Page No.# 1/38
GAHC010050892026
undefined
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WP(C)/1487/2026
UNITED DRILLING TOOLS LIMITED
HAVING ITS REGISTERED OFFICE AT 139A, FIRST FLOOR, ANTRIKSH
BHAVAN, 22 KASTURBA GANDHI MARG, NEW DELHI 11001, ALSO HAVING
ITS OFFICE ADDRESS AT 26TH FLOOR, ASTRALIS TOWER, SUPERNOVA
COMPLEX, SECTOR 94 NOIDA, 201301 DIST. GB NAGAR, UTTAR PRADESH,
INDIA REPRESENTED BY ITS DULY AUTHORIZED REPRESENTATIVE MR.
ANAND MISHRA, COMPANY SECRETARY.
VERSUS
OIL INDIA LIMITED AND 3 ORS
A COMPANY INCORPORATED UNDER THE COMPANIES ACT 1956 AND
HAVING ITS REGISTERED OFFICE ADDRESS AT DULIAJAN, DIBRUGARH,
786602 REPRESENTED BY THE RESIDENT CHIEF EXECUTIVE, OIL INDIA
LTD., DULIAJAN, DIBRUGARH, ASSAM.
2:THE OFFICDR OF THE DIRECTOR OPERATIONS
OIL INDIA LTD.
CORPORATE OFFICE
OIL HOUSE
PLOT NO. 19 SECTOR 16A
NOIDA 201301 UTTAR PRADESH.
3:THE OFFICE OF THE GENERAL MANAGER
MATERIALS
OIL INDIA LTD.
DULIAJAN
DIBRUGARH
ASSAM 786602
4:THE OFFICE OF THE GENERAL MANAGER
Page No.# 2/38
MATERIALS
OIL INDIA LTD.
DULIAJAN
DIBRUGARH
ASSAM 786602
5:THE OFFICE OF THE EXECUTIVE DIRECTOR (C AND P)
OFFICIATING
OIL INDIA LTD. DULIAJAN
DIBRUGARH
ASSAM 78660
BEFORE
HON’BLE MR. JUSTICE DEVASHIS BARUAH
For the Petitioner(s)
: Ms. G. Goswami, Sr. Advocate
: Mr. A. Neog, Advocate
For the Respondent(s)
: Mr. D. Saikia, Sr. Advocate
: Mr. A. Sharma, Advocate
·
Date on which Judgment was reserved
: N/A
·
Date of Pronouncement of Judgment
: 25.08.2026
·
Whether the pronouncement is of
the Operative Part of the Judgment
: Yes
·
Whether the full Judgment has been
Pronounced
: No
JUDGMENT AND ORDER (ORAL)
Heard Ms. G. Goswami, the learned Senior counsel assisted by
Mr. A. Neog, the learned counsel appearing on behalf of the
Petitioner and Mr. D. Saikia, the learned Senior counsel assisted by
Mr. A. Sharma, the learned counsel appearing on behalf of the
Page No.# 3/38
Respondent Nos. 1, 2, 3 and 4.
PREFACE:
2.
The present writ petition has been filed by the Petitioner
seeking the following reliefs:
“(a)
Certiorari shall not be issued to set aside/quash the order dated
10.10.2025 issued by OIL blacklisting the Petitioner and putting the
Petitioner under the Holiday List of OIL for 2 years w.e.f. 29.07.2025;
(b)
Certiorari shall not be issued to set aside/quash the order dated
12.12.2025 issued by OIL cancelling the contract dated 03.03.2025 and
encashing the performance security submitted by the Petitioner vide
letter dated 19.12.2025;
(c)
Certiorari shall not be issued to set aside/quash the order dated
15.12.2025 issued by OIL affirming the Banning Order dated 10.10.2025;
(d)
Certiorari shall not be issued to set aside/quash the new tender no vide
Bid Number: GEM/2025/B/6558258 issued by OIL on 11.08.2025.”
3.
At the outset, the learned Senior counsel appearing on behalf
of the Petitioner submitted that insofar as the reliefs sought for at
Serial Nos. (b) and (d), the Petitioner would not like to insist in the
present proceedings and would like to avail a separate proceedings
as envisaged under law and as such, necessary liberty be granted
to the Petitioner. The learned Senior counsel also submitted that
the instant writ petition be confined to the reliefs sought for at
Serial Nos. (a) and (c).
Page No.# 4/38
4.
A perusal of the reliefs at Serial Nos. (a) and (c) would show
that the Petitioner's grievance in the present writ petition is the
order dated 10.10.2025 whereby the Petitioner as well as all its
associate firms were blacklisted for a period of 2 (two) years with
effect from 29.07.2025 as well as the order dated 15.12.2025
which was affirmed by the Appellate Authority.
BRIEF FACTS OF THE CASE:
5.
The Petitioner is a company engaged in the business of
manufacture and supply of several critical patented products used
by the Respondent OIL such as wire line winches, stabilizers and
casing pipes. It is claimed by the Petitioner that the Petitioner has
been doing business with the Respondents for the last 35 years.
6.
On 01.08.2024, a Notice Inviting Tender was issued for supply,
installation and commissioning of 2 (two) numbers of truck
mounted hydraulic wire line winches at a contract value of
Rs.13,73,60,000/-. The Petitioner participated in the said tender
process and in doing so, executed the Integrity Pact which is a
requirement for each bidder. On 03.03.2025, the contract was
awarded to the Petitioner as the single bidder.
7.
On 03.05.2025, an FIR was registered under the provisions of
the Bharatiya Nyaya Sanhita, 2023 (for short ‘BNS’) and the
Page No.# 5/38
Prevention of Corruption Act, 1988 (for short ‘the Act of 1988’) by
the CBI, New Delhi, against various persons including one Shri
Prayas Chakravorty - Deputy GM of Oil India and 2 (two) officials of
the Petitioner company, namely Shri Jyoti Kumar Singh, DGM Sales
and Marketing; and Mr. Kanal Gupta, Managing Director of the
Petitioner Company. The said FIR was registered and numbered as
RC2172025A0012 under the provisions of Section 61(2) of the BNS
read with Sections 7, 9, 10 and 12 of the Act of 1988.
8.
All the 3 (three) persons who were named in the FIR, i.e. Shri
Prayas Chakravorty, Shri Jyoti Kumar Singh and Shri Kanal Gupta
were arrested. Subsequent thereto, on 27.06.2025, a Charge Sheet
was submitted against Shri Prayas Chakravorty, Shri Jyoti Kumar
Singh and Shri Kanal Gupta as well as the Petitioner company
under Section 61(2) of the BNS and Sections 7, 9, 10 and 12 of the
Act of 1988. Vide an order dated 14.08.2025, cognizance was
taken under Section 61(2) of the BNS and Sections 7, 9, 10 and 12
of the Act of 1988 against Shri Prayas Chakravorty, Shri Jyoti
Kumar Singh and Shri Kanal Gupta as well as the Petitioner
company.
9.
Subsequent thereto, the Supplementary Charge Sheet was
submitted on 22.12.2025 wherein at Paragraph 16.7, it was
mentioned that during the course of further investigation, no
Page No.# 6/38
irregularity could be found in the allotment of tenders to the
Petitioner. It was also mentioned that the payments have been
made to the Petitioner after receipt of the materials and all
materials have been found received and duly recorded in the
Goods Received Notes, (GRNs). In addition to the above, it was
opined in the said Supplementary Charge Sheet that no
involvement of other officers of OIL could be revealed in the
allotment of tender dated 01.08.2024 (Purchase Order dated
03.03.2025) and no evidence could be found which show that
other employees of the Petitioner company were involved in bribing
Shri Prayas Chakravorty and other employees of the OIL for other
tenders/purchase orders, awarded to the Petitioner.
10. The employees as well as the Managing Director of the
Petitioner were granted bail.
11. In the meantime, on 04.05.2025, OIL wrote to the Petitioner
informing the Petitioner about the events of 03.05.2025. On
02.07.2025, OIL informed the Petitioner that the events narrated in
the FIR prima facie constituted violation of Section 2(1)(i) of the
Integrity Pact and other provisions of the tender and OIL had
therefore decided to suspend delivery of materials against the
tender.
12. On 15.07.2025, the Petitioner responded requesting OIL to
Page No.# 7/38
revoke the order of suspension pending completion of investigation
under the FIR and adjudication by the competent Court. However,
on 29.07.2025, a Show Cause Notice was issued to the Petitioner
asking the Petitioner to Show Cause as to why the Petitioner
should not be blacklisted. The Petitioner was also placed under
suspension for a period of 3 (three) months.
13.
The Petitioner responded to the Show Cause Notice by
submitting
a
Preliminary
Reply
dated
13.08.2025,
thereby
requesting for several documents referred to in the Show Cause
Notice and also denied all allegations leveled in the FIR/Show
Cause Notice and sought the indulgence of the Oil India in at least
keeping the Show Cause Notice in abeyance pending investigation.
The documents which were sought for by the Petitioner were:
(a) CBI's letter dated 04.05.2025;
(b)
Note prepared by the concerned Department of Oil under
Clause 8(i) of the 2023 Banning Policy;
(c)
Committee report under Clause 8(i) of the 2023 Banning
Policy;
(d) Document to show that the Show Cause Notice was vetted by
OIL's legal department under Clause 4(iii) of the 2023 Banning
Policy;
Page No.# 8/38
(e)
Competent Authorities' approval for issuance of the Show
Cause Notice again in terms with Clause 4 of the 2023 Banning
Policy; and
(f) Any other documents relied on in the Show Cause Notice.
14.
It is averred by the Petitioner that on 01.09.2025, OIL
responded to the Petitioner's letter dated 13.08.2025 stating that
the documents sought for by the Petitioner being internal
documents of OIL could not be provided to the Petitioner. The
Petitioner was further provided another opportunity to submit the
Show Cause reply by 08.09.2025. It is further apparent from the
materials on record that the Petitioner sought for further extension
of time for submitting the detailed reply.
15. On 22.09.2025, the Petitioner instead of submitting the reply
to the Show Cause Notice filed a writ petition being WP(C)
No.5719/2025 before this Court. This Court vide an order dated
24.09.2026 issued notice but was not inclined to stay the Show
Cause proceedings. However, this Court granted the Petitioner 7
(seven) days time to file its reply.
16. The final reply was filed by the Petitioner on 03.10.2025.
17. During the pendency of the said writ petition, on 10.10.2025,
the impugned order of blacklisting was passed whereby the
Page No.# 9/38
Petitioner and all its allied firms were placed under Holiday List of
OIL and thereby debarring them from participating against OIL's
future tenders for a period of 2 (two) years with effect from
29.07.2025 i.e. the date of the suspension order.
18. The Petitioner thereupon preferred an Appeal on 08.11.2025
to the Director (Operations) under Clause 10 of the Banning Policy.
19. On 12.12.2025, the contract entered into with the Petitioner
dated 03.03.2025 was cancelled and the performance security
submitted against the work order dated 03.03.2025 was forfeited.
20. On 15.12.2025, the Appellate Authority dismissed the Appeal
thereby affirming the order of putting the Petitioner in the Holiday
List dated 10.10.2025.
21. The Petitioner on coming to learn about the termination of the
contract as well as the blacklisting of the Petitioner vide the order
dated 10.10.2025, which have been further affirmed by the
Appellate Authority on 15.12.2025, withdrew the writ petition being
WP(C) No.5719/2025 with a liberty to challenge the communication
dated 12.12.2025 whereby the contract pertaining to the work
order dated 03.03.2025 was terminated and the performance
security was forfeited. Liberty was granted while withdrawing the
writ petition on 16.12.2025.
Page No.# 10/38
22. The Petitioner thereupon approached this Court by filing the
present writ petition on 10.03.2026.
23. The learned Coordinate Bench of this Court vide an order
dated 16.03.2026 issued notice. No interim directions was passed
though the Petitioner sought for.
24. The Respondent Nos. 1 to 4 filed their affidavit-in-opposition
on 30.03.2026 wherein the justifications were provided as to why
the contract was terminated and the performance security was
forfeited. In addition to that, the Respondent Nos. 1 to 4 have also
supported the impugned Banning Order dated 10.10.2025 as well
as the Appellate Order dated 15.12.2025. It is categorically
mentioned in the said affidavit-in-opposition that after issuance of
the Show Cause Notice to the Petitioner on 29.07.2025, various
opportunities were granted to the Petitioner to submit the reply.
The Petitioner instead of submitting the reply, filed a preliminary
reply on 13.08.2025 whereby the Petitioner requested for certain
internal documents of OIL for preparing the final reply on the Show
Cause Notice. It was further mentioned that vide the letter dated
01.09.2025, the Petitioner was duly informed that the documents
sought for are pertaining to internal proceedings and the referred
letter of the CBI was a mere forwarding letter of the subject FIR.
The Petitioner was further advised to submit the final reply, if any,
Page No.# 11/38
within 08.09.2025 and in the event of no response, the preliminary
reply dated 13.08.2025 would be treated as the final reply.
25. It was further stated in the affidavit-in-opposition that the
Petitioner did not submit any reply rather sought for another 3
(three) weeks' time to file a reply vide a communication dated
04.09.2025. The Respondent OIL vide the letter dated 06.09.2025
extended the timeline upto 15.09.2025 to file the reply. However,
instead of filing the reply, the Petitioner approached this Court by
filing the writ petition being WP(C) No.5719/2025 challenging the
OIL’s Show Cause Notice cum Suspension Letter dated 29.07.2025.
The said writ petition was listed for motion on 24.09.2025, on
which date this Court while issuing notice categorically observed
that there was no case made out for passing any interim directions
till the next date. However, during the course of the proceedings,
the learned counsel who appeared on behalf of the OIL in WP(C)
No.5719/2025 served the documents to the Petitioner’s counsel.
The said aspect was recorded at Paragraph No.12 of the order
dated 24.09.2025. This Court further vide the said order, permitted
the Petitioner to file the reply within 7 (seven) days before the
Competent Authority.
26. It was further stated in the affidavit-in-opposition that the
Petitioner submitted the final reply on 03.10.2025. However, as the
Page No.# 12/38
final reply was submitted on 03.10.2025, the Respondent
Authorities did not take note of the said reply taking into account
that the final reply was submitted beyond the period of 7 (seven)
days and proceeded to decide the proceedings on the basis of the
earlier preliminary reply submitted by petitioner on 13.08.2025.
Subsequent thereto, on the recommendation given by the
Final Committee on 08.10.2025 whereby it was recommended that
the Petitioner should be put in the Holiday List till the conclusion of
the judicial proceedings, the Competent Authority, vide a Speaking
Order dated 10.10.2025 had put the Petitioner in the Holiday List
for a period of 2 (two) years w.e.f. 29.07.2025. It was further
mentioned that the Respondent OIL had also vide the letter dated
12.12.2025, cancelled the contract dated 03.03.2025 awarded to
the Petitioner and the performance security was forfeited. In
addition to that, the Respondents have in their affidavit-inopposition justified the order dated 10.10.2025.
27.
The Respondents have filed an additional affidavit on
11.06.2026 thereby bringing on record the certified copy of the
charge sheet which was filed on 27.06.2025.
28.
The Petitioner filed an additional affidavit on 23.07.2026
whereby
the
representation
submitted
on
25.02.2026
and
29.04.2026 seeking revocation of the order of debarment were
Page No.# 13/38
brought on record.
29. In the backdrop of the above, let this Court now consider the
respective submissions made on behalf of the parties.
SUBMISSIONS MADE ON BEHALF OF THE LEARNED COUNSEL FOR
THE PARTIES:
30. Ms. G. Goswami, the learned Senior counsel appearing on
behalf of the Petitioner submitted that putting a company in a
Holiday List amounts to blacklisting. Blacklisting of a company
amounts to a civil death entailing grave consequences. Under such
circumstances, the action on the part of the Respondent
Authorities to proceed with the Show Cause proceedings initiated
on the basis of the Show Cause Notice dated 29.07.2025 without
considering
the
Show
Cause
Reply
dated
03.10.2025
is
unreasonable and unfair apart from violating the principles of
natural justice. The learned Senior counsel appearing on behalf of
the Petitioner submitted the principles of natural justice not only is
confined to issuance of a Show Cause Notice, but also the
consideration of the reply and if the reply had not been taken into
account on a very technical ground that it was submitted on
03.10.2025, which was otherwise required to be submitted on
01.10.2025 and 02.10.2025 being a holiday, shows that the action
on the part of the Respondent Authorities in passing the impugned
Page No.# 14/38
order is unfair and unreasonable thereby violating the mandate of
Article 14 of the Constitution.
31. The learned Senior counsel further drawing the attention of
this Court to the Banning Policy of OIL, 2023 submitted that Para 4
stipulates as to when an agency can be considered for debarment.
For the purpose of such consideration, there is a requirement of a
determination that the bidder had breached the Code of Integrity
as per Rule 175 of the General Financial Rules, (GFR), 2017. The
learned Senior counsel submitted that without a determination that
there is a violation of Rule 175 of the GFR, the question of the
debarment does not arise. The learned Senior counsel further
submitted that in Para 5.1 also, it is the mandate that in respect of
an
ongoing
contract,
a
contractor
shall
be
put
on
a
banning/debarment list of OIL after following the due process.
There is a requirement of determination/conclusion arrived at, that
the irregularities have been committed and then only such action
of termination be taken.
32. The learned Senior counsel referring to the impugned order
dated 10.10.2025 submitted that there is no determination or
conclusion arrived at by the Respondent Authorities independently
but merely on the basis of the FIR lodged by the CBI, the Charge
Sheet submitted and the cognizance taken by the Court, the
Page No.# 15/38
decision was taken that continuing business with the Petitioner
facing a criminal trial of bribery or corruption poses significant
reputational, operational and compliance risk for OIL and it is
under such circumstances, the impugned banning order was
passed.
33. The learned Senior counsel further referred to Rule 151 of the
GFR and submitted that a debarment from bidding is permitted
when a bidder is convicted under the Act of 1988 or the Indian
Penal Code or any law for the time being in force. Again, referring
to Rule 175 of the GFR, and more particularly Rule 175(2), the
learned Senior counsel submitted that there has to be a conclusion
reached that bidder or the prospective bidder as the case may be,
had contravened the Code of Integrity to take appropriate
measures. The learned Senior counsel therefore submitted that in
the present facts and circumstances, the impugned order of
banning cannot be sustained in law. The learned Senior counsel
further submitted that if the impugned banning order cannot be
sustained in law, the consequential appellate order dated
15.12.2025 cannot also be sustained in law.
34. Mr. D. Saikia, the learned Senior counsel appearing on behalf
of the Respondents on the other hand submitted that as per the
Banning Policy, 2023, the power has been conferred upon the
Page No.# 16/38
Respondents to take action for debarment if there is a breach to
the Code of Integrity as per Rule 175 of the GFR. The learned
Senior counsel submitted that Rule 175 of the GFR specifically
prohibits making offer, solicitation or acceptance of bribe, reward
or gift, or any material benefit, either directly or indirectly, in
exchange of an unfair advantage in the procurement process or to
otherwise influence the procurement process. In the instant case,
it would show from the FIR as well as the charge sheet that
specific allegations have been made against the Petitioner as well
as his officials. Based upon the various documents, a prima facie
finding has been arrived at. It was prima facie established that the
Petitioner had violated the integrity pact and accordingly, the
impugned order dated 10.10.2025 was passed.
35.
The learned Senior counsel further submitted that all
opportunities were granted to the Petitioner and as such, they
cannot be allowed to make a submission that the principles of
natural justice were violated.
36.
The
learned
Senior
counsel
further
referred
to
the
recommendations of the Final Committee as regards the violation
of Section 2 of the Integrity Pact wherefrom it would show that
every contention made by the Petitioner were taken into
consideration.
Page No.# 17/38
37.
The learned Senior counsel submitted that Rule 175
empowered the Respondent OIL to take appropriate measures
when a breach of the Code of Integrity is prima facie established
and therefore the Respondent OIL can very well act before the
conclusion of trial in order to safeguard its interest.
38. The learned Senior counsel also submitted that it is not known
as to when the criminal trial would culminate and therefore based
upon the documents which are available including the FIR and the
charge sheet and the cognizance order, prima facie satisfaction was
established that a case has been made out for debarment of the
Petitioner for violating the Code of Integrity.
39.
The learned Senior counsel for the Respondents further
submitted that a perusal of Para 5.1 of the Banning Policy would
show that what is required is prima facie establishment of the
charges and in the instant case, the satisfaction was more than
prima facie established.
ANALYSIS AND DETERMINATION:
40. Blacklisting has always been viewed by the Courts as a drastic
remedy and the orders passed have been subjected to rigorous
scrutiny. In Erusian Equipment & Chemicals Ltd. Vs. State of West
Bengal reported in (1975) 1 SCC 70, the Supreme Court observed
Page No.# 18/38
that blacklisting has the effect of preventing a person from the
privilege and advantage of entering into a lawful relationship with
the Government for the purpose of gains. It was further observed
that the fact that the disability is created by the order of
blacklisting indicates that the relevant authority is to have an
objective satisfaction. In the case of B.S.N. Joshi & Sons Ltd. Vs.
Nair Coal Services Ltd. reported in (2006) 11 SCC 548, the Supreme
Court observed that when a contractor is blacklisted by a
Department he is debarred from obtaining a contract, but in terms
with the Notice Inviting Tender where a tenderer is declared to be
a defaulter, he may not get any contract at all. It may result in
winding up his business. In other words, it would entail a
disastrous effect upon the contractor. In the case of Blue Dreamz
Advertising Private Limited and Another Vs. Kolkata Municipal
Corporation and Others reported in (2024) 15 SCC 264, the
Supreme Court observed that the debarment is issued for
protecting public interests from those contractors and recipients
who are non-responsible, lacks business integrity, or engages in
dishonest or illegal conduct, or are otherwise unable to perform
satisfactorily. In other words, the debarment as a remedy is to be
invoked in cases where there is a harm or potential harm for the
public interest, particularly in cases where a person's conduct has
demonstrated that debarment as a penalty alone will protect public
Page No.# 19/38
interest and deter the person from repeating his actions which
have a tendency to put public interest in jeopardy. The Supreme
Court further observed in the said judgment about the implication
of a person blacklisted, inasmuch as any person blacklisted is
rendered ineligible and thereby the person would not only be
debarred from dealing with the employer concerned, but because
of his disqualification, the person’s dealings with other entities are
also proscribed. It was also observed that it is common that in
Notice Inviting Tenders, one of the conditions of eligibility is that
the agency should not be blacklisted from anywhere.
41. From the settled propositions of law, it is clear that the
blacklisting is a drastic measure and therefore, it is the requirement
of law that when such drastic measures are taken, there has to be
an objective satisfaction of the competent authority.
42. In the backdrop of the above, let this Court consider as to
whether the impugned order dated 10.10.2025 calls for any
interference.
43. The materials on record would show that the Petitioner herein
was granted a contract on 03.03.2025. On 03.05.2025, an FIR was
lodged by the Central Bureau of Investigation, New Delhi, against
one Shri Prayas Chakravorty, the Deputy GM of Oil India and 2
officials of the Petitioner. The said Shri Prayas Chakravorty and the
Page No.# 20/38
2 officials of the Petitioner were arrested. They were granted bail
subsequently. Be that as it may, charge sheet was submitted not
only against Shri Prayas Chakravorty but also against the 2 officials
of the Petitioner Company as well as the Petitioner Company.
Pursuant to the charge sheet which was submitted on 27.06.2025,
cognizance was taken by the Court vide order dated 14.08.2025
under Section 61(2) of the BNS and Sections 7, 9, 10, and 12 of
the Act of 1988.
44. It is also relevant to take note of that a Supplementary Charge
Sheet was submitted on 22.12.2025. In the Supplementary Charge
Sheet more particularly at Paragraph Nos. 16.5, 16.6 and 16.7, it
was categorically mentioned that upon further investigation, no
irregularity could be found in the allotment of tenders to the
Petitioner. Taking into account its relevance, Paragraph Nos. 16.5,
16.6, 16.7 of the Supplementary Charge Sheet are reproduced
herein under:
“16.5.
That after investigation a charge sheet dated 27.06.2025, was filed
before this Hon'ble Court against 04 accused persons viz. Prayas
Chakravorty (A-1), Jyoti Kumar Singh(A-2), Kanal Gupta (A-3) and
M/s. United Drilling Tools Limited (UDTL) through its Authorized
Representatives (A-4) for the offence u/s. 61(2) of BNS and under
sections 7, 9, 10 and 12 of the PC Act, 1988 (as amended in 2018)
and substantive offences thereof. The further investigation of this
case was also kept open to ascertain the role of other officers of
Page No.# 21/38
OIL/UDTL in the instances of bribes of this case as well as in other
tenders allotted to M/s. UDTL.
16.6.
During the course of further investigation, apart from the
tender/Purchase
Order
No.GEMC-511687779896608
dated
03.03.2025, other tenders which were allotted to M/s UDTL by Oil
India Limited, Duliajan during the period 2020 to 2025, have also
been scrutinized. Further investigation has revealed that accused
Prayas
Chakravorty
was
not
associated
with
the
said
tenders/Purchase Orders as he was on deputation in Directorate
General of Hydrocarbons (DGH), Noida, from 2017 to May, 2024.
During
further
investigation,
no
association
of
Sh.
Prayas
Chakravorty has been found with any other tender allotted to M/s
UDTL by OIL since 2020 except Purchase Order No.GEMC511687779896608 dated 03.03.2025.
16.7.
During the course of further investigation no irregularity could be
found in the allotment of tenders to M/s UDTL. Further, it is
revealed that the payments have been made to the vendor M/s.
UDTL after the receipt of materials. All materials have been found
received and duly recorded in Goods Received Notes (GRNs). No
criminal involvement of other officers of OIL could be revealed in
the allotment of tender bearing number GeM/2024/B/5237250
dated 01.08.2024 (Purchase Order no. GEMC-511687779896608
dated 03.03.2025. No evidence could be found which show that
other employees of M/s. UDTL was also involved in bribing to Prayas
Chakravorty
and
other
employees
of
OIL,
for
other
submission
of
the
tenders/purchase orders, awarded to M/s. UDTL.”
45.
In
the
meantime,
prior
to
the
Supplementary Charge Sheet on 22.12.2025, the Show Cause
Page No.# 22/38
Notice was issued on 29.07.2025 asking the Petitioner to show
cause as to why the Petitioner should not be blacklisted. The
record reveals that the Petitioner sought for various documents
and on the ground of not furnishing those documents, the
Petitioner claiming that it was not provided an adequate
opportunity, filed a writ petition before this Court which was
registered and numbered as WP(C) No.5719/2025. It is however
relevant to take note of that on 13.08.2025, the Petitioner
submitted a preliminary reply to the Show Cause Notice dated
29.07.2025. The Respondent OIL, while granting opportunities to
the Petitioner to submit the Show Cause Reply, at all times
informed the Petitioner that in the circumstance no reply was
submitted, the Show Cause proceedings shall be decided on the
basis of the preliminary reply dated 13.08.2025.
46. The order dated 24.09.2025 passed in WP(C) No.5719/2025 is
of relevance inasmuch as this Court while issuing notice making it
returnable on 17.10.2025 did not pass any interim directions
staying the Show Cause proceedings. This Court opined that the
act on the part of the Respondent OIL to issue the Show Cause
Notice and putting the Petitioner under suspension, prima facie
appeared to be in consonance with Para 4.3 of the Banning Policy.
However, this Court granted the Petitioner liberty to file the reply
within 7 (seven) days from 24.09.2025 before the Competent
Page No.# 23/38
Authority.
47. The period of 7 (seven) days from 24.09.2025 expired on
01.10.2025. The Petitioner submitted the reply on 03.10.2025 and
this aspect is duly admitted by the Respondents in their affidavitin-opposition at Paragraph Nos. 15 and 16.
48.
In spite of the reply submitted on 03.10.2025, the
Respondents admittedly did not take into consideration the
contents of the said reply on the ground that the reply was
submitted on 03.10.2025 and not on 01.10.2025. It may not be
out of place to observe that 02.10.2025 was a holiday and the
Final Committee submitted its recommendation on 08.10.2025 at a
time when the Petitioner's reply dated 03.10.2025 was already
there on records.
49. The question therefore arises as to whether the Respondent
Authorities while taking such drastic measures of blacklisting was
reasonable and rational to proceed with the adjudication of the
Show Cause Notice without taking into account the reply dated
03.10.2025. It may not be out of place to mention that the
Petitioner was granted time by the Respondent OIL to file the reply
by 15.09.2025. Till 24.09.2025, in spite of not submitting the reply,
the Respondent Authorities did not take any action. This Court had
granted a liberty to the Petitioner to submit the reply within 7
Page No.# 24/38
(seven) days. The Petitioner, no doubt had faulted, in not
submitting the reply by 01.10.2025 but submitted the reply on
03.10.2025 when no decision was taken by the Respondents. It is
the opinion of this Court that when such drastic measures are in
the contemplation to be taken which amounts to a civil death of a
Company, the Respondent Authorities ought to have been more
rational and reasonable to take on record the reply dated
03.10.2025. No Heaven would have fallen had the reply dated
03.10.2025 was taken on record while arriving at the decision to
blacklist the Petitioner.
50. There are various facets of the principles of natural justice.
Merely issuance of a notice would not be sufficient if the reply
submitted in pursuance to the notice is not taken into
consideration. On this ground alone, it is the opinion of this Court
that the impugned order dated 10.10.2025 cannot be sustained in
law.
51. Let this Court now take note of the merits of the case as
regards the challenge to the impugned order dated 10.10.2025.
The terms of the tender required each bidder to submit the Code
of Integrity Pact. Section 2 of the Integrity Pact stipulates the
commitments of the bidder/contractor. Amongst the various
commitments, it was the commitment of the Bidder that the
Page No.# 25/38
bidder/contractor will not directly or through any other bidder or
firm, offer, promise, or give to any of the Principal's employees
involved in the tender process or the execution of the contract, or
to any third person, any material or immaterial benefit which he or
she is not legally entitled to, in order to obtain in exchange any
advantage of any kind whatsoever during the tender process or
during
the
execution
of
the
contract.
It
is
also
the
bidder's/contractor's commitment that they would not commit any
offence under the relevant anti-corruption laws of India.
52. Section 3 of the Integrity Pact further stipulates that if a
bidder/contractor has committed a transgression through a
violation of Section 2 or in any other form such as to put his
reliability or risibility as bidder into question, the Principal would be
entitled to disqualify the bidder from the tender process or to
terminate the contract, if already signed.
53. Therefore, from a perusal of Section 2 and Section 3 of the
Integrity Pact, it is clear that the power conferred upon the
Principal to disqualify a bidder from the tender process and exclude
from future contracts is subject to commission of a transgression of
Section 2. The said aspect is important which would be seen in the
later stages of the present judgment.
54. In the backdrop of the above, let this Court now take note of
Page No.# 26/38
the Banning Policy, 2023. Para 4.0 is with the heading
“PROVISIONS
FOR
ACTION
IN
CASE
OF
ERRING/DEFAULTING AGENCIES”.
In terms with Para 4.1, an agency can be considered for
debarment if it is determined that the bidder had breached the
Code of Integrity as per Rule 175 of the General Financial Rules,
(GFR) 2017.
Para 4.1.1 refers to the Code of Integrity contained in Rule
175 of the GFR.
Para 4.2 has no relevance to the present proceedings and as
such, not further dealt with.
55. Para 5.0 of the Banning Policy, 2023 is with the heading
“ACTION AGAINST ERRING/DEFAULTING AGENCIES IN
RESPECT OF AN ONGOING TENDER/CONTRACT WHERE
THE AGENCY HAS ERRED/DEFAULTED”. Para 5.1 of the
Banning Policy, 2023 being relevant for the purpose of the present
dispute is reproduced herein under:
“5.1 Action against agencies in respect of an ongoing tender/contract,
where the agency has erred/defaulted any of the provisions
mentioned above in para 4.1 & 4.2:
(i)
The
irregularities
evaluation of bids:
are
prima-facie
established
during
Page No.# 27/38
If it is prima-facie established that, bidder has erred / defaulted any
of the provisions mentioned above in para 4.1 & 4.2; the Company
shall reject the bid of such bidder and shall not consider for further
evaluation/ award. If the bid is rejected after price bid opening and
such bidder happens to be the lowest evaluated bidder, the tender
shall be scrapped and retendered. Further, the Earnest Money
Deposit (EMD)/Bid Security, if applicable and submitted by such
bidder shall be forfeited.
(ii)
The irregularities are prima-facie established after award of
the contract:
(a)
During execution of Contract:
If the contractor is found to have erred / defaulted any of the
provisions mentioned above in para 4.1 & 4.2, in respect of ongoing
contract, such contractor shall be put on banning/debarment list of
OIL after following the due process.
The concerned contract/order where irregularities have been
committed shall be suspended forthwith by the Engineer-in-charge,
who is supervising the contract, with the approval of the concerned
Head of Sphere / Fields /Pipeline Headquarter, as applicable. The
work/services/supply and payment shall be suspended, after taking
into cognizance of provisions under para 5.2 below. The action shall
be initiated for putting the vendor on banning/debarment list.
After following the due process, the order/contract where it has been
concluded that irregularities have been committed
shall be
terminated. The contract Performance Bank Guarantee submitted by
the Contractor shall be forfeited. Any payment due to the contractor
for work already executed and accepted shall be payable after
adjustment of any amount due from the contractor as per the
Page No.# 28/38
provision of the contract.
In this case no Risk and Cost Clause will be applicable.
(b)
The irregularities are prima-facie established after execution of
the contract during defect liability period:
If it is found after execution of the contract, that the contractor erred
/ defaulted any of the provisions mentioned above in para 4.1 & 4.2,
such agency shall be banned for future business with OIL after
following the due process. The contract performance bank guarantee
submitted by the contractor shall be forfeited, if the same is in
Company custody.
(iii)
Irregularities prima-facie established after expiry/completion
of contract/supply:
If the contractor is found to have erred / defaulted any of the
provisions mentioned above in para 4.1 & 4.2, in respect of expired
contract, such contractor shall be put on banning/debarment list of
OIL after following the due process. However, this clause shall be
applicable if the alleged irregularity is noticed and action initiated
within 01 (one) year of last payment made under the contract/supply.
The contract performance bank guarantee submitted by the
contractor shall be forfeited, if the same is in Company custody.”
56.
A reading of Para 5.1 would show that against three
eventualities, three separate Clauses i.e. Clause (i), Clause (ii) and
Clause (iii) are stipulated.
Clause (i) relates to irregularities prima facie established
during evaluation of the bids. The opening words of Clause (i) are
Page No.# 29/38
“if it is prima facie established”. It is of importance to note that the
said Clause do not provide banning/debarment. However, from a
perusal of Clauses (ii) and (iii), it is seen that the contents of the
said Clauses do not mention about prima facie established though
in the heading it is mentioned that the irregularities are prima facie
established. It is also of importance to perceive that Clause (ii) and
(iii) of Para 5.1 contemplates banning/debarment. The contents of
Clauses (ii) and (iii) would further make it apparent what is
conceived is determination/conclusion of the existence of facts
which show that the Contractor had erred/defaulted in any of the
provisions mentioned in Para 4.1 and 4.2 of the Banning Policy or
for that matter, commission of the irregularities. It also formulates
the manner in which such decision is to be arrived at i.e. by
following the due process. However in respect to Clause (i) of Para
5.1 of the Banning Policy, such formulation of the manner to arrive
at the decision is not there.
57. This Court also finds it relevant to observe that a banning
policy has to be in consonance with the settled principles of law. A
drastic measure of blacklisting which entails the consequence of a
civil death to a contractor cannot be based upon a prima facie
satisfaction. It has to be determinative to arrive at a satisfaction
that the existent facts calls for drastic action against the contractor.
It may not be out of place to observe that the term “prima facie” is
Page No.# 30/38
latin term meaning “at first sight” or “on the face of it”. Therefore,
the term “prima facie established” would mean a established on a
cursory glance. If this Court accepts that blacklisting/debarment
can be carried out merely on being prima facie established, it
would result in drastic consequences being taken without a proper
assessment on available material facts. It may not be out of place
to observe that in the case of Blue Dreamz Advertising Private
Limited (supra), the Supreme Court observed debarring a person
albeit for a certain number of years tantamounts to civil death
inasmuch as the said person is commercially ostracized resulting in
serious consequences for the person and those who are employed
by him.
58. Rule 151 of the GFR comes into play when a bidder had been
convicted of an offence under the Act of 1988 or the Indian Penal
Code or any other law for the time being in force causing any loss
of life or property or causing a threat to public health as part of
execution of a public procurement contract.
59. Rule 175 of the GFR would show that when there is a violation
to the Code of Integrity, after providing the person to be affected a
reasonable opportunity of being heard, a conclusion has to be
arrived at that the bidder or the prospective bidder, as the case
may be, had contravened the Code of Integrity and then the
Page No.# 31/38
Competent Authority may take appropriate measures. The term
“comes to the conclusion” as appearing in Rule 175(2) also
postulates that there has to be an objective satisfaction reached
independently on the materials available that the Code of Integrity
had been violated. Additionally, Rule 175 of GFR does not mention
about prima facie established but rather refers to conclusion.
60. This Court now finds it relevant to take note of the Final
Committee's recommendation dated 08.10.2025 as well as the
impugned
order
recommendation
dated
dated
10.10.2025.
08.10.2025
A
perusal
of
the
would
show
that
the
satisfaction reached is prima facie satisfaction. The said prima facie
satisfaction is not based upon independent assessment or enquiry
on the materials available but based upon an FIR filed by the CBI,
the Charge Sheet submitted by the CBI, the cognizance taken by
the Court and the reluctance of the Respondents to carry on
business with a contractor who is being tried before a Criminal
Court on the allegation of forgery/bribery.
61. Let this Court now analyze the basis of the prima facie
satisfaction. The first document is the FIR submitted by the Central
Bureau of Investigation. It is well settled that an FIR is not a
substantive evidence. It only triggers the criminal investigation. It
can at best be used for the limited purpose of corroborating or
Page No.# 32/38
contradicting the informant who lodged, in a criminal trial. {See
Sk. Hasib Vs. State of Bihar reported in (1972) 4 SCC 773}.
The next document is the Charge Sheet submitted by the
Central Bureau of Investigation. A Charge Sheet is the culmination
of the investigation and records the Investigating Officer's opinion formed on the material collected - that a case for trial against the
named accused. It is not a substantive piece of evidence and the
contents of the Charge Sheet has to be proved independently by
admissible evidence in a criminal trial.
The third document is the order of taking cognizance. The order
of taking cognizance implies application of mind of Judicial Court to
the suspected commission of offence for the purpose of proceeding
under the Code of Criminal Procedure, 1973 or the Bharatiya
Nagarik Suraksha Sanhita, 2023.
The above documents solely cannot be made the basis for
taking the drastic step of blacklisting without an independent
assessment made on the basis of any enquiry by the Competent
Authority to arrive at a conclusion that there exists materials
justifying the penalty of debarment.
The reason for passing the impugned debarment order dated
10.10.2025 is the reluctance of the Respondent OIL in carrying on
Page No.# 33/38
a business with a contractor who is facing a trial on allegations of
bribery and corruption. Neither the Banning Policy of the
Respondent OIL nor the General Financial Rules, 2017 provides a
stipulation that a contractor facing a criminal trial involving
allegations of bribery/corruption would be debarred/blacklisted.
Rather Rule 151 of the General Financial Rules, 2017 stipulates
steps for debarment/blacklisting upon conviction. It is also of
importance to note the Rule 175(2) of the General Financial Rules,
permit
the
Competent
Authority
to
debar
impose
debarment/blacklisting upon conclusion reached that there is
violation to the Code of Integrity.
62. Considering the above, it is therefore the opinion of this Court
that the impugned order dated 10.10.2025, by which the Petitioner
was put into the Holiday List cannot be sustained in law as it is not
based upon an objective satisfaction of the Competent Authority on
the basis of the materials available. The filing of an FIR,
submission of the Charge Sheet as well as cognizance taken by the
Court, in the opinion of this Court cannot be the basis without
there being an independent assessment on the basis of the
materials available.
63. At this stage, let this Court consider an important aspect which
stems from the submission made by the learned Senior counsel
Page No.# 34/38
appearing on behalf of the Respondents that the proceedings of
debarment cannot await the final culmination of the criminal trial.
This aspect is an important aspect taking into account that in the
final reply submitted by the Petitioner on 03.10.2025, the Petitioner
had made an alternative plea that the debarment proceedings
should be stalled pending the criminal trial. It is the opinion of this
Court that a proceedings for debarment/blacklisting is a separate
proceedings invoked on the basis of the terms of the tender,
banning policies etc. It is completely distinct and different from a
criminal trial inasmuch as, in a proceedings for debarment, what is
to be decided is based upon the materials available before the
Competent Authority whether an action of debarment is justified.
The touchstone is preponderance of probabilities unlike in a
criminal trial where the evidence is to be proved beyond
reasonable doubt.
64. Therefore, for deciding a proceedings for debarment, what is
required are materials/evidence justifying action to be taken in
terms with the terms of the contract, banning policies etc. It has to
be decided by following the principles of natural justice and not
strictly within the contours of the Bharatiya Sakshya Adhiniyam,
2023. The decision so taken to debar a contractor has to be
reasonable, rational, non-arbitrary as well as applying the doctrine
of proportionality. In other words, while taking a decision for
Page No.# 35/38
debarment, what is to be looked into is as to whether the action
taken conforms to Article 14 of the Constitution of India.
Therefore, in the opinion of this Court, the pendency of a criminal
proceedings would not act as an impediment to initiate or take
action for debarment.
65. In the previous segments of the instant judgment, this Court
has already opined that the impugned order dated 10.10.2025
cannot be sustained in law primarily for two reasons. First, on the
ground of unreasonableness and irrationality inasmuch as the final
reply dated 03.10.2025 was not taken into consideration while
deciding the show cause proceedings initiated vide the Show Cause
Notice dated 29.07.2025. The second reason is that the competent
authority without arriving at an independent assessment on the
basis of the materials available with the authority have passed the
impugned order merely on the basis that an FIR had been lodged,
charge sheet filed, cognizance taken and the Respondents’
reluctance to carry on business with a company which is alleged of
offences pertaining to bribery/corruption.
66. Taking into account the above, it is the opinion of this Court
that this is a fit case for remand to the competent authority of the
Respondent OIL to take a fresh decision on merits, after setting
aside the impugned order dated 10.10.2025 and the Appellate
Page No.# 36/38
order dated 15.12.2025.
67. This Court further takes note of the submission made by the
learned Senior counsel appearing on behalf of the Petitioner that
the Petitioner is not insisting on the relief at Serial Nos. (b) and (d)
and have sought liberty to initiate separate proceedings as
envisaged under law. It is the opinion of this Court that the
blacklisting/debarring is a completely separate cause of action from
that of termination of the contract and forfeiture of the security
deposit. Under such circumstances, it is therefore the opinion of
this Court that the Petitioner should be granted the leave to file
separate proceedings, if so advised, as envisaged under law
challenging the communication dated 12.12.2025 whereby the
contract dated 03.03.2025 was cancelled and the performance
security was forfeited and other consequential actions.
CONCLUSION:
68. Accordingly, the instant writ petition therefore stands disposed
of with the following observations and directions:
(i)
The impugned Banning Order dated 10.10.2025 passed by the
Executive Director (C&P) i.e. the Respondent No.4 is set aside
and quashed.
(ii) The impugned order dated 15.12.2025 passed by the Director
Page No.# 37/38
(Operations) i.e. the Respondent No.2 is set aside and
quashed.
(iii) The question as to whether the Petitioner should be debarred
on the basis of the Show Cause Notice dated 29.07.2025 is
remanded back to the Competent Authority of the Respondent
OIL to be decided afresh. This Court further directs that while
deciding afresh, the competent authority of Respondent OIL
shall not only take into consideration the Petitioner’s
preliminary reply dated 13.08.2025 but also the final reply
dated 03.10.2025, the representations dated 25.02.2026 and
29.04.2026 and further provide the Petitioner an opportunity
of personal hearing.
(iv) This Court further directs that the said decision be taken by
the Competent Authority of OIL within a period of 60 (sixty)
days from the date a certified copy of the instant judgment is
served upon the Executive Director, (C&P). Till such decision is
taken within the period stipulated above, the suspension of
the Petitioner which was imposed vide the communication
dated 29.07.2025 shall continue.
(v)
The Petitioner herein is granted the liberty in respect to the
reliefs sought for at Serial Nos. (b) and (d) to file separate
proceedings, if so advised.
Page No.# 38/38
(vi) There shall be no order as to costs.
Bijoy Saha
Bijoy Saha
Date: 2026.08.27
20:32:32 +05'30'
Comparing Assistant
JUDGE
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review