Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Page No.# 1/38
GAHC010055192026
2026:GAU-AS:8922
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WP(C)/1619/2026
GB LOGISTICS COMMERCE LIMITED
REP. BY MANOJ RATHI , AGED 55 YRS,
S/O- LATE SHIV KISHAN RATHI, HAVING REGD OFFICE AT STAND ROAD,
5TH FLOOR, ROOM NO-508A, KOLKATA, PIN-700001
VERSUS
THE UNION OF INDIA AND ORS
REP. BY THE SECRETARY , MINISTRY OF CONSUMER AFFAIRS, FOOD AND
PUBLIC DISTRIBUTION , GOVT. OF INDIA, KRISHI BHAWAN, DR.
RAJENDRA PEASAD ROAD, NEW DELHI-01
2:THE FOOD CORPORATION OF INDIA
REP. BY ITS GM
REGIONAL OFFICE
ASSAM REGION
3RD FLOOR
MT TOWER
PALTAN BAZAR
GUWAHATI-08
3:THE GENERAL MANAGER (REGION)
FCI
REGIONAL OFFICE
ASSAM REGION
3RD FLOOR
MT TOWER
PALTAN BAZAR
GUWAHATI-08
4:THE MANAGER
FCI
Page No.# 2/38
DIV. OFFICE
GUWAHATI
MITRA BUILDING
ASHRAM ROAD
ULUBARI
GUWAHATI-07
5:THE ASTT. GENERAL MANAGER
FCI
REGIONAL OFFICE
ASSAM REGION
3RD FLOOR
MT TOWER
PALTAN BAZAR
GUWAHATI-08
6:THE DIVISIONAL MANAGER
FCI
DIV. OFFICE
GUWAHATI
MITRA BUILDING
ASHRAM ROAD
ULUBARI
GUWAHATI-07
7:THE BRANCH MANAGER
HDFC BANK LTD.
BUILDWELL COMPOUND
NEAR DARWIN CAMPUS
BESIDE
NEEPCO BHAWAN
ZOO ROAD
GUWAHATI-0
BEFORE
HONOURABLE MR. JUSTICE DEVASHIS BARUAH
For the Petitioner(s)
: Mr. P. K. Goswami, Sr. Advocate
Mr. B. P. Borah, Advocate
For the Respondent(s) : Mr. K. Gogoi, CGC
Mr. B. K. Singh, SC, FCI
Mr. M. Smith, Advocate
Page No.# 3/38
Date on which judgment is reserved
: NA
Date of pronouncement of judgment
: 18.06.2026
Whether the pronouncement is of the
Operative part of the judgment?
: Yes
Whether the full judgment has been
Pronounced?
: NA
JUDGMENT AND ORDER (ORAL)
Heard Mr. P. K. Goswami, the learned Senior Counsel assisted
by Mr. B. P. Borah, the learned counsel appearing on behalf of
the Petitioner. Mr. K. Gogoi, the learned counsel appears on
behalf of the Union of India; Mr. B. K. Singh, the learned counsel
appears on behalf of the Respondent Nos.2 to 6 and Mr. M.
Smith, the learned counsel appears on behalf of the Respondent
No.7.
PREFACE
2.
The Petitioner herein which is a Company registered under
the provisions of the Companies Act, 2013 has assailed the order
dated 23.02.2026 issued by the Respondent No.3. The Petitioner
has also assailed the consequential actions taken on the basis of
the impugned order dated 23.02.2026 whereby the part of the
Security Deposit so submitted on 23.12.2025 was forfeited and
the remaining part which relates to a Bank Guarantee of
Page No.# 4/38
Rs.70,65,000/- was invoked and the amount appropriated by the
Respondents. Additionally, the Petitioner had assailed the
issuance of the Notice Inviting Tender dated 05.03.2026.
BRIEF FACTS OF THE CASE
3.
A Notice Inviting E-Tender dated 29.08.2025 was issued by
the Respondent No.3 inviting bids from eligible contractors for
Road Transport Contract for transportation of goods from Ex-RH
Salchapara to FSD Badarpurghat via weighbridge having an
estimated value of Rs.4,83,00,000/-.
4.
The said Notice Inviting E-Tender is regulated by various
terms and conditions. Part-A contains the Technical Bid. This
Part-A is hereinafter referred to as ‘the Bid Document’. In the Bid
Document, there is a Chapter with the heading “General
Information to Tenderers”. This Chapter for the same of
convenience is hereinafter referred to as “GITT”. There is an
Annexure-I which forms the part of the Bid Document. The
heading of the Annexure-I reads as “Terms and Conditions
governing contracts for Transportation of Food grains from
Depots/Mandis/Railheads
etc.”
This
Document
hereinafter
referred to as “Annexure-I”.
5.
Clause 6 of the GITT is the provision dealing with earnest
money and it is stipulated that earnest money would be 2%
Page No.# 5/38
value of the contract, i.e. amounting to Rs.26,91,432/-. It is also
relevant to take note of that Clause 6(iii) stipulated that the
Micro & Small Enterprises would be exempted from payment of
the earnest money deposit.
6.
Clause 7 of the GITT stipulates the conditions pertaining to
Security Deposit. Sub-clauses (i), (ii), (iii), (iv) and (v) of Clause
7 of the GITT being relevant are reproduced herein under:“7. (i) The successful Tenderer shall furnish, within fifteen working
days of acceptance of his tender, a Security Deposit for the due
performance of his obligations under the contract. The Security
Deposit shall consist of:
(a) A sum equivalent to 5% of the value of the Contract
submitted electronically through NEFT/RTGS/Other electronic
means in favour of the General Manager, Food Corporation of
India. The contractor at his option may deposit 50 (fifty)
percent of this amount within fifteen working days of
acceptance of his tender while the balance 50 (fifty) percent
may be paid by the contractor by deductions at the rate of 10
(ten) per cent from the admitted bills. The Security Deposit
shall not earn any interest.
(b) Another sum equivalent to 10% of the value of contract, in
the form of an irrevocable and unconditional Bank Guarantee
(including e-Bank Guarantee) issued by 'Scheduled Commercial
Bank' notified by RBI (excluding all Urban/Rural/State CoOperative banks and Gramin Banks) in the format prescribed in
Page No.# 6/38
Appendix-IV which shall be enforceable till six months after
the expiry of the contract period.
(c) If applicable, an additional sum equivalent to 10% of the
value of the contract (in addition to a & b above), in terms of
an undertaking provided by the tenderer for relaxation of
eligibility conditions, in the form of an irrevocable and
unconditional Bank Guarantee (including e-Bank Guarantee)
issued by 'Scheduled Commercial Bank' notified by RBI
(excluding all Urban/Rural/State Co-Operative banks and
Gramin Banks) in the format prescribed in Appendix-V which
shall be enforceable till six months after the expiry of the
contract period.
(ii) In case of failure of tenderer to deposit the Bank Guarantee as
stipulated in clause 7(i) (b) & (c) within 15 working days of
acceptance of his tender, further extension of 15 working days can be
given subject to levy of penalty @ 1% of the whole amount of the
Security Deposit.
(iii) The Security Deposit furnished by the Tenderer will be subject
to the terms and conditions given in the Tender and the Corporation
will not be liable for payment of any interest on the Security
Deposit.
(iv) In the event of the Tenderer's failure, after the communication
of acceptance of the tender by the Corporation, to furnish the
requisite Security Deposit under clause 7(i) a by the due date or
requisite Security Deposit in the form of Bank Guarantee under 7(i) b
& 7(i)c including extension period (applicable to submission of BG
Page No.# 7/38
only), his Contract shall be summarily terminated besides forfeiture
of the Earnest Money and the Corporation shall proceed for
appointment of another contractor. Any losses or damages arising
out of and incurred by the Corporation by such conduct of the
contractor will be recovered from the contractor, without prejudice
to any other rights and remedies of the Corporation under the
Contract and Law. The contractor will also be debarred from
participating in any future tenders of the Corporation for a period of
two years. After the completion of prescribed period of two years,
the party may be allowed to participate in the future tenders of FCI
provided all the recoveries/dues have been effected by the
Corporation
and
there
is
no
dispute
pending
with
the
contractor/party.
(v) If the successful tenderer had previously held any contract and
furnished security deposit, the same shall not be adjusted against
this tender and a fresh security deposit will be required to be
furnished.”
7.
Now let this Court take note of Annexure-I. Clause IX of the
Annexure-I stipulates about the Security Deposit. It is clearly
mentioned in Clause IX(a) of Annexure-I the reason why the
Security Deposit is required to be submitted by the Contractor. It
is mentioned that Security Deposit is required for the due, proper
and complete discharge of all the obligations by the Contractor.
What the Security Deposit would comprise of had been
mentioned in Sub-clauses (i), (ii) and (iii) of Clause IX(a) of
Page No.# 8/38
Annexure-I which is pari materia to Clause 7(i) of the GIIT.
Clauses IX(b), IX(c), IX(d), IX(e) and IX(f) of Annexure-I being
relevant are reproduced herein under:“(b) In case of failure of tenderer to deposit the Bank Guarantee as
stipulated in clause 7(i) (b) & (c) within 15 working days of
acceptance of his tender, further extension of 15 working days can
be given subject to levy of penalty @ 1% of the whole amount of
the Security Deposit.
(c) Upon satisfactory performance of the services and on completion
of all the obligations by the contractor under the terms of the
contract and on submission of "Compliance Certificate/Confirmation
of deposit of EPF by way of affidavit duly executed by the Employer
(i.e. Contractor/Bidder)/No Due Certificate" from the concerned
authority designated under EPF and MP Act 1952 showing due and
correct deposit in respect of the employees employed by or through
him for the contract period and on obtaining a "No Demand
Certificate" from the assigned authority of Food Corporation of
India, the Security Deposit will be refunded to the contractor subject
to deductions, if any from the Security as may be necessary for
recovering the claims of Food Corporation of India against the
contractor. The Food Corporation of India will not be liable for
payment of any interest on the Security Deposit. For any EPF
violations which may be detected at any later stage, the contractor
shall be liable and will be proceeded against as per law.
The tenderer should be registered with EPFO as an independent
Page No.# 9/38
employer, having separate code number as required for an employer
under the provisions of EPF and MP Act 1952 and the EPF Scheme
framed thereunder.
(d) The General Manager shall have the rights to forfeit the entire or
part of the amount of security deposit lodged by the contractors or
to appropriate the security deposit or any part, thereof in or towards
the satisfaction of any sum due to be claimed for any damages,
losses charges, expenses or costs that may be suffered or incurred
by the Corporation. The decision of General Manager (Region) in
respect of such losses, damages, charges, costs or expenses shall
be final and binding on the contractors.
(e) Whenever the Security Deposit falls short of the specified
amount, the Contractor shall make good the deficit so that the total
amount of Security Deposit shall not at any time be less than
specified amount.
(f) In the event of the Tenderer failure, after the communication of
acceptance of the tender by the Corporation, to furnish the requisite
Security Deposit under clause 7(i)a by the due date or requisite
Security Deposit in the form of Bank Guarantee under 7(i)b & 7(i)c
including extension period (applicable to submission of BG only), his
Contract shall summarily terminated besides forfeiture of the
Earnest Money and the Corporation shall proceed for appointment of
another contractor. Any losses or damages arising out of and
incurred by the Corporation by such conduct of the contractor will
be recovered from the contractor, without prejudice to any other
rights and remedies of the Corporation under the Contract and Law.
Page No.# 10/38
The contractor will also be debarred from participating in any future
tenders of the Corporation for a period of two years. After the
completion of the prescribed period of two years, the party may be
allowed to participate in the future tenders of FCI provided all the
recoveries/dues have been effected by the Corporation and there is
no dispute pending with the contractor/party.”
8.
This Court further finds it relevant to take note of Clause XI
of Annexure-I which relates to the provisions of Summary
Termination. Sub-Clauses (b) and (c) of Clause XI of Annexure-I
being relevant are reproduced herein under:(b) The General Manager shall also have without prejudice to other
rights and remedies, the right, in the event of breach by the
contractor of any of the terms and conditions of the contract to
terminate the contract forthwith and to get the work done for the
unexpired period of the contract at the risk and cost of the
contractor and / or forfeit the security deposit or any part thereof
for the sum or sums due for any damages, losses, charges,
expenses or costs that may be suffered or incurred by the
Corporation due to the contractor's negligence or unwork-man like
performance of any of the services under the contract.
(c) The contractor shall be responsible to supply adequate and
sufficient
labour,
scales/trucks/carts/any
other
transport
vehicle/container for loading/unloading, transport & carrying out any
other services under the contract in accordance with the instructions
issued by the General Manager or an officer acting on his behalf. If
Page No.# 11/38
the contractor fails to supply the requisite number of labour scales
and trucks/carts, the General Manager shall at his entire discretion
without terminating the contract be at liberty to engage other
labour, scales, trucks/carts, etc. at the risk and cost of the
contractor, who shall be liable to make good to the Corporation all
additional charges, expenses, cost or losses that the Corporation
may incur or suffer thereby. The contractor shall not, however, be
entitled to any gain resulting from entrustment of the work to
another party. The decision of the General Manager shall be final
and binding on the contractor.”
9.
For the purpose of the instant dispute, this Court need not
traverse upon the other Clauses of the GITT/Annexure-I.
10. The Petitioner herein who was interested, submitted its Bid.
On 04.12.2025, the Letter of Acceptance was issued in favour of
the Petitioner for Road Transport Contract for transportation of
goods from Ex-RH Salchapara to FSD Badarpurghat via
weighbridge on regular basis for a period of two years. By the
said Letter of Acceptance, the Petitioner was advised to furnish
the Security Deposit which comprised of a sum equivalent to 5%
of the estimated value of the contract totaling to Rs.23,55,000/and a sum equivalent to 15% of the estimated value of the
contract amounting to Rs.70,65,000/- in the form of irrevocable
and unconditional Bank Guarantee. It was further mentioned that
the said Security Deposit along with the Bank Guarantee should
Page No.# 12/38
be furnished within 15 working days, i.e. on or before
23.12.2025 from the date of issuance of the Letter of
Acceptance. In the said Letter of Acceptance, it was also
mentioned that the last date for submitting the determined Bank
Guarantee without any late fee was 23.12.2025 and the last date
for submitting the determined Bank Guarantee with 1% late fee
along with applicable GST was on 13.01.2026. Clauses 1, 2 and 6
of the Letter of Acceptance dated 04.12.2025 being relevant, are
reproduced herein under:“1. You are advised to furnish the Security Deposit comprising of:
i) A sum equivalent to 5% of the estimated value of contract
submitted electronically through NEFT/RTGS/ECS amounting
to Rs.23,55,000/- (Rupees Twenty Three Lakh Fifty Five
Thousand Only). However, the contractor at his option may
deposit 50 (fifty) percent of this amount i.e., 2.5% within
fifteen working days of acceptance of his tender as initial
Security Deposit at the time of joining of the contract while
the balance 50 (fifty) percent may be paid by the contractor
by deductions @ 20 (twenty) percent from the admitted bills
unto the completion of 5% declared Security Deposit.
However, if the actual value of contract increases from the
estimated value of the contract, the deduction of 2.5% from
admitted bills of contractor shall be continued unto the closure
of the contract. If there are less than 5 (five) admitted bills of
Page No.# 13/38
the contractor, the recovery of SD shall be up to the admitted
bills only. The Security Deposit shall not earn any interest.
ii) A sum equivalent to 15% of estimated value of contract
amounting to Rs.70,65,000/- (Rupees Seventy Lakh Sixty Five
Thousand
Only)
in
the
form
of
an
irrevocable
and
unconditional Bank Guarantee (including e-Bank Guarantee)
issued by 'Scheduled Commercial Bank' notified by RBI
(excluding all Urban/Rural/State Co-operative banks and
Gramin Banks) through SFMS platform to the FCI banker as
per MTF clause no.-7 (vi) under General information to
tenderers on non-judicial stamp paper of appropriate value
purchased in the name of issuing bank in the prescribed
format of Appendix-IV of the MTF which shall be enforceable
till six months after the expiry of the contract period as per
tender terms and conditions of MTF.
2.
You are requested to furnish prescribed security deposit along with
bank guarantee as stated above within 15(fifteen) working days,
i.e., on or before 23.12.2025, from issue of this letter as per MTF.
6.
If BGs are submitted after the due date, the late fee will be
payable by the contractor as given below:
·
The last date for submitting the determined Bank Guarantee
without any late fee- 23.12.2025.
·
The last date for submitting the determined Bank Guarantee
with 1% Late fee along with applicable GST- 13.01.2026.
·
Late fee will be calculated on the total security amount
Page No.# 14/38
(SD+BG).”
11.
The materials on record show that in so far as the
compliance sought for at Clause 1 (i) of the Letter of Acceptance
dated 04.12.2025, the Petitioner duly complied with the same.
However, the Petitioner admittedly did not submit the Security
Deposit by way of a Bank Guarantee which was the requirement
in terms with Clause 1 (ii) of the Letter of Acceptance on or
before 23.12.2025. The records reveal that as the Petitioner did
not submit the Bank Guarantee within 23.12.2025 of the amount
of Rs.70,65,000/- various emails were issued to the Petitioner on
26.12.2025, 05.01.2026, 07.01.2026, 09.01.2026, 12.01.2026
and last one on 13.01.2026 at 4:33 PM.
12.
The materials on record further show that the Petitioner
though at the last moment, took steps before the Respondent
No.7 for the issuance of the Bank Guarantee on 13.01.2026. This
aspect is apparent from Page 142 of the writ petition, i.e. the
Bank Statement of the Petitioner which is a part of Annexure-E
to the writ petition. The said document shows that the
Respondent No.7 deducted an amount of Rs.10,59,750/- from
the current account of the Petitioner maintained in the
Respondent No.7 Bank for the purpose of issuance of the Bank
Guarantee. It is also noticed that on account of certain
technical/system related issues at the Respondent 7’s end, the
Page No.# 15/38
Bank Guarantee could not be processed and issued on
13.01.2026. However, on 14.01.2026, the Bank Guarantee was
issued which was submitted by the Petitioner on 15.01.2026. It is
also relevant to observe that the penalty amount of 1% was
transferred to the Respondent Corporation on 13.01.2026. The
fact that on account of the fault of the Respondent No.7, the
Bank Guarantee could not be issued is apparent from the
communication dated 03.02.2026 issued by the Respondent No.7
which is at Page 146 (Part of Annexure-E to the writ petition). It
may not be out of place to mention that on 14.01.2026 was a
holiday in the office of the Respondent No.2 to 6.
13.
On 03.02.2026, a Show Cause Notice was issued to the
Petitioner to explain the reasons for non-submission of the Bank
Guarantee within the stipulated date, i.e. by 13.01.2026 and why
action should not be taken against the Petitioner as per Clause
6(i), Clause 7(iv), Clause 13, Clause 14(VI), Clause IX(f), Clause
XI(b) and Clause XI(c) and the tender submission undertaking,
thereby summarily terminating and debarring the Petitioner from
participating in any Tender Enquiry with FCI for a period of two
years and get the work done for the unexpired period of the
contract at the risk and cost of the Petitioner.
14.
The Petitioner thereupon submitted a reply on 05.02.2026
stating inter alia that though the Petitioner took steps for
Page No.# 16/38
arranging the Bank Guarantee and submitting the same before
the Respondent FCI Authorities on 13.01.2026, but on account of
the fault of the Respondent No.7 Bank, the Bank Guarantee
could not be processed. It was also mentioned that the Bank
Guarantee which was dated 14.01.2026 was duly submitted on
15.01.2026 and it did not result in any financial loss, risk or
prejudice to the Corporation. It was further mentioned that there
was no willful default or any breach on the part of the Petitioner.
The Bank Guarantee which was duly submitted was valid,
enforceable
and
effective
from
the
stipulated
date,
i.e.
13.01.2026 and further, the proposed actions of forfeiture,
debarment,
termination,
risk
and
cost
execution
were
disproportionate and unwarranted.
15.
The Respondent No.3 thereupon passed the order on
23.02.2026 whereby the contract with the Petitioner was
terminated; the Petitioner was debarred from participating in any
other Tender Enquiry with the FCI for a period of two years from
the date of issuance of the order dated 23.02.2026; forfeiture of
the deposited Security Deposit of Rs.11,77,500/- and the Bank
Guarantee dated 14.01.2026 amounting to Rs.70,65,000/-.
Furthermore, the Respondent Corporation would proceed for
appointment of another contractor for the same contract work on
a regular basis for a period of two years at the risk and cost of
Page No.# 17/38
the Petitioner.
16.
The records further reveal that in pursuance to said order
dated 23.02.2026, the Bank Guarantee dated 14.01.2026 was
invoked by the Respondent No.4 by a communication dated
25.02.2026. On 05.03.2026, a fresh Notice Inviting Tender was
issued for the same work. It is under such circumstances, the
Petitioner has approached this Court by filing the present writ
petition.
17. The record reveals that vide an order dated 18.03.2026, the
learned Coordinate Bench of this Court while issuing notice
passed interim directions to the effect that the Respondent FCI
Authorities may proceed with the tender process initiated by the
NIT dated 05.03.2026, but the said tender process shall not be
finalized without the leave of the Court. It was also directed that
the Respondent FCI Authorities who have received the amount
upon invoking the Bank Guarantee shall keep the said amount in
an interest bearing instrument until further orders.
18.
The records further reveal that the Petitioner had filed an
additional affidavit on 18.03.2026 itself wherein the Model
Tender
Form
pertaining
to
22.0011.0(11.0)/21/2025-Cont
the
E-Tender
Division
for
No.RO
Road
AS-
Transport
Contract for transportation of goods from Ex-RH Salchapara to
Page No.# 18/38
FSD Badarpurghat via weighbridge was brought on record.
19.
An affidavit-in-opposition was filed by the Respondent
Nos.2 to 6 on 20.04.2026. A perusal of the said affidavit-inopposition shows that the said Respondents took the plea of
alternative and efficacious remedy available to the Petitioner in
approaching the Grievance Redressal Committee for redressing
its grievances rather than approaching this Court by invoking
jurisdiction under Article 226 of the Constitution. On merits, the
Respondents have reiterated the factual aspects which have
been already dealt herein above. The Respondents have also
justified their action and more particularly the order dated
23.02.2026 as well as the invocation of the Bank Guarantee
dated 25.02.2026. In addition to that, the Respondents also
justified their authority and power in terms with the contract
agreement to go for a fresh tender in respect to the same work
at the risk and cost of the Petitioner. The Respondents have also
enclosed the various reminders which have been issued to the
Petitioner as Annexure-2 Series and contended in the affidavit-inopposition that the Petitioner was granted ample opportunities
and reminders and in spite of that, the Petitioner did not submit
the Bank Guarantee of the amount of Rs.70,65,000/- within the
period stipulated in the contract.
20.
This Court also takes note of that an affidavit-in-reply was
Page No.# 19/38
filed by the Petitioner on 29.05.2026 wherein the Petitioner,
apart from reiterating and reaffirming the statements made in
the writ petition, further denied the allegations which have been
made in the affidavit-in-opposition.
SUBMISSIONS MADE BY THE LEARNED COUNSELS FOR THE
PARTIES
21. Mr. P. K. Goswami, the learned Senior Counsel appearing on
behalf of the Petitioner submitted that a perusal of the materials
on record would clearly show that it was for the circumstances
beyond the control of the Petitioner that the Petitioner could not
submit the Bank Guarantee on 13.01.2026. Referring to the bank
statement, the bank guarantee as well as the communication
which had been issued by the Respondent No.7 on 03.02.2026,
the learned Senior Counsel submitted that the Respondent No.7
had duly admitted that it was on account of a technical glitch
that the Bank Guarantee could not be issued to the Petitioner on
13.01.2026. The learned Senior Counsel further submitted that
the representative of the Petitioner waited at the Respondent
No.7’s bank till 7:00 PM as would be seen from the reply so
submitted to the Show Cause Notice. The non-consideration of
the aforesaid aspect by the Respondent Authorities, more
particularly the Respondent No.3 makes the action on the part of
Page No.# 20/38
the Respondent No.3 unreasonable and irrational.
22. The learned Senior Counsel further referring to the Clauses
6 of the GITT submitted that the said Clause categorically
stipulates as regards Earnest Money. Taking into account that the
petitioner is an MSME, the Petitioner was exempted from
payment of any Earnest Money. The learned Senior Counsel
further referring to Clause No.7 of the GITT and Clause IX of the
Annexure-I submitted that the Respondent Authorities did not
have the authority and jurisdiction to invoke the Bank Guarantee
in as much as if there was a failure to submit within the
prescribed period, the Respondent Authorities in terms with
Clause 7(iv) of the GITT/Clause IX(f) of Annexure-I could have at
best terminated the contract and forfeited the Earnest Money.
However, in the instant case, the Respondent Authorities have
accepted the Security Deposit, and if the Security Deposit was
accepted, there is an implied waiver on the part of the
Respondent Authorities to Clause 7(iv) of the GITT/Clause IX(f)
of the Annexure-I. The learned Senior Counsel further submitted
by elaborating on the scope of Clause 7(iv) of the GITT/Clause
IX(f) of Annexure-I that the Respondent Authorities could not
have issued the Show Cause Notice or taken the consequential
actions which is the subject matter impugned in the instant
proceedings.
Page No.# 21/38
23.
Per contra, Mr. B. K. Singh, the learned counsel appearing
on behalf of the Respondent Nos.2 to 6 submitted that the
tender conditions were clear and specific. In addition to that, the
Respondents have also clearly mentioned in the Letter of
Acceptance dated 04.12.2025 that the Petitioner was required to
submit the Bank Guarantee on or before 23.12.2025, and if it
was not submitted, the said Bank Guarantee along with an
additional 1% with GST should be submitted on or before
13.01.2026. The learned counsel further submitted that in spite
of various reminders which have been issued as would be
apparent from the affidavit so filed by the Respondents, the
Petitioner having not submitted, the Respondent Authorities were
justified in taking actions which have been impugned in the
instant proceedings. The learned counsel further submitted that
the Petitioner was a habitual defaulter in various contracts and
as the Petitioner was not required to deposit any Earnest Money,
the Security Deposit was forfeited so that upon risk and cost
imposed upon the Petitioner, the amount could be adjusted from
the Security Deposit which had been forfeited.
ANALYSIS AND DETERMINATION
24. The relevant portion of Clause 7 of the GITT as well as the
relevant Sub-clauses of Clause IX of Annexure-I have already
been quoted herein above.
Page No.# 22/38
25.
From a perusal of Clause 7(i) of the GITT/Clause IX(a) of
the Annexure-I would show what the Security Deposit would
consist of. This aspect would be further apparent from a perusal
of Clause 1 of the Letter of Acceptance. The Security Deposit
which was required to be submitted in the present case were in
two parts.
(a) An amount of Rs 23,55,000/- (Rupees Twenty Three
lakhs and Fifty Five thousand) only. This amount constituted
5% of the estimated value of the contract and was required
to be transferred through NEFT/RTGS/ECS.
The contract however had the option of paying the entire
5% of the contract value in the aforesaid manner or pay
2.5%, i.e. Rs.11,77,500/- within 15 working days from the
date of acceptance of the contractor's tender (which would
be the date of issuance of the Letter of Acceptance). In the
instant case, the Letter of Acceptance was issued on
04.12.2025. The remaining 2.5% of the Security Deposit
shall be deducted @ 20% from the admitted bills till the
completion of the total 5% of the Security Deposit. In terms
with the Letter of Acceptance, it was clearly mentioned that
Rs.11,77,500/23.12.2025.
had
to
be
deposited
on
or
before
Page No.# 23/38
(b) The second part of the Security Deposit is a sum which
is equivalent to 15% of the estimated value of the contract
which had been clearly mentioned to be Rs.70,65,000/-.
This amount is not required to be deposited through
RTGS/NEFT/ECS. This amount of Rs.70,65,000/- was
required to be guaranteed on the basis of an irrevocable
and
unconditional
Bank
Guarantee
(including
e-bank
guarantee) issued by a Scheduled Commercial Bank notified
by the RBI, through SFMS Platform to the FCI Banker. The
said irrevocable and unconditional Bank Guarantee has to
be in the format prescribed in Appendix IV of the MTF. The
said Bank Guarantee was required to be valid for a period of
six months after the expiry of the contract period.
26.
Clause 7(ii) of the GITT/Clause IX (b) of Annexure-I read
with the Clause 2 and Clause 6 of the Letter of Acceptance
makes it clear that the Petitioner had to:
(a)
Pay
Rs.11,77,500/-
by
RTGS/NEFT/ECS
to
the
Respondent FCI on or before 23.12.2025.
(b)
Submit
an
irrevocable
and
unconditional
Bank
Guarantee of Rs.70,65,000/- on or before 23.12.2025.
or
Submit
the
irrevocable
and
unconditional
Bank
Page No.# 24/38
Guarantee of Rs.70,65,000/- on or before 13.01.2026
alongwith 1% which is late fee alongwith applicable GST
which would be Rs.1,11,156/-.
27.
Clause 7(iv) of the GITT/Clause IX(f) of Annexure-I
stipulates that in the circumstances the Security Deposit is not
furnished in terms with Clause 7(i)(a), 7(i)(b) and 7(i)(c)
including the extension period which is only applicable to BG
submission only, the Respondent FCI would take the following
actions:
(a) Summarily terminate the Contract;
(b) Forfeit the Earnest Money;
(c) Proceed for appointment of another contractor at the
risk and cost of the Petitioner; and
(d) Debar the contractor for a period of two years from
participating in future tenders of the FCI provided all the
recoveries/dues have been effected by the FCI and there is
no dispute pending with the contractor.
28. At this stage, it is also relevant to take note of Clause XI of
Annexure-I as the said Clause deals with Summary Termination.
Sub-clauses (a) and (c) of Clause XI are not relevant for the
purpose of the present dispute. However, a perusal of Sub-clause
(b) of Clause XI of Annexure-I would show that the said Sub-
Page No.# 25/38
clause is of general nature whereby power to summary
termination of the contract is provided. It is well settled that that
when terms of a contract confers a power on account of a
specific breach, the power has to be exercised under the said
Clause and not taking resort to the general clause for taking
action. It is therefore the opinion of this Court that if there is a
breach to Clauses 7(i)(a), 7(i)(b) or 7(i)(c) of the GITT, the
power could only be exercised in terms with Clause 7(iv) of the
GITT/Clause (IX) (f) of the Annexure-I.
29.
In the backdrop of the above, let this Court analyze the
factual aspect which led to the present dispute. The Petitioner on
23.12.2025 duly transferred the amount of Rs.11,77,500/through NEFT to the Respondent FCI. This amount was a part of
the Security Deposit. The Petitioner did not submit the
irrevocable and unconditional Bank Guarantee of Rs.70,65,000/on or before 23.12.2025. Under such circumstances, the
Petitioner was required to submit the prescribed Bank Guarantee
on or before 13.01.2026 alongwith a late fee of 1% with
applicable GST. The Petitioner transferred the late fee of 1%
alongwith GST on 13.01.2026 to the Respondent FCI. However,
the Petitioner did not submit the prescribed Bank Guarantee on
or before 13.01.2026. Rather, the Petitioner submitted the
prescribed Bank Guarantee on 15.01.2026. It may not be out of
Page No.# 26/38
place to mention that 14.01.2026 was not a working day in the
Respondent FCI, and as such, the submission of the Bank
Guarantee by the Petitioner on 15.01.2026 has to be construed
as on the next working day after 13.01.2026.
30.
The fact that the prescribed Bank Guarantee upon being
submitted by the Petitioner on 15.01.2026 was duly accepted by
the Respondent FCI is not in doubt in as much as the
Respondent FCI has upon receipt of the prescribed Bank
Guarantee invoked the said Bank Guarantee and thereupon
accepted the proceeds of the prescribed Bank Guarantee.
31. The materials on record further reflect that the Respondent
No.7 had deducted a particular amount from the Bank account of
the Petitioner on 13.01.2026 for the purpose of issuance of the
Bank Guarantee. It was also acknowledged by a communication
dated 03.02.2026 issued by the Respondent No.7 that on
account of a technical glitch, the Bank Guarantee could not be
processed on 13.01.2026 and therefore the Bank Guarantee was
issued on 14.01.2026, keeping intact the validity period from
13.01.2026, i.e. the last date for submission of the Bank
Guarantee.
32. Now the question arises as to whether the impugned order
dated 23.02.2026 passed by the Respondent No.3 can be said to
Page No.# 27/38
be fair, reasonable, rational and legal whereby not only the
actions permitted under Clause 7(iv) of the GITT/Clause (ix) (f)
of Annexure-I were taken, but also the entire Security Deposit
was forfeited.
33.
This Court finds it relevant at this stage to take note of
Section 63 of the Indian Contract Act, 1872 (for short, “the Act
of 1872”). The said Section 63 being relevant is quoted herein
below:“63. Promisee may dispense with or remit performance of promise .—
Every promisee may dispense with or remit, wholly or in part, the
performance of the promise made to him, or may extend the time
for such performance, or may accept instead of it any satisfaction
which he thinks fit.
34.
A perusal of the above quoted Section would show that the
general principle regarding waiver of contractual obligation is
engraved in the said Section. The said Section stipulates that it is
open to a promisee to dispense with or remit, wholly or in part,
the performance of the promise made to him or he can accept
instead of it any satisfaction which the promisee thinks fit. There
is no necessity that there should be a consideration or any
specific agreement to constitute the waiver. In the case of, Citi
Bank N.A vs. Standard Chartered Bank and Others , reported in
(2004) 1 SCC 12, the Supreme Court dealt with Section 63 of the
Page No.# 28/38
Act of 1872 and observed that the promisee can act unilaterally
unlike Section 62 of the Act of 1872. Paragraph No.50 of the said
judgment is reproduced herein under:“50. Under Section 63, unlike Section 62, a promisee can act
unilaterally and may
(i) dispense with wholly or in part, or
(ii) remit wholly or in part,
the performance of the promise made to him, or
(iii) may extend the time for such performance, or
(iv) may accept instead of it any satisfaction which he thinks fit.”
35. In the case of S. Brahmanand and Others vs. K. R. Muthugopal
(Dead) and Others, reported in (2005) 12 SCC 764, the Supreme
Court observed at paragraph No.34 of the said judgment the
scope and ambit of Section 63 of the Act of 1872. Paragraph
No.34 of the said judgment being relevant is reproduced herein
under:“34. Thus, this was a situation where the original agreement of
10-3-1989 had a “fixed date” for performance, but by the
subsequent letter of 18-6-1992 the defendants made a request
for postponing the performance to a future date without fixing
any further date for performance. This was accepted by the
plaintiffs by their act of forbearance and not insisting on
performance forthwith. There is nothing strange in time for
Page No.# 29/38
performance being extended, even though originally the
agreement had a fixed date. Section 63 of the Contract Act, 1872
provides that every promisee may extend time for the
performance of the contract. Such an agreement to extend time
need not necessarily be reduced to writing, but may be proved
by oral evidence or, in some cases, even by evidence of conduct
including forbearance on the part of the other party. Thus, in this
case there was a variation in the date of performance by express
representation by the defendants, agreed to by the act of
forbearance on the part of the plaintiffs. What was originally
covered by the first part of Article 54, now fell within the purview
of the second part of the article. Pazhaniappa Chettiyar v. South
Indian Planting and Industrial Co. Ltd. was a similar instance
where the contract when initially made had a date fixed for the
performance of the contract but the Court was of the view that
“in the events that happened in this case, the agreement in
question though started with fixation of a period for the
completion of the transaction became one without such period on
account of the peculiar facts and circumstances already explained
and the contract, therefore, became one in which no time was
fixed for its performance” and held that what was originally
covered by the first part of Article 113 of the Limitation Act, 1908
would fall under the second part of the said article because of the
supervening circumstances of the case.”
36.
In the case of, Kailash Nath Associates vs. Delhi Development
Authority and Another, reported in (2015) 4 SCC 136, the Supreme
Page No.# 30/38
Court
further
observed
that
the
promisee
can
certainly
unilaterally extend the time for payment under Section 63 of the
Act of 1872 if the time for payment was not for the benefit of the
promisee but for the benefit of the promisor. Paragraph No.25 of
the said judgment being relevant is reproduced herein under:“25. However, such is not the position here. In the present case, the
appellant is the promisor and DDA is the promisee. In such a
situation, DDA can certainly unilaterally extend the time for payment
under Section 63 of the Contract Act as the time for payment is not
for DDA’s own benefit but for the benefit of the appellant…..”
37.
In the backdrop of the above principles, it is relevant to
take note of that as per the terms of Clause 7(iv) of the
GITT/Clause IX(f) of the Annexure-I read with Clauses 2 and 6 of
the Letter of Acceptance, the Petitioner was required to submit
to the Respondent FCI who is the promisee, the prescribed Bank
Guarantee on or before 13.01.2026. The prescribed Bank
Guarantee was submitted by the Petitioner who was the
promisor on 15.01.2026 which was duly accepted by the
Respondent FCI without reserving any rights. It was only on
03.02.2026, the Show Cause Notice was issued. The records
further reveal that vide order dated 23.02.2026 which is
impugned in the present proceedings, the Respondent No.3
directed
forfeiture
of
the
entire
Security
Deposit
of
Page No.# 31/38
Rs.11,77,500/- alongwith the amount of Rs.70,65,000/- which
was guaranteed by the Bank Guarantee that too when on
account of the late submission of the said Bank Guarantee,
actions were initiated vide the Show Cause Notice dated
03.02.2026. In the opinion of this Court, the moment the
Respondent FCI accepted the prescribed Bank Guarantee on
15.01.2026, and thereupon acted on it by invoking the same and
appropriating the proceeds of the Bank Guarantee, the
Respondent FCI who was the promisee would be deemed to
have extended the period of submission by conduct to
15.01.2026.
38.
The question now therefore arises whether after extending
the period of submission of the prescribed Bank Guarantee by
conduct and acting thereupon, would it be fair, reasonable,
rational and legal to pass the impugned order dated 23.02.2026
and the subsequent consequential action of invoking the Bank
Guarantee vide the communication dated 25.02.2026 and also
initiating a fresh process for initiating fresh Bids.
39.
In this respect, this Court finds it relevant to take note of
the judgment of the Supreme Court in the case of Kumari
Shrilekha Vidyarthi and Others vs. State of U.P. and Others , reported
in (1991) 1 SCC 212. In the said judgment, the Supreme Court
had observed that once the State is a party to a contract, it has
Page No.# 32/38
an obligation in law to act fairly, reasonably and justly which are
facets of Article 14 of the Constitution. Paragraph Nos.22, 23 and
24 of the said judgment are reproduced herein under:“22. There is an obvious difference in the contracts between private
parties and contracts to which the State is a party. Private parties
are concerned only with their personal interest whereas the State
while exercising its powers and discharging its functions, acts
indubitably, as is expected of it, for public good and in public
interest. The impact of every State action is also on public interest.
This factor alone is sufficient to import at least the minimal
requirements of public law obligations and impress with this
character the contracts made by the State or its instrumentality. It is
a different matter that the scope of judicial review in respect of
disputes falling within the domain of contractual obligations may be
more limited and in doubtful cases the parties may be relegated to
adjudication of their rights by resort to remedies provided for
adjudication of purely contractual disputes. However, to the extent,
challenge is made on the ground of violation of Article 14 by alleging
that the impugned act is arbitrary, unfair or unreasonable, the fact
that the dispute also falls within the domain of contractual
obligations would not relieve the State of its obligation to comply
with the basic requirements of Article 14. To this extent, the
obligation is of a public character invariably in every case
irrespective of there being any other right or obligation in addition
thereto. An additional contractual obligation cannot divest the
Page No.# 33/38
claimant of the guarantee under Article 14 of non-arbitrariness at
the hands of the State in any of its actions.
23. Thus, in a case like the present, if it is shown that the impugned
State action is arbitrary and, therefore, violative of Article 14 of the
Constitution, there can be no impediment in striking down the
impugned act irrespective of the question whether an additional
right, contractual or statutory, if any, is also available to the
aggrieved persons.
24. The State cannot be attributed the split personality of Dr Jekyll
and Mr Hyde in the contractual field so as to impress on it all the
characteristics of the State at the threshold while making a contract
requiring it to fulfil the obligation of Article 14 of the Constitution
and thereafter permitting it to cast off its garb of State to adorn the
new robe of a private body during the subsistence of the contract
enabling it to act arbitrarily subject only to the contractual
obligations and remedies flowing from it. It is really the nature of its
personality as State which is significant and must characterize all its
actions, in whatever field, and not the nature of function,
contractual or otherwise, which is decisive of the nature of scrutiny
permitted for examining the validity of its act. The requirement of
Article 14 being the duty to act fairly, justly and reasonably, there is
nothing which militates against the concept of requiring the State
always to so act, even in contractual matters. There is a basic
difference between the acts of the State which must invariably be in
public interest and those of a private individual, engaged in similar
activities, being primarily for personal gain, which may or may not
Page No.# 34/38
promote public interest. Viewed in this manner, in which we find no
conceptual difficulty or anachronism, we find no reason why the
requirement of Article 14 should not extend even in the sphere of
contractual matters for regulating the conduct of the State activity.”
40.
Based on the facts of this case, it is the opinion of this
Court that the impugned order dated 23.02.2026 is arbitrary,
unreasonable and irrational. The reasons being that the
Respondent FCI by their conduct had extended the period of
submission of the prescribed Bank Guarantee by accepting it.
This aspect is proved by the fact that though Clause 7(iv) of the
GITT/Clause IX (f) of the Annexure-I did not permit forfeiture of
the Security Deposit, but the Respondent No.3 vide the order
dated 23.02.2026 forfeited the Security Deposit, the Respondent
No.3 on 25.02.2026 invoked the Bank Guarantee and the
proceeds of the Security Deposit had been appropriated by the
Respondent FCI. Under such circumstances, there was no breach
by the Petitioner. Resultantly, the drastic measures taken by the
Respondent FCI was totally uncalled for, that too when there was
no loss caused to the Respondent FCI. Paragraph No.29 of the
judgment in the case of Kailash Nath Associates (supra) being
relevant is reproduced herein under:“29. Based on the facts of this case, it would be arbitrary for DDA
to forfeit the earnest money on two fundamental grounds. First,
Page No.# 35/38
there is no breach of contract on the part of the appellant as has
been held above. And second, DDA not having been put to any
loss, even if DDA could insist on a contractual stipulation in its
favour, it would be arbitrary to allow DDA as a public authority to
appropriate Rs 78,00,000 (Rupees seventy-eight lakhs) without
any loss being caused. It is clear, therefore, that Article 14 would
apply in the field of contract in this case and the finding of the
Division Bench on this aspect is hereby reversed.”
41.
In that view of the matter, the instant writ petition stands
disposed of with the following observations and directions:(A) The impugned order dated 23.02.2026 passed by the
Respondent No.3 is set aside and quashed. Accordingly, the
following observations and directions are passed:(i) The termination of the contract pertaining to ETender
No.RO
AS-22.0011.0(11.0)/21/2025-Cont
Division for Road Transport Contract for transportation
of goods from Ex-RH Salchapara to FSD Badarpurghat
via weighbridge vide the impugned order dated
23.02.2026 is set aside and quashed.
(ii) The Letter of Acceptance dated 04.12.2025 stands
restored.
(iii) The forfeiture of the amount of Rs.11,77,500/which is a part of the Security Deposit vide the
Page No.# 36/38
impugned order dated 23.02.2026 is interfered with
and it shall revert back to the Respondent Nos.2 to 6
and form a part of the Security Deposit so submitted
by the Petitioner in pursuance to the Letter of
Acceptance dated 04.12.2025.
(iv) The action on the part of the Respondent No.4 to
invoke the Bank Guarantee vide the communication
dated 25.02.2026 cannot be sustained in view of
setting aside the impugned order dated 23.02.2026.
However, as the communication dated 25.02.2026 has
already
been
acted
upon
and
the
amount
of
Rs.70,65,000/- has already been transferred to the
FCI, the FCI would be required to return the amount
to the Respondent No.7.
(v) The instant judgment was dictated in the open
Court and being lengthy, it may take some time to be
uploaded. The date and time of uploading of the
judgment would be mentioned in the body of the
judgment. This Court grants 10 working days time to
the Petitioner to submit a fresh Bank Guarantee of
Rs.70,65,000/- in the prescribed form and manner to
the Respondent No.3 from the date of uploading of the
present judgment.
Page No.# 37/38
(vi) This Court further observes and directs that upon
receipt of the Bank Guarantee from the Petitioner as
directed herein above, the Respondent FCI shall remit
within 7 working days the amount of Rs.70,65,000/along with the interest accrued (as there was direction
in the order dated 18.03.2026 to keep the proceeds of
the Bank Guarantee in an interest bearing instrument)
to the Respondent No.7.
(vii) This Court further observes and directs that in
case the Petitioner fails to submit the Bank Guarantee
as directed in Clause (v) herein above, the Respondent
FCI would be at liberty to initiate steps in terms with
Clause 7 (iv) of GITT/Clause IX(f) of the Annexure-I.
(viii) The debarment of the Petitioner vide the
impugned order dated 23.02.2026 cannot be sustained
for the reasons aforesaid, for which the same is set
aside and quashed.
(ix) The Letter of Acceptance dated 04.12.2025 having
been revived upon setting aside the order dated
23.02.2026, the impugned Notice Inviting Tender
dated 05.03.2026 cannot also survive, for which the
said Notice Inviting Tender dated 05.03.2026 is set
Page No.# 38/38
aside and quashed.
(B) There shall be no order as to costs.
(C) Interim order stands vacated.
(D) The Registry shall provide a copy of the present
judgment to Mr. B. K. Singh, the learned Standing Counsel
of the FCI for due compliance.
JUDGE
signed by Pradip Kumar Kalita
Pradip Kumar Kalita Digitally
Date: 2026.06.22 19:57:14 +05'30'
Comparing Assistant
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review