IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 10th AUGUST, 2026
IN THE MATTER OF:
#
CNR No. DLHC010151542021
+
ARB. A. (COMM.) 18/2021 & I.A. 5100/2021
ASIAN HOTELS (NORTH) LTD
Through:
.....Petitioner
Mr. Rajiv Nayyar, Senior Advocate
with Mr. Sidhant Kumar, Ms.
Anushka Shah, Ms. Moomal Joshi,
Mr. Joginder Singh, Mr. Rajeshwar
Singh, Ms. Molly Agarwal and Mr.
Pratyush Srivastava, Advocates.
versus
HARMAN SINGH BAWA
Through:
.....Respondent
Mr. Sandeep P. Agarwal, Senior
Advocate with Mr. Rajesh Pathak,
Mr. Siddhant Nath, Mr. Bhavishya
Makhija, Mr. Amaan Khan, Mr
Rajesh Pathak, and Ms. Tanya
Chanda, Advocates.
#
CNR No. DLHC010166312021
+
ARB. A. (COMM.) 20/2021 & I.A. 5807/2021
ASIAN HOTELS (NORTH) LTD
Through:
.....Petitioner
Mr. Rajiv Nayyar, Senior Advocate
with Mr. Sidhant Kumar, Ms.
Anushka Shah, Ms. Moomal Joshi,
Mr. Joginder Singh, Mr. Rajeshwar
Singh, Ms. Molly Agarwal and Mr.
Pratyush Srivastava, Advocates.
versus
GURSHARAN SINGH BAWA
.....Respondent
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
Through:
Mr. Sandeep P. Agarwal, Senior
Advocate with Mr. Rajesh Pathak,
Mr. Siddhant Nath, Mr. Bhavishya
Makhija, Mr. Amaan Khan, Mr
Rajesh Pathak, and Ms. Tanya
Chanda, Advocates.
#
CNR No. DLHC010508022021
+
ARB. A. (COMM.) 22/2021 & I.A. 7950/2021, I.A. 2254/2022
ASIAN HOTELS (NORTH) LTD
Through:
.....Petitioner
Mr. Rajiv Nayyar, Senior Advocate
with Mr. Sidhant Kumar, Ms.
Anushka Shah, Ms. Moomal Joshi,
Mr. Joginder Singh, Mr. Rajeshwar
Singh, Ms. Molly Agarwal and Mr.
Pratyush Srivastava, Advocates.
versus
RAJWANT SINGH BAWA
Through:
.....Respondent
Mr. Sandeep P. Agarwal, Senior
Advocate with Mr. Rajesh Pathak,
Mr. Siddhant Nath, Mr. Bhavishya
Makhija, Mr. Amaan Khan, Mr
Rajesh Pathak, and Ms. Tanya
Chanda, Advocates.
#
CNR No. DLHC010314072022
+
O.M.P. (COMM) 344/2022 & CCP(O) 32/2024, I.A. 13212/2022,
I.A. 42247/2024
ASIAN HOTELS (NORTH) LTD
Through:
.....Petitioner
Mr. Rajiv Nayyar, Senior Advocate
with Mr. Sidhant Kumar, Ms.
Anushka Shah, Ms. Moomal Joshi,
Mr. Joginder Singh, Mr. Rajeshwar
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
Singh, Ms. Molly Agarwal and Mr.
Pratyush Srivastava, Advocates.
versus
GURSHARAN SINGH BAWA
.....Respondent
Through: Mr. Sandeep P. Agarwal, Senior
Advocate with Mr. Rajesh Pathak,
Mr. Siddhant Nath, Mr. Bhavishya
Makhija, Mr. Amaan Khan, Mr
Rajesh Pathak, and Ms. Tanya
Chanda, Advocates.
#
CNR No. DLHC010314082022
+
O.M.P. (COMM) 345/2022 & CCP(O) 54/2024, I.A. 13216/2022
ASIAN HOTELS (NORTH) LTD
Through:
.....Petitioner
Mr. Rajiv Nayyar, Senior Advocate
with Mr. Sidhant Kumar, Ms.
Anushka Shah, Ms. Moomal Joshi,
Mr. Joginder Singh, Mr. Rajeshwar
Singh, Ms. Molly Agarwal and Mr.
Pratyush Srivastava, Advocates.
versus
HARMAN SINGH BAWA
Through:
.....Respondent
Mr. Sandeep P. Agarwal, Senior
Advocate with Mr. Rajesh Pathak,
Mr. Siddhant Nath, Mr. Bhavishya
Makhija, Mr. Amaan Khan, Mr
Rajesh Pathak, and Ms. Tanya
Chanda, Advocates.
#
CNR No. DLHC010314092022
+
O.M.P. (COMM) 346/2022 & CCP(O) 31/2024, I.A. 13220/2022
ASIAN HOTELS (NORTH) LTD
.....Petitioner
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
Through:
Mr. Rajiv Nayyar, Senior Advocate
with Mr. Sidhant Kumar, Ms.
Anushka Shah, Ms. Moomal Joshi,
Mr. Joginder Singh, Mr. Rajeshwar
Singh, Ms. Molly Agarwal and Mr.
Pratyush Srivastava, Advocates.
versus
RAJWANT SINGH BAWA
Through:
.....Respondent
Mr. Sandeep P. Agarwal, Senior
Advocate with Mr. Rajesh Pathak,
Mr. Siddhant Nath, Mr. Bhavishya
Makhija, Mr. Amaan Khan, Mr
Rajesh Pathak, and Ms. Tanya
Chanda, Advocates.
#
CNR No. DLHC010247132022
+
OMP (CONT.) 2/2022
ASIAN HOTELS (NORTH) LIMITED
Through:
.....Decree Holder
Mr. Rajiv Nayyar, Senior Advocate
with Mr. Sidhant Kumar, Ms.
Anushka Shah, Ms. Moomal Joshi,
Mr. Joginder Singh, Mr. Rajeshwar
Singh, Ms. Molly Agarwal and Mr.
Pratyush Srivastava, Advocates.
versus
HARMAN SINGH BAWA
Through:
#
.....Judgement Debtor
Mr. Sandeep P. Agarwal, Senior
Advocate with Mr. Rajesh Pathak,
Mr. Siddhant Nath, Mr. Bhavishya
Makhija, Mr. Amaan Khan, Mr
Rajesh Pathak, and Ms. Tanya
Chanda, Advocates.
CNR No. DLHC010363432022
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
+
OMP (ENF.) (COMM.) 187/2022 & EX.APPL.(OS) 3495/2022,
EX.APPL.(OS)
3774/2022,
EX.APPL.(OS)
1558/2023,
EX.APPL.(OS) 63/2025, EX.APPL.(OS) 600/2025
RAJWANT SINGH BAWA
.....Decree Holder
Through:
Mr. Sandeep P. Agarwal, Senior
Advocate with Mr. Rajesh Pathak,
Mr. Siddhant Nath and Ms. Tanya
Chanda, Advocates.
versus
ASIAN HOTELS (NORTH) LTD
.....Judgement Debtor
Through: Mr. Rajiv Nayyar, Senior Advocate
with Mr. Sidhant Kumar, Ms.
Anushka Shah, Ms. Moomal Joshi,
Mr. Joginder Singh, Mr. Rajeshwar
Singh, Ms. Molly Agarwal and Mr.
Pratyush Srivastava, Advocates.
#
CNR No. DLHC010363442022
+
OMP (ENF.) (COMM.) 188/2022 & EX.APPL.(OS) 3497/2022,
EX.APPL.(OS) 696/2023, EX.APPL.(OS) 1559/2023, EX.APPL.(OS)
1101/2024, EX.APPL.(OS) 64/2025, EX.APPL.(OS) 601/2025
GURSHARAN SINGH BAWA
Through:
.....Decree Holder
Mr. Sandeep P. Agarwal, Senior
Advocate with Mr. Rajesh Pathak,
Mr. Siddhant Nath and Ms. Tanya
Chanda, Advocates.
versus
ASIAN HOTELS (NORTH) LTD
.....Judgement Debtor
Through: Mr. Rajiv Nayyar, Senior Advocate
with Mr. Sidhant Kumar, Ms.
Anushka Shah, Ms. Moomal Joshi,
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
Mr. Joginder Singh, Mr. Rajeshwar
Singh, Ms. Molly Agarwal and Mr.
Pratyush Srivastava, Advocates.
#
CNR No. DLHC010363892022
+
OMP (ENF.) (COMM.) 189/2022 & EX.APPL.(OS) 3499/2022,
EX.APPL.(OS) 1563/2023, EX.APPL.(OS) 65/2025, EX.APPL.(OS)
609/2025
HARMAN SINGH BAWA
.....Decree Holder
Through:
Mr. Sandeep P. Agarwal, Senior
Advocate with Mr. Rajesh Pathak,
Mr. Siddhant Nath and Ms. Tanya
Chanda, Advocates.
versus
ASIAN HOTELS (NORTH) LTD
.....Judgement Debtor
Through: Mr. Rajiv Nayyar, Senior Advocate
with Mr. Sidhant Kumar, Ms.
Anushka Shah, Ms. Moomal Joshi,
Mr. Joginder Singh, Mr. Rajeshwar
Singh, Ms. Molly Agarwal and Mr.
Pratyush Srivastava, Advocates.
CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
JUDGMENT
1.
By way of the present Judgment, this Court shall dispose of the
captioned Petitions under Section 34 as well as Appeals under Section 37 of
the Arbitration and Conciliation, 1996 [“Arbitration Act”].
2.
The party aggrieved by the various orders of the Arbitral Tribunal in
all the captioned matters under Sections 34 and 37 of the Arbitration Act is
Asian Hotels (North) Ltd. It is agreed that other than the fact that the
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
amounts and the apartment numbers involved in the contracts in question are
different, the relevant clauses under which disputes have arisen as well as
the orders passed by the Arbitral Tribunal are common and have the same
effect. As such, with the consent of all the parties represented through their
counsels, this Court shall examine the pleadings and documents as filed
under the Petition being O.M.P. (COMM) 344 of 2022, which has been filed
under Section 34 of the Arbitration Act against the Final Award dated
20.05.2022 passed by the Arbitral Tribunal in the proceedings titled „M/s
Gursharan Singh Bawa v. Asian Hotels (North) Limited‟ [“Impugned
Award”].
3.
A brief factual background of the dispute between the parties herein,
as well as the procedural history, which is borne out from the material on
record, is stated as under:
(i)
The Petitioner granted to the Respondent leasehold rights for a
period of 99 years, with a provision of automatic renewal after 99
years, in relation to the Apartment No. 3001, 3 rd Floor situated at
Block A, New Tower, Hotel Hyatt Regency, Bhikaji Cama Place,
New Delhi [“the Premises”], by way of a registered Lease Deed
dt. 11.12.2018, which shall be referred to as the 1st Lease Deed.
The Hotel Hyatt Regency, Bhikaji Cama Place, New Delhi, shall
be referred to as the Hotel.
(ii) In accordance with the terms of the 1st Lease Deed, the
Respondent paid a one-time rent amounting to Rs. 6,09,94,000/-,
along with a sum of Rs. 2,77,200/-, equivalent to 6 months
interest-free maintenance charges to the Petitioner.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
(iii) Shortly after the 1st Lease Deed was executed, the Respondent
executed a registered Lease Deed dated 31.12.2018 in favour of
the Petitioner, whereby the Premises was leased back to the
Petitioner w.e.f. 01.01.2019, for an initial period of fifteen years in
consideration of rent of Rs. 9,21,000/- per month with the
stipulation for increase of rent @15% on the rent payable on
expiry of each period of 36 months of the lease terms. This shall
be referred to as the 2nd Lease Deed. It is this 2nd Lease Deed
which is the focal point of the dispute between the parties herein.
(iv) Under the 2nd Lease Deed, two lock-in periods were provided
under Clause 12, one for the Respondent, extending to 15 years
and the other for the Petitioner, extending to 84 months.
(v) In accordance with the terms of the 2nd Lease Deed, the Petitioner
paid a sum of Rs. 55,26,000/- to the Respondent by way of an
interest-free security deposit, equivalent to 6 months‟ rent.
(vi) Not long after the aforesaid Lease Deeds were executed between
the parties, the COVID-19 pandemic struck the country, due to
which a nationwide lockdown was imposed by the Government of
India on 23.03.2020. However, shortly thereafter, vide a
Notification dated 30.05.2020 published by the Ministry of Home
Affairs, the Government of India permitted activities pertaining to
hotels, restaurants and other hospitality activities to resume from
08.06.2020.
(vii) Despite of the Notification dated 30.05.2020 published by the
Ministry of Home Affairs, the Petitioner, in the midst of the lockin period, sent a Termination Notice dated 27.06.2020 to the
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
Respondent, thereby invoking Clause 15.2 of the 2nd Lease Deed
and
terminating
the
2nd
Lease
Deed
w.e.f.
25.03.2020
[“Termination Notice”].
(viii)As per the Petitioner, it was constrained to send the Termination
Notice, as it was prevented from utilizing the Premises due to the
restrictive governmental regulations suspending the operation of
the Hotel, in light of the COVID-19 pandemic. For this reason, the
Petitioner claimed that it was not responsible for any
consequences and/or liabilities/obligations under the 2nd Lease
Deed w.e.f. 25.03.2020. By way of this Termination Notice, the
Petitioner also called upon the Respondent to take possession of
the Premises and refund the security deposit.
(ix) The Respondent sent a Letter dated 14.07.2020, asking the
Petitioner to recall its Termination Notice and continue payment
of the agreed lease rent and applicable taxes to the Respondent
under and as per the 2nd Lease Deed. It was the Respondent‟s case
that the Petitioner had no right to terminate the 2nd Lease Deed
under Clause 15.2 in the duration of the lock-in period.
(x) The Petitioner responded to the Respondent‟s Letter dated
14.07.2020, stating that due to the restrictive orders of the
Government of India, it had become financially impossible for the
Petitioner to comply with the terms of the 2nd Lease Deed. The
Petitioner further stated that it had vacated the Premises and was
not liable to pay the lease rental w.e.f. 26.03.2020 until the date of
termination of the 2nd Lease Deed, due to the complete lockdown
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
and stoppage of hotel operations brought on in light of the
COVID-19 pandemic.
(xi) Aggrieved by the actions of the Petitioner, the Respondent
invoked arbitration under and as per Clause 15.4 of the 2 nd Lease
Deed vide a Letter dated 23.07.2020.
(xii) Despite receipt of the Letter dated 23.07.2020, the Petitioner sent
a Letter dated 12.08.2020 to the Respondent, enclosing the set of
keys to the Premises and stating that the possession of the
Premises have been fully handed over to the Respondent.
(xiii)Since no proper response was received by the Respondent
regarding its invocation of arbitration, the Respondent approached
this Court by way of Petitions under Section 9 as well as Section
11 of the Arbitration Act, seeking interim protection as well as
appointment of an arbitrator to adjudicate upon the disputes
between the parties. This Court, vide Order dated 23.11.2020,
disposed of these Petitions under Section 9 and 11 of the
Arbitration Act, by constituting the Arbitral Tribunal and directing
the Arbitral Tribunal to treat the Respondent‟s Petition under
Section 9 as one under Section 17 of the Arbitration Act.
(xiv) After the Respondent filed its Statement of Claims on 01.03.2021,
the Arbitral Tribunal passed an Order dated 05.03.2021, disposing
of the Application under Section 17 of the Arbitration Act, by
observing that the Respondent had successfully made out a case
under Section 17(1)(ii)(b) of the Arbitration Act, by establishing
inter alia that the balance of convenience lay in favour of grant of
interim protection to the amount fixed under Clause 12.2 of the 2nd
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
Lease Deed. The Arbitral Tribunal also observed that the
Respondent successfully demonstrated the possibility of the
Premises being unavailable at the culmination of the proceedings,
in the event an award is passed in favour of the Petitioner. Having
observed as such, the Arbitral Tribunal granted the following
reliefs vide its Order dated 05.03.2021:
(a) The Petitioner must always maintain an amount of Rs.
9,22,13,989/- along with applicable taxes in its bank
account till the disposal of the arbitration proceedings;
(b) The Respondent shall pay the maintenance charges for
availing services from the Petitioner; and
(c) The Respondent shall maintain an amount of Rs.
58,67,271/- in its bank account till the disposal of the
arbitration proceedings, towards the Security Deposit
held by it.
(xv) The above Order dated 05.03.2021 passed by the Arbitral Tribunal
was assailed by the Petitioner by way of an appeal filed before this
Court under Section 37(2)(b) of the Arbitration Act, being ARB.
A. (COMM.) No. 20 of 2021, which is one of the matters being
disposed of by way of the instant Judgment. Other similar appeals
against this Order dated 05.03.2021 have been filed vide ARB. A.
(COMM.) 18 of 2021 and 22 of 2021.
(xvi) It is pertinent to note that the appeal bearing ARB. A. (COMM.)
22 of 2021 filed by the Petitioner in the dispute between the
Petitioner and one Rajwant Singh Bawa, was disposed of by this
Court vide an Order dated 19.05.2021, modifying the directions of
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
the Arbitral Tribunal as contained in the Order dated 05.03.2021,
to the following extent:
(a) The Petitioner shall deposit the up-to-date arrears of
monthly rent and applicable tax, reckoned with effect
from March, 2020, with the Registrar General of this
Court by way of a demand draft covering the said
amount, which shall be deposited in an interest bearing
fixed deposit, to abide by further directions to be passed
by the Arbitral Tribunal.
(b) The Petitioner shall also deposit, monthly, with the
Registrar General of this Court, the amount of Rs.
10,28,000/- towards rent payable in respect of the
Premises. This amount would also be deposited in an
interest bearing fixed deposit and the Petitioner would
continue to abide by the further directions to be passed
by Arbitral Tribunal.
(xvii) The Petitioner thereafter filed its Statement of Defence before the
learned Sole Arbitrator on 02.04.2021, while its Counter-Claims
came to be filed on 12.06.2021.
(xviii) In the interregnum, the Respondent filed an application before the
Arbitral Tribunal, alleging non-compliance of the Order dated
05.03.2021 on part of the Petitioner, and requesting initiation of
contempt proceedings against the Petitioner. The Arbitral Tribunal,
upon receipt of this application, observed that the Order dated
05.03.2021 was not being complied with by the Petitioner, which
may have the effect of rendering the arbitration proceedings futile.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
For this reason, the Arbitral Tribunal made a representation vide a
Letter dated 02.07.2021 to this Court under Section 27(5) of the
Arbitration Act, for taking appropriate action(s) against the
Petitioner‟s default in complying with the Order dated 05.03.2021.
This culminated into the petition being O.M.P. (CONT.) 2 of 2022,
vide Order dated 31.05.2022 passed by this Court in the Appeals
filed by the Petitioner under Section 37 of the Arbitration Act.
(xix)
After the completion of pleadings and filing of the affidavits of
admission/denial, the Arbitral Tribunal heard the final
arguments advanced on behalf of the parties and reserved
orders on 12.11.2021. Ultimately, the Impugned Final Award
dated came to be passed by the Arbitral Tribunal on 20.05.2022.
4.
A tabular summary of the findings of the Arbitral Tribunal in the
Impugned Award on the claims and counter-claims is given below:
S.No. Claims filed by the Respondent
before the Arbitral Tribunal
1.
Restoration of the 2nd Lease Deed
with all consequential benefits
2.
3.
4.
Decision of the Arbitral
Tribunal
Award in the sum of Rs.
8,50,62,276/- along with
interest @7% p.a. w.e.f.
25.03.2020 until realisation
in favor of the Respondent
Damages towards mental tension, Rejected for lack of
agony and harassment
evidence
Litigation Expenses including costs Award in the sum of Rs.
on the present arbitration
5,00,000/- in favor of the
Respondent
Pendente lite and future interest
Included in the sum
awarded under Claim No. 1
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
S.No. Counter-Claims filed by the Petitioner
before the Arbitral Tribunal
1.
Rs. 55,66,000/- towards Refund of
Interest Free Security Deposit furnished
by the Petitioner under the 2nd Lease
Deed
2.
Specific Performance Clause 6.6 of the
1st Lease Deed dated 11.12.2018 and
execute the Maintenance Agreement qua
the Premises
3.
4.
5.
6.
7.
Rs. 12,94,524 towards Deposit of
Interest Free Maintenance Deposit with
the Petitioner Claimant under the 1st
Lease Deed dated 11.12.2018 read with
Maintenance Agreement
Rs. 72,41,904/- towards Arrears of
maintenance charges from 01.04.2020 to
31.03.2022 under the 1st Lease Deed
dated 11.12.2018 read with Maintenance
Agreement
Direction to the Respondent to continue
paying Maintenance Charges under the
1st Lease Deed dated 11.12.2018 read
with Maintenance Agreement
Decision
of
the
Arbitral Tribunal
Rejected
Held to be outside the
purview for having
been based on Clause
6 of the 1st Lease
Deed – Rejected.
Held to be outside the
purview for having
been based on Clause
6 of the 1st Lease
Deed – Rejected.
Held to be outside the
purview for having
been based on Clause
6 of the 1st Lease
Deed – Rejected.
Held to be outside the
purview for having
been based on Clause
6 of the 1st Lease
Deed – Rejected.
Held to be outside the
purview for having
been based on Clause
6 of the 1st Lease
Deed – Rejected.
Rs. 2,50,000/- towards Deposit of
Interest Free Refundable Maintenance
Security Deposit-For utility Charges with
the Petitioner under the 1stLease Deed
dated 11.12.2018 read with Maintenance
Agreement
Rs. 2,83,666/- towards Reimbursement Award in the sum of
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
of Property Tax for the period upto 20192020 paid by the Petitioner on behalf of
Respondent under the 2nd Lease Deed
dated 31.12.2018
8.
9.
5.
Rs. 4,55,112/- towards Payment of
Property Tax under the 1stLease Deed
dated 11.12.2018 for FY 2020-2021 and
FY 2021-2022
Rs. 1,04,672/- towards Payment of
amount towards Sinking Funds under the
First Lease Deed dated 11.12.2018
10.
Rs. 83,048/- towards Reimbursement of
insurance premium charges towards the
Insurance Policy Cover on pro rata basis
under the 1stLease Deed dated
11.12.2018
11.
Pre-arbitration, pendente lite and future
interest as well as legal costs and
expenses incurred by Petitioner in the
preparation and conduct of these
arbitration proceedings.
Rs. 2,83,666/- along
with simple interest
@7% p.a. w.e.f.
01.04.2019
till
realization in favor
of the Petitioner
Award in the sum of
Rs. 4,55,112/- in
favor
of
the
Petitioner
Held to be outside the
purview for having
been based on Clause
6 of the 1st Lease
Deed – Rejected.
Award in the sum of
Rs. 83,048/- along
with simple interest
@7% p.a. w.e.f.
12.06.2021
till
realization
Rejected.
Before this Court, the Petitioner assails the Impugned Award to the
extent that it allows the claims of the Respondent and rejected the counterclaims of the Petitioner.
6.
Before delving into the rival contentions of the parties advanced
before this Court, a reference to the relevant provisions under the Contract,
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
i.e., the 2nd Lease Deed, is pertinent to made. The same are being reproduced
to read as under:
“12. TERMINATION AND ITS CONSEQUENCES
12.1 The Lessor shall not have the rights to terminate this
Deed during the initial term of the Deed i.e. for 15 (fifteen)
years except in case of violation and breach of the terms of
this Deed by the Lessee which has not been cured by the
Lessee within a period of 30 days of receipt of notice from
the Lessor in this regard. In case, the breach/ violation is
not cured within such 30 days, the Lessor shall be entitled
to terminate the lease by giving notice of 30 days in
writing.
12.2 The Lessee shall not have the rights to terminate this
Deed during an initial 84 (Eighty Four) months ("Lockin Period") of the Deed. However/ the Lessee can
terminate this Deed by giving 6 (six) month advance
notice of Termination of this Deed to Lessor any time
after the expiry of 84 (Eighty Four) months of Lock-in
Period. The termination prior to initial 84 months of this
Deed can only be done by Lessee in case of violation and
breach of the following critical terms of this Deed by the
Lessor which has not been cured by the Lessor within a
period of 30 days of receipt of notice from the Lessee in
this regard. In case, the breach/violation is not cured
within such 30 days, the Lessee shall be entitled to
terminate the Lease by giving notice of 30 days in writing.
The Lessee shall not be liable to pay any rent or any
amount to the Lessor upon expiry of the 30 days' notice
period and shall handover the Sad Property to the Lessor,
.normal wear and tear excepted.
The said critical terms of the Deed are:
(a) Non-compliances, breach or non-performance of
the terms and conditions, covenants and warranties as
offered by the Lessor under this Deed, which are not
rectified or made good by the Lessor within 30 days of
written notice by the Lessee;
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
(b) Non-compliances, breach or non-performance of
the terms and conditions, covenants and warranties as
offered by the Lessor under this Deed of a nature due to
which the Lessee is unable to have unhindered,
uninterrupted, peaceful and vacant use, possession,
enjoyment and the entitlement of the leasehold rights of the
Demised Premises and if such defaults are not rectified or
made good by the Lessor within 30 days of written notice
by the Lessee;
Further if the Lessee terminates the Lease during the
Lock-in Period due to any reason whatsoever other than
due to the breach/violation of the critical terms mentioned
above by the Lessor not cured within the notice period, the
Lessee shall be fully liable to pay the Rent and applicable
taxes thereon for the entire unexpired period of the Lock-in
Period then remaining.
Further if the Lease gets terminated within the Lockin Period by the Lessor due to violation/breach by the
Lessee that is not cured by the Lessee within a period of 60
days of receipt of notice from the Lessor in this regard,
then without prejudice the Lessor's rights to claim
outstanding dues, claims, damages, interest if any, the
Lessee shall also be liable to pay Rent for the entire
unexpired period of the Lock-in Period then remaining.
15.1 Conformity - The Parties hereby confirms that they
have carefully read the terms and conditions of Lease of
the said Property as set forth in detail in this Deed and
understood their respective obligations and liabilities set
forth herein and the parties undertakes to abide by all the
terms and conditions of the same. The Lessor further
assures the Lessee that it has taken proper advice of
competent legal counsel / advocates interpreting the
provisions of the Deed before execution of the same.
15.2 Force Majeure – In the event the Said Property or
any part thereof is destroyed or damaged due to a Force
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
Majeure event, not caused by any wilful act or negligence
of
the
Lessee
thereby
rendering
it
impossible/unsafe/unfit/non-feasible to operate out of the
Said Property then, the Lessee may, temporarily vacate the
Said Property, as may be required to enable the Lessor to
carry out repairs to restore the Said Property to as good
condition as it was in on the Lease Commencement Date.
In such an event, all payments specified under this Deed
for this Said Property or portion thereof shall abate till the
time the Said Property is repaired and restored to as good
condition as it was in at the time of handover of the Said
Property for interior fit-outs.
The Lessee shall not be held responsible for any
consequences or liabilities under this Deed if it is
prevented in performing its obligations under the terms of
this Deed by reasons of any restrictive governmental laws
or regulations, riots, insurrection, war terrorist action
strike Public demonstrations rallies acts of God, etc.”
(Emphasis Supplied)
7.
Learned Senior Counsel appearing the Petitioner has advanced the
following arguments while praying for the partial setting aside of the
Impugned Award on the ground that it is perverse, based on „no evidence‟,
violates the fundamental policy of India, principles of natural justice and is
contrary to the principles of natural justice:
(i)
The Impugned Award is contrary to Sections 73 and 74 of the
Indian Contract Act, 1872 [“ICA”], for the reasons that Clause
12.2 of the 2nd Lease Deed is not a genuine pre-estimate of
damages. Accordingly, the reliance by the Arbitral Tribunal on the
judgment of the Apex Court in Chunilal V. Mehta and Sons Ltd.,
vs. Century Spinning and Manufacturing Company Ltd., (1962)
Supp 3 SCR 549, is erroneous, as unlike the said case, Clause
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
12.2 of the 2nd Lease Deed, does not contain words like
“compensation” or “liquidated damages”.
(ii) Without prejudice to the foregoing submission, it is further
submitted that the Impugned Award violates Section 73 and 74 of
the ICA, since the Respondent did not provided any pleading,
proof or quantification of damages. Rather, at Paragraphs 28 and
29 of its Statement of Claims, the Respondent itself claimed that
Sections 73 and 74 have no applicability to the present case.
(iii) The Impugned Award is contrary to the law laid down by the Apex
Court in Kailash Nath Associates v. DDA, (2015) 4 SCC 136,
which requires pleading and proof of damages, even where there
is a genuine pre-estimation of damages in accordance with Section
73 of ICA.
(iv) It is submitted that contrary to the Respondent‟s case, it was very
much possible to prove damages in the present case, since there
was no restriction cast on the Respondent on the use of the
Premises, barring that under Clause 6 of the 2nd Lease Deed,
which specifies that the Respondent/Lessor shall not be entitled to
use the club facility in the Hotel. Rather, Clause 9 of the 1st Lease
Deed specifically empowers the Respondent to use the Premises
for any purpose permitted by law.
(v) The Impugned Award results in an unjust enrichment of the
Respondent, who has the benefit of possession of the Premises as
well as rent from 26.03.2020 till 01.01.2026. This is contradictory
to the judgments of the Apex Court in Maula Bux v. Union of
India, (1969) 2 SCC 554 and Fateh Chand v. Balkishan Dass, AIR
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
1963 SC 1405, which both dictate that a party cannot retain the
benefit while also recovering full contractual sum, as if no benefit
had reverted.
(vi) The Arbitral Tribunal overlooked Clause 9 of the 2nd Lease Deed,
which obliges the parties thereto to comply with the terms of the
1st Lease Deed.
(vii) The Arbitral Tribunal did not consider that there was no subsisting
obligation under Clause 10 of the 2nd Lease Deed, as the 2nd Lease
Deed stood terminated by way of the Termination Letter, and the
Respondent‟s plea for restoration was rejected by the Arbitral
Tribunal.
(viii)In line with the Judgment of the Apex Court in Renusagar Power
Co. Ltd. v. General Electric Co. (1984) 4 SCC 679 and Salter
India (P) Ltd. v. Rakesh Nayyar, 2009 SCC OnLine Del 3049,
Clause 15.4 of the 2nd Lease Deed, which is the arbitration clause,
has to be considered in the widest amplitude and would therefore
extend to all the counter-claims arising under the 1st Lease Deed
as well.
8.
Per contra, learned Counsel for the Respondent has opposed the
instant Petitions inter alia on the following grounds:
(i)
The objections raised by the Petitioner do not fall within the
permissible scope of interference by a court under Section 34 of
the Arbitration Act. Reliance is placed on the Judgments of the
Apex Court in MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC 163
and Delhi Airport Metro Express (P) Ltd. v. DMRC, (2022) 1
SCC 131.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
(ii) The Respondent was not required to prove any damage in the
instant case, as the Petitioner, under and as per Clause 12.2 of the
2nd Lease Deed, had already agreed for payment of certain
specified amount in case of termination of the lease during the
lock-in period.
(iii) The award of amounts by the Arbitral Tribunal for the unexpired
lock-in period is based on the settled principle that if the parties
had already agreed for a particular sum as a consequence of the
breach of a contract, there is no further need or legal requirement
on part of the adversely affected party to prove any damages. In
any event, the fact as to whether damages were proved or not, is
not a valid ground for interference by this Court under Section 34
of the Arbitration Act.
(iv) The Arbitral Tribunal has specifically distinguished the Judgment
of the Apex Court in Kailash Nath (Supra) from the facts of the
present case, rendering a reasonable and plausible view. As such,
the question as to whether or not the Arbitral Tribunal‟s
interpretation of the said judgment is correct, cannot be delved
upon by this Court at the stage of proceedings under Section 34 of
the Arbitration Act.
(v) The Petitioner‟s argument that there was no restriction on usage of
the Premises by the Respondent is unfounded, as the Premises
forms an integral part of the Petitioner‟s Hotel and Respondent
cannot use the same without the pleasure and permission of the
Petitioner.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
(vi) While the Arbitral Tribunal has harmoniously interpreted Clauses
15.2 and 12.2 of the 2nd Lease Deed, it is the Petitioner who has
selectively interpreted Clause 15.2, while ignoring the effect of
Clause 12.2 of the 2nd Lease Deed and unjustly taking refuge to
the temporary government-imposed restrictions to terminate the
lease deed during the COVID-19 pandemic.
(vii) Since it was the allegation of the Petitioner that the Respondent is
not entitled to prove any damages, onus was on the Petitioner
itself to prove this stance. Reliance, in this regard, is placed on the
Judgment of the Apex Court in Construction and Design Services
vs. Delhi Development Authority, (2015) 14 SCC 263 and Oil and
Natural Gas Corporation Ltd. vs. Saw Pipes Ltd., (2003) 5 SCC
705.
9.
Heard the learned Counsels for the parties and perused the material on
record.
10.
Before delving into the merits of the case and the rival contentions of
the parties, it is crucial for this Court to remind itself of the boundaries
within which it can exercise the power under Section 34 of the Arbitration
Act. In the present case, objection to the Impugned Award is that it is
perverse, based on no-evidence and violates the fundamental policy of
Indian laws. Reference is thus made to the Judgment of the Apex Court in
OPG Power Generation (P) Ltd. v. Enexio Power Cooling Solutions (India)
(P) Ltd., (2025) 2 SCC 417, which discusses the term „in contravention with
the fundamental policy of Indian law‟ as under:
―In contravention with the fundamental policy of Indian
law
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
51. As discussed above, till the 2015 Amendment the
expression ―in contravention with the fundamental policy of
Indian law‖ was not found in the 1996 Act. Yet,
in Renusagar [Renusagar Power Co. Ltd. v. General
Electric Co., 1994 Supp (1) SCC 644] , in the context of
enforcement of a foreign award, while construing the
phrase ―contrary to the public policy‖, this Court held that
for a foreign award to be contrary to public policy mere
contravention of law would not be enough rather it should
be contrary to:
(a) the fundamental policy of Indian law; and/or
(b) the interest of India; and/or
(c) justice or morality.
55. The legal position which emerges from the aforesaid
discussion is that after ―the 2015 Amendments‖ in Section
34(2)(b)(ii) and Section 48(2)(b) of the 1996 Act, the phrase
―in conflict with the public policy of India‖ must be
accorded a restricted meaning in terms of Explanation 1.
The expression ―in contravention with the fundamental
policy of Indian law‖ by use of the word ―fundamental‖
before the phrase ―policy of Indian law‖ makes the
expression narrower in its application than the phrase ―in
contravention with the policy of Indian law‖, which means
mere contravention of law is not enough to make an award
vulnerable. To bring the contravention within the fold of
fundamental policy of Indian law, the award must
contravene all or any of such fundamental principles that
provide a basis for administration of justice and
enforcement of law in this country.
56. Without intending to exhaustively enumerate instances
of such contravention, by way of illustration, it could be
said that:
(a) violation of the principles of natural justice;
(b) disregarding orders of superior courts in India or
the binding
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
effect of the judgment of a superior court; and
(c) violating law of India linked to public good or
public interest, are considered contravention of the
fundamental policy of Indian law.
However, while assessing whether there has been a
contravention of the fundamental policy of Indian law, the
extent of judicial scrutiny must not exceed the limit as set
out in Explanation 2 to Section 34(2)(b)(ii).‖
11.
Perversity as a ground challenge has also be discussed by the Apex
Court in OPG Power Generation (Supra), as follows:
―Perversity as a ground of challenge
69. Perversity as a ground for setting aside an arbitral
award was recognised in Western Geco [ONGC
Ltd. v. Western Geco International Ltd., (2014) 9 SCC
263 : (2014) 5 SCC (Civ) 12] . Therein it was observed
that an arbitral decision must not be perverse or so
irrational that no reasonable person would have arrived
at the same. It was observed that if an award is
perverse, it would be against the public policy of India.
70. In Associate Builders [Associate Builders v. DDA,
(2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] certain tests
were laid down to determine whether a decision of an
Arbitral Tribunal could be considered perverse. In this
context, it was observed that where:
(i) a finding is based on no evidence; or
(ii) an Arbitral Tribunal takes into account
something irrelevant to the decision which it arrives
at; or
(iii) ignores vital evidence in arriving at its decision,
such decision would necessarily be perverse.
However, by way of a note of caution, it was observed
that when a court applies these tests it does not act as
a court of appeal and, consequently, errors of fact
cannot be corrected. Though, a possible view by the
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
arbitrator on facts has necessarily to pass muster as
the arbitrator is the ultimate master of the quantity and
quality of evidence to be relied upon. It was also
observed that an award based on little evidence or on
evidence which does not measure up in quality to a
trained legal mind would not be held to be invalid on
that score.
71. In Ssangyong [Ssangyong Engg. & Construction Co.
Ltd. v. NHAI, (2019) 15 SCC 131 : (2020) 2 SCC (Civ)
213] , which dealt with the legal position post the 2015
Amendment in Section 34 of the 1996 Act, it was observed
that a decision which is perverse, while no longer being a
ground for challenge under ―public policy of India‖,
would certainly amount to a patent illegality appearing
on the face of the award. It was pointed out that an award
based on no evidence, or which ignores vital evidence,
would be perverse and thus patently illegal. It was also
observed that a finding based on documents taken behind
the back of the parties by the arbitrator would also
qualify as a decision based on no evidence inasmuch as
such decision is not based on evidence led by the parties,
and therefore, would also have to be characterised as
perverse [ See Ssangyong Engg. case, (2019) 15 SCC
131, para 41 : (2020) 2 SCC (Civ) 213] .
72. The tests laid down in Associate Builders [Associate
Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ)
204]
to
determine
perversity
were
followed
in Ssangyong [Ssangyong Engg. & Construction Co.
Ltd. v. NHAI, (2019) 15 SCC 131 : (2020) 2 SCC (Civ)
213] and later approved by a three-Judge Bench of this
Court in Patel Engg. Ltd. v. North Eastern Electric Power
Corpn. Ltd. [Patel Engg. Ltd. v. North Eastern Electric
Power Corpn. Ltd., (2020) 7 SCC 167 : (2020) 4 SCC
(Civ) 149]
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
73. In a recent three-Judge Bench decision of this Court
in DMRC Ltd. v. Delhi Airport Metro Express (P)
Ltd. [DMRC Ltd. v. Delhi Airport Metro Express (P) Ltd.,
(2024) 6 SCC 357 : (2024) 3 SCC (Civ) 112 : 2024 INSC
292] , the ground of patent illegality/perversity was
delineated in the following terms : (SCC p. 376, para 39)
―39. In essence, the ground of patent illegality is
available for setting aside a domestic award, if the
decision of the arbitrator is found to be perverse, or
so irrational that no reasonable person would have
arrived at it; or the construction of the contract is
such that no fair or reasonable person would take; or,
that the view of the arbitrator is not even a possible
view. A finding based on no evidence at all or an
award which ignores vital evidence in arriving at its
decision would be perverse and liable to be set aside
under the head of ―patent illegality‖. An award
without reasons would suffer from patent illegality.
The arbitrator commits a patent illegality by deciding
a matter not within its jurisdiction or violating a
fundamental principle of natural justice.‖
12.
The fulcrum of controversy between the parties, as observed by the
Arbitral Tribunal, was the Termination Notice sent by the Petitioner to the
Respondent under Clause 15.2 of the 2nd Lease Deed, and whether the
Petitioner was empowered to do so.
13.
Perusal of the Impugned Award on the aforesaid question shows that
the Arbitral Tribunal interpreted Clause 15.2 of 2nd Lease Deed in two parts
– first, which applies to a force majeure event which destroys or damages
the property and renders the lease impossible, unsafe, unfit, and non-feasible
to operate out of the said property; and second, which deals with a situation
created by restrictive governmental laws or regulations, riots, insurrection,
war, terrorist action, strike, public demonstration, rallies, acts of God, etc.,
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
that prevent the lessee from discharging its obligations cast on him under the
terms of the lease deed. The Arbitral Tribunal deemed the first part as
inapplicable, since it was neither the case of the Petitioner that there was a
force majeure event leading to destruction of the Premises, nor that the
Premises was damaged in any manner. As for the second part, the Arbitral
Tribunal opined that though it relieved the Petitioner/lessee from the
consequences arising from not being able to meet its obligations, it did not
confer any right on the lessee to terminate the lease. Rather, the Arbitral
Tribunal viewed the Petitioner‟s decision to terminate the 2 nd Lease Deed as
a deliberate act and not a passive submission to an event which
prevented/precluded/hindered it from discharging its obligations.
14.
The Arbitral Tribunal further took into account the fact that though a
lockdown was imposed by the Government of India for a few months,
restaurants and hospitality services were permitted to function, subject to
adherence with the COVID-19 guidelines, from 08.06.2020 or so, which is
much prior to the date on which the Petitioner sent the letter terminating the
2nd Lease Deed with a retrospective effect from 25.03.2020. Thus, while
concluding that the Petitioner did not have a right to terminate the 2 nd Lease
Deed under Clause 15.2, the Arbitral Tribunal observed that the Petitioner
was even less empowered to do so with a retrospective effect. The Arbitral
Tribunal buttressed its interpretation of the second part of Clause 15.2 with
the judgments of the Apex Court in Alopi Prashad vs. UOI, (1960) 2 SCR
793 and Panna Lal vs. State of Rajasthan, (1975) 2 SCC 633, which hold
that a contract is not frustrated merely because the circumstances in which
the contract was made, are altered.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
15.
Additionally, effect of the Petitioner‟s act of terminating the 2nd Lease
Deed on ground of the same having become onerous, financially unviable or
difficult to operate, was considered by the Arbitral Tribunal in light of
Section 56 of the ICA, which is being extracted below for reference:
―56. Agreement to do impossible act.—An agreement to
do an act impossible in itself is void.
Contract to do an act afterwards becoming impossible or
unlawful.—A contract to do an act which, after the
contract is made, becomes impossible, or, by reason of
some event which the promisor could not prevent,
unlawful, becomes void when the act becomes impossible
or unlawful.
Compensation for loss through non-performance of act
known to be impossible or unlawful.—Where one person
has promised to do something which he knew, or, with
reasonable diligence, might have known, and which the
promisee did not know, to be impossible or unlawful, such
promisor must make compensation to such promisee for
any loss which such promisee sustains through the nonperformance of the promise.‖
16.
The Arbitral Tribunal applied Section 56 of the ICA after recalling
some notable judgments of the Apex Court in Raja Dhruv Dev Chand vs.
Raja Harmohinder Singh, AIR 1968 SC 1024 and T. Lakshmipathi and Ors.
v. P. Nithyananda Reddy and Ors,. (2003) 5 SCC 150, to eventually
conclude that even when an executed contract becomes difficult and onerous
to operate by a party to the contract, it cannot resile from it and cannot
escape payment of rent or legal obligations and liabilities.
17.
Lastly, the Arbitral Tribunal distinguished a Judgment passed by a
Coordinate Bench of this Court in Ramanand v. Dr. Girish Soni, 2020 SCC
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
OnLine Del 635, which was relied upon by the Petitioner to argue that the
doctrine of frustration, which is encapsulated in Section 56 of the ICA, has
no application in a case where there is a force majeure clause. The Arbitral
Tribunal observed that it was the Petitioner who, in actuality, could not even
avail the doctrine of force majeure which is incorporated under Section
108(B)(e) of the Transfer of Property Act, 1882 [“TPA”], which reads as
under:
“108. Rights and liabilities of lessor and lessee.—
xxx
(B) Rights and Liabilities of the Lessee
xxx
(e) if by fire, tempest or flood, or violence of an army or
of a mob, or other irresistible force, any material part of
the property be wholly destroyed or rendered
substantially and permanently unfit for the purposes for
which it was let, the lease shall, at the option of the
lessee, be void:”
18.
The Arbitral Tribunal took note that this Court in Ramanand (Supra),
held that there has to be complete destruction of property before recourse
can be had to Section 108(B)(e) of the TPA. After the above in-depth
discussion, the Arbitral Tribunal gave the following conclusions:
“61. In the light of the above it is held as under:
i. Respondent was not empowered to terminate the
lease deed under clause 15.2 of the lease deed- 2.
Therefore, termination of the lease deed under clause
15(2) was illegal;
ii. The reason for termination on the alleged ground
that the performance or operation of the lease deed had
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
become impossible financially and practically suffers from
vice of invalidity; and
iii. Even the termination of lease deed cannot be
justified under section 56 of the Contract Act or section
108(B)(e) of the Transfer of Property Act.‖
19.
In the opinion of this Court, the wordings of Clause 15.2 of the 2 nd
Lease Deed are clear as day to determine whether or not the Petitioner was
entitled to terminate the 2nd Lease Deed or not. The simple answer, which
aligns with the view taken by the Arbitral Tribunal, is no. Yet, this Court
deems it fit to also refer to the wordings of the Notification dated 24.03.2020
bearing No. 40-3/2020-DM-I(A) released by the Ministry of Home Affairs
imposing a nation-wide lockdown owing to the COVID-19 pandemic.
Relevant portion of the said Notification reads as under:
“Whereas in exercise of the powers under section 6(2)(i) of
the Disaster Management Act. 2005, the National Disaster
Management Authority (NOMA), has Issued an Order no.
1- 29/2020-PP (Pt.II) dated 24.03.2020 {Copy enclosed)
directing the Ministries/ Departments of Government of
India, State/Union Territory Governments and State/
Union Territory Authorities to take effective measures so
as to prevent the spread of COVID-19 in the country;
Whereas under directions of the aforesaid Order of
NOMA, and in exercise of the powers, conferred under
Section 10(2)(1) of the Disaster Management Act. The
undersigned, in his capacity as Chairperson, National
Executive Committee, hereby issues guidelines, as per the
Annexure, to Ministries/ Departments of Government of
India, State/Union Territory Governments and State/Union
Territory Authorities with the directions for their strict
implementation. This Order shall remain in force, in all
parts of the country for a period of 21 days with effect from
25.03.2020.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
XXX
7. Hospitality Services to remain suspended
Exceptions:
a. Hotels, homestays, lodges and motels, which are
accommodating tourists and persons stranded due to
lockdown, medical and emergency staff, air and sea crew.
b. Establishments used/ earmarked for quarantine
facilities.‖
20.
The lockdown was further extended till 31.05.2020, by way of
another Notification released by the Ministry of Home Affairs, relevant parts
whereof read as under:
―And whereas Delhi Disaster Management Authority
(DDMA) has notified lockdown in Territory of NCT of
Delhi w.e.f. 25th March, 2020 till midnight of 14th April,
2020 to curb the menace of COVID-19 vide order dated
25.03.2020 along with the guidelines;
And whereas, Delhi Disaster Management Authority
(DDMA)
has
issued
various
subsequent
orders/Instructions to authorities concerned of NCT of
Delhi to take all required measures to appropriately deal
with the situation;
And whereas, Govt. of India has extended the lockdown
period all over India, Including the territory of NCT of
Delhi, further w.e.f. dated 15.04.2020 to 3rd May, 2020 to
curb the menace of COVID-19.‖
21.
Subsequently, the lockdown was relaxed vide a Notification dated
21.08.2020 bearing No. F.DDMA/COVID-19/2020/1/292, allowing the
opening of hotels. Relevant extract of the said Notification reads as under:
―And whereas, in pursuance of Ministry of Home Affairs,
Govt. of India Order as well as DO letter dated 29.07.2020,
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
DDMA has issued Order No. 275 dated 31.07.2020 with
regard to extension of lockdown in the containment zones
and to maintain status quo (except removal of night curfew)
in the territory of NCT of Delhi till the mid night of
31.08.2020;
And whereas, Ministry of Home Affairs, Govt. of India,
vide Order No. 40- 3/2020-DM-l(A) dated 30.05.2020
annexed with guidelines for Phased Re-opening (Unlock
1) has already permitted to open Hotels & other hospitality
services in the area outside the Containment Zones with
the observation & compliance of Standard Operating
Procedure (SOP) to be prescribed by the Ministry of
Health & Family Welfare, Govt. of India. Ministry of
Health & Family Welfare, Govt. of India vide OM dated
04.06.2020 has also issued SOP for Hotels & other
hospitality services, which is enclosed herewith;
And whereas, the current situation of ongoing pandemic of
COVID-19 in Delhi has been reviewed during the meeting
of Delhi Disaster Management Authority held, through
video conferencing, on August 19, 2020 under the
Chairmanship of Hon'ble Lt. Governor, Delhi and it has
been decided that the Hotels will be allowed to open in NCT
of Delhi in all the areas outside the Containment Zones:
Now, therefore, in exercise of powers conferred under
section 22 of the Disaster Management Act, 2005, the
undersigned, In his capacity as Chairperson, State
Executive Committee, DDMA, Govt. of NCT of Delhi,
hereby, In partial modification of DDMA order dated
31.07.2020, directs all authorities concerned that Hotels
shall be permitted to operate throughout the NCT of Delhi
in all areas, except in containment zones, subject to the
strict compliance of Standard Operating Procedure (SOP)
issued in this regard by Ministry of Health & Family
Welfare, Govt. of India dated 04.06.2020, annexed with this
order as well as other directions / instructions / guidelines
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
issued by the Government of India and Government of NCT
of Delhi from time to time.‖
22.
The above notifications released by the Ministry of Home Affairs fall
within the ambit of „restrictive governmental laws or regulations‟, which is
envisioned in the second part of Clause 15.2 of the 2nd Lease Deed.
However, what is pertinent in the above Notification dated 21.08.2020 is
that vide an Order dated 30.05.2020, the Government of India had permitted
the re-opening of hotels and other hospitality services, subject to their
compliance with the Standard Operating Procedures. Therefore, while
temporary restrictions were in place, they were certainly not in perpetuity.
23.
A perusal of Clause 15.2 of the 2nd Lease Deed, more so, the second
part thereof, as dissected by the Arbitral Tribunal, indicates that there is no
mention of the parties‟ power to terminate the 2 nd Lease Deed under Clause
15.2. The only respite that the Petitioner, as the lessee, may be entitled to is
not being responsible for any consequences or not liabilities if it was
prevented in performing its obligations under the terms of the 2 nd Lease
Deed by reasons of any restrictive governmental laws or regulations, etc. –
nothing more, nothing less. Therefore, this Court has no hesitation in
concurring with the view taken by the Arbitral Tribunal that termination of
the 2nd Lease Deed under Clause 15.2 was illegal.
24.
The next array of questions posed before the Arbitral Tribunal were
regarding Clause 12 of the 2nd Lease Deed, to determine whether or not
Clause 12 rendered the 2nd Lease Deed as determinable and as such,
incapable of being specifically performed as per Section 14(1)(d) of the
Specific Relief Act, 1963 [“SRA”] and further as to whether or not the
„penultimate sub-clause‟ dealing with the obligation of the Petitioner to pay
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
on termination survives and whether or not the Respondent was entitled to
monetary relief.
25.
Clause 12.1 of the 2nd Lease Deed provided that the lessor shall have
no right to terminate the lease deed during the initial term of the deed, i.e.,
for 15 years. The Clause also provides an exception, in a situation where the
lessee violates the terms of the 2nd Lease Deed and does not cure the breach
within 30 days of the receipt of the notice given by the lessor in that regard,
the lessor has the right to terminate the lease by giving further notice of 30
days in writing to the lessee. Further, Clause 12.2 fixes a mandatory lock-in
period of 84 months, during which the lessee is injuncted from terminating
the 2nd Lease Deed. But in case the lessor violates the critical terms of the
2nd Lease Deed which are specified in sub clauses (a) and (b) thereof, and it
fails to cure the breach within a period of 30 days of the receipt of notice
from the lessee in that regard, the lessee will not be liable to deposit any rent
or any amount with the lessor during the notice period and on expiry of 30
days the lessee is entitled to hand over the apartment to the lessor. Now, the
„penultimate sub-clause‟ of Clause 12.2 of the 2nd Lease Deed provides that
in case the lease is terminated by the lessee before the expiry of the lock-in
period for any reason whatsoever, other than the reason of violation of the
critical terms remaining uncured by the lessor, the lessee has been made
fully liable to pay the lease rent along with applicable taxes thereon for the
entire balance lock-in period.
26.
The Arbitral Tribunal, after analysing the applicable case-laws in light
of the wording of the „penultimate sub-clause‟, held that the 2nd Lease Deed
was determinable and consequently, incapable of being specifically
performed in terms of Section 14(1)(d) of the SRA. There is no challenge to
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
this observation of the Arbitral Tribunal by either parties herein. Even this
Court does not find any reason to interfere with the findings in the Impugned
Award on this aspect. With that, the next related questions that remained to
be answered were as to whether or not the „penultimate sub-clause‟ dealing
with the obligation of the Petitioner to pay on termination survives and
whether or not the Respondent was entitled to monetary relief.
27.
On the remaining two questions regarding monetary relief, the
Arbitral Tribunal was of the opinion that the Petitioner cannot be allowed to
approbate and reprobate at the same time, by stating that it had the right to
terminate the 2nd Lease Deed as also the right to avoid the obligation to pay
the stipulated amount after termination of the contract. The Arbitral Tribunal
also considered the case, where if the Petitioner took resort to the
„penultimate sub-clause‟ under Clause 12.2 of the 2nd Lease Deed to
terminate the contract, its obligation to pay would not perish at the same
time. Having observed that, the Arbitral Tribunal held that the „penultimate
sub-clause‟ under Clause 12.2 of the 2nd Lease Deed survived the
termination of the contract by way of the Termination Notice – which was
done prior to the expiry of the lock-in period – and will continue to remain
operative until the Petitioner discharges its liability to pay the agreed amount
to the Respondent.
28.
Having observed the aforesaid, the adjoining question remaining for
consideration by the Arbitral Tribunal was as to whether or not the
Respondent was entitled to monetary relief, for which it decided as to
whether or not the Respondent was required to prove loss or damage
Inarguably, observations of the Arbitral Tribunal in the Impugned Award on
this question is the heart of the controversy before this Court.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
29.
The first remark of the Arbitral Tribunal on the above question was
that in the present case, it was not possible to ascertain loss suffered by the
Respondent on account of the premature termination of the 2 nd Lease Deed
by the Respondent and there existed no such standard in the contract. As
such, the Arbitral Tribunal, while relying on the landmark decision of the
Apex Court in Maula Bux (Supra), held that this was a case where since it
was not possible to assess compensation for breach of contract, the sum
specified by the parties in the „penultimate sub-clause‟ under Clause 12.2
would be considered as a genuine pre-estimate of compensation. The
Arbitral Tribunal turned its attention to the exchange of letters between the
parties, starting from the Termination Notice. For the sake of convenience,
firstly, the Termination Notice is being reproduced hereinbelow:
To,
Mr. Gursharan Singh Bawa
H. No. 21, Ground Floor,
Road No. 78, West Punjabi Bagh
New Delhi-110026
SUB: NOTICE FOR TERMINATION OF LEASE
DEED DATED 31.12.2018 IN TERMS OF CLAUSE
15.2 OF THE DEED.
Dear Sir,
Vide the registered Lease Deed dated 31.12.2018, you had
lease Service Apartment No. 3001, Third Floor, situated in
New Tower in Hotel Hyatt Regency, Bhikaji Cama Place,
New Delhi in favour of the undersigned on the basis of
mutually agreed terms and conditions duly recorded in the
said Lease Deed (hereinafter referred to as ‗Lease Deed‘).
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
We would like to draw your kind attention to Clause 15.2
of the Lease Deed. You are well aware that the
undersigned has been prevented from utilising the leased
premises due to the restrictive governmental regulations
suspending the operations of hotels and is therefore not
responsible for any of its consequences and or
liabilities/obligations under the lease deed with effect from
25.03.2020.
The situation and restrictive orders due to which the
undersigned has been unable to utilise the leased premises
has already exceeded several months and consequent
thereto, the Lease Deed stands terminated with immediate
effect.
Pursuant to said termination, you are called upon to take
possession of the premises. Simultaneously you are also
requested to refund the entire security deposit for which
you may please contact Sanjeev Malik in the Accounts
Department at sanjeev.malik@ahlnorth.com
Regards,
For Asian Hotels (North) Ltd.
Authorised Signatory‖
30.
Next, the Letter dated 18.07.2020 sent by the Petitioner which
clarifies its stand regarding termination of the 2nd Lease Deed, reads as
under:
―ASIAN HOTELS (NORTH) LIMITED
By Speed Post/Email
Date: 18th July, 2020
Mr. Gursharan Singh Bawa (Lessor)
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
H.No. 21, Ground Floor,
Road No. 78
West Punjabi Bagh
New Delhi-110026
Sub: Statement of Accounts of leased Service
Apartment No. 3001 consequent to termination of
Lease Deed.
Dear Sir,
This is in reference to our communication dated
27.06.2020.
You are conscious and aware of the fact that due to
unavoidable circumstances and the restrictive regulatory
requirements we have been unable to operate the Hotel
property for more than three months now. There is still
grave uncertainty as to when the Government would permit
the shutdown of the Hotels to be lifted. Under these
compelling circumstances it had become impossible for
us to financially and practically adhere to the terms of the
Lease. Accordingly, the Lease had to be terminated with
immediate effect.
We would like to put on record that Asian Hotels (North)
Ltd. has already vacated the premises. We would also like
to record that the premises are deemed to be in your
possession effective 27.06.2020 and we are not,
consequent to the termination, liable to pay any lease
rentals.
We are not liable to pay and therefore have not paid lease
rentals for the period 26.03.2020 till date of termination
of the lease as aforesaid due to complete lockdown and
stoppage of hotel operations. The embargo on opening of
Hotels in Delhi still continues.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
In terms of the Lease Deed we had paid a deposit of Rs.
55,26,000/- and as a consequence of the termination of the
Lease we are entitled to the refund of the said deposit. It
appears that certain payments are due to you as per
statement enclosed. You may deduct the amounts due to
you out of the security deposit and remit the balance
amount of Rs. 59,87,924/- within a period of one week.
Failure on your part to do the needful as aforesaid would
leave us with no other option except to initiate legal
proceedings.
Your Faithfully,
Dalip Singh Rawat
For ASIAN HOTELS (NORTH) LTD.‖
[Emphasis Supplied]
31.
Upon reading of the above two letters, the Arbitral Tribunal formed
an opinion that since the Petitioner never claimed that the amount fixed
under the „penultimate sub-clause‟ of Clause 12.2 is unreasonable or not a
pre-estimation of loss suffered by the Respondent due to the premature
termination of the 2nd Lease Deed, fixation of rent as a measure of loss to the
Respondent in the event of a premature termination of the 2nd Lease Deed
was a reasonable one.
32.
The Impugned Award further depicts that the Arbitral Tribunal, while
relying on the judgments of the Apex Court in ONGC vs. Saw Pipes Ltd.
(Supra), and Construction and Design Services (Supra), cast the onus to
show that no loss was suffered by the Respondent on account of the
premature termination of the 2nd Lease Deed on the Petitioner, for the reason
that the Respondent‟s monetary claim was based on a pre-estimated amount
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
specified by the parties on the breach of Clause 12.2 of the 2 nd Lease Deed.
The Arbitral Tribunal observed that since the Petitioner violated Clause 12.2
of the 2nd Lease Deed, the onus was on it to show that the Respondent did
not suffer any loss as a result of its breach and the amount stipulated was a
penalty.
33.
A further examination on the above aspect was undertaken by the
Arbitral Tribunal by drawing similarities to the decision of the Apex Court
in Chunilal V. Mehta (Supra) to the facts of the present case, while
distinguishing the instant dispute with the factual matrix contained in the
judgment of Kailash Nath (Supra). The similarities between the instant case
and the features that emerge from the Chunilal V. Mehta (Supra) case, as
jotted down by the Arbitral Tribunal are being extracted below:
“104. Features that emerge from Chunilal Mehta (Supra)
and features of the subject case have striking similarities.
These are juxtaposed as under:
Sr.
No.
I.
Chunilal Mehta Case
Instant Case
In terms of the agreement firm
Chunilal Mehta & Co. was
appointed as managing agent
of respondent company for a
period of 21 years.
II.
The Board of Directors of
respondent
company
terminated
the
agency
agreement before the expiry of
21 years.
Clause 14 of the Agreement
between the parties provides
that in case respondent
In terms of lease deed 2 apartment was given
on lease to respondent
for a period of 15 years
with a lock-in period of
84 months
Respondent terminated
the lease agreement
before the expiry of
lock-in period of 84
months
Clause 12.2 of the lease
deed provides that
lessee shall not have
III.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
terminates agreement before
the period of 21 years, the
Managing
Agency
shall
receive from respondent as
compensation or liquidated
damages for the loss of
appointment a sum equal to
the aggregate amount of the
monthly salary of not less
than Rs. 6000 for and during
the whole of the unexpired
portion of the term of agency.
IV.
The
managing
agency
agreement was terminated
before the expiry of 21 years.
V.
Clause 14 shows that the
party
have
themselves
provided for the specified
amount of damages that
would be payable by the
company to the managing
agent if the managing agency
agreement was terminated
before the expiry of 21 years.
right to terminate the
deed during initial 84
months of the deed and
a sub-clause thereof
provides that if the
lessee during the lockin period due to any
reason
whatsoever
other than due to
violation of critical
terms, the lessee is fully
liable to pay the rent
for the entire unexpired
lock-in period.
The lease deed was
terminated before the
expiry of lock in period
of 84 months
Clause 12.2 read with
its penultimate sub
clause show that parties
have
themselves
provided the amount
payable by respondent
to claimant in case the
lease agreement is
terminated before a
period of 84 months.
Respondent
has
admitted
that
the
stipulation for payment
of
rent
for
the
unexpired
lock-inperiod on pre-mature
termination of lease is
as a matter of law, a
liquidated
damages
provision.‖
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
34.
What the Arbitral Tribunal especially took note of from the Chunilal
V. Mehta (Supra) Judgment, was that the Apex Court did not consider the
salary for the unexpired period of the terminated managing agency, akin to
earnest money. Correspondingly, in the facts and circumstances of the
instant case, it observed that unpaid rent for the unexpired lock-in period
also cannot be treated as earnest money.
35.
On the other hand, the Arbitral Tribunal distinguished the instant case
from the features arising in Kailash Nath (Supra), firstly on the basis that in
Kailash Nath (Supra), the Apex Court was dealing with a case wherein a
party deposited a certain sum specifically as earnest money with the DDA,
on the basis of a contractual stipulation, which also dictated that the said
earnest money would be forfeited on the failure on part of the said party to
despite the balance money. Secondly, it was noted that the Apex Court
eventually held that neither was there any breach by the party that had
deposited the earnest money, nor did the party having forfeited the earnest
money, i.e., the DDA, suffered any loss. Most importantly, the Apex Court
observed that insistence on a contractual stipulation, even when the
forfeiting party did not suffer any loss, and allowing such a party to
appropriate the monies, would be arbitrary.
36.
To fully appreciate the above distinction drawn by the Arbitral
Tribunal, this Court deems it fit to refer to the a few more important facts
involved in the Kailash Nath (Supra) case before the Apex Court. The appeal
arose out of a public auction conducted by the DDA, wherein the appellant
made the highest bid. As per the following terms of the bid, the appellant
deposited a particular sum as earnest money in favour of the DDA:
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
―2. xxx
(ii) The highest bidder shall, at the fall of the hammer, pay
to the Delhi Development Authority through the officer
conducting the auction, 25% of the bid amount as earnest
money either in cash or by Bank Draft in favour of the
Delhi Development Authority, or Cheque guaranteed by a
Scheduled Bank as "good for payment for three months" in
favour of the Delhi Development Authority. If the earnest
money is not paid, the auction held in respect of that plot
will be cancelled.
(iii) The highest bid shall be subject to the acceptance of
Vice-Chairman, DDA or such other officer(s) as may be
authorized by him on his behalf. The highest bid may be
rejected without assigning any reason.
(iv) In case of default, breach or non-compliance of any of
the terms and conditions of the auction or
misrepresentation by the bidder and/or intending
purchaser, the earnest money shall be forfeited.
(v) The successful bidder shall submit a duly filled-in
application in the form attached immediately after the close
of the auction of plot in question.
(vi) When the bid is accepted by the DDA, the intending
purchaser shall be informed of such acceptance in writing
and the intending purchaser shall, within 3 months thereof,
pay to the Delhi Development Authority, the balance 75%
amount of the bid, in cash or by Bank Draft in favour of the
Delhi Development Authority or by Cheque guaranteed by a
Scheduled Bank as "good for payment for three months" in
favour of the Delhi Development Authority. If the bid is not
accepted, the earnest money will be refunded to the
intending purchaser without any interest unless the earnest
money is forfeited under para 2 (iv) above.‖
[Emphasis Supplied]
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
37.
The deposit of earnest money by the appellant in Kailash Nath
(Supra) was acknowledged by the DDA, however, the appellant thereafter
sought some more time to deposit the remaining 75% amount, due to the
economic recession affecting the country at the relevant time. Time for
deposit came to be extended. However, later it transpired that due to certain
developments, the DDA forfeited the earnest money deposited by the
appellant and cancelled the bid/allotment in favour of the appellant.
Moreover, later, the DDA sold the plot in question to a different bidder for a
sum of Rs. 11.78 crores, which was more than the appellant‟s bid. Against
this action, the appellant first filed a suit for specific performance, which
came to be dismissed by a Coordinate Bench of this Court, albeit with a
direction to the DDA to refund the earnest money to the appellant. This
order was appealed against by the DDA before a Division Bench of this
Court, who set aside the order passed by the Coordinate Bench to hold that
the DDA‟s forfeiture was in order. Thereafter, the appellant approached the
Apex Court.
38.
One of the primary observations of the Apex Court in Kailash Nath
(Supra) was that since there was no breach of contract on part of the
appellant, which is a precondition as per clause (iv) of the terms of the bid, it
was an arbitrary action on part of the DDA to forfeit the earnest money. The
Apex Court also observed that since DDA did not suffer any loss, it would
be arbitrary to allow it to appropriate the earnest money deposited by the
appellant therein.
39.
Now that the Court has recalled the facts involved in Kailash Nath
(Supra), there is no hesitation in holding that the instant case involves vastly
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
different factual circumstances. First and foremost, the instant case is not
related to earnest money. Secondly, it was never the case of the Petitioner
that the Respondent violated the terms of the 2nd Lease Deed, so as to bring
the termination thereof within the ambit of Clause 12.2. Rather, it was the
Respondent‟s case that the Petitioner breached the „lock-in period‟ provision
encapsulated within Clause 12.2, and as such, breached the 2nd Lease Deed.
Thirdly, the fact that the DDA sold the plot in question on a substantially
higher bid than that of the appellant, was sufficient to conclude that no loss
was suffered by the DDA. Per contra, in the present case, it has been
established that the Respondent could not sub-lease the Premises to any
other persons, since the Premises was a part of the Petitioner‟s Hotel.
40.
From the above discussion, this Court has no hesitation in holding that
the Arbitral Tribunal is correct in holding that the judgment of the Apex
Court in Kailash Nath (Supra) is inapplicable to the facts of the present case.
As such, reliance on the same by the learned Senior Counsel for the
Petitioner is also erroneous. Consequently, this Court is of the view that the
Arbitral Tribunal, after conducting an in-depth analysis into the facts of the
present case, relevant contractual provisions, applicable legal provisions and
case laws, has arrived at a plausible view to conclude that the Respondent
was entitled to the amount designated by the parties themselves under
Clause 12.2 of the 2nd Lease Deed, once a breach thereof occurs.
41.
This Court recalls another landmark Judgment delivered by the Apex
Court in Fateh Chand (Supra), observing as under:
“8… The section is clearly an attempt to eliminate the
somewhat elaborate refinements made under the English
common law in distinguishing between stipulations
providing for payment of liquidated damages and
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
stipulations in the nature of penalty. Under the common
law a genuine pre-estimate of damages by mutual
agreement is regarded as a stipulation naming liquidated
damages and binding between the parties : a stipulation in
a contract in terrorem is a penalty and the Court refuses to
enforce it, awarding to the aggrieved party only
reasonable compensation. The Indian Legislature has
sought to cut across the web of rules and presumptions
under the English common law, by enacting a uniform
principle applicable to all stipulations naming amounts to
be paid in case of breach, and stipulations by way of
penalty.
10. Section 74 of the Contract Act deals with the measure
of damages in two classes of cases (i) where the contract
names a sum to be paid in case of breach and (ii) where
the contract contains any other stipulation by way of
penalty. We are in the present case not concerned to
decide whether a covenant of forfeiture of deposit for due
performance of a contract falls within the first class. The
measure of damages in the case of breach of a stipulation
by way of penalty is by Section 74 reasonable
compensation not exceeding the penalty stipulated for. In
assessing damages the Court has, subject to the limit of the
penalty stipulated, jurisdiction to award such
compensation as it deems reasonable having regard to all
the circumstances of the case. Jurisdiction of the Court to
award compensation in case of breach of contract is
unqualified except as to the maximum stipulated; but
compensation has to be reasonable, and that imposes upon
the Court duty to award compensation according to settled
principles. The section undoubtedly says that the aggrieved
party is entitled to receive compensation from the party
who has broken the contract, whether or not actual
damage or loss is proved to have been caused by the
breach. Thereby it merely dispenses with proof of ‗actual
loss or damages‘; it does not justify the award of
compensation when in consequence of the breach no legal
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
injury at all has resulted, because compensation for breach
of contract can be awarded to make good loss or damage
which naturally arose in the usual course of things, or
which the parties knew when they made the contract, to be
likely to result from the breach.
15. Section 74 declares the law as to liability upon breach
of contract where compensation is by agreement of the
parties pre-determined, or where there is a stipulation by
way of penalty. But the application of the enactment is not
restricted to cases where the aggrieved party claims relief
as a plaintiff. The section does not confer a special benefit
upon any party; it merely declares the law that
notwithstanding any term in the contract pre-determining
damages or providing for forfeiture of any property by way
of penalty, the court will award to the party aggrieved only
reasonable compensation not exceeding the amount named
or penalty stipulated. The jurisdiction of the court is not
determined by the accidental circumstance of the party in
default being a plaintiff or a defendant in a suit. Use of the
expression ‗to receive from the party who has broken the
contract‘ does not predicate that the jurisdiction of the
court to adjust amounts which have been paid by the party
in default cannot be exercised in dealing with the claim of
the party complaining of breach of contract. The court has
to adjudge in every case reasonable compensation to
which the plaintiff is entitled from the defendant on breach
of the contract. Such compensation has to be ascertained
having regard to the conditions existing on the date of the
breach.‖
42.
Further, even though the Arbitral Tribunal has rightly distinguished
the judgment from the facts of the present case, a reference is appropriate to
the following principles laid down by the Apex Court in Kailash Nath
(Supra):
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
―43. On a conspectus of the above authorities, the law on
compensation for breach of contract under Section 74 can
be stated to be as follows:
43.1. Where a sum is named in a contract as a liquidated
amount payable by way of damages, the party complaining
of a breach can receive as reasonable compensation such
liquidated amount only if it is a genuine pre-estimate of
damages fixed by both parties and found to be such by the
court. In other cases, where a sum is named in a contract
as a liquidated amount payable by way of damages, only
reasonable compensation can be awarded not exceeding
the amount so stated. Similarly, in cases where the amount
fixed is in the nature of penalty, only reasonable
compensation can be awarded not exceeding the penalty so
stated. In both cases, the liquidated amount or penalty is
the upper limit beyond which the court cannot grant
reasonable compensation.
43.2. Reasonable compensation will be fixed on wellknown principles that are applicable to the law of contract,
which are to be found inter alia in Section 73 of the
Contract Act.
43.3. Since Section 74 awards reasonable compensation
for damage or loss caused by a breach of contract, damage
or loss caused is a sine qua non for the applicability of the
section.
43.4. The section applies whether a person is a plaintiff or
a defendant in a suit.
43.5. The sum spoken of may already be paid or be
payable in future.
43.6. The expression ―whether or not actual damage or
loss is proved to have been caused thereby‖ means that
where it is possible to prove actual damage or loss, such
proof is not dispensed with. It is only in cases where
damage or loss is difficult or impossible to prove that the
liquidated amount named in the contract, if a genuine preestimate of damage or loss, can be awarded.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
43.7. Section 74 will apply to cases of forfeiture of earnest
money under a contract. Where, however, forfeiture takes
place under the terms and conditions of a public auction
before agreement is reached, Section 74 would have no
application.‖
43.
In view of the law laid down by the Apex Court in the foregoing case
laws and upon perusal of the Impugned Award, what becomes the
foundation of the Arbitral Tribunal‟s conclusion that the Respondent was
not obligated to prove damages, was the fact that the Premises was a service
apartment in the premises of the Petitioner‟s Hotel, wherein the services
being provided were by the Petitioner‟s Hotel itself. As such, the Premises
was a part of the Petitioner‟s Hotel. This, as rightly observed by the Arbitral
Tribunal, would bring up a situation where it is unlikely for an individual to
make bookings for the Premises without the facilities that go with it in the
Petitioner‟s Hotel. In these circumstances, it was impossible for the
Respondent to sub-lease the Premises to a third party for purpose of
mitigation of losses. Therefore, the contention of the learned Senior Counsel
for the Petitioner that since there was no effort to mitigate losses, it was
upon the Respondent to plead and prove losses for claiming damages,
cannot be accepted.
44.
For the foregoing reasons, this Court has no hesitation in agreeing to
the views of the Arbitral Tribunal, to the effect that the Respondent was
entitled to unrealized rental amounts for the unexpired lock-in period,
having occurred on account of the premature termination of the 2 nd Lease
Deed and as such, breach of Clause 12.2 by the Petitioner.
45.
Thus, this Court is in agreement with the observations of the Arbitral
Tribunal qua the Claims made before it by the Respondent.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
46.
The next challenge laid by the Petitioner to the Impugned Award is
against the dismissal of its Counter-Claims no. 2, 3, 4, 5, 6 and 9. The
Petitioner alleges that the 2nd Lease Deed subsumed within itself the 1st
Lease Deed by virtue of Clause 9 of the 2nd Lease Deed and as such, the
Arbitral Tribunal was wrong in concluding that the abovementioned claims
were outside the ambit of the 2nd Lease Deed, having been based on Clause
6 of the 1st Lease Deed.
47.
Clause 9.1 of the 2nd Lease Deed reads as under:
―9.1 Notwithstanding the terms of this deed, the parties
shall ensure to comply with their respective obligations
under the original deed to the extent it does not contradict
this deed.‖
48.
Since the above clause mandates compliance of the clauses of the 1 st
Lease Deed only to the extent that they do not contradict those in the 2 nd
Lease Deed, the Arbitral Tribunal highlighted the entire role-reversal of the
parties in the two contracts, i.e., in the 2 nd Lease Deed, as per Clause 10.3,
the Petitioner was liable to bear maintenance charges while as per Clause 6
of the 1st Lease Deed, the Respondent was liable to pay such charges to the
Petitioner. Since this was the only contradictory factor, the Arbitral Tribunal
dismissed the Counter-Claims based on Clause 6 of the 1st Lease, as being
contradictory to and outside the scope of the 2nd Lease Deed.
49.
The above view does not warrant any interference, having been based
on the clear reading of the wordings of the contractual provisions, as also
having arrived at after distinguishing the case laws relied upon by the
Petitioner. It is clear that both the 1st and 2nd Lease Deeds operate in their
independent atmosphere and existence of one does not affect the other.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
Accordingly, the dismissal of the Counter-Claims no. 2, 3, 4, 5, 6 and 9 as
having been based on Clause No. 6 of the 1st Lease Deed, also does not
shock the conscience of this Court and deserves to be upheld.
50.
A careful and comprehensive perusal of the Impugned Award
demonstrates that the Arbitral Tribunal has examined the pleadings,
documentary material, correspondence exchanged between the parties, and
the evidence led in support of their respective claims and assertions. The
Impugned Award reflects due consideration of the relevant facts and
surrounding circumstances germane to the disputes.
51.
The Impugned Award reflects a plausible and reasoned interpretation
of the contract and an evaluation of evidence within the jurisdiction of the
Arbitral Tribunal. It is well settled that a court exercising limited supervisory
jurisdiction under Section 34 of the Arbitration Act cannot re-appreciate
evidence or substitute its own interpretation of contractual clauses where the
view taken by the Arbitral Tribunal is a possible and reasonable one.
52.
Viewed in its entirety, the Impugned Award reflects a reasoned and
structured adjudication of the disputes by the Arbitral Tribunal within the
confines of the contractual terms agreed upon by the parties, the material
placed on record, and the jurisdiction vested in the Arbitral Tribunal. The
Impugned Award demonstrates due application of mind to the pleadings,
evidence, and relevant contractual provisions.
53.
In view of the foregoing discussion, this Court is of the considered
opinion that the Petitioner has failed to establish any ground under Section
34(2) or Section 34(2A) of the Arbitration Act warranting interference with
the Impugned Award.
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
54.
Accordingly, the Petitions being O.M.P. (COMM) 344/2022, O.M.P.
(COMM) 345/2022 and O.M.P. (COMM) 346/2022 filed by the Petitioner,
along with pending Application(s), if any, stand dismissed.
55.
Since the Impugned Award, being the final award passed by the
Arbitral Tribunal is upheld, the appeals being filed by the Petitioner being
ARB. A. (COMM.) 18/2021, ARB. A. (COMM.) 20/2021 and ARB. A.
(COMM.) 22/2021, filed by the Petitioner against the Interim Order dated
05.03.2021 passed by the Arbitral Tribunal, are disposed of as infructuous,
along with pending Application(s), if any.
OMP (CONT.) 2/2022, OMP (ENF.) (COMM.) 187/2022, OMP (ENF.)
(COMM.) 188/2022 & OMP (ENF.) (COMM.) 189/2022
56.
List on 05.10.2026.
SUBRAMONIUM PRASAD, J
AUGUST 10, 2026
AP
Signed By:RAHUL
SINGH
19:08:23
ARB. A. (COMM.) 18/2021 etc.
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review