Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
2026:HHC:19374
IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA.
CARBC No. 44 of 2025
Reserved on: April 30, 2026
Decided on: May 22, 2026
Uploaded on: May 26, 2026
________________________________________________________
Vijay Kumar Sharma
……….. Petitioner
Versus
The State of H.P. and others
.. Respondents
________________________________________________________
Coram:
Hon’ble Mr. Justice Sandeep Sharma, Judge.
Whether approved for reporting? 1 Yes.
For the petitioner
Ms. Madhu P. Singh and
Parveen Chauhan, Advocates.
For the respondents
Mr. Navlesh Verma,
Advocate General.
Mr.
Additional
________________________________________________________
Sandeep Sharma, Judge
Instant objections filed under S.34 of the Arbitration and
Conciliation Act (hereinafter, ‘Act’), as amended upto date, lays
challenge to award dated 24.7.2023, passed by respondent No.4-Sole
Arbitrator with a prayer to set aside the award qua claim 1(b) and to
modify the same qua claim 1(a) and 2.
2.
Quintessential facts, as emerge from record and pleadings of
parties are that vide letter No. PW.rMP.2016-2725-26, dated 5.5.2016,
respondents invited tenders for “C/o 55.00 mtr. Span Box double lane
bridge over Rai Khad including both side approaches on Rampur
Gaura Mashnoo Sarahan Jeori road at RD 52/095 in Tehsil Rampur,
District Shimla, Himachal Pradesh under CRF (Job No. CRF-HP-201516 84).”
Whether the reporters of the local papers may be allowed to see the judgment?
3.
2026:HHC:19374
On 15.6.2016, respondents uploaded departmental GAD No.
609/Bridge/2016-17 alongwith other documents and last date of receipt
of tender was 23.6.2016. On 21.6.2016, petitioner uploaded technical
proposal alongwith bid. On 17.8.2016, after receipt and elevation of
Technical Bids, technically qualified bidders were called for the meeting
for Normalization of Conditions and the successful bidders after
technical elevation were given chance to give revised financial bids.
The petitioner participated in this meeting and minutes of meeting
became part of the agreement. In the meeting of Normalization of
Conditions, the variations and deviations and price to be paid therefor
was finalized as per Paras 27 and 28 of Minutes of Meeting of meeting,
forming part of the agreement dated 4.11.2016.
4.
After meeting petitioner herein was declared successful bidder
and his Financial Bid for Rs.7.50 Crore was accepted by the
Department and Letter of Acceptance was duly signed by the parties
for execution of the work in question, for determining the rights and
obligations of the parties. In terms of clause 31.1 of agreement,
Engineer-in-Chief may make any alterations, additions to or omission
from the work as described in the tender documents, including change
in the lines, levels, positions and work dimensions of any part of the
work, that may, in his opinion, be necessary and for that purpose, he
shall have absolute power to order the contractor to do and the
contractors shall carry out the same as provided in the agreement.
5.
As has been taken note herein above, during evaluation of
Technical Bid, respondents held a meeting on 17.8.2016, for
Normalization of Conditions as per tender documents. Under condition
2026:HHC:19374
No. 30 and 31 of the Normalization of Conditions, the prospective
bidders agreed that geological/ sub soil investigation for ascertaining
the strata beneath the natural ground levels (and confirming the safe
founding levels for susbstructure) is required to be carried out and logs
chart of test boring is also required to be prepared as per IRC78 (latest
edition). The safe bearing capacity test shall be conducted. Nothing
extra shall be paid by the Department for carrying out these
investigations. This will also include ascertaining the actual silt factor
at the proposed founding levels or proposing fixing of founding levels
on the basis of log charts. The prospective contractor’s liability to
conduct sub soil investigation was decided and accepted by the parties
on 17.8.2016, after submission of bids on 23.6.2016.
6.
As per condition No. 27 of Normalization of Conditions, for any
deviation/variation, instead of Clauses 31, 59 and 60 of the contract
document, the Schedule of Variation items was made applicable. It was
agreed that levels for ascertaining the increase/ decrease in depth of
foundation and raising/lowering of deck levels and increase/ decrease
span shall be with respect to parameters in the finally approved GAD
based upon sub soil investigations and geotechnical report to be
conducted by contractor. It was further agreed that portion of bridge
beyond the faces of abutments i.e. portion of the bridge over the river
shall be considered as part of superstructure and the remaining portion
as part of sub-structure for operation of the payment schedule
mentioned in the Normalization of Conditions dated 17.8.2016 and
thus, the sub soil investigations were required to be conducted by the
contractor after acceptance of the tender. On 17.8.2016, after opening
2026:HHC:19374
of the Technical Bids, an obligation was cast upon the claimant to get
the sub soil investigation and geo-technical report.
7.
Before finalizing the Financial Bid of the objector, the L-1 bidder,
negotiation was held by the respondents with the claimant on
5.10.2016 wherein his quoted lump sum rates of Rs.7.76 Crores was
reduced to Rs.7.50 and further said amount was bifurcated by the
claimant on strenuous persuasion by them and the lump sum tender
amount was lowered as under:
i) Construction of bridge part
Rs.460.00 Lakh
ii) Construction of approaches portion
Rs.290.00 Lakh
Total
8.
Rs.750.00 Lakh
In the said negotiation meeting, the claimant agreed that the
amount of Rs.460.00 Lakh as negotiated will be applicable for the
increase/ decrease in span on pro-rata basis. In case the span of
bridge increases, the contractor agreed that the rebate for construction
of approaches from bridge side shall be as per the rate of increase or
decrease of bridge payable to him. The negotiated financial terms
dated 5.10.2016 forms the part of the agreement dated 4.11.2016.
9.
In afore background, claimant was declared lowest bidder, who
pursuant to being declared success bidder executed agreement dated
4.11.2016. The investigations regarding sub soil condition and geotechnical reports were got done by the claimant from Government
approved labs. Revised GAD dated 31.1.2017 was approved by the
competent authority and claimant submitted re-revised GAD (SrahanS0IR alongwith a forwarding letter dated 28.5.2017, wherein he had
clearly urged the respondents to analyze the specific or implied
2026:HHC:19374
complexities ramifications and implications of the re-revised proposal
S-01(R-2) vis-à-vis
variations alongwith physical, technical and
financial viability to its entirety, within the framework of the agreement
and if found suitable at the departmental end, the approval of the same
be conveyed to facilitate further submission of drawings and designs.
10.
As per this GAD the founding level for Sarahan side abutment,
A-1 was proposed as 1944.00 mts and for Jeori side abutment, A-2 it
was fixed as was 1925.0 mts with safe bearing capacity for Sarahan
side abutment as 123.22 tonne/sqm and for Jeori side abutment as
129.02 tonne/sqm. However, the Department considered bearing
capacity of 45 tonne/ sqm for designing the two abutments. Upon
excavation for Sarahan Side abutment foundation upto the level of
1946.38 mts hard rock in the entire foundation area was found.
However, for Jeori side abutment, upon excavation upto 1928 mts no
hard rock was found which could provide required safe bearing
capacity of 45 tonne/smt.
11.
On 26.4.2017, a joint inspection of the site was conducted by
the Executive Engineer of the department alongwith the Design
Consultant Mr. V.S. Verma of the petitioner wherein it was decided to
check the bearing capacity for Jeori side abutment at level 1928.00
mtrs. Upon verification by the technical expert the bearing capacity of
35.45 tonne/sqm was found at location of abutment A2. The Design
Consultant further opined that an abutment having a height of 29 mtrs
cannot be stabilized on the strata having bearing capacity of 35.45
tonne/sqm. The prevalent soil classification of silt mixed with gravel can
create uncontrollable situation during increased water presence at the
2026:HHC:19374
founding level. Therefore, the design consultant concluded that
abutment A-2 is required to be substituted with a Pier with extra
provision for abutment for an additional dry span of 27 mts to manage
load dispersal within recommended norms. Accordingly, re-revised
GAD was submitted on 28.5.2017.
12.
On 21.5.2017, claimant submitted Geo technical report (GTR).
Though as per Notice inviting Tender as well as agreement, the span
of bridge was 55.00 mts, whereas, as Geo-technical report dated
21.5.2017, and due to sub soil conditions prevailing on Jeori side, the
total span of the constructed bridge was extended to82.00 metres
alongwith a central pier and therefore re-revised GAD No. SAPRAHAN
S-01(R-2) with span arrangement of 2 Abutments and central Pier and
geo-technical
Department
report
dated
21.5.2017
were
submitted
to
the
alongwith request to consider the specific and implied
complexities, ramifications and implications of the re-revised proposal
S-01( R-2) with variations alongwith physical technical and financial
viability to be examined in its entirety within the framework of the
agreement and if found suitable, approval to be conveyed.
13.
On
Department
30.5.2017,
sent
the
Executive
re-revised
Engineer
of
GAD
dated
the
respondent
28.5.2017
to
Superintending Engineer, for approval and allegedly added without
consent of claimant that he had verbally agreed not to claim extra
amount for construction of dry span of 27.00 metre as per re-revised
proposal and claimant was directed to appear in the office of Chief
Engineer, South zone to submit undertaking regarding ‘No Claim’.
2026:HHC:19374
14.
On 1.6.2017, claimant, claimant gave his no claim certificate
undertaking therein that if his revised GAD is approved, which have
one pier and two spans of 55.00 metres and 27.00 metres (on Jeori
side), he will construct the bridge on the same awarded cost of
Rs.750.00 Lakh only and will not claim anything extra on this account
in future and this would be full and final settlement and the claimant will
not seek any arbitration or approach any court of law in this regard.
(available at page 252 of paper book).
15.
On 8.6.2017, respondents released re-revised GAD with the
stipulation pasted on it that the bridge under consideration alongwith
the approaches shall be constructed at the awarded amount of Rs.7.50
Crore and contractor will not claim anything extra in this account. The
approved GAD showed two spans of bridge 55.00 metres and 27.00
metres and construction of pier for safe bearing capacity as per geotechnical reports. As per agreement, stipulated date of completion of
work was 18.11.2011 but actually the work was completed on
14.11.2019, after seeking extensions from the Department, from time
to time, on the grounds accepted by the Department.
16.
Claimant raised construction of
82.00 metres bridge as per
revised-GAD, approved on 8.6.2017 and 169.00 metre approach
towards Jeori side and 191.23 metres approach towards Sarahan side.
During construction period claimant submitted various bills as per
completion of various milestones and informed the department on
23.2.2019 that payment for the work done to the extent of 91.50% had
been made to him against the items of work as incorporated payments
schedule of the agreement but the payment of 27.00 metres
2026:HHC:19374
construction of extra span of bridge was not released to the claimant,
as per conditions of Normalization of Conditions, over and above the
contract price of Rs.7.50 Crore for construction of 55.00 metres bridge
in between the centre to centre of bearing and including construction of
155.00 metres Jeori side approach and 190.00 metres long approach
road on Sarahan side.
17.
Claimant, claimed that additional span of 27.00 metres in
between centre to cenre of bearing was payable to the claimant due to
increase in span from 55.00 metres to 82.00 metres and the payment
of said increase is admissible to the claimant, on pro rata rate of
Schedule of Variation of the agreement, as Normalization of Conditions
and accordingly, the claimant claimed extra cost payable over lump
sum initial contract price, 27.00 metre at the rate of Rs.7.50 Crore
/55.00 per metre length = Rs.3,68,18,182.00. The amount was not paid
to the claimant, hence, dispute arose inter se parties.
18.
The respondent No.3 did not accept the bill in totality and
recommended payment for Rs.2,25,81,818.00 and forwarded the claim
of the claimant for extra 27.00 metre bridge span to the Superintending
Engineer, 11th Circle, HPPWD Rampur. The claimant sent reminder for
refund of sales tax, payment of 10th and final bill, reimbursement of
GST, revised 10th and final bill for making payment including payment
for 27.00 metres span of bridge, the payment for which was approved
and recommended for approval of the competent authority, by
respondent No.3 on 20.4.2019. Since no action was taken by
respondents, claimant sent reminders dated 1.1.2020, 20.3.2020,
28.10.2020, 2.11.2020 for release of payment and refund of sales tax,
2026:HHC:19374
payment of 10th and final bill for making payment including the payment
for 27.00 metres span of bridge.
19.
Since no response from respondents was received, claimant
submitted requirement for appointment of sole arbitrator, to conduct
amicable settlement meeting followed by reminder for appointment of
arbitrator.
20.
In the afore background, Shri K.K. Kampani (Retired Engineer-
in-Chief) came to be appointed as Sole Arbitrator, who, taking note of
pleadings adduced by respective parties passed impugned Award
dated 24.7.2023, allowed claims Nos. 1(a) and 2 and rejected claims
Nos. 1(b), 3 and.
21.
In the afore background, claimant has approached this Court,
praying therein to set aside the impugned Award in respect of claims
No. 1(b) and 3 and further to award interest on the amounts awarded
under claims Nos. 1(a) and 2.
22.
Precisely, the grouse of the claimant, as highlighted in grounds
of objections as well as canvassed by learned counsel for the claimant
is that learned arbitrator has fallen in grave error while allowing claim
No.1(a) inasmuch as he failed to award interest with effect from
29.9.2017. Learned counsel for claimant vehemently argued that when
payment was wrongly deducted from 3rd running bill, non grant of
interest is against statutory provisions of Arbitration and Conciliation
Act. Learned counsel for the claimant further argued that the sole
arbitrator wrongly declined relief under claim No. 1(b) regarding
additional
cost
for
construction
of
27.00
metres
bridge
by
misinterpreting that 27.0 metre bridge is substitution to the contracted
2026:HHC:19374
length of 55.0 metres of bridge and its cost is already included in the
cost of approach roads on both sides of bridge and is covered under
contracted amount of Rs.7.50 Crore.
23.
Learned counsel for the claimant further argued that learned
Arbitrator has failed to consider agreed normalization conditions dated
17.8.2016, forming part of agreement and the ‘no claim’ letter extracted
from the claimant under duress and coercion duly drafted and
corrected by the respondents, having admitted during the course of
proceedings by respondents. It came to be further argued on behalf of
learned counsel for the claimant that learned Arbitrator, ignored
recommendations dated 20.4.2019, for release of payment for 27.00
metres extra bridge made by Er. Sandeep Kumar Sobti, who submitted
his affidavit in evidence but learned Arbitrator returned the affidavit
without examination in chief and cross-examination. Learned counsel
for the claimant further argued that learned Arbitrator failed to
appreciate the line diagram submitted by RW-7, wherein RW-7, has
categorically stated that on Jeori side, the claimant has executed an
approach road of 196.00 metres and he has been paid only for 169.00
metres approach against the bill raised by him for 196.00 metres
approach road. The difference of 196 and 169 metres comes to 27.00
metres, which in no manner is an approach but is a part of extended
bridge of 27.00 metres, as per re-revised GAD dated 8.67.2017 and no
payment against aid 27.00 metres length has been made to the
claimant.
24.
While referring to Annexure A-3, learned counsel for the
claimant argued that learned Arbitrator failed to appreciate the agreed
2026:HHC:19374
terms of agreement and the evidence on record to prove the
admissibility of Claim under this head. Learned counsel for the claimant
further argued that regarding claim No.2, learned Arbitrator allowed the
claim alongwith interest after one month of award and not awarded the
interest from 30.3.2021, when the said amount was due to the
claimant, which is contrary to provisions of S.31(7)(a) of the Act
25.
Learned counsel for the claimant further argued that learned
Arbitrator has fallen in grave error while rejecting claim qua arbitration
cost. Learned counsel for the claimant submitted that claimant
approached the respondent Department on 2.6.2021, for amicable
settlement of dispute and respondent did not take any steps to call a
meeting for amicable settlement, which necessitated the claimant to
approach respondents for appointment of Arbitrator and thus, claimant
is entitled to recover arbitration cost, which he has been forced to bear
due to acts of omission and commission on the part of respondents.
26.
Lastly, learned counsel for the claimant argued that on account
of interest on amounts as claimed under claim No. 1(a) and 2, interest
has not been granted as per provisions of S.31(7)(a) of the Act hence,
the award needs to be interfered with.
27.
Pursuant to notices issued in instant preceding respondent
State has filed detailed reply, wherein facts as have been taken note
herein above, have not been denied rather an attempt has been made
to refute claim of the claimant on the ground that no payment as is
being claimed through arbitration proceedings is payable rather,
claimant has been paid all due and admissible payment.
28.
2026:HHC:19374
Shri Navlesh Verma, learned Additional Advocate General
argued that no grounds within the purview of S.34 of the Act have been
made out, as such, no interference is called for. He submitted that the
award can be interfered only on the grounds as mentioned in
S.34(2)(a)(I) to S.34(2)(b)(II) of the Act and none of grounds raised in
the petition falls within the ambit of provisions of afore Section, hence,
the objections deserve dismissal.
29.
Learned Additional Advocate General submitted that as per
Normalization of Conditions, dated 17.8.2016, rebate was given to
contractor and same were accepted by him. He submitted that since
tender was on lump sum basis, rates for 55 metre span bridge
including the approaches coupled with the fact that portion beyond
faces of abutments mentioned with the claim i.e. portion of the bridge
as mentioned is not part of the bridge but the dry span of 27 metres
constructed by claimant is part of approaches, claimant is estopped
from claiming any separate payment qua construction of dry span of 27
metres. He submitted that had claimant not constructed dry span of 27
meter he would have constructed 54.00 metres on both sides counter
fort walls as per Condition No. 26 of Normalization of Conditions,
agreed by contractor on 17.8.2016, which would have resulted in extra
cost to the claimant and claimant constructed this dry span of 27
metres for his own convenience.
30.
Mr. Verma submitted that otherwise also as per own undertaking
given by claimant, he cannot claim any amount over and above
Rs.7.50 Crore. He submitted that the claimant agreed that amount of
Rs.460.00 Lakh as negotiated will be applicable for increase or
2026:HHC:19374
decrease in span on pro-rata basis and in case span of bridge
increases, the claimant agreed that
the rebate for construction of
approaches from bridge side shall be as per rate of increase or
decrease of bridge payable to the contractor. He submitted that nothing
was altered and claimant never challenged the award letter and
received all the payments on the basis of award letter, whereby he
came to be awarded the work.
31.
While disputing claim that respondents did not go into the
technical and financial viability of revised GAD dated 28.5.2017, Mr.
Verma, learned Additional Advocate General stated that it is wrong to
suggest that Executive Engineer, of his own, incorporated conditions
that contractor had agreed that he would not claim any extra for
construction of dry span of 27 metre as per revised proposal. Mr.
Verma stated that undertaking was voluntarily given by claimant and
there was no occasion for the Executive Engineer to procure such
undertaking. He submitted that hard rock was found in entire
foundation area of Sarahan side abutment, while loose soil on Jeori
side abutment and as per periling soil conditions, GAD was revised
with revised foundation level of both side abutments which was
approved by Chief Engineer (South Zone) office vide letter No.
PW(Bridges) Raikhad/2017-945-46, dated 29.3.2017 and due to loose
strata towards Jeori side abutment at revised foundation level of
1928.00 metre, the soil was tested to check bearing capacity at revised
level which as reported by M/s Geo Tech. Engineers and Consultant,
New Shimla was 34.45 Tonn per sqm, against the desired bearing
capacity of 45 tonne per sqm.
32.
2026:HHC:19374
Lastly Mr. Verma submitted that it is sole prerogative of learned
Arbitrator to award interest and in that regard, claimant cannot claim
interest, as a matter of right. With these submissions, Mr. Verma,
sought dismissal of the objections.
33.
I have heard the learned counsel for the parties and gone through the
record of the case.
34.
Before ascertaining the correctness of rival submissions made
by the learned counsel for the parties, this court finds it necessary to
elaborate upon the scope of the appellate court exercising jurisdiction
to review the findings of an award.
35.
By now it is well settled that scope of appellate Court in
exercising power under the Act to review the finding of an award is
narrow/limited, especially when award is upheld or substantially upheld
under Section 34 of the Act. Reliance in this regard is placed upon
judgment dated 11.8.2023, passed by the Hon’ble Apex Court in Civil
Appeal No. 3798 of 2023 titled as Larsen Air Conditioning and
Refrigeration Company v. Union of India, wherein it has been held
that Section 34 the Act, permits the Court to interfere with an award
sans the grounds of patent illegality to go to the root of the matter and
cannot be of a trivial nature. Relevant paras of the afore judgment
reads as under:
“15. The limited and extremely circumscribed jurisdiction of the court
under Section 34 of the Act, permits the court to interfere with an
award, sans the grounds of patent illegality, i.e., that “illegality must go
to the root of the matter and cannot be of a trivial nature”; and that the
tribunal “must decide in accordance with the terms of the contract, but
if an arbitrator construes a term of the contract in a reasonable
manner, it will not mean that the award can be set aside on this
2026:HHC:19374
ground” [ref: Associate Builders (supra)]. The other ground would be
denial of natural justice. In appeal, Section 37 of the Act grants
narrower scope to the appellate court to review the findings in an
award, if it has been upheld, or substantially upheld under Section 34.
It is important to notice that the old Act contained a provision (15.
Power of court to modify award.—The court may by order modify or
correct an award— (a) where it appears that a part of the award is
upon a matter not referred to arbitration and such part can be
separated from the other part and does not affect the decision on the
matter referred; or (b) where the award is imperfect in form, or
contains any obvious error which can be amended without affecting
such decision; or (c) where the award contains a clerical mistake or an
error arising from an accidental slip or omission.) which enabled the
court to modify an award. However, that power has been consciously
omitted by Parliament, while enacting the Act of 1996. This means
that the Parliamentary intent was to exclude power to modify an
award, in any manner, to the court. This position has been iterated
decisively by this Court in Project Director, National Highways No. 45E
and 220 National Highways Authority of India v M. Hakeem (2021) 5
SCR 368.
42. It can therefore be said that this question has now been
settled finally by at least 3 decisions [McDermott International
Inc. v. Burn Standard Co. Ltd.13], [Kinnari Mullick v.
Ghanshyam Das Damani14], [Dakshin Haryana Bijli Vitran
Nigam Ltd. v. Navigant Technologies (P) Ltd.15] of this Court.
Even otherwise, to state that the judicial trend appears to
favour an interpretation that would read into Section 34 a
power to modify, revise or vary the award would be to ignore
the previous law contained in the 1940 Act; as also to ignore
the fact that the 1996 Act was enacted based on the Uncitral
Model Law on International Commercial Arbitration, 1985
which, as has been pointed out in Redfern and Hunter on
International Arbitration, makes it clear that, given the limited
judicial interference on extremely limited grounds not dealing
with the merits of an award, the “limited remedy” under Section
34 is coterminous with the “limited right”, namely, either to set
aside an award or remand the matter under the circumstances
mentioned in Section 34 of the Arbitration Act, 1996.”
36.
Similarly, in Konkan Railway Corporation Ltd v. Chenab
Bridge Project Undertaking, 2023 (9) SCC 85, the Hon’ble Apex
2026:HHC:19374
Court has held that jurisdiction of the Court under Section 37 of the Act
is akin to that under Section 34 of the Act, as such, the courts ought
not to interfere with arbitral award in a casual and cavalier manner.
Most importantly, the Hon’ble Apex Court held that mere possibility of
an alternative view on facts or interpretation of contract does not entitle
Courts to reverse findings of the Arbitral Tribunal. Relevant paragraphs
from the decision are as follows:-
“19. Therefore, the scope of jurisdiction under Section 34 and Section
37 of the Act is not akin to normal appellate jurisdiction (UHL Power
Company Ltd. v. State of Himachal Pradesh (2022) 2 SCC (Civ) 401,
para 15. See also: Dyna Technologies Pvt Ltd v. Crompton Greaves
Limited (2019) 20 SCC 1, para 24, 25). It is well-settled that courts
ought not to interfere with the arbitral award in a casual and cavalier
manner. The mere possibility of an alternative view on facts or
interpretation of the contract does not entitle courts to reverse the
findings
of
the
Arbitral
Tribunal
(Ssangyong
Engineering.
&
Construction Company Ltd. v. National Highways Authority of India
(NHAI) (2019) 15 SCC 131; Parsa Kente Collieries Ltd. v. Rajasthan
Rajya Vidyut Utpadan Nigam Ltd., (2019) 7 SCC 236, para 11.1). In
Dyna Technologies Private Limited v. Crompton Greaves Limited
(2019) 20 SCC 1, this Court held:
“24. There is no dispute that Section 34 of the Arbitration Act
limits a challenge to an award only on the grounds provided
therein or as interpreted by various courts. We need to be
cognizant of the fact that arbitral awards should not be
interfered with in a casual and cavalier manner, unless the
court comes to a conclusion that the perversity of the award
goes to the root of the matter without there being a possibility
of alternative interpretation which may sustain the arbitral
award. Section 34 is different in its approach and cannot be
equated with a normal appellate jurisdiction. The mandate
under Section 34 is to respect the finality of the arbitral award
and the party autonomy to get their dispute adjudicated by an
2026:HHC:19374
alternative forum as provided under the law. If the courts were
to interfere with the arbitral award in the usual course on
factual aspects, then the commercial wisdom behind opting for
alternate dispute resolution would stand frustrated.
25. Moreover, umpteen number of judgments of this Court
have categorically held that the courts should not interfere with
an award merely because an alternative view on facts and
interpretation of contract exists. The courts need to be cautious
and should defer to the view taken by the Arbitral Tribunal
even if the reasoning provided in the award is implied unless
such award portrays perversity unpardonable under Section 34
of the Arbitration Act.
XX XX XXX
25. The principle of interpretation of contracts adopted by the
Division Bench of the High Court that when two constructions
are possible, then courts must prefer the one which gives
effect and voice to all clauses, does not have absolute
application. The said interpretation is subject to the jurisdiction
which a court is called upon to exercise. While exercising
jurisdiction under Section 37 of the Act, the Court is concerned
about the jurisdiction that the Section 34 Court exercised while
considering the challenge to the Arbitral Award. The
jurisdiction under Section 34 of the Act is exercised only to see
if the Arbitral Tribunal’s view is perverse or manifestly arbitrary.
Accordingly, the question of reinterpreting the contract on an
alternative view does not arise. If this is the principle applicable
to exercise of jurisdiction under Section 34 of the Act, a
Division Bench exercising jurisdiction under Section 37 of the
Act cannot reverse an Award, much less the decision of a
Single Judge, on the ground that they have not given effect
and voice to all clauses of the contract. This is where the
Division Bench of the High Court committed an error, in reinterpreting a contractual clause while exercising jurisdiction
under Section 37 of the Act. In any event, the decision in
Radha Sundar Dutta (supra), relied on by the High Court was
decided in 1959, and it pertains to proceedings arising under
the Village Chaukidari Act, 1870 and Bengal Patni Taluks
Regulation of 1819. Reliance on this judgment particularly for
2026:HHC:19374
interfering with the concurrent interpretations of the contractual
clause by the Arbitral Tribunal and Single Judge under Section
34 of the Act is not justified.”
37.
In Bombay Slum Redevelopment Corporation Pvt. Ltd. v.
Samir Barain Bhojwani (2024) 7 SCC 218, the Hon’ble Apex Court
reiterated that supervisory role of Courts is very restricted in dealing
with appeals under Section 37 of the Act. Hon’ble Apex Court has
further held that scope of interference in a petition under Section 34 of
the Act is very narrow and jurisdiction under Section 37 of the Act is
very narrower. Hon’ble Apex Court further held that since parties to the
lis themselves chose to go before the Arbitral Tribunal instead of
availing remedy before the traditional Civil Courts, Courts must be very
conservative while dealing with arbitral awards and confine themselves
to the grounds strictly available under Section 34 of the Act.
38.
In Reliance Infrastructure Ltd. v. State of Goa (2024) 1 SCC
479, Hon’ble Apex Court interpreting expression ‘patent illegality’ held
that mere a mere illegality is not a patent illegality, rather to interfere
patent illegality, illegality must be apparent on the face of the award
and not the one which is culled out by way of a long drawn analysis of
pleadings and evidence. Relevant paragraphs of the afore judgment
are being reproduced as under:
“57. As noticed, arbitral award is not an ordinary adjudicatory order so
as to be lightly interfered with by the Courts under Sections 34 or 37 of
the Act of 1996 as if dealing with an appeal or revision against a
decision of any subordinate Court. The expression “patent illegality”
has been exposited by this Court in the cases referred hereinbefore.
The significant aspect to be reiterated is that it is not a mere illegality
2026:HHC:19374
which would call for interference, but it has to be “a patent illegality”,
which obviously signifies that it ought to be apparent on the face of the
award and not the one which is culled out by way of a long-drawn
analysis of the pleadings and evidence.
58. Of course, when the terms and conditions of the agreement
governing the parties are completely ignored, the matter would be
different and an award carrying such a shortcoming shall be directly
hit by Section 28(3) of the Act, which enjoins upon an Arbitral Tribunal
to decide in accordance with the terms of contract while taking into
account the usage of trade applicable to the transaction. As said by
this Court in Associate Builders vs. DDA9, if an Arbitrator construes
the term of contract in a reasonable manner, the award cannot be set
aside with reference to the deduction drawn from construction. The
possibility of interference would arise only if the construction of the
Arbitrator is such which could not be made by any fairminded and
reasonable person.
95. The narrow scope of “patent illegality” cannot be breached by
mere use of different expressions which nevertheless refer only to
“error” and not to “patent illegality”. We are impelled to reiterate what
has been stated and underscored by this Court in Delhi Airport Metro
Express (P) Ltd. Vs. DMRC10 that restraint is required to be shown
while examining the validity of arbitral award by the Courts, else
interference with the award after reassessing the factual aspects
would be defeating the object of the Act of 1996. This is apart from the
fact
that
such
an
approach
would
render
several
judicial
pronouncements of this Court redundant if the arbitral awards are set
aside by categorizing them as “perverse” or “patently illegal” without
appreciating the contours of these expressions.”
39.
In S.V. Samudram v. State of Karnataka (2024) 3 SCC 623,
the Hon’ble Apex Court has concluded that though jurisdiction of Court
under Section 34 is fairly narrow and moreover, when it comes to
jurisdiction under Section 37, it is all the more circumscribed. The
relevant paras of the afore judgment read as under:-
2026:HHC:19374
“46. It has been observed by this Court in MMTC Ltd. v. Vedanta Ltd.
(2019) 4 SCC 163.
“14. As far as interference with an order made under Section 34,
as per Section 37, is concerned, it cannot be disputed that such
interference under Section 37 cannot travel beyond the
restrictions laid down under Section 34. In other words, the court
cannot undertake an independent assessment of the merits of the
award, and must only ascertain that the exercise of power by the
court under Section 34 has not exceeded the scope of the
provision. Thus, it is evident that in case an arbitral award has
been confirmed by the court under Section 34 and by the court in
an appeal under Section 37, this Court must be extremely
cautious and slow to disturb such concurrent findings.” (Emphasis
Supplied)
47. This view has been referred to with approval by a bench of three
learned Judges in UHL Power Company Ltd v. State of Himachal
Pradesh (2022) 4 SCC 116. In respect of Section 37, this court
observed:-
“16. As it is, the jurisdiction conferred on courts under Section
34 of the Arbitration Act is fairly narrow, when it comes to the
scope of an appeal under Section 37 of the Arbitration Act, the
jurisdiction of an appellate court in examining an order, setting
aside or refusing to set aside an award, is all the more
circumscribed.”
xx xx xx
49. We may also notice that the circumscribed nature of the exercise
of power under Sections 34 and 37 i.e., interference with an arbitral
award, is clearly demonstrated by legislative intent. The Arbitration Act
of 1940 had a provision (Section 15) which allowed for a court to
interfere in awards, however, under the current legislation, that
provision has been omitted (Larsen Air Conditioning and Refrigeration
Company v. Union of India and Ors. 2023 SCC OnLine 982 (2-Judge
Bench). 50. The learned Single Judge, similar to the learned Civil
2026:HHC:19374
Judge under Section 34, appears to have not concerned themselves
with the contours of Section 37 of the A&C Act. The impugned
judgment (S.V. Samudram v. State of Karnataka, 2017 SCC OnLine
Kar 6559) reads like a judgment rendered by an appellate court, for
whom reexamination of merits is open to be taken as the course of
action.”
40.
It is quite apparent from the aforesaid exposition of law laid
down by the Hon’ble Apex Court that scope of interference by this
Court while exercising power under Section 34 of the Act is very-very
limited. Courts should not interfere with an award merely because an
alternative view on facts and interpretation of contract exists, rather
courts need to be cautious and should defer to the view taken by the
Arbitral Tribunal even if the reasoning provided in the award is implied
unless such award portrays perversity unpardonable under Section 34
of the Act.
41.
Now being guided by aforesaid law on the subject, this Court
would make an attempt to ascertain the correctness of rival
submissions made by both the parties.
42.
Following claims and counter-claims were made by respective
parties before learned Arbitrator:
The claimant’s claim:
1.
On account of work done but no paid
a) Amount withheld in the pretext of Sale Tax
2,57,850.00
deduction
b) Extra work for 27 mt increase in bridge length
3,68,18,182
over and above the scope of the contract
2.
On account of reimbursement of extra GST paid
29,99,861
by claimant after 1.7.2017
On account of cost of arbitration towards fee of
8,70,000
2026:HHC:19374
Ld. Arbitration and cost of attending hearing and
other miscellaneous expenses
4.
To be
On account of interest on the amount of all the
calculated at
claims
the time of
award
4,09,45,893
Total
The counter claim:
1)a)
On account of revision of the founding level f the
Rs.6,00,000
Sarahan side abutment R.L. 1940 to 1944
b)
On account of revision of the founding level of the
6,75,000
Jeori side abutment R.L. 1925 to 1928
b) Extra work for 27 mt increase in bridge length
3,68,18,182
over and above the scope of the contract
Total
12,75,000
On account of cost of arbitration fees attending
11,50,000
hearings and administrative expenses
24,25,000
Total
43.
Learned Arbitrator, vide impugned Award dated 24.7.2023,
allowed the following claims/counter-claims of parties:
Claim of claimant
Sr.
Claim item
Amount
Amount
claimed
awarded
Claim No. 1(a)
2,57,850
2,57,850.00
Claim 1(b)
3,68,18,182
Nil
No.
Claim
No.2 29,99,861
Remark
Amount to be Claim dt. 7.10.21
(reimbursement
finalized by the not contested by
of GST)
o/o the SE 11th the respondent
Circle HPPWD
Rampur
(HP)
within
one
month award of
2026:HHC:19374
subject
cited
cost
Claim No. 3 (on 8,70,000
Nil
account of cost
of arbitration)
4.
Claim No.4 on Included
in
account
of the award of
interest
claim as and
where
applicable
Amount awarded in favour of claimant Rs.32,57,511
Claim of Department
Sr.
Claim item
No.
Counter
Amount
Amount
claimed
awarded
12,75,000
6,00,000
11,50,000
Nil
Remark
claim No1
Revision
of
founding
level
Counter
claim No.2
Amount awarded in favour of respondent is Rs.6,00,000/-.
44.
After making adjustments, the learned Arbitrator held the
claimant entitled to Rs.26,57,711. Learned Arbitrator observed in
impugned Award that, “If however, the claim of the reimbursement of
the GST finalized and paid by respondent department, within one
month of award fo the subject cited work by this forum, then the value
of final award of subject cited work will be the resultant of
Rs.2,57,850(sale tax) + value of claim of reimbursement finalized by
the o/o SE HPPWD Rampur –(minus) Rs.6,00,000.00 (counter claim)
2026:HHC:19374
in favour of the claimant.” It is further observed that interest for delay in
payment shall be payable @ 7% per annum in case of the claim of
reimbursement of GST as and where become applicable.
45.
Claimant is aggrieved on account of the fact that no interest has
been awarded in his favour under claim Nos. 1(a) and 2, though he has
been held entitled to refund of withheld sale tax and reimbursement of
GST. Lastly, petitioner is aggrieved of rejection of claim 3 whereby
arbitration cost came to be refused.
46.
Major grouse of the petitioner is that he could not have been
denied payment qua construction work of 27 metres additional span of
bridge. It is undisputed that tender was invited for work C/o 55.00 mtr.
Span Box double lane bridge over Rai Khad including both side
approaches on Rampur Gaura Mashnoo Sarahan Jeori road at RD
52/095 in Tehsil Rampur, District Shimla, Himachal Pradesh under
CRF (Job No. CRF-HP-2015-16 84). It is also not in dispute that
claimant being lowest bidder came to be awarded aforesaid work vide
award letter dated 4.11.2016. Pursuant to said award of work, parties
executed agreement No. 21, for 2016-17. As per agreement,
stipulated date for commencement of work and completion was
19.11.2016 and 18.11.2018 respectively whereas, work was completed
on 14.11.2019. It is also not in dispute that claimant was repeatedly
granted extension of time. It is also not in dispute that claimant along
with other technically qualified bidders was called for meeting i.e.
Normalization of Conditions, whereafter, he was given chance to give
revised financial bid. In the meeting for Normalization of Conditions, for
variation and deviation and prices to be paid were fixed as per para 27
2026:HHC:19374
and 28 of minutes of meeting, forming part of agreement dated
4.11.2016.
47.
It is also not in dispute that after opening of Technical Bid,
claimant along with other bidders was under obligation to get sub soil
testing and get geo-technical report. Claimant being successful bidder
submitted GAD Sarahan S0-2 and sub soil investigation report to the
respondent where-after, a joint inspection was conducted by Executive
Engineer of the respondent Department alongwith Design Consultant,
Shri V.S. Verma of the petitioner and it was decided to check the
bearing capacity for Jeori side abutment at level 1928.00 metres. Upon
verification by the technical expert of bearing capacity of 35.45
Tonne/sqm, was found at the location of abutment A2. The Design
Consultant further opined that an abutment having a height of 29
metres cannot be stabilized on the strata having bearing capacity of
35.45 tonne/sqm. It was decided to check bearing capacity for Jeori
side abutment at level 1928.00 metres. Upon verification by technical
expert, safe bearing capacity of 35.45 one was found at A2 whereas,
design consultant opined that abutment having height of 28 cannot be
stabilized on strata having 34.5 tonne bearing capacity. Since prevalent
soil classification of silt mixed with gravel could create uncontrollable
situation during increased water presence at the founding level,
therefore, the design consultant concluded that abutment A-2 is
required to be substituted with a Pier with extra provision for abutment
for an additional dry span of 27 metres to manage load dispersal within
recommended norms. Accordingly, re-revised GAD was submitted on
28.5.2017.
2026:HHC:19374
48.
Though as per NIT as well as agreement, span of bridge was 55
metres, whereas, as per geo-technical report dated 21.5.2017 and due
to sub-soil conditions, prevailing on Jeori side, the total span of the
constructed bridge was 82.00 metres alongwith a central pier and
therefore, re-revised GAD No. SARAHAN S-01 (R-2) with span
arrangement of 2 abutments and central pier and geo-technical report
dated 21.5.2017, were submitted to the Department alongwith the
request to consider the specific and implied complexities, ramifications
and implications of the re-revised proposal S-01 (R-2) with variations
alongwith the request to consider the specific and implied complexities,
ramifications and implications alongwith physical technical and financial
viability be examined to its entirety within the framework of the
agreement and if found suitable, approval was sought to be conveyed.
49.
On
30.5.2017,
Executive
Engineer
of
the
respondent
Department sent re-revised GAD dated 28.5.2017 to Superintending
Engineer, for approval specifically mentioning therein that claimant had
verbally agreed not to claim extra amount for construction of dry span
of 27.00 metres as per re-revised proposal.
50.
Pursuant to communication, claimant was asked to come
present in the office of Chief Engineer (South one), where he submitted
an undertaking dated 1.6.2017, regarding no claim. Relevant portion of
Annexure C-9 is reproduced herein
“The contractor has agreed verbally not to claim extra amount for
construction of dry span of 27.00 m as per re-revised proposal. The
contractor has agreed that he will submit an undertaking to this effect before
the approval of the re-revised GAD.
It is also brought to your kind notice that during excavation of the Jeori side
abutment, the surrounding land including a 20 m stretch of road got slided
2026:HHC:19374
down and it is apprehended that the abutting land having apple orchard
pertaining to private land owner may also slide down during rainy season. An
early action to restore the damaged road portion and necessary protection
work to safe guard
the structure is required. However, this work is not
included in the agreement for the subject cited work, but is necessarily/
urgently required as per prevailing site conditions. Necessary direction in this
regard may kindly be issued to this office at the earliest please.
The re-revised GAD proposal along with structural drawings and design is
enclosed herewith for getting it approved from the competent authority. ”
51.
Reading of aforesaid communication is very material for
adjudication of controversy in the case at hand. Bare perusal of
aforesaid communication suggests that meeting was held in office of
authority on 1.6.2017, wherein detailed discussion regarding bridge
was held. Lump sum tender submitted by claimant for construction of
bridge was inclusive of approaches on Sarahan and Jeori sides.
Original GAD was approved with single span of 55 metre with
approaches on both sides. However, as has been taken note here
above, as per site condition as well as report submitted by committee,
it was found more appropriate to construct additional span of 27
metres, instead approaches due to low load bearing on Jeori side in
addition to
original span of 55.0 metres, With the construction of
additional span of 27 metres, length of approaches on Jeori Side was
to
be
reduced.
Claimant
categorically
stated
in
the
afore
communication that since he had already given same rebate for
approaches from bridge side as per the rates of increase or decrease
of bridge payable to him coupled with the fact that now on account of
increase of 27 metres in span, he was entitled for Rs.27x460/55=
225.81 Lakh, on account of increase in span, but since there was a
decrease in length of approaches from bridge side, claimant is ready to
2026:HHC:19374
give same rebate of 27x460/55= 225.81 Lakh for decrease in length of
approaches from bridge side, meaning that
increase in span was
equal to decrease in cost, due to decrease in length of approaches
from bridge side, hence, no additional
amount was payable to the
claimant and dry span of 27.00 metres was to be treated as part of
approaches.
52.
In nutshell claimant admitted that increase in cost due to
increase in span is equal to decrease in cost due to decrease in length
of approaches on bridge side, hence no additional amount is payable
to him rather, 27 metres dry span shall be treated as part of
approaches. He submitted that if his re-revised GAD is approved,
having one pier and two spans of 55.00 metres and 27.00 metres (on
Jeori side), he will construct bridge on the same awarded cost of
Rs.7.50 Crore and will not claim anything extra on this count in future.
Claimant further agreed that this shall be full and final settlement and
he would not seek any arbitration or approach any court of law. He
further agreed that conditions of Normalization of Conditions shall
remain in force.
53.
In terms of aforesaid communication/ undertaking, claimant
categorically submitted before department that in the event of his being
permitted to raise two spans of 55 and 27 metres on Jeori side, total
length of span of bridge shall be 82 metres, but there will be decrease
in length of approaches. There is nothing on record to suggest that
after his having furnished NOC/undertaking, claimant ever raised any
issue with respect to having his NOC allegedly obtained from him
under coercion, before any competent authority rather, he completed
2026:HHC:19374
the work as per revised GAD and submitted final bill, claiming payment
qua additional span of 27 metres, which prayer of him came to be
rejected by department as well as arbitrator on the ground that he
himself vide communication dated 1.6.2017, Annexure P-2 had given
undertaking to not claim any amount for additional span of 27 metres.
54.
Though, Ms. Madhu, learned counsel for the claimant
vehemently argued that afore communication was extracted under
coercion and as such, same cannot be relied but the court is not
persuaded to agree with afore submission of learned counsel for the
claimant. It is not in dispute that afore communication is dated 1.6.2017
by which time, work had actually not started rather till that time,
petitioner after his having got soil tested, had come to know that upto
foundation level of 1928.00 and and 19250.00 for Jeoi side, ther was
no sign of hard rock which could provide required safe bearing capacity
of 45.00 tonne/sqm.
55.
Though as per NIT as well as agreement, span of bridge was 55
metres, but having taken note of geo-technical report dated 21.5.2017
and due to situation prevailing on Jeori side, total span of constructed
bridge came to be approved as 82 metres, alongwith central pier,
however, even while accepting aforesaid proposal of report submitted
by claimant, Executive Engineer concerned apprised Superintending
Engineer, who was competent authority to give approval that claimant
has verbally agreed to do work as per revised GAD, within lump sum
amount of 7.50 crore quoted by him.
56.
It is not in dispute that though afore communication Annexure C-
8/I was very much in the knowledge of claimant, rather, he acting upon
2026:HHC:19374
afore communication presented himself for meeting in the office of
Chief Engineer, South Zone, on 1.6.2017 and thereafter sent
communication dated 1.6.2017 (Annexure C-9), thereby undertaking
that in case his revised GAD is approved, which has one pier and two
spans of 55 and 27 metres, he will construct bridge for the amount of
Rs. 7.50 Crore, coupled with the fact that after writing said
communication, no objection ever came to be raised at his behest, qua
his being coerced to write said communication, this court is not
persuaded to agree with submission made at the behest of the
claimant that learned Arbitrator could not have taken into consideration
said communication while deciding claim of the claimant, qua additional
span of 27 metres.
57.
Though, at this stage, learned counsel for the claimant referred
to condition No. 27 of Normalization of Conditions for any
deviation/variation to state that Schedule of Variation shall be
applicable but this court is not persuaded to agree with aforesaid
submission of learned counsel for the claimant for the reason that as
per condition No.27 of
Normalization of
Conditions, for any
deviation/variation, claimant, could have claimed amount if any on
account of deviation/ variation on account of increase or decrease in
depth-level span etc., on the ground that while executing work on the
spot, he was compelled to do extra work for execution of project,
however, in the instant case, deviation, increase or decrease or
execution of additional work if any was decided inter se parties before
start of work. Department while accepting re-revised GAD dated
28.5.2017, categorially apprised claimant that he shall not be entitled to
2026:HHC:19374
any extra amount qua the construction of central pier as well as
additional span of bridge measuring 27 metres. Claimant, who had
actually before starting work got the soil testing, himself submitted rerevised GAD therein proposing that abutment A2 (Jeori side) is
required to be substituted with a provision of a pier and dry span of
27.00 metre with abutment extended towards Jeori side approach to
manage the load dispersal within recommended values. While doing
so, claimant was fully aware of the fact that it would be more
appropriate to construct 27 metres span of bridge, instead of
constructing approaches in addition to 55 metres span bridge. With the
construction of 27 metres of span, length of approaches on Jeori side
was to be reduced, hence, claimant himself proposed that he shall not
claim any additional amount for construction of additional 27 metres
span, rather, will construct the same within award/cost of Rs.750.00
Lakh.
58.
Moreover, perusal of undertaking dated 1.6.2017, itself suggests
that the claimant had already given rebate for construction of approach
from bridge side as per rate of increase or decrease payable to him.
Though, on account of increase in span of 27 metres, petitioner
claimed himself entitled to Rs.285.81 Lakh but since on account of
aforesaid construction, length of approach roads from bridge side was
decreased coupled with the fact that he himself agreed to give same
rebate for decease in length of approaches from bridge side, he is
estopped from claiming extra amount.
59.
In nutshell, increase in cost due to increase of 27 metres length
of span bridge is equal to decrease in cost due to decrease in length of
2026:HHC:19374
approach road from bridge side, hence, learned Arbitrator, rightly did
not hold the claimant entitled to the amount as claimed by the claimant,
on account of construction of 27 metres additional bridge, rather, same
rightly came to be treated as part of approaches.
60.
Though, learned counsel for the claimant, while making this
court peruse impugned Award vehemently argued that award qua said
claim is inclusive but this court is not persuaded to agree with afore
submission raised by the claimant. During arguments, learned counsel
specifically referred to page 66 of impugned Award, wherein oral
/written arguments of parties came to be analyzed by the learned
arbitrator. In para 9 of impugned Award, learned Arbitrator observed as
under:
“10[2/5/hj This pertained to the Jeori side Approach as completed at
the site of work for which the diagram has been provided by the
Respondent on 25/6/2022 as asked by this forum. The 155 mt. length
of the Approach on Jeori side adjoining to the 55 mt span Bridge was
integral part of the agreement for its execution as per scope of the
agreement for this work. After the award of this work, the respondent
may consider any left out payment if admissible as per variation
schedule of the agreement as no such alim is pending for
consideration by this forum.”
61.
While referring to said portion of award, learned counsel for the
claimant vehemently argued that learned Arbitrator though arrived at a
conclusion that 155 metres on Jeori side was an integral part of work,
as per scope of agreement for this work, but yet failed to award any
amount qua same, rather, opined that after award, the respondents
may consider any left out amount, as no claim is pending consideration
before him.
62.
2026:HHC:19374
Having perused aforesaid part of the award, this court is
persuaded to agree with learned Additional Advocate General that this
is not finding returned by learned Arbitrator, rather his observation
based on pleadings adduced on record by respective parties. Specific
finding qua said claim has been given in award, which starts from
internal page 69 of award.
63.
Having carefully perused findings returned by learned Arbitrator
qua afore claim, this court is persuaded to agree with learned counsel
for the claimant, that there was no occasion for learned Arbitrator to go
into question with respect to necessity of substituting approach roads
with pier especially when department had accepted the revised GAD
dated 28.5.2017. It is not in dispute that aforesaid revised GAD was
made part of the agreement, however, while doing so, respondent took
undertaking from the claimant, that he shall do the work as per revised
GAD on the same awarded costs of Rs.750 Lakh.
64.
At the cost of repetition, it is observed that though plea has been
raised at the behest of claimant, that communication dated 1.6.2017,
(Annexure C-9) whereby undertaking was given by the claimant ,is
result of coercion but no cogent and convincing evidence in that regard
ever came to be adduced on record by the claimant. Though, there are
certain documents adduced on record, which are signed by officials of
respondent department, suggestive of the fact that claimant has done
extra work, as a result thereof, he is required to be paid additionally but
same may not be of much relevance and on the basis of same,
claimant, cannot claim, extra amount in terms of Schedule of Variation,
2026:HHC:19374
prepared as per condition No. 27 of Normalization of Conditions, for
any deviation/variation.
65.
Having scanned award passed by learned Arbitrator, vis-à-vis
claim put forth by claimant, for payment qua additional span of 27
metres, this court sees no reason to interfere in the award, especially
when learned counsel representing claimant has not been able to point
out any patent illegality in the award. Learned counsel for the claimant,
has not been able to point out that contract agreement entered inter se
parties, enables claimant to claim any amount qua construction of
additional span of 27 metres rather, this court finds that learned
arbitrator having taken note of undertaking dated 1.6.2017 given by
claimant, coupled with the fact that on account of undertaking claimant
was made to perform additional work, which he would have otherwise
not done pursuant to his having acted strictly in terms of NIT, wherein
span of bridge was 55 metres, with both side approaches hence, no
illegality can be submitted to have been by learned Arbitrator, while not
awarding any amount on account of said claim.
66.
However, this court having taken note of the fact that
respondent was not competent to deduct any amount on account of
sale tax deduction after 1.7.2017, when sales tax subsumed in GST,
which submission of claimant was otherwise found merit-worthy by the
learned arbitrator coupled with the fact that no cogent and convincing
evidence ever came to be adduced on record by respondent qua
withholding said amount, there appears to be merit in the claim of the
claimant, that learned arbitrator, while allowing claim of Rs.2,57,17,50
ought to have awarded commensurate interest. Since aforesaid
2026:HHC:19374
amount was withheld without any authority for quite long, petitioner is
entitled to interest and as such, award passed by learned Arbitrator
needs to be modified.
67.
Similarly, this court finds merit in the submission of learned
counsel for the claimant, that learned Arbitrator, while allowing claim
no.2, on account of extra GST that ought to have awarded interest,
especially when said amount was found to be withheld for no
justifiable reason and without any authority of law.
68.
Learned Arbitrator after having perused pleadings and evidence
adduced on record qua respective claims though arrived at a definite
conclusion that for some unknown reason, respondents delayed the
afore claim for more than 20 months and side-tracking this GST claim
dated 7.10.2021 of claimant with some old reference, which is not
relevant in present context. Learned Arbitrator further observed that
respondent vide statement of defense dated 21.2.2022 agreed in
principle to release the payment, under this claim as it became due but
respondent ought to have dealt this claim of claimant dated 7.10.2021
and
released due payment
in this regard as per provision of the
agreement after duly incorporating the Notifications of the competent
authorities issued from time to time, as and where they become
applicable, however, while passing the award, learned Arbitrator
directed respondent No.2 to settle payment for said claim dated
7.10.2021, on its merit within one month of date of award, of the
subject work. While stating that claim set up by claimant shall not be
returned for re-submission, learned Arbitrator further observed that if
claim is not finalized within Ione month specified in award, claimant
2026:HHC:19374
shall be entitled for full value of Rs.29,61,761 as final claim and simple
interest of 7% per annum thereafter, would be payable.
69.
In nutshell grouse of petitioner is that once learned Arbitrator
had
arrived
at
a
definite
conclusion
that
respondents
have
unnecessarily delayed GST claim of claimant for 20 months, which was
actually submitted on 7.10.2021, he ought not have left the matter to be
decided by respondent, rather, while ordering release of sum of
29,99,861, ought to have also awarded adequate interest in favour of
claimant.
70.
Since it is not in dispute that petitioner had submitted claim qua
GST on 7.10.2021 and same was genuine, coupled with the fact
subsequently in arbitration proceedings, respondents agreed to release
amount, learned Arbitrator ought not have directed respondent to
decide afore issue within one month rather, should have ordered
release of same with up-to-date interest.
71.
At this stage, it would be apt to take note of sub-section (7)(a)
and 7(b) of S.31 of the Arbitration and Conciliation Act, which prescribe
for award of interest in an arbitral award. Aforesaid provision reads as
under:
“(7)(a)
Unless otherwise agreed by the parties, where and insofar as
an arbitral award is for the payment of money, the arbitral tribunal may
include in the sum for which the award is made interest, at such rate as it
deems reasonable, on the whole or any part of the money, for the whole or
any part of the period between the date on which the cause of action arose
and the date on which the award is made.
(b)
[ A sum directed to be paid by an arbitral award shall, unless the
award otherwise directs, carry interest at the rate of two per cent. higher than
the current rate of interest prevalent on the date of award, from the date of
award to the date of payment.”
72.
2026:HHC:19374
Since learned Arbitrator has allowed claims 1(a) and 2 of claim
petition, thereby directing the respondents to pay amounts claimed
thereunder, it ought to have awarded interest on the same.
73.
Similarly, this court is persuaded to agree with learned counsel
for the claimant, that the learned Arbitrator has fallen in error while
declining relief qua costs of arbitration proceedings in favour of the
claimant. Sub-section 31(8) and S.31A of the said Act provide for costs
of arbitration. Aforesaid provisions read as under:
“(8) The costs of an arbitration shall be fixed by the arbitral tribunal in
accordance with section 31A.]
Explanation.—For the purpose of clause (a), “costs” means reasonable costs
relating to—
(i) the fees and expenses of the arbitrators and witnesses,
(ii) legal fees and expenses,
(iii) any administration fees of the institution supervising the arbitration, and
(iv) any other expenses incurred in connection with the arbitral proceedings
and the arbitral award.
[31A. Regime for costs.—(1) In relation to any arbitration proceeding or a
proceeding under any of the provisions of this Act pertaining to the
arbitration, the Court or arbitral tribunal, notwithstanding anything contained
in the Code of Civil Procedure,1908 (5 of 1908), shall have the discretion to
determine—
(a) whether costs are payable by one party to another;
(b) the amount of such costs; and
(c) when such costs are to be paid.
Explanation.—For the purpose of this sub-section, “costs” means reasonable
costs relating to—
(i) the fees and expenses of the arbitrators, Courts and witnesses;
(ii) legal fees and expenses;
(iii) any administration fees of the institution supervising the arbitration; and
(iv) any other expenses incurred in connection with the arbitral or Court
proceedings and the arbitral award.
(2) If the Court or arbitral tribunal decides to make an order as to payment of
costs,—
2026:HHC:19374
(a) the general rule is that the unsuccessful party shall be ordered to pay the
costs of the successful party; or (b) the Court or arbitral tribunal may make a
different order for reasons to be recorded in writing.
(3) In determining the costs, the Court or arbitral tribunal shall have regard to
all the circumstances, including—
(a) the conduct of all the parties;
(b) whether a party has succeeded partly in the case;
(c) whether the party had made a frivolous counterclaim leading to delay in
the disposal of the arbitral proceedings; and (d) whether any reasonable offer
to settle the dispute is made by a party and refused by the other party.
(4) The Court or arbitral tribunal may make any order under this section
including the order that a party shall pay—
(a) a proportion of another party’s costs;
(b) a stated amount in respect of another party’s costs; 1. Subs. by Act 3 of
2016, s. 16, for clause
(b) (w.e.f. 23-10-2015). 1. Subs. by Act 3 of 2016, s. 16, for sub-section (8)
(w.e.f. 23-10-2015). 2. Ins. by s.17, ibid. (w.e.f. 23-10-2015). 21
(c) costs from or until a certain date only;
(d) costs incurred before proceedings have begun;
(e) costs relating to particular steps taken in the proceedings;
(f) costs relating only to a distinct part of the proceedings; and (g) interest on
costs from or until a certain date.
(5) An agreement which has the effect that a party is to pay the whole or part
of the costs of the arbitration in any event shall be only valid if such
agreement is made after the dispute in question has arisen.]”
74.
Though, in the case at hand, this court in earlier part of
judgment has held claimant not entitled to any amount qua claim 1(b)
for the reason that he had given an undertaking to do the work as per
revised GAD within lump sum cost of Rs.750 Lakh, but having taken
note of some of communications wherein respondents themselves
proceeded to recommend case of claimant qua aforesaid claim,
coupled with the fact that no specific communication ever came to be
issued by respondent thereby apprising the claimant, that on account
of acceptance of his re-revised GAD he shall not claim any extra
2026:HHC:19374
amount for construction of additional span of 27 metres of bridge,
rather, he shall be paid Rs.7.50 Crore for total work, this court is not
persuaded to agree with findings of learned Arbitrator that there was no
occasion if any for claimant to raise dispute. Moreover, learned
Arbitrator while rejecting aforesaid claim qua arbitration cost, failed to
take note of the fact that besides claim 1(b), claimant had also raised
two claims 1(a) and 2 with regard to reimbursement of GST amount
withheld on a account of sales tax deduction and GST which were
ultimately allowed in favour of claimant, by the learned Arbitrator vide
impugned Award. There is nothing on record to suggest that without
intervention of the arbitrator, claimant, would have got aforesaid
amount, rather, it came to be submitted before learned arbitrator that
amount qua aforesaid both claims is being processed but it is a matter
of fact that same ultimately came to be allowed/paid after passing of
award.
75.
Consequently, in view of detailed discussion made above, the
award passed by the Sole Arbitrator on 24.7.2023, is upheld qua claim
No. 1(b), however, same is modified qua claim Nos. 1(a) and 2, to the
extent that the claimant shall be entitled to interest at the rate of 8% on
the amounts awarded thereunder, from the date same became due
and till the date of actual payment of same by the respondents to the
claimant.
76.
Since, otherwise claims Nos. 1(a) and 2 have been awarded by
the sole arbitrator and even claim No.2 was not resisted by the
respondents, it is clear that the claimant was forced to take recourse to
arbitration to get the amount, which was due to him and in this process,
2026:HHC:19374
he had to engage a counsel and pay the fee of learned Arbitrator.
Therefore, in view of the above, award dated 24.7.2023, qua claim
No.3 is set aside and it is directed that the claimant shall be entitled to
costs of arbitration amounting to Rs. 4.00 Lakh.
77.
The petition is accordingly disposed of in the afore terms. All
pending applications also stand disposed of.
(Sandeep Sharma)
Judge
May 22, 2026
Vikrant
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.