. As
per direction given by High Court.”
[5]
Out of the award, the issues raised are namely, compensation
for construction of the road and damage caused to 22 (twenty two) paddy
land owners. It is Annexure-C/2 to the award. In respect of Annexure –
A/1, A/2 and Annexure-B, there is no dispute; Annexure-C/1 relates to land
affected due to construction of Imphal-Ukhrul road, and the total number of
persons entitled to compensation is 76. Annexure–C/2 relates to
assessment for loss to paddy field due to construction of Imphal-Ukhrul
road and it relates to 22 persons.
[6]
A Division Bench of this Court passed an order prior to the
award and the relevant Para No. 25 & 26 read as follows:-
“25. We are here concerned with Hill areas of Ukhrul subdivision (now district) which are inhabited by the Tangkhul Nagas who
belong to the Scheduled Tribes of Manipur. In AIR 1961, Manipur 31,
Luitang Khullakpa and others Vs. Deputy Commissioner of Manipur and
others, the learned Judicial Commissioner held that there is no
Government Khas land in the hill areas of Ukhrul. The ownership of land
situated in hill villages at, Manipur vests in the villagers. They do not hold
the land under the pleasure of the Government. It was held that if land is
to be acquired for public purpose form the villagers of hill village, provision
of Acquisition Act must be followed. We have gone through the above
judgment and we are of the view that the findings of the learned Judicial
Commissioners are correct and the decision rendered in this case still holds
the field and we entirely in agreement with the findings in the aforesaid
case. In view of what has been discussed above, we do not accept the
submission of the learned Govt. Advocate in this regard.
26. The Deputy Commissioner has also submitted the list of land
owners who have been affected by the construction of the Imphal –
Ukhrul road in response to the direction given by this Court on 28.11.91.
The list shows that there are 22 persons whose paddy fields have been
affected by the construction of the said road. It is also admitted by the
respondent No. 2 in the affidavit that the construction of the road has had
“ indirect effects Admittedly land has been taken away from the owner
and fields have been damaged as a result of construction of the ImphalUkhrul road, but till today no steps have been taken for payment of
compensation to the land owners.”
[7]
This order was challenged before the Supreme Court by the
State, and it was disposed of by the Supreme Court on 06.12.1994. While
setting aside Para 25 & 26 of the High Court’s order above, the Supreme
Court confirmed that the compensation should be given to all the persons
concerned including the 22 persons whose paddy fields were affected in the
course of acquisition and laying of the road. Thereby, an equitable order
was passed. After that, the very same petitioner filed MC (C.R.) No. 325 of
1997 (Ref:- C.R. No. 1 of 1991) which was disposed of on 10.07.2007,
directing the respondents to pay the compensation expeditiously.
[8]
Now, the petitioner pleads for the above stated relief, without
specifying under what head he is claiming the sum of Rs. 94,35,449/(Rupees Ninety Four Lakhs Thirty Five Thousand Four Hundred
and Forty Nine) probably it relates to Annexure–C/1. An objection is
raised by respondent No. 6 stating that the calculation itself is wrong
because according to them, the total amount as per
Annexure-C/1 is
86,36,449/- (Rupees Eighty Six Lakhs Thirty Six Thousand Four
Hundred and Forty Nine). If that is the case, then the claim of 22
(twenty two) persons as per Annexure – C/2 for loss of paddy fields has no
relevance in the present case.
[9]
If the 76 persons listed as per Annexure–C/1 have not been
granted the compensation, they could have very well approached the
authority on the basis of the order dated 10.07.2007 passed in MC (C.R.)
No. 325 of 1997 (Ref:- C.R. No. 1 of 1991). There is no communication
from the petitioner for the last 8 (eight) years as to what steps they have
taken if they claim that the amount has not been paid.
[10]
On the contrary, respondent No. 6 and respondent No. 1- 4
are not clear whether they have discharged their liability and that the
compensation amount has been paid to the 76 persons. On one hand, the
petitioners are vague and bereft of details. They have been going slow even
after Court’s order. The department also appears to be in slumber. The
reply affidavit is as vague as vague can be.
[11]
The right of a person to just compensation is a well
established principle. The State cannot acquire the land and fail to pay
compensation as determined in the award proceedings. The poor people of
hill areas cannot be expected to know the legal rights and act. From the
pleadings and documents, it is evident that the petitioners have been
approaching the authorities and have also obtained judicial orders in their
favour.
[12]
In this circumstance, the Court has no other option except to
direct respondent No. 6 to discharge all the pending claims of all persons in
relation to compensation in terms of the award dated 30.03.1993, if it has
not been discharged so far. If the authority has not paid the award amount,
it is his duty to issue notice to each one of them and pay the compensation
as per the award.
[13]
The compensation amount due to a person should not be
retained by the Government under any circumstance. This Court if forced to
pass such an order because the reply affidavit filed by the aforesaid
respondent is thoroughly vague and without application of mind. The Senior
Officer of the department is directed to call for explanation to each one of
the deponent of the affidavit as to why, they did not respond to the Court’s
direction properly.
[14]
As a result, the Writ Petition stands disposed of with the
direction to respondent No. 6, Collector/Deputy Commissioner, Ukhrul
District, Manipur, to verify the award dated 30.03.1993 (Annexure–A/2) and
the Annexures therein and settle all the pending amounts to the respective
parties if not already settled on or before 30.11.2018, along with the
necessary interest and solatium as applicable to each one of the persons
whose name finds place in the award.
Writ Petition stands disposed of accordingly.
CHIEF JUSTICE
FR/NFR
L.Gangte
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review