IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment Delivered on: 20.03.2026
+
ARB.P. 2139/2025
AMAR KIRTI MEHTA
Through:
.....Petitioner
Mr. Shailesh Kumar Sinha, Mr.
Ashish Pandey, Mr. Suman Kumar,
Mr. Abhishek Dudpuri and Ms.
Vandana, Advs.
versus
NORTHERN RAILWAY & ANR.
.....Respondents
Through: Mr. Bhagwan Sawrup Shukla, CGSC
with Mr. Sarvan Kumar and Ms.
Priya Dwivedi, Advs. for UOI.
CORAM:
HON'BLE MR. JUSTICE VIKAS MAHAJAN
JUDGMENT
VIKAS MAHAJAN, J (ORAL)
1.
The present petition has been filed under Section 11(6) of the
Arbitration and Conciliation Act, 1996 [in short “Act”] seeking appointment
of a Sole Arbitrator to adjudicate the disputes that have arisen between the
parties.
2.
The disputes between the parties have arisen in the context of a
Tender Notice, bearing No. RE/UMB/S&T/Tele/Gr.248/T-51, issued by the
respondents. The petitioner was declared the successful bidder therein,
pursuant to which two Letters of Acceptance [hereinafter “LOAs”] were
issued
in
favour
of
the
petitioner:
the
first
being
LOA
No.
RE/UMB/S&T/Tele/Gr-248/outdoor/L-02 dated 14.06.2019, and the second
being
LOA
No.
Core-UMB-SANDT/RE-UMB-SNTT-Gr286-
od/0128610021293 dated 01.07.2020.
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
3.
It is stated that certain disputes arose between the petitioner and the
respondents regarding the Performance Bank Guarantee [in short “PBG”]
amounting to Rs. 3,71,150/- furnished by the petitioner, as well as the refund
of excess GST amounts deducted by the respondents. The relevant clauses
governing dispute resolution under the subject tender are reproduced
hereinbelow:
“49.
SETTLEMENT
OF
DISPUTE
INDIAN
RAILWAY ARBITRATION RULES (Ref. latest clause 63 &
64 of G.C.C. of respective Railway).
49.1
MATTERS FINALLY DETERMINED BY THE
RAILWAY :- All disputes And differences of any kind
whatsoever arising out of or in connection with the contract,
whether during the progress of the works or after its
completion and whether before or after the determination of
the contract, shall be referred by the contractor to the GM
and the GM shall within 120 days after receipt of the
contractor‟s representation, make and notify decisions on all
matters referred to by contractor in writing provided that
matters for which provision has been made in clauses 8, 18,
22(5), 39, 43(2), 45(a), 55, 55-A(5), 57, 57A, 61(1), 61(2) and
62(1) to (B) of General Conditions of the contract of
Railways or in any clause of special conditions of contract
shall be deemed as excepted matters (matters not arbitrable),
and decision of the Railway authority, thereon shall be final
and binding on the contractor, provided further that excepted
matters shall stand specifically excluded from the purview of
the arbitration clause.
50.
DEMAND FOR ARBITRATION
50.1
(i)In the event of any dispute and difference
between the parties hereto as to the construction or
operation of this contract, or the respective rights and
liabilities of the parties on any matter in question, dispute or
difference on any account, or as to the withholding by the
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
Railway of any certificate to which the contractor may claim
to be entitled to, or if the Railway fails to make a decision
within a period of 120 days, then and in any such case, but
except in any of the excepted matters referred to in clause
45.1 of these conditions, the contractor, after 120 days but
within 180 days of presenting his final claim on disputed
matters, shall demand in writing that the dispute or
difference be referred to Arbitration.
(ii)
The demand for arbitration shall specify the matters
which are in question, or subject of the dispute or difference
as also the amount of claim item wise. Only such dispute(s) or
difference(s) in respect of which the demand has been made,
together with counter claims or set off, given by the Railway,
shall be referred to arbitration and other matters shall not be
included in the reference.
(a)
The arbitration proceedings shall be assumed to
have commenced from the day a written and valid demand for
arbitration is received by the Railway.
(b)
The claimant shall submit his claim stating the facts
supporting the claims along with all relevant documents and
the relief or remedy sought against each claim within a
period of 30 days from the date of appointment of Arbitral
Tribunal. (c)The Railway shall submit its defense statement
arid counter claim(s), if any, within a period of 60 days of
receipt of copy of claims from Tribunal thereafter, unless
otherwise extension has been granted by Tribunal.
(c)
Place of arbitration- The place of arbitration would
be within the geographical limits of the Division of the
Railway where the cause of action arose or the
Headquarters of the concerned railway or any other place
with written consent of both the parties.
(iii)
No new claim shall be added during proceedings by
either party. However, a party may amend or supplement the
original claim or defense thereof during the course of
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
arbitration proceedings subject to acceptance by Tribunal
having due regard to delay in making it.
(iv)
If the Contractor(s) does/do not prefer his/their
specific and final claims in writing, within a period of 90 days
of receiving the intimation from the Railways that the final
bill is ready for payment, he/they will be deemed to have
waived.
(e)
The Engineer shall as soon as may be practicable
after removal of the Contractor fix and determine ex-pane or
by or after reference to the panics or after such investigation
or enquiries as he may consider fit to make or institute and
shall certify what amount (if any) had at the time of rescission
of the contract been reasonably earned by or would
reasonably accrue to the Contractor in respect of the work
then actually done by him under the contract and what was
the value of any unused, or partially used materials, any
constructional plant and any temporary works upon the site
The legitimate amount due to the Contractor after making
necessary deductions and certified by the Engineer should be
released expeditiously.”
(emphasis supplied)
4.
Reference would also be apposite to Clause 63 and 63.1 of the
applicable General Conditions which is as under:“SETTLEMENT OF DISPUTES - INDIAN RAILWAY
ARBITRATION AND CONCILIATION RULES
63.
Conciliation of Disputes:
(i)
This clause is applicable in the tender having
advertised value less than or equal to Rs 50 Crore.
(ii)
All disputes and differences of any kind whatsoever
arising out of or in connection with the contract, whether
during the progress of the work or after its completion and
whether before or after the determination of the contract,
shall be referred by the Contractor to the "Chief Engineer"
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
or "Divisional Railway Manager" through “Notice of
Dispute” provided that no such notice shall be served later
than 30 days after the date of issue of Completion
Certificate by the Engineer. Chief Engineer or Divisional
Railway Manager shall, within 30 days after receipt of the
Contractor’s "Notice of Dispute", notify the name of
conciliator(s) to the Contractor.
(iii)
The Conciliator(s) shall assist the parties to reach
an amicable settlement in an independent and impartial
manner within the terms of contract.
(iv)
If the parties reach agreement on a settlement of the
dispute, they shall draw up and sign a written settlement
agreement duly signed by Engineer In-charge. Contractor
and conciliator(s). When the parties sign the settlement
agreement, it shall be final and binding on the parties.
(v)
The parties shall not initiate, during the conciliation
proceedings, any arbitral or judicial proceedings in respect
of a dispute that is the subject matter of the conciliation
proceedings.
(vi)
The conciliation proceedings shall be terminated as
per Section 76 of 'The Arbitration and Conciliation Act, 1996.
63.1 Matters Finally Determined by the Railway: All
disputes and differences of any kind whatsoever arising out of
or in connection with the contract, whether during the
progress of the work or after its completion and whether
before or after the determination of the contract, shall be
referred by the Contractor to the GM and the GM shall,
within 120 days after receipt of the Contractor‟s
representation, make and notify decisions on all matters
referred to by the Contractor in writing provided that matters
for which provision has been made in Clauses 7(j), 8, 18,
22(5), 39.1, 39.2, 40A,43(2). 45(i)(a). 55, 55-A(5), 57,
57A.61(1). 61(2).62(1), 63(iv) and 63.2.1 of the Standard
General Conditions of Contract or in any Clause (stated as
excepted matter) of the Special Conditions of the Contract,
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
shall be deemed as „excepted matters‟ (matters not
arbitrable) and decisions of the Railway authority, thereon
shall be final and binding on the Contractor, provided further
that 'excepted matters' shall stand specifically excluded from
the purview of the Dispute Adjudication Board (DAB) and
Arbitration.”
5.
It is stated that the subject work was duly completed, and Completion
Certificates in this regard was issued on 26.06.2023 and 02.11.2023.
Subsequently, the petitioner, vide letters dated 30.10.2023 and 20.05.2024,
requested the respondents to refund the excess GST amounts deducted from
the petitioner‟s dues.
6.
In response, the petitioner received a communication dated
28.05.2024 from respondent no. 2, wherein the claim for reimbursement of
the GST amount was expressly denied.
7.
Consequently, a notice invoking arbitration under Section 21 of the
Act was issued by the petitioner to respondent no. 1 on 14.11.2024. The said
notice dated 14.11.2024 is reproduced hereinbelow in extenso:
“LETTER NO :- RTE/GST/NR/01
To,
THE G.M
NORTHERN Railway, Baroda house
New Delhi.
Dated:-14/11/2024
Sub:- Regarding request of appointment of arbitrator since more
than 4 months.
Ref:- LOA No: 1) RE/UMB/S&T/Tele/Gr-248/outdoor/L-02 dated
14.06.2019.
2)
Core-UMB-S
ANDT
0d/0128610021293 dated01/07/2020.
/RE-UMB-SNTT-Gr286-
All references letters are attached along with copy.
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
Respected sir,
With respect to the above said two works we had requested GM
core Prayagraj i.e. RE Division for appointment of arbitrator
since 4 months but because of dissolvement of RE division the
issue is being transferred to your division but nothing is being
progressive since 3 months so we request you to please look into
this matter for appointment of arbitrator for resolving our issue
at the earliest and the relevant correspondences are attached
along with this copy, please do the needful.
Thanks
With Best Regards
AMAR CONSTRUCTIONS
For Amar Construction
-sdProprietor
Copy to
1.PCSTE/NR
2.CEE/project/NR”
8.
The petitioner issued another notice dated 12.03.2025 to respondent
no. 1, reiterating the aforesaid claims. The said letter dated 12.03.2025 is
also reproduced hereinbelow in extenso:
“LETTER NO :- RTE/GST/NR/02
To,
THE PCSTE
NORTHERN Railway, Baroda house New
Delhi.
Dated:-12/03/2025
Sub:- Regarding request of appointment of arbitrator since more
than 14months.
Ref:- LOA No: 1) RE/UMB/S&T/Tele/Gr-248/outdoor/L-02 dated
14.06.2019.
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
2)
Core-UMB-S
ANDT
0d/0128610021293 dated01/07/2020.
/RE-UMB-SNTT-Gr286-
All references letters are attached along with copy.
Respected sir,
With respect to the above said two works we had requested GM
core Prayagraj i.e. RE Division for appointment of arbitrator
since 14 months but because of dissolvement of RE division the
issue is being transferred to your division but nothing is being
progressive since months so we request you to please look into
this matter for appointment of arbitrator for resolving our issue at
the earliest and the relevant correspondences are attached along
with this copy, please do the needful.
Thanks
With Best Regards AMAR CONSTRUCTIONS
For Amar Constructions
-sdProprietor
Copy to 1.GM/NR 2.CEE/project/NR 3.dycste/nr/ambala”
9.
However, vide letter dated 29.05.2025, respondent no. 1 rejected the
petitioner‟s request for the appointment of an arbitrator. The relevant portion
of the said letter dated 29.05.2025, communicating the refusal to appoint an
arbitrator, reads as follows:
“No. NR/UMB/S&T/Tele/Gr 248/0D/L-02
Date: 29.05.2025
M/s Amar Construction,
D2/704, Gagan Vihar Society,
Bibvewadi-Kondhwa Road,
Pune-411037
Subject: Appointment of Arbitrator.
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
Reference : 1. This office LOA No. RE/UMB/S&T/Tele/Gr
248/Outdoor/L-02 dated 14.06.2019.
2. This office letter No. RE/UMB/S&T/Misc/1630(Pt-1V)/089 dated
28.06.2024.
2. Your office letter No. RTE/GST/NR/02 dated 12.03.2025.
3. This office letter No RE/UMB/S&T/Tele/Gr 248/Outdoor dated
02.07.2024.
4. Your office letter No. Nil dated 16.07.2024.
Dear SirG
The outdoor telecom work in Moradabad-Chandausi-Harduaganj,
Barellly-Chandausi (Gr 248) section was completed on 02.07.2024 by
Issuing Final Acceptance Certificate (FAC) vide letter under reference
3 above. All the payments against the above contract have already been
released by the railway.
Vide letter under reference 4 above, It is certified by you that you have
no claim against this contract (Copy enclosed).
In view of the above, it is stated that the claim as submitted by you vide
your office letter under reference 2 above is not considerable as the
contract is already closed.
More over vide letter under 2 above, you are already informed that
your claim of reimbursement of GST does not meet conditions laid
down by Railway Board and is hereby rejected
This is for your kind information.
-sd(Vikram Singh Yadav)
Dy CSTE/Project/NR/UMB
DA: As above.
Copy to:- PCEE/NR/Project/UMB for kind information please.
2. Dy CSTE/HQ/NR/NDLS for kind information please.”
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
10.
Mr. Shailesh Kumar Sinha, learned counsel appearing on behalf of the
petitioner, submits that the Tender Notice, pursuant to which the LOAs were
granted, undisputedly contains an arbitration clause, specifically Clause 50,
titled as “Demand for Arbitration.”
11.
He submits that in light of the said clause, notices dated 14.11.2024
and 12.03.2025 were issued by the petitioner to respondent no.1, for
invoking the arbitral process.
12. He further submits that the Performance Bank Guarantee (PBG)
amounting to Rs. 3,71,150/-, which was furnished by the petitioner on
29.07.2020 to respondent no. 2 in terms of the second LOA, remains
unreturned. It is also contended that a subsequent Fixed Deposit Receipt
(FDR) of an equivalent amount (Rs. 3,71,150/-), which was issued following
certain anomalies that arose in respect of the initial PBG, has similarly not
been returned to the petitioner.
13.
Per contra, Mr. Bhagwan Kumar Shukla, learned counsel for the
respondents, raised four contentions: firstly, the arbitration clause does not
designate New Delhi as the seat of arbitration; secondly, the invocation of
arbitration is barred by contractual limitation; thirdly, the agreement
contains a mandatory pre-arbitral conciliation clause; and fourthly, the
dispute falls within the category of „excepted matters‟ and is, therefore, nonarbitrable.
14.
He further submits that petitioner‟s claim, regarding the non-return of
the Performance Bank Guarantee (PBG) amounting to Rs. 3,71,150/- and
Fixed Deposit Receipt (FDR) of an equivalent amount (Rs. 3,71,150/-) is
entirely misplaced. He contends that the said PBG and FDR has, in fact,
been returned to the petitioner.
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
15.
Having perused the record and heard the learned counsel for the
parties, this Court finds no merit in the objections raised by the learned
counsel for the respondents.
16.
The existence of the Tender Notice and the LOAs is not in dispute;
consequently, the arbitration clause (Clause 50) is also admitted. A perusal
of Sub-clause 50.1(c) reveals that the place of arbitration shall be the
headquarters of the concerned railway. In the present case, the concerned
railway is the Northern Railways, which has its headquarters at “Baroda
House, New Delhi.” Therefore, the respondents‟ contention that the clause
does not designate New Delhi as the seat of arbitration is misplaced and
factually incorrect.
17.
Furthermore, while exercising jurisdiction under Section 11(6) of the
Act, the Court is required to prima facie satisfy itself as to the existence of a
valid arbitration clause, a requirement which stands satisfied in the present
case.
18.
As regards the submission that invocation of arbitration is barred by
contractual limitation, it noted that the petitioner‟s claim for reimbursement
of GST amount was denied by the respondent no. 2 vide letter dated
28.05.2024, and the first request for the appointment of an arbitrator was
made on 14.11.2024, which is after 120 days but before 180 days as
provided in clause 50.1(i).
19.
Even otherwise, the law is well settled that even if arbitration clause
postulate the period within which a claim could have been raised by the
parties to the contractual agreements, such a stipulation in a contractual
obligation would not be valid and binding in view of Section 28 of the
Contract Act, 1872. Reference in this regard may be had to a decision of
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
Hon‟ble Supreme Court in Grasim Industries Limited v. State of Kerala;
(2018) 14 SCC 265. In the said decision the High Court had held that when
the arbitration clause itself prescribes a time-limit for raising the disputes by
appointing an Arbitral Tribunal and to have it settled within 30 days, the
same procedure should be followed or adopted within the time specified.
However, the Hon‟ble Supreme Court observed that the arbitration clause
did not postulate the period within which a claim could have been raised by
the parties to the contract; nevertheless, any such stipulation in the
arbitration clause would not be valid and binding. The relevant extract from
the said decision reads thus:
8. Based on the aforesaid clause, the High Court had recorded its
conclusion as under : (Grasim Industries Ltd. [Grasim Industries
Ltd. v. State of Kerala, 2003 SCC OnLine Ker 630 : (2004) 1 KLT
981] SCC OnLine Ker para 10)
“10. … In view of the specific provision in the arbitration
clause for raising the claim within the same year and to have it
settled by the Arbitral Tribunal within the specified time, the
above request for arbitration was beyond the period prescribed
in the arbitration clause. When the arbitration clause itself
prescribes a time-limit for raising the disputes by appointing an
Arbitral Tribunal and to have it settled within 30 days, the same
procedure should be followed or adopted within the time
specified. The applicant did not make a demand for appointment
of an Arbitral Tribunal within the stipulated time. The notice itself
was issued long after the time stipulated in the arbitration
agreement. It appears that the company was closed down and the
company wanted to dispose of the raw materials and the State did
not permit as materials had been supplied to the company at a
concessional rate. It was at that time the notice was issued for the
arbitration.”
9. Having perused Clause 9 of the supplementary agreement dated
27-10-1988, we are of the view that the interpretation placed by the
High Court on Clause 16, was wholly misconceived. The aforesaid
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
clause, did not postulate the period within which a claim could have
been raised by the parties to the contractual agreements. Even
otherwise, we are of the view that in terms of Section 28 of the
Contract Act, 1872, such a stipulation in a contractual obligation
would not be valid and binding.
xxxx
xxxx
xxxx
11. Section 28(b) unequivocally provides that an agreement which
extinguishes the right of a party on the expiry of a specified period,
would be void. Therefore, even if a restricted period for raising an
arbitral dispute had actually been provided for (as was determined
in the impugned order), the same would have to be treated as void.
12. In view of the legal position expressed hereinabove, the
limitation with reference to the claim raised by the appellant, would
have to be determined only under Article 137 of the Limitation
Act……”
(emphasis supplied)
20.
It now settled proposition of law that the period of limitation for
making a request under section 11(6) of the Act is three years in terms of
Article 137 of the Limitation Act, 1963, and the limitation is to be counted
from the date on which 30 days from the date of notice by one party to the
other for appointing arbitrator expires.1 In the present case the first request
for appointment of an arbitrator was made by the petitioner vide notice dated
14.11.2024 and the petition was filed on 18.11.2025, therefore, the petition
is clearly within the period of limitation.
21.
With respect to the contention raised by Mr. Shukla, that the existence
of a pre-arbitral conciliation clause is mandatory and must be exhausted
before invoking arbitration, this Court finds such an argument to be
misconceived. It has been held in various decisions of this Court that such
pre-arbitral tiers are directory in nature and not a mandatory bar to the
Arif Azim Company Ltd. v. Aptech Ltd., (2024) 5 SCC 313
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
invocation
of
arbitration.
In Jhajharia
Nirman v. South
Western
Railways, 2024 SCC OnLine Del 7133, a Coordinate Bench of this Court,
dealing with a similar arbitration clause in a Railway Contract, has observed
that any pre-condition in an arbitration agreement binding one of the
contracting parties to either exhaust the pre-arbitral amicable resolution
procedures or to take recourse to conciliation are directory, and not
mandatory in nature.
22.
Likewise,
in Oasis
Projects
Ltd. v. National
Highway
&
Infrastructure Development Corporation Limited, (2023) 1 HCC (Del)
525, this Court had observed as under:
“12. The primary issue to be decided in the present petition is,
therefore, as to whether it was mandatory for the petitioner to
resort to the conciliation process by the Committee before
invoking arbitration. Though Article 26.2 clearly states that
before resorting to arbitration, the parties agree to explore
conciliation by the Committee, in my opinion, the same cannot
be held to be mandatory in nature. It needs no emphasis that
conciliation as a dispute resolution mechanism must be
encouraged and should be one of the first endeavours of the
parties when a dispute arises between them. However, having said
that, conciliation expresses a broad notion of a voluntary process,
controlled by the parties and conducted with the assistance of a
neutral third person or persons. It can be terminated by the
parties at any time as per their free will. Therefore, while
interpreting Article 26.2, the basic concept of conciliation would
have to be kept in mind.”
(emphasis supplied)
23.
Similar view has been taken in a recent decision of a coordinate bench
of this court in JCC Infraprojects Bil JV v. North Western Railway Jaipur
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
Rajasthan, Through General Manager and Others; 2026 SCC OnLine Del
285.
24.
Lastly, it was argued by Mr. Shukla, that the present dispute falls
within the category of „excepted matters‟ and is thus non-arbitrable. In this
regard it may observed that a particular claim falls within the scope of
“Excepted Matters” is itself an aspect that is best left to be decided by a duly
constituted Arbitral Tribunal as determination of arbitrability of claims
requires detailed examination of the factual matrix. This position is in
consonance with the decision of a coordinate bench of this court in N.K.
Sharma Vs. The General Manager Northern Railway; [ARB.P. 893/2022];
dated 01.12.2023, wherein, the court examined a similar clause (Clause
63.1) providing for „excepted matters‟, and observed as under –
“18. This Court has also perused the invocation letter dated
01.06.2022 and prima facie, none of the claims raised therein falls
within „excepted matters‟. However, this aspect would require an
in-depth examination of the factual matrix which can be done by
a duly constituted Arbitral Tribunal, as contemplated in the
judgment of the Supreme Court in Vidya Drolia v. Durga Trading
Corpn., (2021) 2 SCC 1.”
(emphasis supplied)
25. The aforementioned position is further fortified by another decision of
this Court in Techno Global Services Private Limited Vs. Gail India
Limited & Anr; [O.M.P. (I) (COMM.) 251/2024]; dated 14.11.2024,
wherein following pertinent observations qua the „excepted matter‟ were
made –
“15. It is noticed that the relief qua payment of outstanding
amounts as referred to in the notice invoking arbitration and
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
interest thereon cannot be said to be ex facie barred. Also,
whether or not the other reliefs falls within the scope of
“Excepted Matters” is an aspect which will require an
interpretative exercise construing the relevant terms of the
contract between the parties in juxtaposition with the relief
sought to be claimed.
16. It has been held in a number of cases that the decision as to
whether, a particular claim falls within the scope of “Excepted
Matters” is itself an aspect that is best left to be decided by a duly
constituted Arbitral Tribunal. In this regards, reference is
apposite to the judgments of this Court in N.K Sharma v. General
Manager Northern Railway, 2023 SCC OnLine Del 7576 and
Braithwaite Burn and Jessop Construction Co. Ltd v. Northern
Railway, 2023 SCC OnLine Del 8176.
17. Importantly, in SBI General Insurance Co. Ltd. Vs. Krish
Spinning, 2024 INSC 532 and Interplay between Arbitration
Agreements under the Arbitration & Conciliation Act, 1996 &
the Indian Stamp Act, 1899, In re, 2023 SCC OnLine SC 1666
and it has now been exclusively and authoritatively laid down that
the scope of enquiry in the present proceedings is confined to
ascertaining the existence of an Arbitration Agreement and
“nothing else”.
(emphasis supplied)
26.
In view of the above, there is no merit in the objections raised by the
learned counsel for the respondents. The petition is thus allowed.
27.
Accordingly, dispute between the parties is referred to arbitration of
Mr. Amandeep Joshi, Advocate, D/1089/2006, [Mob.9818065100].
28.
The arbitration will be held under the aegis of Delhi International
Arbitration Centre, Delhi High Court, Sher Shah Road, New Delhi – 110003
[“DIAC”] and shall be governed by the Rules of DIAC including as to the
remuneration of the learned Arbitrator.
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
29.
The learned Arbitrator is requested to furnish a declaration under
Section 12 of the Act prior to entering upon the reference.
30.
It is made clear that all the rights and contentions of the parties are left
open for adjudication by the learned Arbitrator.
31.
Petition Stands disposed of in the above terms.
VIKAS MAHAJAN, J
MARCH 20, 2026/N.S. ASWAL
Digitally Signed
By:DEEPAK SINGH
07:51:03
ARB.P. 2139/2025
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review