IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on: 17.08.2026
Judgment pronounced on: 10.09.2026
#
+
CNR No. DLHC010300652023
O.M.P. (COMM) 293/2023 & I.A. 14489/2023
ECO GREEN BUILDTECH PVT LTD
Through:
.....Petitioner
Mr. S K Maniktala, Mr. Udit
Maniktala, Mr. Akshay Sharma,
Mr. Sanchit Jain, Mr. Vikas
Rana, Mr. Shikhar Prakash &
Mr. Mohit Sharma, Advs.
versus
VIKARTAN INFRASTRUCTURE PVT LTD .....Respondent
Through:
Mr. Somnath Bharti, Sr. Adv.
with Mr. Bhupesh Narula, Ms.
Rinku Narula, Mr. Anurag
Ekka & Mr. Kanishk Taneja,
Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
JUDGMENT
1.
The present petition is filed under Section 34 of the Arbitration
and Conciliation Act, 1996 (for short ‘the Act’) challenging the award
dated 28.02.2023 and the additional award dated 27.03.2023.
2.
The dispute arises out of the contract for construction and
development of ‘Sikka Kamya Greens, Sector-10, Greater Noida’. The
letter of acceptance dated 09.04.2016 was for a contract value of
Rs.53,73,50,000/- with a stipulated completion period of thirty-four
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
months i.e. up to 08.02.2019. During the execution of the work
dispute arose between the parties concerning inter alia delay in
execution, release of payments and party responsible for the
prolongation of the contract. The parties thereafter executed a
Memorandum of Understanding (MOU) dated 27.09.2018. and effect
thereof is contentious. The respondent alleged that the petitioner failed
to comply with its obligations under the MOU whereas the petitioner
relied upon the MOU for having settled the accounts and claims
between the parties.
2.1
The
respondent
attributed
the
delay
and
consequent
prolongation of the works to breaches committed by the petitioner,
particularly non-release of payments, non-supply of requisite material
and failure to remove various hindrances at site. The respondent
claimed compensation towards amount due for work executed,
escalation, Works Contract Tax (WCT), damages for idling/underutilisation of plant and machinery, additional overheads, material
lying at site, loss of profit/profitability due to non-completion of work
consequent to breach attributable to the petitioner (hereinafter ‘claim
for loss’), interest and costs. The petitioner disputed the claims and
alleged that the delay was attributable to the respondent for failure to
deploy adequate manpower and machinery and abandonment of the
works.
2.2
Arbitration was invoked by the respondent on 13.07.2020. A
sole arbitrator was appointed with the consent of the parties by the
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
Court vide order dated 14.08.2020. During the arbitral proceedings an
independent engineer was appointed as the Local Commissioner
(hereinafter referred to as ‘LC’) to measure the work executed at site
and to prepare an inventory of the material plant, machinery tools and
equipment belonging to the respondent. The LC inspected the site
between 29.08.2020 and 02.09.2020 and submitted the report dated
31.12.2020 followed by a supplementary report dated 28.02.2021.
2.3
Before the arbitral tribunal (for short ‘the tribunal’) the
respondent raised twelve claims aggregating to Rs.15,07,05,796/apart
from
interest
while
the
petitioner
preferred
thirteen
counterclaims aggregating to Rs.4,02,71,750/- apart from interest and
costs. The principal controversy before the tribunal concerned the
party responsible for the delay and the consequences flowing
therefrom.
2.4
Upon
consideration
of
the
contractual
document,
correspondence, MOU, LC report and material placed on record the
tribunal held petitioner to be responsible for delay and breach of
contractual obligations and that no corresponding breach on the part of
the respondent was established. The tribunal further held that the
MOU was binding upon the parties but did not constitute novation of
the original contract. The tribunal partly allowed the claims relating to
work executed, WCT, idling/under-utilisation of machinery, additional
overhead, material lying at site and loss of profit/profitability and
rejected the claims towards escalation and other heads. All the
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
counterclaims of the petitioner were rejected. On an application under
Section 33 of the Act, the tribunal passed the additional award dated
27.03.2023 correcting typographical and computational error in the
original award. Significantly, the computation under claim no.6
relating to additional overheads was corrected from Rs.2,04,53,218/to Rs.2,84,53,218/-.
3.
Learned counsel for the petitioner submits that the award
having passed after expiry of the mandate of the tribunal is liable to be
set aside. The contention is that the rejoinder was filed on 25.02.2022
and the award was passed on 28.02.2023 i.e. beyond the period of one
year. The submission is that the proceedings recorded during
conciliation undertaken by the tribunal were relied upon while passing
the award. Learned counsel assails the amount awarded under claim
no.1 contending that the quantum of work done was determined on the
basis of the report of LC, without affording the petitioner an
opportunity to object to the report. The argument is that the
acceptance of LC report during conciliation proceedings could not
have been relied upon after failure of conciliation. It is submitted that
the tribunal without reconciling the figure of Rs.11,82,55,494/mentioned in the MoU, erred in considering that the respondent
received Rs.10,72,84,936/-. It is urged that the tribunal erroneously
added Krishi Kalyan Cess to the amount awarded that to without the
respondent establishing that the cess was leviable at the relevant time.
3.1
Vis-a-vis claim no.3 it is argued that the tribunal erred in
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
awarding the amount deducted by the petitioner towards WCT as the
tribunal failed to consider that the petitioner was in litigation with the
taxation authorities and for this reason WCT was not deposited.
3.2
The award of Rs.1,04,29,203/- under claim no.4 towards idling
of resources arranged on rent is contested having been allowed in
absence of evidence of rent paid.
3.3
With respect to claim no.6 it is argued that the damages
awarded of Rs.2,84,53,218/- for additional overheads due to breach of
contract was contrary to the terms of the MOU. Submission is that the
respondent failed to produce the evidence to demonstrate deployment
of staff. The submission is that the respondent executed the work even
after the MOU and received the corresponding payments yet the
tribunal awarded damages for overheads claimed for the entire period.
3.4
Insofar as claim no.8 is concerned learned counsel assails the
awarding of cost of building material lying at the site, for having
awarded without evidence of either the existence of the material lying
at site or value thereof.
3.5
Claim no.9 towards claim for loss is stated to have been allowed
in lack of evidence and the quantification was done relying upon the
experience of the arbitrator. The approach of the tribunal for
mitigation of losses was based on conjecture and sheer guess work.
4.
Per contra the challenge to the mandate of the tribunal is
misconceived, the rejoinder was filed on 10.05.2022 and the award
was passed within the period prescribed under Section 29A(1) of the
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
Act. The submission is that no conciliation proceedings as
contemplated under Section 61 of the Act and no initiation as per the
procedure prescribed under Section 62 of the Act were undertaken.
Reliance is placed on the decision of the Calcutta High Court in
MFAR
Constructions
Infrastructure
Private
Development
Limited
Limited
v.
FMAT
Bengal
Shrishti
(ARBAWARD)
No.30/2022.
4.1
For claim no.1 learned counsel for the respondent submits that
the quantum of work executed by the respondent was duly supported
by calculations tabulated in document C-77. The report of the LC was
rightly relied upon by the tribunal for determination of work executed
and it is borne out from the attendance sheet that the LC conducted the
inspection in presence of the parties.
4.2
As regards claim no.3 the submission is that the petitioner
despite deducting the WCT from the payments due, failed to deposit it
with the concerned tax authorities.
4.3
Awarding of claim no.4 is defended by stating that a reasonable
amount was awarded and not the claimed amount. Moreover, there
were documents on record to establish that the machinery and other
resources were arranged on rent and kept available for execution of
the work.
4.4
It is canvassed that once breach of terms of contract by the
petitioner stood established, the respondent was entitled to be
compensated for consequential expenditure and overheads on account
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
of prolongation of work thus claim no.6 was rightly awarded.
4.5
With regard to claim no.8 the argument is that the material and
machinery at site were not permitted to be removed by the petitioner
and the resources could not be deployed for other project. The
submission is that cost of material was calculated in the report of the
LC.
4.6
Vis-a-vis claim no.9 towards claim for loss the contention is that
the respondent was entitled to compensation at the rate of 10% yet the
tribunal awarded only 7.5%. It is canvassed that Hudson formula is a
recognised method and can be relied upon for claiming loss in case of
a breach of contract, in support the judgement of the Calcutta High
Court in State of West Bengal v. S.K. Manjhi FMA 573/2024 is relied
upon.
5.
Heard learned counsel for the parties at length and perused the
relevant record with their able assistance.
6.
The contention of learned counsel for the petitioner that the
mandate of the tribunal expired prior to passing of the award, is
factually wrong. Section 29A(1) of the Act provides that in matters
other than international commercial arbitration the tribunal shall make
the award within twelve months of completion of the pleadings. The
argument of the learned counsel is based upon a fact that the rejoinder
by the respondent was filed on 25.02.2022 whereas from the perusal
of the record it is evident that it was filed on 10.05.2022 and was
dated 25.02.2022. In other words, the pleadings were complete on
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
10.05.2022 and within the prescribed statutory period of twelve
months the award was passed.
7.
Before dealing with the issue of conciliation proceedings
undertaken by the tribunal it would be relevant to reproduce the
relevant portion of the procedural order dated 23.08.2022:
“3. The Respondent raised certain issues regarding the
report submitted by the local Commissioner which
were minor in nature. Both the parties informed that
they were agreeable to amicable settlement of and the
principal amount of their respective claims/counter
claims which was welcomed by this tribunal.
4. The parties started conciliation of their respective
claims and counter claims in the most cordial
environment. The Claimant handed over the detail of
amount payable to him to the Respondent against the
work existing at site and duly measured by the local
Commissioner which was discussed at length and it
was concluded that the Respondent is broadly satisfied
with the report of the local Commissioner in the
corresponding amount of work existing at site except
slight minor variation due to computational mistakes
which was not objected by the Claimant.
5. The Respondent sought some time to verify the
detail of the further claims of the Claimant regarding
material and T &P of the Claimant lying at site with
most positive attitude and stated that he is ready to use
the same on payment basis.
6. Both the parties were hopeful that they would settle
their grievances against each other by way of
conciliation proceedings in the next one or two
meetings for which it was decided with the consent of
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
both the parties that the next meeting would be held on
27 /08/2022 at 1 1 :00 am. The Claimant would arrange
the venue and inform to all concerned in advance. The
expenses of the same shall be borne equally by both the
parties.”
8.
From reading of the procedural order it is evident that the
tribunal undertook conciliation on the request of the parties. In
conciliation proceedings it was recorded that the petitioner raised
objections regarding the report of the LC which were considered to be
minor in nature as both the parties agreed for an amicable settlement
of the principal amounts of their respective claims and counter-claims.
The proceedings recorded during the conciliation were relied while
adjudicating the claims in arbitration. The proceedings during
conciliation cannot be considered and relied upon in case the
arbitration of dispute is necessitated. The proceedings during
conciliation are different but when an issue is contested equal
opportunity is to be provided to both the parties to present their case.
The judgement of the Calcutta High Court in MFAR Constructions
(supra) does not advance the case of the respondent. The dispute is not
as to whether the tribunal could have attempted for conciliation but the
issue is that the contents of the proceedings of conciliation cannot be
relied upon while deciding the subject matter of arbitration and this
was not decided by the Calcutta High Court.
8.1
In case of an unsuccessful settlement through alternative dispute
resolution methods, the confidentiality of such proceedings shall be
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
kept alive and the insights of the proceedings shall not be brought to
the notice of the court. Reliance in this regard be made to the
following decisions of the Supreme Court:
8.2
In Moti Ram v. Ashok Kumar, (2011) 1 SCC 466, it was held:
“2. In this connection, we would like to state that
mediation proceedings are totally confidential
proceedings. This is unlike proceedings in court which
are conducted openly in the public gaze. If the
mediation succeeds, then the mediator should send the
agreement signed by both the parties to the court
without mentioning what transpired during the
mediation proceedings. If the mediation is
unsuccessful, then the mediator should only write one
sentence in his report and send it to the court stating
that the “mediation has been unsuccessful”. Beyond
that, the mediator should not write anything which was
discussed, proposed or done during the mediation
proceedings. This is because in mediation, very often,
offers, counter offers and proposals are made by the
parties but until and unless the parties reach to an
agreement signed by them, it will not amount to any
concluded contract. If the happenings in the mediation
proceedings are disclosed, it will destroy the
confidentiality of the mediation process.
3. We are compelled to observe this because the
mediators should know what kind of reports they
should send to the courts. The report sent in this Court
should not have mentioned the proposals made by the
parties, but should only have stated that the mediation
was unsuccessful.”
8.3
In Perry Kansagra v. Smriti Madan Kansagra, (2019)
20 SCC 753, it was held :
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
“27. We, thus, have line of cases dealing with
mediation/conciliation and other proceedings in
general and Rule 8 of the Rules dealing inter alia,
with custody issues which is in the nature of an
exception to the norms of confidentiality. It is true
that the process of mediation is founded on the
element of confidentiality. Qualitatively, mediation
or conciliation stands on a completely different
footing as against regular adjudicatory processes.
Instead of an adversarial stand in adjudicatory
proceedings, the idea of mediation is to resolve the
dispute at a level which is amicable rather than
adversarial. In the process, the parties may make
statements which they otherwise would not have
made while the matter was pending adjudication
before a court of law. Such statements which are
essentially made in order to see if there could be a
settlement, ought not to be used against the maker of
such statements in case at a later point the attempts
at mediation completely fail. If the statements are
allowed to be used at subsequent stages, the element
of confidence which is essential for healthy
mediation/conciliation would be completely lost.
The element of confidentiality and the assurance that
the statements would not be relied upon helps the
parties bury the hatchet and move towards resolution
of the disputes. The confidentiality is, thus, an
important element of mediation/conciliation.”
(emphasis supplied)
9.
It is pertinent to mention that document C-77 relied by learned
counsel for the respondent to substantiate the quantum of work, does
not enhance the case of the respondent as C-77 is a self-serving
document. There is no discussion in the award of the evidence
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
establishing that the Krishi Kalyan Cess was leviable at the relevant
time. Another facet is that the MOU records an amount of
Rs.11,82,55,494/- as having been paid to the respondent but this
amount was subject to reconciliation. The issue has not been dealt
with and the tribunal proceeded on the basis that there was no dispute
regarding payment of Rs.10,72,84,936/- made to the respondent. The
award
of
claim
no.1
without
reconciling
the
amount
of
Rs.11,82,55,494/- mentioned in MOU, granting of opportunity to the
petitioner to contest the LC report and being bereft of reasons, is
patently illegal and is liable to be set aside.
10.
The respondent made claim no.3 seeking refund of the amount
deducted for WCT and not deposited with the tax authorities. The
petitioner does not dispute the factum of deduction and non-deposit,
the only explanation given is that litigation is pending between the
petitioner and the tax authorities. There is nothing produced on record
to support that pendency of litigation was a ground for non-deposit of
the deducted amount. No case is made out for interference in awarding
of claim no.3.
11.
For claim no.4 the case set up by the respondent was that the
resources arranged on rent remained idle for failure of the petitioner to
supply the requisite material in terms of the contract. The tribunal
under Sections 55 and 73 of the Indian Contract Act, 1872 (for short
‘the Contract Act’) proceeded to deal with the claim. It was held that
the petitioner was in breach of the terms of the contract. The
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
contention of the petitioner that the idling of resources constituted a
part of the overhead was rejected. In absence of evidence of actual
loss or damage suffered by the respondent or the actual rent paid, the
tribunal erred in quantifying and awarding the damages. It would be
apposite to note that the tribunal recorded that the claim for payment
of rent of Rs.2.5 lakhs per month towards machinery was unsupported
by vouchers demonstrating rent had actually been paid. The tribunal
relying upon personal experience in the filed of construction,
quantified the expenses to be two percent of the contract value and
awarded Rs.1,04,29,203/- along with interest. The expertise of the
tribunal cannot substitute the onus to be discharged by the respondent
to prove the actual loss or damage suffered. For awarding of damages
under Section 73 of the Contract Act the twin conditions of the breach
of terms of the contract and consequential actual loss or damage
suffered are mandatory to be established. Reference in this regard be
made to Kailash Nath Associates v. DDA (2015) 4 SCC 136 and
Fateh Chand v. Balkishan Dass, 1963 SCC OnLine SC 49. The
award of claim no.4 is contrary to the provisions of the Contract Act
and the law laid down by the Supreme Court. The award of claim no.4
is patently illegal and liable to be set aside.
12.
Claim no.6 concerns damages towards additional overheads
occasioned due to the breach of contract by the petitioner. The tribunal
held that the claim made was based on the bare minimum requirement
of staff for execution of contract and is not unreasonable. The staff
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
deployment was found to be consistent with trade practise and the site
requirements. It is held that had the petitioner not committed the
breach, the respondent would have completed the work within the
stipulated period thereby not incurring the additional cost. There was
no evidence led by the respondent of additional overhead expenditure
incurred due to breach of contract. The tribunal relied upon personal
experience in the field and CPWD circular MAN-150 and 169 for
quantifying the overhead expenses at 7.5% of the contract value. At
the cost of repetition, the expertise of the tribunal cannot form the
basis for quantification of damages more so, when no evidence of the
expenses incurred was produced. Equally, the reliance placed by the
tribunal upon the trade practice of deployment of staff is unsupported
by evidence on record to establish the prevalence of the trade practice.
It would be relevant to note here that the CPWD circulars relied upon
by the tribunal were not confronted to the petitioner and is in violation
of Section 24(3) of the Act. The relevant portion of the award is
reproduced below:
“11.7.8 On the basis of my long experience in this field
the usage of the trade I have no hesitation that the total
expenditure to be incurred by the contractor in such
type of s building works the minimum expenses to be
incurred by the contractor towards overhead expenses
is 7.îqk of the contract value which also finds' supports
from the CPWD circular MAN-150 and 169.
Accordingly, I have no hesitation to decide that the
expenditure that had been incurred by the Claimant in
the present case for the entire contract period of 34
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
months. was Rs. 4,03,01,250/-or Rs.11,85,330/- per
month or say Rs. 11,85,000/- per month. The Claimant
in the said amount was also required to mitigate the
losses and therefore considering 25% towards
mitigation of losses the said' amount works out to
Rs.8,88,750/- Per month.”
13.
The award under claim no.6 of Rs.2,04,53,218/- alongwith
interest, subsequently corrected by the additional award dated
27.03.2023 to Rs.2,84,53,218/- alongwith interest was awarded on
sheer guess work, personal experience of the tribunal. The claim
awarded is in violation of Section 24(3) of the Act, against the
provisions of the Contract Act and against the decisions of the
Supreme Court in Kailash Nath Associates v. DDA (supra) and Fateh
Chand v. Balkishan Dass (supra) consequently is liable to be set
aside.
14.
The respondent raised claim no.8 pleading that the material at
site was wrongfully retained by the petitioner. The claim was allowed
relying upon the fact that the petitioner made a counter-claim for
parking, storing and guarding charges. The report of LC and the
personal visit of the tribunal to the site was relied to hold that
substantial material was lying at the site. The valuation of material by
the respondent unsupported by evidence was relied upon to award the
claim and a deduction of five percent was made from the claimed
amount. The acceptance of the report of the LC by the petitioner
during the conciliation proceedings could not have been treated as an
acceptance of the report for the purpose of arbitral adjudication. In
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
violation of Section 18 of the Act whereunder the parties are to be
treated equally and fair opportunity is to be provided to present the
case, no opportunity was provided to the petitioner to raise objections
to the report of the LC. The personal inspection by the tribunal of the
site is of no avail, as it neither establish the ownership of the material
lying on the site nor furnish any rational basis for determining the cost
of the material. The respondent failed to produce evidence to either to
prove the ownership or the value of the material lying on the site. The
award of claim no.8 is in absence of evidence and without basis is
patently illegal.
15.
The claim for loss due to non-completion of work consequent to
the breach of contract by the petitioner was the claim no.9.
16.
Before proceeding with the issue it would be fruitful to
reproduce the para of the judgement of the Supreme Court in Unibros
v. All India Radio 2023 SCC OnLine SC 1366 which held as under:
“18. Hudson's formula, while attained acceptability and is well
understood in trade, does not, however, apply in a vacuum.
Hudson's formula, as well as other methods used to calculate
claims for loss of off-site overheads and profit, do not directly
measure the contractor's exact costs. Instead, they provide an
estimate of the losses the contractor may have suffered. While
these formulae are helpful when needed, they alone cannot
prove the contractor's loss of profit. They are useful in assessing
losses, but only if the contractor has shown with evidence the
loss of profits and opportunities it suffered owing to the
prolongation.
19. The law, as it should stand thus, is that for claims related to
loss of profit, profitability or opportunities to succeed, one
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
would be required to establish the following conditions : first,
there was a delay in the completion of the contract; second,
such delay is not attributable to the claimant; third, the
claimant's status as an established contractor, handling
substantial projects; and fourth, credible evidence to
substantiate the claim of loss of profitability. On perusal of the
records, we are satisfied that the fourth condition, namely, the
evidence to substantiate the claim of loss of profitability
remains unfulfilled in the present case.”
(emphasis supplied)
17.
The legal position is that the party claiming loss due to breach
of contract is required to prove the breach; that the delay was not
attributable to the party claiming loss; that the party was engaged in
substantial projects; and lastly cogent evidence substantiating the
claim of loss.
18.
The respondent quantified the claim for loss under claim no.9
relying upon the Hudson formula. The Supreme Court in Unibros
(supra) held that applying the Hudson formula cannot dispense with
the requirement of proving the damages. In the case in hand the
needful was not done.
19.
The tribunal after holding the petitioner responsible for breach
of contract, compensated the respondent for the claim for loss made
under claim no.9 and once again relied upon personal experience and
trade usage for quantifying the damages at 7.5% of the balance
contract value. The relevant paragraphs of the award are reproduced
below:
“14.7.15 The law is very clear that the claim of loss of
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
profit on unexecuted work is payable to the contractor
if the employer commits breach of contract and do not
allow him to execute and complete the whole work
which happened in the present case. Accordingly, I
decide that the Claimant is entitled to this claim for the
loss of profit @7.5% of the balance contract value. The
rate being adopted by me is on the basis of my
experience and also trade usage.
14.7.16 The Claimant has worked out the amount of
his claim with Hudson formula as Rs.5,22,04,901/- and
then by considering the principle of mitigation of
losses he has received the claimed amount by 50% and
claims as sum of Rs.2,61,02,451/-. Although I am not
inclined to disagree with the formula adopted by the
Claimant but the at the same time, the duration
considered by him is not convincing on me.”
20.
The personal knowledge and expertise of the tribunal cannot be
the basis for awarding of the claim and it shall not discharge the onus
of the respondent to prove the claim for loss. The trade practice relied
upon was not proved. The claim awarded is patently illegal and is
liable to be set aside.
21.
The reliance of the respondent on the decision of State of West
Bengal v. M/s. S.K. Maji (supra) is misplaced. In that case, the
tribunal recorded reasons for declining the percentage of profit
claimed and for granting profit at a lower percentage, the approach
adopted was found to be plausible. The present case stand materially
on a different footing, the tribunal has relied upon personal experience
and unproven trade practise to award the claims.
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
22.
In view of the above discussion the petition is allowed, the
impugned award and the additional award are set aside. Pending
application is also disposed of.
AVNEESH JHINGAN, J
SEPTEMBER 10, 2026
‘JK’
Reportable: Yes
Signed By:CHANCHAL
O.M.P. (COMM) 293/2023
15:21:25
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review