The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
20. 07.2018 till 30.09.2018 and according to the petitioner, the respondent No. 3 allowed the request of the petitioner and the petitioner completed executing the whole work within the extended period. [5] It is the case of the petitioner that after about 11 months from the date of completion of the contract work, the petitioner received two showcause notices dated 04.09.2019 and 12.09.2019 from the respondent No. 3 thereby informing the petitioner to show-cause within 7 days as to why action under clause 3(a) and/ or 3(b) of the terms and agreement of the contract shall not be taken against him for breach of the terms and condition of the contract by the petitioner. In the said show-cause notices, the petitioner was further informed that if he failed to submit any showcause within the stipulated period, action will be taken up against him as WP(C) No. 248 of 2020 Page 4 contemplated under clause 3 of the terms and agreement of the contract without further notice. According to the petitioner, he could not submit any reply to the said show-cause notices due to his illness and later on, he came to know that the respondents have taken final action against him under clause 3(a) and (b) of the terms and conditions of the contract by issuing a final action notice dated 30.09.2019, thereby determining the contract and forfeiting the Earnest Money, Security deposit and Performance Guarante…
10. 10.2019 and asking the petitioner to attend for a joint measurement, failing which, the work executed by the petitioner will be measured unilaterally by the respondents in his absence and that the result of the measurement will be final and binding on the petitioner. Having been aggrieved, the petitioner approached this Court by filing the present writ petition for redressing his grievances. [6] Mrs. L. Ayangleima, learned counsel appearing for the petitioner draw the attention of this Court to the terms and conditions of the contract WP(C) No. 248 of 2020 Page 5 under clause 3(i), (ii), (iii) (a) & (b) of the tender documents which are as under:“ Clause-3 When Contract can be Determined Subject to other provision contained in this clause, the Engineer-in-Charge may, without prejudice to any other rights or remedy against the contractor in respect of any delay inferior workmanship, any claims for damages and/or any other provisions of this contract or otherwise, and whether the date of completion has or has not elapsed, by Notice in writing absolutely determine the contract in any of the following cases: “(i) If the contractor having been given by the Engineer-in-Charge a Notice in writing rectify, reconstruct or replace any defective work or that the work is being performed in an inefficient or otherwise improper or un-workmanlike manner shall omit to comply with the requireme…
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
IN THE HIGH COURT OF MANIPUR
signed
LHAINEI Digitally
by
LHAINEICHONG
CHONG HAOKIP
Date: 2022.08.17
HAOKIP 14:28:12 +05'30'
AT IMPHAL
W.P.(C) No. 248 of 2020
Shri Gaikhonlung Panmei, Special Class Contactor aged about 61
years S/O (L) Tariang Panmei of Saramba Village, P.O.
Tamenglong & P.S. Tousem, Tamenglong District, Manipur795156.
... Petitioner
-Versus 1. The Union of India represented by the Secretary, Department of
Food and Public Distribution under the Ministry of Consumer
Affairs, Government of India and its office at Krishi Bhawan,
New Delhi-110001.
2. The Food Corporation of India represented by its
Chairman/Managing Director, Food Corporation of India and its
office at 16-20, Khadya Sadar, Barakhamba Road, New-Delhi110001.
3. Assistant General Manager (Civil Engineering), Food
Corporation of India, Regional Office, Manipur at Old Assembly
Complex, Imphal-795001.
... Respondents
B E F O R E
HON’BLE MR. JUSTICE AHANTHEM BIMOL SINGH
For the Petitioner
:
Mrs. L. Ayangleima, Adv.
For the respondents
:
Mr. W. Darakishwor, Sr.
Panel Counsel &Mr. D.
Julius Riamei, Adv.
Date of Hearing
:
21.07.2022
Date of Judgment & Order
:
17.08.2022
WP(C) No. 248 of 2020
Page 1
Judgment & Order
[1]
Heard Mrs. L. Ayangleima, learned counsel appearing for the
petitioner, Mr. W. Darakishwor, learned senior panel counsel appearing for
the respondent No. 1 and Mr. D. Julius Riamei, learned counsel appearing
for the respondents No. 2 & 3.
The present writ petition had been filed with a prayer for
quashing and setting aside the show-cause notices dated 04.09.2019 and
12.09.2019 as well as the notice on final action under clause 3 of the
agreement dated 30.09.2019 thereby determining the contract earlier
awarded to the petitioner.
[2]
The case of the petitioner is that the Assistant Joint Manager (Civil
Engineering) of the Food Corporation of India (FCI), Regional Office,
Manipur, issued an E-tender notice dated 12.03.2018 inviting online
percentage rate tender under two bids system from the eligible contractors
for executing two works, viz., (i) providing tube well and safe drinking
water facility at FSD Ukhrul, Manipur and (ii) repairing of office building
and AR & MO works at SD Ukhrul, Manipur.
The petitioner being a registered special class work contractor
and being an eligible bidder participated in the tender process by
submitting his bids in respect of the contract work for providing tube well
and safe drinking water facility at SD Ukhrul, Manipur. As the bid
submitted by the petitioner was found to be the lowest, the respondent No.
WP(C) No. 248 of 2020
Page 2
3 issued a work order dated 18.05.2018 in favour of the petitioner and in
the said work order, it is stipulated that the time allowed for carrying out
the work shall be two months from the 15th day after issue of the said work
order.
[3]
On the date of issuance of the work order dated 18.05.2018, the
petitioner entered into a formal agreement with the respondent No. 3 to the
effect that the petitioner shall complete execution of the contract work
within the period prescribed/stipulated in the work order and to maintain
the same at the cost of the petitioner for a period of six months. It is the
case of the petitioner that after executing the formal agreement, he visited
the work site and started executing the work under the supervision of the
respondent No. 3, however, due to law and order problem on the road
from Imphal to Ukhrul and as the hiring charges of heavy drilling
machineries for drilling tube well were very high, the petitioner could not
hire the said machineries as such, the petitioner executed the contract
work by drilling the tube well manually by engaging expert and skilled
workers. It is the case of the petitioner that he informed the respondent
No. 3 about his inability to hire heavy drilling machineries and about the
arrangement of skilled workers by submitting a letter dated 25.95.2018
and continued executing the contract work with the aim to complete it
within the stipulated period.
WP(C) No. 248 of 2020
Page 3
In response to the aforesaid letter of the petitioner dated
25.05.2018, the respondent No. 3 wrote a letter dated 09.07.2018, thereby
informing the petitioner that the contract work had been awarded to him at
his own independently quoted rate and hence, no claims for high hiring
charges of heavy drilling machineries will be entertained by the office at
that stage and directing the petitioner to execute work strictly as per
schedule of the work.
[4]
As the petitioner could not complete the execution of the contract
work in times, he submitted an application dated 20.07.2018 to the
respondent No. 3 for extending the time of completion of the work w.e.f.
20.07.2018 till 30.09.2018 and according to the petitioner, the respondent
No. 3 allowed the request of the petitioner and the petitioner completed
executing the whole work within the extended period.
[5]
It is the case of the petitioner that after about 11 months from the
date of completion of the contract work, the petitioner received two showcause notices dated 04.09.2019 and 12.09.2019 from the respondent No.
3 thereby informing the petitioner to show-cause within 7 days as to why
action under clause 3(a) and/ or 3(b) of the terms and agreement of the
contract shall not be taken against him for breach of the terms and
condition of the contract by the petitioner. In the said show-cause notices,
the petitioner was further informed that if he failed to submit any showcause within the stipulated period, action will be taken up against him as
WP(C) No. 248 of 2020
Page 4
contemplated under clause 3 of the terms and agreement of the contract
without further notice.
According to the petitioner, he could not submit any reply to
the said show-cause notices due to his illness and later on, he came to
know that the respondents have taken final action against him under
clause 3(a) and (b) of the terms and conditions of the contract by issuing a
final action notice dated 30.09.2019, thereby determining the contract and
forfeiting the
Earnest
Money,
Security deposit
and Performance
Guarantee submitted by the petitioner. In the said notice for final action
dated 30.09.2019, the petitioner was informed that the remaining
unexecuted work will be taken out from him and gave it to another
contractor to complete the work and that he shall have no claim to
compensation for any loss sustained by him and the petitioner was also
informed that the work executed by him will be measured up on
10.10.2019 and asking the petitioner to attend for a joint measurement,
failing which, the work executed by the petitioner will be measured
unilaterally by the respondents in his absence and that the result of the
measurement will be final and binding on the petitioner. Having been
aggrieved, the petitioner approached this Court by filing the present writ
petition for redressing his grievances.
[6]
Mrs. L. Ayangleima, learned counsel appearing for the petitioner
draw the attention of this Court to the terms and conditions of the contract
WP(C) No. 248 of 2020
Page 5
under clause 3(i), (ii), (iii) (a) & (b) of the tender documents which are as
under:“ Clause-3
When Contract can be Determined
Subject to other provision contained in this clause, the
Engineer-in-Charge may, without prejudice to any other
rights or remedy against the contractor in respect of any
delay inferior workmanship, any claims for damages and/or
any other provisions of this contract or otherwise, and
whether the date of completion has or has not elapsed, by
Notice in writing absolutely determine the contract in any of
the following cases:
“(i)
If the contractor having been given by the
Engineer-in-Charge a Notice in writing rectify,
reconstruct or replace any defective work or that
the work is being performed in an inefficient or
otherwise improper or un-workmanlike manner
shall omit to comply with the requirement of such
Notice for a period of seven days thereafter.
“(ii)
If the contractor has, without reasonable cause,
suspended the progress of the work or has failed to
proceed with the work due diligence so that in the
opinion of the Engineer-in-Charge (which shall be
final and binding) he will be unable to secure
completion of the work by the date for completion
and continues to do so after a Notice in writing of
seven days from the Engineer-in-Charge.
“(iii)
If the contractor fails to complete the work within
the stipulated date or items of work with individual
date of completion, if any stipulated, on or before
such date(s) of completion and does not complete
them within the period specified in a Notice given in
writing in that behalf by the Engineer-in-Charge.
“(a)
To determine or rescind the contract as aforesaid
(of which Termination or Rescission Notice in
writing to the Contractor under the hand of the
Engineer-in-Charge shall be Conclusive evidence).
Upon such determination or rescission, the Earnest
Money Deposit, Security Deposit already recovered
and Performance Guarantee under the Contract
shall be liable to be forfeited and shall be absolutely
at the disposal of the FCI.
WP(C) No. 248 of 2020
Page 6
“(b)
After giving Notice to the contractor to measure up
the work of the contractor and to take such whole, or the
balance or part thereof, as shall be un-executed out of his
hands and to give it to another contractor to complete the
work, the contractor, whose contract is determined or
rescinded as above, shall not be allowed to participate in
the Tendering process for the balance work.
In the event of above courses being adopted by the
Engineer-in-Charge, the contractor shall have no claim to
compensation for any loss sustained by him by reasons of
his having purchased or procured any materials or entered
into any engagements or made any advances on account
or with a view to the execution of the work or the
performance of the contract. In case action is taken under
any of the provision aforesaid, the contractor shall not be
entitled to recover or be paid any sum for any work thereof
or actually performed under this contract unless and until
the Engineer-in-Charge has certified in writing the
performance of such work and the value payable in respect
thereof and he shall only be entitled to be paid the value so
certified.”
[7]
Mrs. L. Ayangleima, learned counsel appearing for the petitioner
submitted that the respondents issued the impugned show-cause notices
dated 04.09.2019 and 12.09.2019 under clause 3(ii) & (iii) of the terms and
conditions of the contract and final action had been taken against the
petitioner under clause 3(a) and (b) of the terms and conditions of the
contract erroneously and illegally, inasmuch as, such provisions are
relevant only when the contractor is unable to secure completion of the
work or fails to complete the work within the stipulated period and that
such notice can be given either before expiry of the stipulated period for
execution of the work or when the contractor fails to execute the work
within the stipulated time.
WP(C) No. 248 of 2020
Page 7
The learned counsel submitted that in the present case, as
the petitioner had completed execution of the work on 30.09.2018, the
respondents could not have issued the impugned show-cause notices and
took final action against the petitioner after about 11 months from the date
of completion of the contract work. The learned counsel accordingly
submitted that the respondent No. 3 issued the impugned show-cause
notices and took final action against the petitioner arbitrarily and illegally
and accordingly, such action are not sustainable in the eyes of law and the
same are liable to be quashed and set aside.
[8]
The learned counsel for the petitioner further submitted that in the
report submitted by a committee after inspection of the work executed by
the petitioner, it has been clearly opined that the petitioner has not done
the work as per the specification, meaning thereby that the petitioner had
executed the contract work, however, not in accordance with the
specification. According to the learned counsel for the petitioner, in such a
situation, the respondent No. 3 ought to have issued the show-cause
notices under clause 3(i) of the terms and conditions of the contract if at all
respondents are not satisfied with the work executed by the petitioner and
not under clause 3(ii) & (iii) of the terms and conditions of the contract
work as had been done arbitrarily and illegally by the respondent No. 3 in
the present case. The learned counsel accordingly submitted that the
WP(C) No. 248 of 2020
Page 8
impugned show-cause notices and the impugned notice of final action
taken against the petitioner are liable to be quashed and set aside.
[9]
Mr. D. Julius Riamei, learned counsel appearing for the respondents
No. 2 & 3 submitted that the contract work for providing tube well and safe
drinking water facility at FSD Ukhrul was to be executed within two months
from the 15th day of issuing the work order dated 18.05.2018. As the
petitioner was unable to execute the contract work within the stipulated
period of two months, he requested for extension of the period for
completion of the contract work till 30.09.2018 by submitting an application
dated 20.07.2018 to the respondent No. 3.
[10]
When the petitioner failed to execute the contract work within the
stipulated period, a committee consisting of three officials of the FCI
carried out an inspection of the contract work on 27.08.2019 and
submitted a report dated 28.08.2019. In the said report, it is clearly stated
that upon inspection, it was found that the petitioner had connected two
P.V.C. Pipes from the newly drilled Borewell to the existing old tube well
and put the submersible pump into the old tube-well and that one of the
P.V.C. Pipes is directly connected to the outlet of submersible pump and
other was used for carrying electrical connection to the submersible pump.
In the said report, it is also stated that the item of boring of the tube well
considered in the tender was machine boring but the contractor had done
manual boring and provided 75 mm diameter G.I. Pipes and that the depth
WP(C) No. 248 of 2020
Page 9
of the boring was unknown and water was not pump out from the new tube
well but it was connected to the old tube well with P.V.C Pipes and water
was drawn out from the old tube-well through the submersible pump
connected in the old tube-well and accordingly, the committee was of the
opinion that the petitioner did not execute the work as per the
specification. Thereafter, the committee recommended that appropriate
action may be taken by the competent authorities as per the terms and
conditions of the contract.
[11]
It has been submitted by the learned counsel for the respondents
No. 2 & 3 that on a bare perusal of the said committee report dated
28.08.2019, it is crystal clear that the petitioner failed to execute the
contract work, inasmuch as, the new tube well was not complete and
unworkable as no water was pump out from it.
As the petitioner failed to execute the contract work, the
impugned show-cause notices were issued and when the petitioner failed
to submit any reply thereto, the respondents have issued the notice of final
action dated 30.09.2019 thereby determining the contract. The learned
counsel accordingly submitted that no illegality or irregularity had been
committed by the respondent No. 3 while issuing the impugned showcause notices and the impugned notice of final action.
[12]
Mr. D. Julius Riamei, learned counsel further submitted that the
petitioner has neither intimated nor submitted any letters to the respondent
WP(C) No. 248 of 2020
Page 10
No. 3 regarding completion of the contract work till date and the petitioner
has not raised any claim for payment of the bills for the work being
executed by him. Moreover, after the respondent No 3 have taken the final
action on 30.09.2019, the petitioner submitted a letter dated 03.10.2019 to
the respondent No. 3 stating, inter-alia, that the matter regarding nonexecution of the contract work had been discussed with the respondent
No. 3 and that the petitioner had already proposed to cancel the said
contract work as the same was non-executable and for calling a fresh
tender. In the said letter, the petitioner also stated that he had not claimed
and will not claim any bill/payment for the work executed by him. The
learned counsel submitted that in view of such conduct of the petitioner, it
is crystal clear that the petitioner had himself admitted that he did not
complete the execution of the contract work and accordingly, there is no
ground or reason for interfering with the impugned show-cause notices
and impugned action taken by the respondent No. 3 and the present writ
petition is liable to be dismissed as being devoid of merit.
[13]
I have heard the learned counsel appearing for the parties at length
and have also carefully examined the materials available on record. On
careful examination of the aforesaid committee report dated 28.08.2019
and letter of the petitioner dated 03.10.2019, addressed to the respondent
No. 3 and also taking into consideration the undisputed fact that the
petitioner has neither submitted any work completion report nor raised any
WP(C) No. 248 of 2020
Page 11
claim for payment of bills for the work executed by him till date, there is no
doubt that the petitioner did not execute the contract work completely and
as such, this Court is of the considered view that there is no substance or
merit in the contention raised by the counsel for the petitioner and that the
respondent No. 3 did not commit any illegality or irregularity in issuing the
impugned show-cause notices and the final action taken by him against
the petitioner under clause 3(ii) & (iii) read with clause 3(a) & (b) of the
terms and conditions of the contract. In the result, the present writ petition
fails and accordingly, the same is dismissed as being devoid of merit.
In view of the facts and circumstances of the present case,
there will be no order as to costs.
JUDGE
FR/NFR
Lhaineichong
WP(C) No. 248 of 2020
Page 12
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review