HIGH COURT OF TRIPURA
AGARTALA
RSA No.01 of 2015
1. Shri Goutam Saha,
son of late Rajmohan Saha
2. Smt. Nilima Saha,
wife of Shri Goutam Saha
- both are the residents of Durgabari Road,
P.O. Agartala, P.S. West Agartala,
District: West Tripura
----Appellant(s)
Versus
Shri Haradhan Saha,
son of late Rajmohan Saha,
resident of Durgabari Road, P.O. Agartala,
P.S. West Agartala, District: West Tripura
---- Respondent(s)
For Appellant(s)
:
Mr. S. Deb, Sr. Adv.
Mr. S.M. Chakraborty, Sr. Adv.
Ms. B. Chakraborty, Adv.
For Respondent(s)
:
Mr. K. N. Bhattacharjee, Sr. Adv.
Mr. Soumendu Roy, Adv.
Mr. Kohinoor N. Bhattacharjee,
Adv.
Date of Hearing
:
23.04.2018
Date of delivery of
Judgment and Order :
29.06.2018
Whether fit for
Reporting
YES
:
HON‟BLE MR. JUSTICE S. TALAPATRA
Judgment & Order
This is an appeal under Section 100 of the CPC from
the judgment dated 22.09.2014 delivered in Title Appeal
No.23 of 2013 by the Additional District Judge, West Tripura,
Agartala, Court No.5 on affirmance of the judgment dated
04.02.2013 delivered in Title Suit No.113 of 2010 by the Civil
Judge, Senior Division, West Tripura, Agartala.
02.
The plaintiff-respondent herein instituted the suit
being Title Suit No.113/2010 for declaration, recovery of
possession and perpetual injunction. It is the case of the
plaintiff that he was the owner of the land as described in the
Schedule-1 of the plaint. Out of the said land he had sold the
land with the building as described in the Schedule-2A to
Purnima
Chowdhury,
Suchitra
Chowdhury
and
Sikha
Chowdhury by the registered deed of sale dated 11.05.1992
and the land with building as described in the Schedule 2B to
Shikha Saha (Roychoudhury) by the registered deed of sale
dated 12.05.1992. Purnima Choudhury and two others as
stated sold the entire land with building as described in the
Schedule-2A of the plaint to the defendant No.1, Gautam
Saha by the registered deed of sale by 18.05.1992 and
Shikha Saha (Roychoudhury) sold her land with building
under Schedule-2B to Nilima Saha, the defendant No.2 by
the registered deed of sale dated 18.05.1992. After such
purchase the defendants namely Gautam Saha and Nilima
Saha mutated their names in the record of right in respect of
the
land
as
described
in
the
Schedule
2A
and
2B
respectively. The total area purchased by the defendants,
the appellants herein is 79x35 sq.ft. which has been
described in the Schedule-2.
03.
It is to be noted that the Schedule-2 land is
situate in the northern part of the land as described in the
Schedule-1. After the said sale the remaining part forming
the southern part of the land as described in the Schedule-1
and separately described in the Schedule-3 remained with
the plaintiff. The plaintiff has got the valid title and he is in
the possession of the land recorded under Khatian No.30113.
The land described in the Schedule-3A, 3B and the land with
the part of the room described as the Schedule-3C are the
suit land. The Schedule-3A land has been curved out for
purpose of passage with the limited right from the land
described in the Schedule-2A and 2B and for purpose of
turning of their vehicle keeping the title intact with the
plaintiff. The owner and the occupier of the land comprised in
the Schedule-2A and 2B have been permitted to use that
space along with the plaintiff. They were also allowed to
remove the steps from the piece of land adjacent south of
the building sold to Purnima Choudhury and others. But they
did not remove the steps even though they have been using
the space as a common path with the plaintiff. Purnima
Choudhury and others as stated had sold the land and
building as described in the Schedule-2A and Schedule 2B to
the defendants-appellants. The plaintiff raised objection that
the right to use the said space as described in the Schedule
3A at the time of the subsequent sale by Purnima Choudhury
and others is not transferred to the defendants.
04.
The defendant-appellant No.1 is the full blood
brother of the respondent whereas the defendant-appellant
No.2 is the wife of the defendant-appellant No.1. Because of
the relation the plaintiff-respondent did not obstruct or
object to the use of the space as described in the Schedule3A by the defendant-appellant for purpose of their passage.
According to the plaintiff-respondent, taking advantage of
this relation the defendant-appellants are not only using the
land described Schedule-3A but also encroaching the land of
Schedule-3B occasionally by passing and turning their
vehicle and sometimes even they park their vehicle in the
space as described in the Schedule-3A. Thus, they create
obstruction in using this passage by the plaintiff. According
to the plaintiff, the defendant-appellants do not have any
right or title to enjoy the land described in the Schedule-3A
in any manner. Whenever the plaintiff raised objection the
defendant-appellants assured him that they would not repeat
such acts in future. When the plaintiff-respondents took
preparation to raise a wall along the north boundary of his
land as described in Schedule-3B sometime in the first week
of April, 2010, the defendant-appellants objected without
having any legal right. Even the defendant-appellants do not
have any right to create disturbance in the possession of the
plaintiff over the land as described in Schedule-3B. The
defendant-appellants even do not have any right to cause
any disturbance or create obstruction in the passage as
described in the Schedule-3A as the title of the said land
remains with the plaintiff-respondent. But the defendantappellants repeated such breach by throwing the assurance
in the wind and hence the suit has been instituted. So far the
steps as constructed earlier in the land which is described in
the Schedule-3A is concerned part of those steps were
removed by the defendant-appellants. But from the western
side the steps had not been removed. On the contrary,
without taking any permission from the plaintiff-respondent
the
defendant-appellants
started
constructing
a
room
covering a part of the land as described in the Schedule-3A
which has been separately shown as the Schedule-3C.
05.
The defendants requested the plaintiff-respondent
allow them to raise a temporary construction removing the
eastern part of the steps for the purpose of Durga Puja in the
year 2005. Since the appellant No.1 is the full blood brother
of the plaintiff-respondent, a temporary construction on their
promise of removing the same after the puja was allowed.
But after puja, the defendant-appellants did not remove the
construction from the land as described in the Schedule-3C
by ignoring the demands made by the plaintiff-respondent. It
has been asserted in the plaint as follows:
“This way the time passed and the defendants kept the
plaintiff under assurance to remove the part of the
room in schedule 3C but they did not any have not kept
their promise. So in the 1st week of April 2010 the
plaintiff again asked the defendants to remove the part
of the room on schedule 3C but this time the
defendants told him clearly that they would not do so.
The plaintiff has become entitled to seek recovery of
possession of the land of schedule 3C removing the
part of the room constructed upon the land of schedule
3C and in case the defendants do not remove the same
within such time as may be allowed by the Court, the
plaintiff may be allowed to remove the same at the cost
of the defendants.”
06.
In the first week of May, 2010 the plaintiff-
respondent mobilised materials such as bricks for purpose of
constructing wall on the boundary of the land as described in
the Schedule 3B. When on 05.08.2010, the workers of the
plaintiff
started
measuring
for
making
preparation
to
construct the wall on the boundary of the land as described
in the Schedule 3B the defendant-appellant No.1 raised
serious objection and there had been exchange of words
between the defendant-appellant No.1 and the respondent.
According to the plaintiff, the defendant-appellant No.2 also
supported and participated in the said objection. The
plaintiff-respondent
is
apprehensive
that
if
he
started
construction of the said boundary wall again the defendantappellants would raise objection though the defendant-
appellants do not have any right to object in respect of the
construction over the boundary on the land as described in
the Schedule-3B. For purpose of peaceful construction of the
boundary wall, on the face of the said objection, the plaintiffrespondent
instituted
the
suit.
Since
the
defendant-
appellants have been regularly parking their vehicle on the
passage as described in the Schedule 3B or using that space
as described in the Schedule 3B for making turn, the
plaintiff-respondent had realized that the privilege granted
for use of the land was being seriously breached. Hence, it
has been urged in the suit to issue the decree restraining the
defendant-appellants from creating any obstruction to the
enjoyment of the passage as described in the Schedule-3A
by the plaintiff by parking their car or by any means so that
the plaintiff may have full use and enjoyment of the passage.
The defendant-appellants have no title over the land of the
Schedule-3A. The defendants have no right, title and interest
whatsoever over the land of the Schedule-3B. Despite that
for obstruction created by the defendant-appellant, the
plaintiff could not construct his wall. For that purpose, i.e to
construct the wall peacefully, the suit has also been
instituted by the plaintiff-respondent.
07.
In this conspectus of fact, the plaintiff-respondent
has urged in the suit for a decree of declaration, declaring
that the defendant-appellants have illegally constructed a
part of the room on the land as described in the Schedule 3C
in the plaint and that the defendants do not have any right
to create disturbance or to encroach the land as described in
the Schedule 3B. Further, it has been urged that a decree for
recovering the possession removing the illegal construction
or that part of the room from the land as described in the
Schedule 3C or by removing any other obstruction. As
consequential relief, the plaintiff urged for the decree for
perpetual injunction restraining the defendant-appellants
from entering into the land as described in the Schedule 3B
and from encroaching the land described in the Schedule 3A
by their vehicle and from disturbing the possession of the
plaintiff
thereon
anyway,
however
subject
to
use
as
permitted. Further, the plaintiff-respondent has urged for a
decree of perpetual injunction restraining the defendants
from disturbing the plaintiff-respondent while constructing
the wall along the north boundary of his land as described in
the Schedule 3B, from disturbing or damaging the wall after
construction and also from disturbing the plaintiff from using
the space under the Schedule 3A as the passage in any
manner.
The
pleadings
are
mostly
admitted
by
the
defendant-appellants by their written statement filed jointly.
In para-12 of the said written statement, it has been
asserted as under:
“In the month of July, 2010 the defendant No.2
purchased one new vehicle manufactured by General
Motors and naturally started utilizing the said Ejmali
road for movement of the said vehicle from garage to
main road. The said purchase of the new vehicle by the
defendant No.2 has made the plaintiff highly jealous
and to harass the defendants he has filed the present
suit to satisfy his inimical attitude and jealousy against
the defendants particularly the defendant No.2.”
08.
Certain allegations have been made in the paraof
the
joint
written
statement
in
respect
of
the
management of the sewer and discharge of the foul waters
from toilets. But no such relief has been claimed by way of
counter-claim against the plaintiff. Based on the rival
pleadings, the trial court [the court of the Civil Judge, Senior
Division,
Court
No.1]
framed
the
following
issues
for
determining the suit:
(i)
Whether the suit is maintainable;
(ii)
Whether the defendants are threatening to enter into the
suit land of Schedule- 3B by keeping their vehicle illegally
and unauthorisedly;
(iii)
Whether the defendants have illegally constructed a part
of the room on the land of schedule-3C of the plaint;
(iv)
Whether the defendants have any right to possess or
enter into the land of schedule-3B;
(v)
Whether the defendants are legally bound to remove their
construction of room from the land of schedule 3C;
(vi)
Whether the Plaintiff is entitled to restrain the defendants
from entering into the land of Schedule 3B and keeping
their vehicle there;
(vii)
Whether the defendants are liable to be restrained from
obstructing the plaintiff from constructing wall along the
North boundary of his land of Schedule 3B and from
damaging the wall after construction;
(viii) Whether the defendants are liable to be restrained from
disturbing the plaintiff from exercising common use of the
path described on the Schedule-3;
(ix)
Whether the plaintiff is entitled to any relief/reliefs, as
prayed for.
09.
and
Having recorded the evidence both documentary
oral,
the
objection
as
raised
in
respect
of
the
maintainability of the suit on the ground of limitation was
discarded on observing that the suit was filed within three
years in terms of the Article 58 of the Limitation Act from the
date
of
denial
to
remove
the
illegal
construction
or
temporary construction etc. It has been observed thereafter
as follows:
“Thus from these evidences it can be concluded that
the defendants objected to something for which they
are not entitled to. It has already been decided that on
the 3B schedule land only the plaintiff has exclusive
title and right to use the same. Defendants without
holding any right is not entitled to raise any objection
for constructing a wall by the plaintiff for better
enjoyment of his own land i.e. Schedule 3B land.
Though in such a situation it agreeable that the
defendants will face some problems in moving their
vehicle if plaintiff constructs the said wall, but in
absence of any legal right in favour of the defendants
to prevent the plaintiff in doing so this Court is in not in
a position to help the defendants. While dealing with
this kind of situations the observation of Hon‟ble Apex
Court in State of Madhya Pradesh vs. Dharam Bir 1998
SC was “The Court has to remain impartial and not
swayed by sympathy, in order to deliver any justice for
ensuring that the faith of public in the justice delivery
system is not eroded.”
Further it has been observed that the defendantappellants‟ right over the land as described in the Schedule3A encompasses to the extent of alighting and boarding their
vehicle and not beyond that. Hence the construction over the
land [Schedule 3C] is without having any right existing in
favour of the defendants. The defendants in no way could
controvert the claim of the plaintiff that they have no legal
right over the land as described in the Schedule-3C.
10.
In terms of the finding as returned by the trial
court by the judgment dated 04.02.2013, the reliefs as noted
below were granted by the trial court. The decree was drawn
in conformity thereof.
11.
“(i)
That the defendants have no right of their any
construction over the schedule-3C land of the plaint and
they have no right to create disturbance to the possession
of the plaintiff on the land of schedule 3-B;
(ii)
The Plaintiff is entitled for recovery of possession of the
land of Schedule 3-C and for this defendants are directed
to remove the construction of a part of room is Schedule
3-C, within two months from the date of passing of this
judgment, alternatively Plaintiff is at liberty to remove the
same at the cost of the defendants;
(iii)
The defendants are perpetually restrained from entering
into the land of Schedule 3-B and from encroaching upon
the said land by their vehicle and from disturbing the
possession of the plaintiff therein in any way if plaintiff
likes construction of wall along the North boundary of the
land of schedule 3-B;
(iv)
Further the defendants are restrained from disturbing the
Plaintiff from using the space of the land of Schedule 3-A
as passage;
(v)
Cost of the suit is to be borne by the defendants of their
own.”
Being aggrieved by that judgment, the appellants
herein, filed an appeal under Section 96 of the CPC being
Title Appeal No.23 of 2013 in the court of the Additional
District Judge, West Tripura, Agartala and that appeal was
subsequently transferred to the court of the Additional
District Judge, West Tripura, Agartala, Court No.5 for
hearing. By the impugned judgment dated 22.09.2014, the
appeal was dismissed by affirming the judgment of the trial
court. However, some modification were made in the
following terms, inter alia:
“The appellants are hereby restrained from parking
their vehicle within the land of Schedule 3A and from
encroaching upon the land of Schedule 3B.”
12.
For purpose of elaboration it can be observed that
the first appellate court has appreciated the objections raised
in the memorandum of appeal. In respect of the objection
contending that the suit is barred by limitation, it has been
held that there is no infirmity in the finding returned by the
trial court inasmuch as the cause of action consists of bundle
of facts which give cause to enforce the legal right for
redressal in a court of law. It must include an act done by
the defendant, since in the absence of such an act no cause
of action would possibly accrue or would arise. Thus the
cause of action as stated by the plaintiff, gives rise to such
cause and the suit was instituted within a prescribed period
of limitation as provided under Article 58 of the Limitation
Act. Whether the plaintiff is entitled to get consequential
relief of perpetual injunction restraining the defendants from
disturbing the plaintiff in constructing boundary-wall along
with northern boundary as described in the Schedule 3B and
from damaging the boundary-wall after its construction is
over and further from encroaching upon the land of the
plaintiff-respondent by turning/keeping their vehicle and
from using the said land [described in the schedule 3A] by
the respondent without obstruction. It has been further
observed that by the declaration [Exbt.A] the plaintiff-
respondent had permitted his vendees to use the Schedule3A for a very limited purpose of „turning/keeping‟ of own
vehicle and thus enjoying the use of the Schedule 3A. A
harmonious reading of the declaration in Ext.A makes it
abundantly clear that the plaintiff-respondent has made it
very clear that the title over the land of Schedule-3A shall
always remain with the respondent and can never be
acquired or encumbered by his vendees by virtue of the said
declaration.
13.
The plaintiff-respondent has further asserted that
he has been using the land of Schedule-3A measuring 35 ft.
in length and 7 ft. in breadth keeping the same vacant for
purpose of his use. Thus the intention of the respondent as
could be gathered is to maintain his right to use this land
being the exclusive title holder. He has merely permitted his
vendees to use this land for the limited purpose specifically
mentioned in the declaration [Exbt.A]. It is apparent from
the bare reading of the declaration that the plaintiffrespondent has permitted the appellants to use the land for
passage, for bringing gas-line etc. and for „turning/keeping‟
their vehicle. This declaration is to be constructed keeping in
mind that the respondent neither surrendered nor intended
to surrender his right to use over that land but he has
merely permitted his vendees for limited purpose only. The
permission for „turning/keeping‟ their vehicle would only be
enforceable if, it does not interfere with the free use of that
land by the respondent. In other words, the permission so
granted for the limited purpose would entirely be ineffectual
if it, in any manner whatsoever, interferes with the free use
of this land by the respondent.
14.
It is to be noted that the land as described in the
Schedule-3A
leads
to
the
ejmali
road
of
the
family
connecting the Durgabari Road. It would be apparent that
the defendant-appellants have not taken any plea in their
written statement that in the case of construction of the wall,
he would not be able to move their vehicle from the garage
through
the
land
of
Schedule-3A
and
the
defendant-
appellants will suffer any irreparable injury if they are
restrained from keeping the vehicle on the land as described
in the Schedule 3A. However, they have stated that they will
not be able to move the vehicle out from the garage. Their
garage is beyond the limits of the land as described in the
Schedule 3A but in fact, they keep the vehicle on the land of
Schedule 3A in the open and obstruct the free use of the
land in the Schedule 3A by the plaintiff-respondent, which is
instrumental to irreparable loss to the respondent.
15.
Having regard to all these aspects of the matter,
the first appellate court affirmed the finding of the trial court.
Similarly, in respect of the Schedule 3B land which is still
vacant, it has been clearly observed that the defendant-
appellant does not have any right. The first appellate court
has concurred with the finding of the trial court on making
certain
observations
on
interpretation
of
the
clause
appearing in the declaration [Exbt.A]. It has been observed
by the first appellate court as follows:
“In the present context, the act of „turning/keeping
their vehicle‟ would be complete as soon as the vehicle
enters, takes necessary turn, stops for a reasonable
time to allow the passenger(s) to alight therefrom and
mover out. I am, therefore, unable to accept the
meaning of the words „keeping the vehicle‟ as „parking
the vehicle‟ within the meaning of the Declaration
(Ext.A).”
Thus, the first appellate court has interfered with
the said interpretation of the trial court, despite the
concurrence as noted above. The said interpretation lends to
the result that „keeping the vehicle‟ would not mean „parking
the vehicle‟.
16.
Can the defendant-appellant be allowed to raise a
plea that the plaintiff-respondent is bound to provide that
the space as described in the Schedule B for turning of their
vehicle? Both the courts below have concurred that the
Defendant-appellants
do
not
have
any
right
even
to
temporary or momentary occupartion over the land as
described in the Schdule-3B. So far the recovery of the land
by removing the temporary construction over the land as
described in the Schedule-3C, the first appellate court has
specifically observed that the construction had started
unauthorisedly and subsequently the plaintiff-respondent did
allow the said construction to be used for a very limited
period. But on expiry of that period when the defendantappellants denied to remove the construction/structure, it
gave rise to the cause of action for suing the defendantappellants. It is also admitted by the defendant-appellants
that the part of the room has been constructed over the land
as described in the Schedule-3C. On its western part, the
steps are lying within the land in the Schedule-3A, which is
owned by the plaintiff-respondent exclusively. The owner has
a right to recover possession from a permissive occupier by
removing his construction. Thus, the first appellate court has
concurred with the finding of the trial court. The other issues
may not be very relevant for determining the present appeal.
As stated, being aggrieved by that judgment
dated 22.09.2014 as passed by the first appellate court, this
appeal has been filed.
17.
At the time of admitting the said appeal, the
following substantial questions of law were formulated:
(i)
Whether the findings of the trial Court affirmed by the
appellate Court in respect of the cause of action and in
respect of the limitation were according to law?
(ii)
Whether the judgment and decree passed by the trial
Court and affirmed by the appellate Court suffer from
perversity for non-consideration of the document marked
Exbt.A?
The appellant was provided leave for raising any
other substantial question of law but they did not raise any
other substantial question of law.
18.
Mr. S. Deb, learned senior counsel as well as Mr.
S. M. Chakraborty, learned senior counsel appearing for the
appellants have submitted that the impugned judgment
stands on incorrect reading of the registered declaration
[Exbt.A] which was executed by the plaintiff-respondent
creating the limited right to use in favour of the transferee
[Exbt.A] or the succeeding purchasers. The said declaration
dated 11.05.1992, according to Mr. Deb, learned senior
counsel, has clearly provided that there is a vacant land on
the southern side of the land purchased by the predecessor
of the defendant-appellants measuring 35ft x 7ft from east
to west comprised in Dag No.11418/51014 and Khatian
No.30113 of Mouja Agartala, sheet No.14. On the southern
side of that land the „septic tank‟ of the plaintiff-respondent
and on the southern side of that septic tank there situate his
own building. The said land measuring 35ft x 7ft was kept
vacant for movement and use of the plaintiff-respondent. On
the northern side of his residential plot measuring 37ft x 9 ft
6 inch there is another road connecting the Durgabari Road
and he can enter into his land by that road also. On the
western side of his land there is an ejmali path and drain for
use of his brothers. It has been recited in the declaration
that
Purnima
Chowdhury,
Suchitra
Chowdhury,
Sikha
Chowdhury and Sikha Saha (Roy Chowdhury) purchased his
land. Smt. Purnima Chowdhury and others would enter their
land by the road situated on the northern side of his
residential building measuring 9‟-6‟‟ in width and the vacant
land measuring 35ft x 7inch spread over east to west or vice
versa. The said space can be used by them for their
movement. Even for turning the vehicle or keeping the
vehicle they can use that land heritably. But the ownership of
the land shall stand with the plaintiff-respondent. In this
regard, no objection can be raised by their successors. It has
been clarified in the said declaration that if Purnima
Chowdhury and others sell their purchased property to a
third party, then the third party-purchaser will be entitled to
use that ejmali road and the said vacant land (35ft x 7ft).
But under no circumstances, they will claim any other right,
including the ownership right over the said land. But they
can draw their water supply, electricity and gas line along or
over that land. The said registered declaration [Exbt.A],
according to Mr. Deb, learned senior counsel has been
wrongly interpreted by both the courts below. According to
him, the said declaration has created the right not only of
the movement but of „parking‟ the vehicle over the said
vacant land (35ft x 7ft) as described in the Schedule-3C.
19.
Further, Mr. Deb, learned senior counsel has
strenuously contended that the suit was hopelessly barred by
limitation and both the courts below has wrongly construed
the starting point of limitation and thus read the evidence
perversely. According to him, the cause of action arose
sometime in 2005, but the suit was not filed within three
years
and
an
imaginary
cause
has
been
shown
on
05.08.2010. On the basis of that imaginary cause of action
the suit was filed. According to Mr. Deb, learned senior
counsel on a bare reading of the plaint, it would be apparent
that there are multiple causes of action. While determining
the issue of limitation both the trial court and the first
appellate court had made out a third case which was never
projected in the plaint.
20.
Appearing for the plaintiff-respondent, Mr. K.N.
Bhattacharjee, learned senior counsel has submitted that the
cause of action comprises a bundle of facts, one of which
may give cause to enforce the legal injury for redress in a
court of law and give the plaintiff right to claim relief against
the defendant. It must include some act done by the
defendants since in the absence of such an act no cause of
action would possibly accrue or would arise. The reference
has been made to a decision of the apex court in South East
Asia Shipping Co. Ltd. Vs. Nav Bharat Enterprises Pvt.
Ltd reported in (1996) 3 SCC 443.
21.
Mr. Bhattacharjee, learned senior counsel has
further submitted that there can be no right to sue until at
least a clear and unequivocal threat to infringe the right
emerges.
In
the
case
in
hand,
according
to
Mr.
Bhattacharjee, learned senior counsel, it is on first week of
April, 2010 the said cause of action arose and subsequently
arose on 05.08.2010. Even if, for purpose of counting the
limitation, the first cause of action is treated as the starting
point of limitation, the suit is within the period of limitation in
terms of Section 58 of the Limitation Act. In this regard, Mr.
Bhattacharjee, learned senior counsel has relied on a
decision of the apex court in Rashtriya Ispat Nigam Ltd
Vs. Prathyusha Resources and Infra Private Limited
and Another reported in (2016) 12 SCC 405. In that
report, the apex court has held as under:
“We shall now consider the settled law on the subject.
This Court in a catena of judgments has laid down that
the cause of action arises when the real dispute arises
i.e. when one party asserts and the other party denies
any right. The cause of action in the present case is the
claim of the respondent/claimant to the determination
of base year for the purposes of escalation and the
calculation made thereon, and the refusal of the
appellant to pay as per the calculations.”
22.
To elucidate further, Mr. Bhattacharjee, learned
senior counsel has emphatically submitted that when the
defendant-appellant refused to remove the construction from
the Schedule-3C land in the first week of April, 2008, the
first cause of action arose and thereafter on 05.08.2010
when the defendant-appellants raised objection asking the
plaintiff-respondent
to
stop
piling
of
the
construction
materials for the boundary wall along the northern boundary
of the land as described in the Schedule-3B. According to Mr.
Bhattacharjee, learned senior counsel, cause of action
comprises a bundle of facts. Thus, against the concurrent
finding in respect of the cause of action vis-a-vis the
maintainability of the suit, the ground framed on limitation
cannot be re-agitated in the second appeal, inasmuch as the
question of limitation is a mixed question of law and fact. In
this regard, he has relied further on a decision of the apex
court in Workmen of M/s. Binny Ltd. vs. Management of
Binny Ltd. and Another reported in AIR 1986 SC 509
where the apex court has held as under:
“The respondent company pleaded in their return that
consequent to the amalgamation, the respondent
company (Binny & Company Limited) became a single
unit and all the employees were covered by the same
terms of the Payment of Bonus Act. They denied that
the business activities of the former Binny & Co.
Limited
constituted
a
separate
department
or
undertaking as envisaged in the Payment of Bonus Act.
According to them there was only a single balancesheet for the whole Binny Limited. They admitted that
separate profit and loss account was prepared for the
year 1969 for the finance, trading and agency division
and the garment factory (former Binny & Company
Limited) as required in the scheme of amalgamation,
but no separate balance-sheet was prepared. The
company relied uponSection 3 of the Payment of Bonus
Act which stated that the various companies which
have been amalgamated should be treated as part of
the same establishment under the Act for the purpose
of computation of bonus.”
23.
In continuation, Mr. Bhattacharjee, learned senior
counsel has expanded his submission having stated that
when the real dispute arises then only the cause of action
arises. He has referred to a decision of the apex court in C.
Mahammad Yunus vs. Syed Unnissa and Ors. reported in
AIR 1961 SC 808 where the apex court after observing that
the suit for declaration with a consequential relief for
injunction is not a suit for declaration simpliciter has
observed that the period for the right to sue prescribed by
Article 120 has to be computed from the date of right to sue
accrues and there could be right to sue until there is an
accrual of the right asserted in the suit and its infringement
or at least „a clear and unequivocal threat to infringe that
right‟. This law has been reinstated in Daya Singh & Anr.
vs. Gurdev Singh & Ors. reported in AIR 2010 SC 3240.
Even in Rashtriya Ispat Nigam Ltd (supra) it has been
observed by the apex court that the cause of action arises
when the real dispute arises meaning when the one party
asserts and the other party denies any right.
24.
In
order
to
buttress
his
contention
Mr.
Bhattacharjee, learned senior counsel has relied on another
decision of the apex court in Dudh Nath Pandey vs.
Suresh Chandra Bhattasali reported in AIR 1986 SC
1509 where the supreme court had occasion to asses the
scope of fresh appraisal of evidence on the finding on
limitation. In Dudh Nath Pandey (supra), the apex court
has observed that the finding on the question of limitation by
the first appellate court on appraisal of the evidence after
taking into consideration the entire circumstances in the case
was a finding of fact which could not have been set aside by
the High Court in its exercise of power under Section 100 of
the CPC. On placing reliance on the law as enunciated by the
apex
court
in
Dudh
Nath
Pandey
(supra),
Mr.
Bhattacharjee, learned senior counsel has asserted that in
the present case the finding on the limitation is the
concurrent finding of fact and there is no perversity and as
such this court should discard that challenge.
25.
In
sequel,
Mr.
Bhattacharjee,
learned
senior
counsel has relied on another decision in Karnataka Board
of
Wakf
vs.
Anjuman-E-Ismail
Madris-Un-Niswan
reported in AIR 1999 SC 3067 where the apex court has
considered the aspect of re-appreciating the evidence to
appreciate the concurrent finding of fact in a second appeal.
The apex court in Karnataka Board of Wakf (supra) has
observed that unless there exists perversity in returning the
concurrent finding, the High Court while exercising his
jurisdiction in a second appeal should not in a casual manner
for satisfying its subjective
domain interfere with the
concurrent finding of the two courts below.
26.
Mr. Bhattacharjee, learned senior counsel has
clearly submitted that while reading the declaration [Exbt.A],
the first appellate court has committed no error. He has
further submitted that from the map as attached to the
plaint, being the part of pleadings, it would be apparent that
there is no ambiguity in the relief as claimed by the plaintiffrespondent. The location of Schedule-2A and Schedule-2B
vis-a-vis the Schedule-3C and Schedule-3A has clearly been
delineated,
even
the
location
of
Schedule-3B
is
well
delineated and in this regard no objection cannot be raised
by the defendant-appellants. Finally, Mr. Bhattacharjee,
learned senior counsel has submitted that it is true that the
defendant-appellant No.1 is the full blood brother of the
plaintiff-respondent, but this cannot be treated as an
element to over-ride the claim of the plaintiff-respondent by
way of making an substantive assignment. The law shall take
its course with all its rigours. The mandatory provisions of
law cannot be given a go-bye in the manner as proposed.
Moreover, the element of adjustment was only the case of
the defendant-appellants. They have asserted their rights on
the basis of the declaration in [Exbt.A]. In this regard Mr.
Bhattacharjee, learned senior counsel has relied on a
decision of the apex court in State of M.P. and Another vs.
Dharam Bir reported in (1998) 6 SCC 165 where the apex
court while dealing with the aspects of „human approach‟ has
observed that:
“The plea that the Court should have a "human
approach" and should not disturb a person who has
already been working on this post for more than a
decade also cannot be accepted as the Courts are
hardly swayed by emotional appeals. In dispensing
justice to the litigating parties, the courts not only go
into the merits of the respective cases, they also try to
balance the equities so as to do complete justice
between them. Thus the courts always maintain a
human approach. In the instant case also, this
approach has not been departed from. We are fully
conscious that the respondent had worked on the post
in question for quite a long time but it was only in ad
hoc capacity. We are equally conscious that a selected
candidate who also possesses necessary educational
qualification is available. In this situation, if the
respondent is allowed to continue on this post merely
on the basis of his concept of "human approach", it
would be at the cost of a duly selected candidate who
would be deprived of cleared the selection. In fact, it is
the "human approach" which requires us to prefer the
selected candidate over a person who does not possess
even the requisite qualification. The Courts as also the
Tribunal have no power to override the mandatory
provisions of the Rules on sympathetic consideration
that a person, though not possessing the essential
educational qualifications. should be allowed to
continue on the post merely on the basis of his
experience. Such an order would amount to altering or
amending the Statutory provisions made by the
Government under Article 309 of the Constitution.”
[Emphasis added]
27.
Mr. Bhattacharjee, learned senior counsel has
further submitted that in a second appeal, a new plea cannot
be raised before the High Court and in this regard he has
referred a decision of the apex court in Karunanidhi vs.
Seetharama Naidu and Others reported in (2017) 5
SCC 483.
28.
Mr. Bhattacharjee, learned senior counsel has
added to contend that the plea of adjustment has been
raised as additional plea and it cannot be considered by this
court in this appeal.
29.
In reply, Mr. S. Deb, learned senior counsel
appearing for the appellants has submitted that the High
Court can interfere with the finding of facts when the finding
recorded by the courts below are found to be perverse. Even
re-appreciation of evidence is permissible in exceptional
circumstances. He has place his reliance in order to buttress
on D.R. Rathna Murthy vs. Ramappa reported in (2011)
1 SCC 158.
“Undoubtedly, the High Court can interfere with the
findings of fact even in the Second Appeal, provided the
findings recorded by the courts below are found to be
perverse i.e. not being based on the evidence or
contrary to the evidence on record or reasoning is
based on surmises and misreading of the evidence on
record or where the core issue is not decided. There is
no absolute bar on the re-appreciation of evidence in
those proceedings, however, such a course is
permissible in exceptional circumstances.”
In
Hanamantha
this
regard
Ranoji
vs.
the
reference
Mahadev
to
Rajappa
Channabasappa
reported in (2000) 6 SCC 120, Hafazat Hussain vs.
Abdul Majeed reported in (2001) 7 SCC 189
and
Bharatha Matha vs. R. Vijaya Renganathan reported in
(2010) 11 SCC 483 has been made.
30.
It has been also asserted that the right to sue
accrues when the right to sue first accrues. In L.C.
Hanumanthappa vs. H.B. Shivakumar reported in (2016)
1 SCC 332, the apex court has laid down the law as under:
“We have heard learned counsel for the parties. It is
not disputed that Article 58 of the Limitation Act would
apply to the amended plaint inasmuch as it sought to
add the relief of declaration of title to the already
existing relief for grant of permanent injunction.”
31.
It
has
been
further
contended
that
while
enacting Article 58 of the 1963 Act, the legislature has
designedly made a departure from the language of Article
120 of the earlier Act. The word “first” has been used
between the words “sue” and “accrued”. This would mean
that if a suit is based on multiple causes of action, the period
of limitation will begin to run from the date when the right to
sue first accrues. To put it differently, successive violations
of the right will not give rise to a fresh cause and the suit will
be liable to be dismissed, if it is beyond the period of
limitation counted from the day when the right to sue first
accrued. In this regard, a decision of the apex court in
Khatri Hotels (P) Ltd. vs. Union of India reported in
(2011) 9 SCC 126 has been pressed to elucidate. In Khatri
Hotels (supra) the apex court had occasion to observe as
under:
“While enacting Article 58 of the 1963 Act, the
legislature has designedly made a departure from the
language of Article 120 of the 1908 Act. The word
`first' has been used between the words `sue' and
`accrued'. This would mean that if a suit is based on
multiple causes of action, the period of limitation will
begin to run from the date when the right to sue first
accrues. To put it differently, successive violation of the
right will not give rise to fresh cause and the suit will
be liable to be dismissed if it is beyond the period of
limitation counted from the day when the right to sue
first accrued.”
The said law has been restated in Board of
Turstees of Port of Kandla vs. Hargovind Jasraj and
Anorther reported in (2013) 3 SCC 182.
32.
Mr. Bhattacharjee, learned senior counsel has
rejoined with leave of the court, by stating that the
declaration [Exbt.A] has created a notional right of use
without transfer of any character and part of the title.
33.
Mr. S. Deb, learned senior counsel has reiterated
that injunction against the „parking‟ emanates from a
complete non-reading of Exbt.A and as such the finding is
wholly perverse. In the second appeal this court can
appreciate the evidence for purpose of ascertaining the
correct position of fact.
34.
True it is that that the first appellate court has
issued the
decree of
perpetual
injunction against
the
defendant-appellants in respect of Schedule-3B land and
declared the limited right of use over the Schedule-3C land.
There is no doubt the construction as made by the
defendant-appellants over a part of the Schedule-3C along
with the steps has been sought to be recovered by removing
all
construction
and
obstruction,
if
any.
It
has
been
accordingly directed.
35.
Having appreciated the rival contentions, this
court is of the view that from a bare reading of the
declaration [Exbt.A] it would appear that, the limited right of
use has been created by the said declaration in favour of the
successor of the predecessor of the defendant-appellants and
as such whatever right has been created by the declaration
[Exbt.A] it can be enjoyed by the defendant-appellants.
Therefore, to determine this appeal what rights have been
created by Exbt.A, the said instrument is required to be
revisited. By the declaration the plaintiff-respondent had
created rights in favour of Smt. Purnima Chowdhury, Smt.
Suchitra Chowdhury, Smt. Sikha Chowdhury and Smt. Sikha
Saha (Roy Choudhury) and their successors. For purpose of
appreciation, the relevant part from the said declaration may
gainfully be extracted:
“I do hereby admit, promise and declare that the land
of mine with rayati jote title, which I have sold out to
Smt. Purnima Chowdhury, Smt. Suchitra Chowdhury,
Smt. Sikha
Chowdhury and Smt. Sikha Saha (Roy
Chowdhury), and accordingly they have also become
the owners over the said land by way of purchase; Smt
Purnima Chowdhury and others, along with their
successors shall use and enjoy possession over the
„ejmali‟ road measuring 9‟-6‟‟ inches in breadth,
towards the northern direction from Durgabari
„bari‟(sic) as well as the drain, by virtue of being the
title-holder with all of my rights. And to the further
north of the same, Smt. Chowdhury and others, along
with theirs successors, shall be able to make
movements over my own land measuring 35‟- 0‟‟ feet in
length from east to west and 7‟ – 0‟‟ feet in breadth,
and shall be entitled to use the same for turning their
own vehicle(s), for keeping the vehicles(s) and to use
the same in succession by renovating it. But the entire
ownership title of the same remains and shall remain
with me. Neither me, nor my son(s), grandson(s) or
any of my successors have or shall have any objection
to it. If Smt. Purnima Chowdhury and others want to
sell out their purchased property to any other third
party or parties then the purchaser(s) and subsequent
purchasers shall be entitled to use the land of the
„ejmali‟ road and my own vacant land. Under no
circumstances shall Smt. Chowdhury and others be
entitled to rayati jote title of my vacant land, nor shall
they be able to raise any claim of title over it. If smt.
Chowdhury and others raise any claim of title over my
vacant land then it shall not be legally accepted. They
will be able to take (their) water (connection),
electricity (connection) and gas line to their own
respective lands over the said land.”
36.
Interpretation of that clause as appearing in the
declaration [Exbt.A], as extracted, has become the bone of
contention.
The
trial
court
has
observed
that
Ext.A
categorically declares that the plaintiff retains his title over
the land belonging to Schedule 3A, 3B and 3C and hence he
is entitled to enjoy the land in any manner he likes. Further
it has been observed that:
“Thus from these evidences it can be concluded that
the defendants objected to something for which they
are not entitled to. It has already been decided that on
the 3B schedule land only the plaintiff has exclusive
title and right to use the same. Defendants without
holding any right is not entitled to raise any objection
for constructing a wall by the plaintiff for better
enjoyment of his own land i.e Schedule 3B land. Though
is such a situation it agreeable that the defendants will
face some problems in moving their vehicle if plaintiff
constructs the said wall, but in absence of any legal
right in favour of the defendants to prevent the plaintiff
in doing so this Court is in not in a position to help the
defendants. While dealing with this kind of situations
the observation of Hon‟ble Apex Court in State of
Madhya Pradesh vs. Dharam Bir 1998 SC was The Court
has to remain impartial and not swayed by sympathy,
in order to deliver any justice for ensuring that the faith
of public in the justice delivery system is not eroded.”
[Emphasis added]
37.
On the basis of that finding, the decree was
issued declaring that the defendants have no right to erect
construction over the Schedule-3C land of the plaint and
they have no right to create disturbance on the land of the
Schedule-3B. Further, the decree has been issued for
recovery of the possession of the land on the Schedule-3C
and for that purpose the defendants have been directed to
remove the construction and the part of room over the
Schedule-3C within two months from the date of passing of
this judgment, alternatively the plaintiff shall be at liberty to
remove the said construction etc. at the cost of the
defendants.
Further,
the
decree
has
been
passed
by
perpetually restraining the defendants from entering and
interfering with the possession of the Schedule 3B from
encroaching upon the said land by their vehicle or by
disturbing the possession of the plaintiff in any way including
creating obstruction in construction of a wall along the
northern boundary of the land as described in the Schedule3B. By a further decree, the defendants have been restrained
from creating obstruction or disturbance so that the plaintiff
cannot use and enjoy the space of the land of Schedule-3A
as the passage.
38.
The first appellate court has in modification issued
a specific decree by restraining the appellants from „parking‟
their vehicle within the land in the Schedule-3A and from
encroaching upon the land in the Schedule-3B. The first
appellate court while interpreting the extent of use in terms
of the declaration has observed as under:
“The language used in the Declaration in giving
permission for specific purpose of keeping/turning the
vehicle has to be strictly constructed to mean „turning
of their vehicle within the limits of Schedule 3A, and
not beyond that‟. The appellants are, therefore,
inherently obliged under the Declaration in question to
have any vehicle of the size of the vehicle should
always be comfortable enough to turn the same within
the limits of the land of Schedule 3A. The Ld. Trial Court
has rightly held that permission to turn the vehicle has
been given within specified area of the land of Schedule
3A, and not beyond that. The appellants, in the absence
of a specific legal permission, cannot be permitted to
use the land of Schedule 3B for keeping/turning their
vehicle and to obstruct the construction of the said
boundary wall. I, therefore, uphold the findings of the
Ld. Trial Court except the finding on the parking of the
vehicle. Point No.2 is accordingly decided in favour of
the respondent.”
While
„turning/keeping‟
interpreting
of
the
vehicle
the
phrase
as
appearing
viz.
in
the
declaration [Exbt.A], the first appellate court has observed
that “keeping their vehicle” cannot be read as having the
same, or nearly the same meaning of the words “parking
their vehicles”. „Parking‟ is the act of stopping a vehicle in a
„Car Park‟ or „by the side of the road where it can be left‟.
39.
The final question that falls for consideration that
whether the interpretation of the first appellate court in
respect of the limited right created by the declaration
[Exbt.A] is wholly perverse and unsustainable. This court has
revisited the clauses for purpose of a keen reading but does
not find any difficulty in understanding the clear meaning of
the clause. This court finds that the interpretation as
provided by the first appellate court is a true meaning of the
declaration, if read harmoniously. Moreover, the dominant
possession of the title holder cannot be truncated by way of
interpretation. The right that has been created cannot be
expanded
by any
court
going
beyond
the declaration
[Exbt.A]. Tool of purposive interpretation cannot be adopted
on the clause of the declaration [Exbt.A]. The meaning of
keeping appears very restrictive in the declaration. But the
restrictive meaning has to be adopted by this court to make
a balance between the property right and its use. Mere
etymological
meaning
sometimes
does
not
serve
the
purpose, inasmuch as the entire declaration has to be read
to
get
the
respondent).
intention
of
the
declarant
(the
plaintiff-
40.
The ordinary meaning of „keep‟ according to the
Stroud‟s Judicial Dictionary of Words and Phrases (7th
Edition) is a phrase for a particular purpose and it is used for
that purpose on more than one occasion. But how many or
how frequent those occasions shall be a question of fact to
be determined in each case (Marks vs. Benjamin, 9 L.J.
M.C. 20). It is a common knowledge that the word keep or
for that matter, keeping has its different etymological
dimensions and uses. In the manner, the word „keeping‟ has
appeared in the declaration, it has to be understood in that
context and manner of the said instrument.
41.
The plaintiff-respondent has clearly retained his
title and his right to use the space, but created a limited
right of use in favour of the predecessor of the defendantappellants or their successors. Thus, there cannot be any
amount of doubt that whatever right has been created by the
said
instrument,
can
be
enjoyed
by
the
defendant-
appellants. Therefore, the defendant-appellants have the
right to use the land as described in Schedule-3A for purpose
of their easement, for taking the vehicle to their garage
which is situated on their own land and to take out the
vehicle from the garage. They can also keep the vehicle in a
stationary condition for purpose of alighting or boarding the
vehicle. For that purpose the vehicle can be kept on the said
passage for a reasonable time, but it cannot be parked there
and as such the interpretation as provided by the first
appellate court is acceptable in the context. The fundamental
intention which flows from the text of the said declaration is
that by such uses, the defendant-appellants cannot obstruct
the
enjoyment
of
the
plaintiff-respondent
under
any
circumstances. As such, the vehicle can be kept for a
reasonable time in the manner, as stated above, on the said
land without obstructing the enjoyment of the plaintiffrespondent.
42.
Therefore, this court does not find any perversity
in the finding of the first appellate court which has affirmed
the judgment of the trial court with modification. By
restraining the defendant-appellants from parking the vehicle
over the land as described in the Schedule A of the plaint,
the first appellate court has made the decree complete. The
declaration and the other directions by way of decree,
therefore do not warrant any interference from this court.
43.
So far the question of limitation is concerned in
para-6 of the plaint the plaintiff has asserted as under:
“But after the puja the defendants were not removing
the construction from the land of schedule 3C inspite of
demand by the plaintiff. This way the time passed and
the defendants kept the plaintiff under assurance to
remove the part of the room in schedule 3C but they did
not and have not kept their promise. So in the 1st week
of April 2010 the plaintiff again asked the defendants to
remove the part of the room on schedule 3C but this
time the defendants told him clearly that they would
not do so.”
The cause of action arises from a clear refusal by
the defendant-appellant. As such, the right of the plaintiffrespondent was infringed and was threatened to infringe for
the first time on that occasion.
44.
From scrutiny of the written statement, it is
observed that the said statement has been flatly denied. But
the defendant-appellants‟ case has not been unfolded why
they were not removing the said construction erected on the
Schedule-3A land. In the para-4 of the written statement,
they have only averred that the statement about the
limitation in para-9 is wholly imaginary, but such position
has not been taken in respect of para-6 of the plaint. The
plaintiff-respondent has proved that statement in respect of
cause of action by adequate evidence. In para-5 of his
examination-in-chief filed under Order 18 Rule 4 of the CPC
the plaintiff-respondent has categorically stated as under:
“So in the 1st week of April 2010 I again asked the
defendants to remove the part of the room on schedule
3C but this time the defendants told me clearly that
they would not do so. I have become entitled to seek
recovery of possession of the land of schedule 3C
removing the part of the room constructed upon the
land of schedule 3C and in case the defendants do not
remove the same within such time as may be allowed
by the Court, then I may be allowed to remove the
same at the cost of the defendants.”
There had been no cross-examination in this
regard.
45.
Moreover, in the examination-in-chief filed by the
defendant-appellant No.1, there is no assertion in contra-
distinction of the asserted fact by the plaintiff and as such,
both the courts have rightly accepted the first week of April,
2010 for accrual of the cause of action. Hence the suit which
was filed on 01.10.2010 is within the period of limitation as
prescribed under Article 58 of the Schedule to the Limitation
Act, 1963. For arriving at such finding, the aid of the reports
which have been relied on by the learned counsel for the
parties, are not essential but supplemental. For that reason,
further reference to those reports have been avoided. The
determination of limitation fundamentally hinges on the fact
as established by evidence. So far this case is concerned, it
is not a case of multiple causes of action as asserted and
hence, according to this court, the objection raised in this
regard is without any substance and accordingly the same is
discarded.
Having observed thus, the judgment of the first
appellate court stands affirmed.
In the result, the appeal stands dismissed.
Draw the decree accordingly.
Send down the LCRs thereafter.
JUDGE
Moumita
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review