The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
14. For all what has been said, analysed and discussed hereinabove, the present petition is disposed of by directing respondent Nos. 1 and 2 to release the requisite payment in favour of the petitioner for the works mentioned at Serial Nos. 1, 3, 4, 5, 8, 10, 11, 14, 15, 16, 19, 21 and 23 and respondent Nos. 1, 4 and 5 are directed to release the payment regarding the works mentioned at Serial Nos. 2, 6, 7, 9, 12, 13, 17, 18, 20 and 22 of the minutes of the meeting dated 14.11.2023 within a period of three months from the receipt of this order, failing which, the petitioner shall be entitled to interest at the rate of 6% per annum from the date of filing of this petition.
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
Uploaded 12.08.2026
WP(C) No. 1585/2023(O&M)
…..Appellant(s)/Petitioner(s)
Abdul Rashid Malik
Through: Mr. Arshad Hussain, Adv.
Mr. Rahoof Khan, Adv.
Q
vs
.…. Respondent(s)
U. T. of J&K and others
Through: Ms. Monika Kohli, Sr. AAG with
Ms. Sagira Jaffer, Adv.
Ms. Pallvi Sharma, Adv. vice
Mr. Ravinder Gupta, AAG
CORAM: HON’BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
ORDER
10.08.2026
1.
The petitioner has filed the present petition for directing the respondents to
release admitted pending amount of ₹28.932/- lacs for the work of
restoration of roads, executed by him in the year 2014 & 2019 duly
authenticated by the Tehsildar Chassana/Mahore.
2.
It is stated by the petitioner that he approached respondent No. 2 for release
of pending amount, but the same has not been released till date, despite the
fact that respondent No. 5 vide communication dated 26.04.2023 has
admitted petitioner’s entitlement to the above mentioned amount. The
petitioner further claims to have submitted the representation dated
15.05.2023 but the same has not been decided by the respondents.
3.
Respondent Nos. 3 and 5 have filed the response, stating therein that neither
any agreement was executed between the petitioner and the then Executive
Engineer, PWD (R&B), Special Sub-Division Mahore nor there was any
administrative approval, technical sanction or tendering process regarding
the works allegedly executed by the petitioner. Therefore, the present
petition is liable to be dismissed. The petitioner has a remedy of filing civil
suit against the respondents. It is further stated by the respondents that the
present petition has been filed after about 9/4 years, as such, the same is
hopelessly time barred. As per available record, the details of works
executed were submitted to Chief Planning Officer, Reasi and further, the
details of all the works executed by the contractor/petitioner with remarks
against each work were submitted to the Additional District Development
Commissioner, Reasi by the respondent No. 5 vide communication dated
04.08.2023. It is also urged that the said works came to be executed on the
verbal instructions by the District Administration in view of the emergent
situation, by the contractor and the said work was executed during the
period between years 2014 and 2019 under the State Disaster Response
Fund (SDRF). The claim of the petitioner was put up in SDRF meeting held
on 13.11.2023 and in the said meeting, it was informed to the Committee
members that the works have been executed departmentally without
following any codal formalities i.e. accord of administrative approval,
technical sanction and tendering process. Moreover, the Tehsildar Chassana
in his report informed the Committee that no such types of incidents like
rainfall/cloud burst/flash floods are mentioned in the records of concerned
Police Station/Chowki. Accordingly, the Committee decided to reject
WP(C) No. 1585/2023
SDRF claims of the contractor/petitioner at S. Nos. 1, 3, 4, 5, 8, 10, 11, 14,
15, 16, 19, 21 and 23 on the report submitted by the Executive Engineer,
PWD(R&B) Division Mahore and Tehsildar Chassana and the works at Sr.
Nos. 2, 6, 7,9, 12, 13, 17, 18, 20 and 22 were rejected by the Committee
since these were not covered under the SDRF norms. Further the claim of
the petitioner came to be rejected by respondent No. 2 vide his
communication dated 14.11.2021.
4.
The right of other respondents to file response was closed in terms of order
dated 15.09.2025. However, respondent Nos. 1, 2, & 4 in terms of an
application have placed on record the minutes of the meeting held on
13.11.2023 and signed on 14.11.2023, whereby the claim of the petitioner
was rejected.
5.
Learned counsel for the petitioner has vehemently argued that the petitioner
had undertaken and executed the works entrusted to him by the respondents
during the years 2014 and 2019, but despite completion of the works, the
legitimate and admitted dues payable to the petitioner have not been
released by the respondents. Learned counsel submits that the petitioner has
repeatedly approached the concerned authorities for release of the
outstanding amount and has also submitted representation. However,
despite such requests, no effective action has been taken by the
respondents, nor has any cogent reason been communicated to the
petitioner for withholding the payment.
6.
On the other hand, learned counsel for the respondents submits that neither
any agreement was executed between the petitioner and the then Executive
Engineer, PWD(R&B), Special Sub-Division Mahore, nor there was any
WP(C) No. 1585/2023
administrative approval, technical sanction or tendering process. He has
further argued that the present petition has been filed after a delay of about
of 9/4 years, as such, the same is hopelessly time barred.
7.
Heard learned counsel for the parties and perused the record.
8.
The first contention raised by the respondents is that the instant writ
petition has been filed belatedly. However, vide communication dated
26.04.2023 addressed by respondent No. 5 to respondent No. 4 i.e. the
Chief Planning Officer, Reasi, states that the petitioner has executed the
works during the year 2014 and 2019 under SDRF and the detailed
estimates were duly authenticated by the Tehsildar Mahore/Chassana for an
amount of ₹28.932/-. The respondents have not at all denied the said
communication. Rather the Executing Department in its response has
admitted that the work was executed by the petitioner, but the codal
formalities were not followed.
9.
So far as the contention of the respondents with regard to the applicability
of doctrine of delay and laches in the present petition is concerned, it needs
to be noted that the execution of the work has been admitted by the
respondents, though they have subsequently rejected the claim of the
petitioner in terms of SDRF meeting held on 13.11.2023 allegedly on the
basis of the report obtained from the SHO Police Station Chassana dated
10.11.2023. This clearly shows that the respondents have not at all denied
the execution of the works by the petitioner, but have rather admitted the
same. If the works were executed by the petitioner in connivance with the
officials of the respondents, then what steps have been taken by them
against their officials. It has become routine for the Government to deny the
WP(C) No. 1585/2023
legitimate claims of contractors by raising false and mis-conceived pleas.
This is a classic case, where the claim has been rejected on the basis of
report of Tehsildar, who, in turn, had obtained a report regarding the
rainfall/landslides form the Police, whereas in the communication dated
26.04.2023 it is specifically mentioned that the works have been
authenticated by Tehsildar concerned.
10.
This Court in Rattan Singh Parmar vs. Union Territory of J&K and
others, 2025:JKLHC-JMU-444, has already considered the issue of delay
and laches in approaching the court for redressal of the grievances by the
contractor and has observed in paras 9, 10, 12, 13 and 14 as under:
“09. The only issue that requires consideration is as to whether the
respondents can take plea of delay and laches to object the claim of
the petitioner, once they are admitting that the balance amount of
Rs. 22.74 lacs is payable to the petitioner.
10.
India is a welfare State and is 5th largest economy of the
world. The Government, in order to develop infrastructure to ease
the life of the residents of this country, has been collaborating with
the private sector. A Contractor may be a man of means or a small
contractor, who executes the work, often after borrowing loan from
Financial Institutions, with a hope that the amount due to him
would be released in his favour after the completion of work or as
per the terms and conditions of agreement. The delay in releasing
payment for one reason or another for the work carried out by the
small contractor often puts the small contractor in financial
doldrums and may result into bankruptcy bringing the contractor
and his family to the brink of starvation and vagrancy. The
Government must put in place the mechanism in place so that the
situation that has arisen in this case does not arise in future.
11.........
12.
In terms of Article 300-A of the Constitution of India, no
person can be deprived of his property save by authority of law.
When a contractor executes work to the satisfaction of the
Government, more particularly when there is admission on the part
of the respondent with regard to the completion of the work by the
petitioner, non-payment of the same cannot be denied only on the
ground that the petition has been filed after an inordinate delay.
13.
In Madras Port Trust v. Hymanshu International, the
Hon’ble Supreme Court has held as follows:
WP(C) No. 1585/2023
“2. We do not think that this is a fit case where we should proceed
to determine whether the claim of the respondent was barred by
Section 110 of the Madras Port Trust Act (II of 1905).
The plea of limitation based on this section is one which the court
always looks upon with disfavor and it is unfortunate that a public
authority like the Port Trust should, in all morality and justice, take
up such a plea to defeat a just claim of the citizen. It is high time
that governments and public authorities adopt the practice of not
relying upon technical pleas for the purpose of defeating legitimate
claims of citizens and do what is fair and just to the citizens. Of
course, if a government or a public authority takes up a
technical plea, the Court has to decide it and if the plea is wellfounded, it has to be upheld by the court, but what we feel is
that such a plea should not ordinarily be taken up by a
government or a public authority, unless of course the claim is
not well-founded and by reason of delay in filing it, the
evidence for the purpose of resisting such a claim has become
unavailable. Here, it is obvious that the claim of the respondent
was a just claim supported as it was by the recommendation of the
Assistant Collector of Customs and hence in the exercise of our
discretion under Article136 of the Constitution, we do not see any
reason why we should proceed to hear this appeal and adjudicate
upon the plea of the appellant based on Section 110 of the Madras
Port Trust Act (II of 1905).
3. We accordingly revoke the special leave granted to the appellant,
and direct that theappellant do pay the cost of the respondents.”
(emphasis added)
14.
In Vidya Devi v. State of H.P1, Hon’ble Supreme Court
of India has held under:
“12.12. The contention advanced by the State of delay and laches
of the appellant in moving the Court is also liable to be rejected.
Delay and laches cannot be raised in a case of a continuing cause
of action, or if the circumstances shock the judicial conscience of
the Court. Condonation of delay is a matter of judicial discretion,
which must be exercised judiciously and reasonably in the facts
and circumstances of a case. It will depend upon the breach of
fundamental rights, and the remedy claimed, and when and how
the delay arose. There is no period of limitation prescribed for the
courts to exercise their constitutional jurisdiction to do substantial
justice.
11.
Thus, in that view of the matter, the respondents being the welfare State
cannot raise the plea of delay and laches, particularly when the execution of
the work has been admitted by the respondents. Insofar as the minutes of
WP(C) No. 1585/2023
the meeting dated 13.11.2023 relied upon by the respondents in rejecting
the SDRF claim of the petitioner, it needs to be noted that the report of
Tehsildar based on information obtained from the SHO Police Station,
Chassana has only been used as a camouflage to deny the justified claim of
the petitioner. The list of the works executed by the petitioner appended
with the communication dated 04.08.2023, clearly demonstrates that the
works were executed and the estimates were duly sent by the officials of the
PWD(R&B) Department. The contention of the respondents that the codal
formalities were not followed by the petitioner is misconceived.
12.
This Division Bench of this Court in LPA No. 137/2020 titled, Union
Territory of J&K and others vs. Sanjeev Kumar, decided on 23.02.2021
has held as under:
“09. The enquiry reports mentioned above on which the appellants
seek to place reliance today was never placed before the writ Court
and was not a part of the writ Court record. Even the objections
filed by the Planning Department as also the J&K Housing Board
do not suggest that there was any apprehension in the mind of the
Planning Department or the Housing Board with regard to the
manner in which the contracts stood allotted to the
petitioner/respondent herein. While it may be true that certain
codal formalities might not have been followed before the
allotment of the contract in favour of the respondent herein, yet
the Government as also the Housing Board permitted not only
the allotment of contract but also its completion at the relevant
point of time.
10. The petitioner who was allotted the contract by the Housing
Board cannot be expected to first verify as to whether the
contract that has been allotted to him was being executed
within the territorial jurisdiction of the Housing Board or not,
nor was he expected to refuse the execution of the work simply
because the subject matter of the work was not put to open
tendering system. Needless to say that the contractor did
execute the works upon being allotted to him for which some
amount is certainly due to him.
(emphasis added)
WP(C) No. 1585/2023
13.
The decision taken by the Committee in its meeting dated 13.11.2023 to
reject the claim of the petitioner is not justified.
14.
For all what has been said, analysed and discussed hereinabove, the present
petition is disposed of by directing respondent Nos. 1 and 2 to release the
requisite payment in favour of the petitioner for the works mentioned at
Serial Nos. 1, 3, 4, 5, 8, 10, 11, 14, 15, 16, 19, 21 and 23 and respondent
Nos. 1, 4 and 5 are directed to release the payment regarding the works
mentioned at Serial Nos. 2, 6, 7, 9, 12, 13, 17, 18, 20 and 22 of the minutes
of the meeting dated 14.11.2023 within a period of three months from the
receipt of this order, failing which, the petitioner shall be entitled to interest
at the rate of 6% per annum from the date of filing of this petition.
(RAJNESH OSWAL)
JUDGE
Jammu
10.08.2026
Rakesh PS
Whether the order is speaking:
Whether the order is reportable:
Rakesh Kumar
2026.08.12 13:06
I attest to the accuracy and
integrity of this document
Jammu
WP(C) No. 1585/2023
Yes/No
Yes/No
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review