The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
16. It is clear from the material on record that the delay in completion of the work was not attributable to the claimant and the Arbitral Tribunal was justified in allowing Claim Nos.1, 2, 7, 10 and 14. The Commercial Court has adequately appreciated the material on record and dismissed the petition filed by the appellant under Section 34 of the A&C Act.
17. In view of the aforementioned, it cannot be held that the Award suffers from patent illegality and is liable to be interfered with. Hence, the above appeal is dismissed as being devoid of merit.
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
-1-
COMAP No. 478 of 2025
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 9TH DAY OF JANUARY, 2026
PRESENT
THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
AND
THE HON'BLE MR. JUSTICE C.M. POONACHA
COMMERCIAL APPEAL NO. 478 OF 2025
BETWEEN:
THE EXECUTIVE ENGINEER
MANGALORE UNIVERSITY
MANGALAGANGOTRI
DAKSHINA KANNADA
DISTRICT - 574199
…APPELLANT
(BY MR. ARIHANT R SUNGAY, ADVOCATE FOR
SRI. T P RAJENDRA KUMAR SUNGAY, ADVOCATE)
AND:
Digitally
signed by
NIRMALA
DEVI
Location:
HIGH
COURT OF
KARNATAKA
1.
M/S. BSR INFRACTECH INDIA LTD.
CORPORATE OFFICE AT NO.851,
D BLOCK, 15TH CROSS,
SAHAKARNAGAR
BENGALURU - 560092
2.
JUSTICE ANAND BYRA REDDY
FORMER JUDGE,
HIGH COURT OF KARNATAKA
SOLE ARBITRATOR
ARBITRATION AND CONCILIATION
CENTER 3RD FLOOR,
EAST WING,
KHANIJA BHAVAN,
RACE COURSE ROAD,
BENGALURU - 560001.
…RESPONDENTS
(BY SRI. ZULFIKIR KUMAR SHAFI, ADVOCATE FOR R1)
-2-
COMAP No. 478 of 2025
THIS COMAP IS FILED UNDER SECTION 13(1A) OF
COMMERCIAL COURTS ACT, 2015 READ WITH SECTION 37
OF
THE
ARBITRATION
AND
CONCILIATION
ACT,
PRAYING TO SET ASIDE THE IMPUGNED ORDER DATED
03.07.2025 PASSED BY THE LXXXV ADDITIONAL CITY CIVIL
AND
SESSIONS
JUDGE,
AT
BENGALURU,
(CCH-86)
(COMMERCIAL COURT) DISMISSING COM.AP NO.179/2024
AND CONSEQUENTLY, SET ASIDE THE ARBITRAL AWARD
DATED 04.09.2024 PASSED BY
RESPONDENT NO.2 IN
AC.NO.593/2023 AND DISMISS RESPONDENT NO.1 CLAIM
PETITION.
THIS APPEAL HAVING BEEN HEARD AND RESERVED
FOR JUDGMENT, COMING ON FOR PRONOUNCEMENT THIS
DAY, JUDGMENT WAS PRONOUNCED AS UNDER:
CORAM: HON'BLE MR. VIBHU BAKHRU ,CHIEF JUSTICE
and
HON'BLE MR. JUSTICE C.M. POONACHA
CAV JUDGMENT
(PER: HON'BLE MR. JUSTICE C.M. POONACHA)
1.
The present appeal is filed under Section 13(1A) of
Commercial Courts Act, 2015 (CC Act) r/w Section 37 of the
Arbitration & Conciliation Act, 1996 (A&C Act), calling in question
the judgment dated 03.07.2025 by the Court of LXXXV Addl. City
Civil & Sessions Judge, Bengaluru (CCH-86), (Commercial Court)
-3-
COMAP No. 478 of 2025
and the Award dated 04.09.2024 passed in A.C. No.593/2023 by
the Sole Arbitrator/Arbitral Tribunal.
2.
The relevant facts are that the respondent No.1 was the
successful tenderer in the tender notification dated 15.07.2016
issued by the appellant for construction of 'International Hostels,
Class Room Complex and Auditorium Interior Works' for Mangalore
University at Mangalore. It was agreed between the parties to
execute the works at 19.50% above the schedule of rates (SR) of
the Public Works Department (PWD) of the Government of
Karnataka for the year 2015-16. The contract was executed on
17.10.2016 and the work order was issued by the appellant on
20.10.2016. The total contract value was `53,77,00,802/- excluding
service tax which was to be reimbursed on submission of vouchers
disclosing the payment to the concerned authorities. The contract
was to be completed within 18 months including monsoon.
3.
It was the claim of the respondent-claimant that the project
site was not available and was not free from obstacles. Apart from
the physical possession of the project site, the claimant also is
stated to have faced certain other constraints like non-availability of
sand in the Mangalore area, non release and delay in payment of
running bills, etc. It is the contention of the claimant that the
-4-
COMAP No. 478 of 2025
appellant had entrusted additional works apart from the scope of
work that was entrusted by the work order. That despite various
constraints, the claimant had successfully completed work of the
value of `4585 lakhs as against the contract value of `5377 lakhs
(approximately 86%), which was the financial progress. The
physical progress at the site was stated to be more than the
financial progress.
4.
It is the further case of the claimant that the appellant has
executed a supplementary Agreement dated 13.03.2018 towards
extra items and excess quantities for a total value of `9.45 crores.
The claimant having contended that the appellant had not paid
various amounts in terms of the running bills submitted by the
claimant and since the claimant was unable to proceed further with
the work at its own cost, stopped the execution of the work and got
issued a legal notice on 01.09.2021. However, in the hope of an
amicable settlement the claimant withdrew the said notice vide
letter date 18.12.2021. That since the appellant failed to comply
with its assurances, the claimant got issued a letter dated
29.07.2022 and thereafter invoked the arbitration clause.
5.
In the arbitral proceedings, the claimant made a total of 15
claims in a total sum of `81,57,85,316/-. The appellant entered
-5-
COMAP No. 478 of 2025
appearance in the arbitration proceedings and filed its statement of
objections, as also made a total of 7 counter claims of a total sum
of `100 crores. The Arbitral Tribunal framed 24 points for
consideration. By award dated 04.09.2024, the Arbitral Tribunal
partly allowed the claim petition, rejected the counter claim and
ordered as under:
Claim No.1 (Pending R.A. bills produced, for
Rs.8.12 Crore, with interest thereon @ 18% from
the date each of the said bills fell due, till the date
of realization.)
Claim No.2 (Price Adjustment bills for about
Rs.1.44 Crore with interest thereon @ 18% from
the date the said bills fell due, till the date of
realization.)
Claim No.7 (Towards Unproductive/Additional
Overhead Charges, nominally assessed at Rs.50
Lac, with interest thereon at 24% per annum from
the date of this Award till the date of realization)
Claim No.10 (Towards Statutory Payments and
Reimbursement for about Rs.2.99 Crore, with
interest at the rate of 18% from the date the
statutory payments are shown to be made, till the
date of realization)
Claim No.14: The respondent shall be liable to
pay GST, to the Claimant, on the above amounts
awarded, as applicable.
c. The Claimant shall be entitled to the costs of
these proceedings, to be paid by the Respondent,
in terms of Section 31 A of the Arbitration and
Conciliation Act, 1996.
-6-
COMAP No. 478 of 2025
d. The stamp duty on this award, is payable as
per the Karnataka Stamp Act, 1957.
6.
Being aggrieved, the appellant filed a petition under Section
34 of the A&C Act before the Commercial Court. The claimant
entered appearance before the Commercial Court and contested
the proceedings. The Commercial Court by its judgment dated
03.07.2025 dismissed the petition filed by the appellant with costs.
Being aggrieved, the appellant has preferred the present appeal.
7.
The primary contention put forth by the appellant is that the
conclusion of the Arbitral Tribunal, which was affirmed by the
Commercial Court holding that the appellant was responsible for
the delay, is erroneous.
It is contended that in the Bill Of
Quantities, which formed a part of the contract, it was clearly
provided that the claimant was to clear the vegetation, grass, trees
and hence, no delay can be attributed to the appellant. It is further
contended that the Contract provided for site visit, site inspection
and queries, which demonstrate that the claimant had prior
knowledge of the site.
The findings of the Arbitral Tribunal
attributing the delay to the appellant for shortage of sand was also
sought to be impeached.
-7-
COMAP No. 478 of 2025
8.
In this context, the Arbitral Tribunal had noticed that the
Contract provided for 5000 cubic metres of rock, whereas during
the excavation, the claimant encountered 42000 cubic metres of
rock, which was unforeseen.
9.
Clause 21 of the Conditions of Contract, reads as under:
"21. Possession of Site: 21.1 The Employer shall
give possession of all parts of the Site to the
Contractor. If possession of a part is not given by the
date stated in the Contract Data the Employer is
deemed to have delayed that start of the relevant
activities and this will be Compensation Event.
10.
It is clear that the Contract having specifically provided that it
was the appellant who was required to give possession of all parts
of the site to the claimant, the Arbitral Tribunal was justified in
holding that the appellant was responsible for the delay. Further,
there is no material on record to indicate that the claimant was
aware as to the extent of rock that was required to be removed
from the site for commencement of the work. The Tribunal, noticing
clause 21 of the Conditions of Contract as well as the
acknowledgement for handing over and taking over the site (Ex.R1)
held that the said document generally stated that the site has been
handed over and did not establish that all parts of the site were
-8-
COMAP No. 478 of 2025
examined for obstacles and/or hindrance free site was handed over
to the claimant.
11.
It was also noticed that the appellant had sent a letter
(Annexure-R3) to the Deputy Commissioner to provide for sand for
construction. It was held that the shortage of sand was beyond the
control of the claimant. It was also noticed that the delay in the
completion of the project was solely on the part of the appellant for
not having handed over an obstacle free worksite to the claimant to
commence the work.
12.
Further, the permissions/approvals for removing the trees
were to be obtained by the appellant. Hence, it cannot be held that
the finding of delay by the Arbitral Tribunal has been arrived at
without any material on record.
Under the circumstances, the
finding of the Arbitral Tribunal, regarding delay attributable to the
appellant which was affirmed by the Commercial Court does not
suffer from any patent illegality and is not liable to be interfered
with.
13.
Another contention put forth by the appellant is that the
Arbitral Tribunal has not considered the counter claim put forth by
the appellant.
In this regard, it is pertinent to note that the
-9-
COMAP No. 478 of 2025
consideration of the counter claim of the appellant would have
arisen if it was held that the claimant was responsible for the delay
in execution of the Contract. The Tribunal has held that "only if the
respondent succeeds in defeating all the claims of the claimant by
establishing that the claimant has committed breach of contract,
the counter claim would arise for consideration". The appellant not
having succeeded in establishing that the delay in completion of
the Contract was solely attributable to the claimant, the rejection of
the counter claim by the Arbitral Tribunal, which has been affirmed
by the Commercial Court cannot be faulted.
14.
It is also sought to be contended that the Commercial Court
had not dealt with all the grounds urged by the appellant in the
petition filed under Section 34 of the A&C Act. In this context, it is
pertinent to note that the primary ground regarding delay and
rejection of the counter claim have been adequately addressed by
the Commercial Court.
15.
It is also pertinent to note that the claimant had completed
86% of the work and admittedly 82.94% of the payments were
made. Additional works were also entrusted by the appellant to the
claimant, to which a supplementary agreement was also executed.
- 10 -
COMAP No. 478 of 2025
16.
It is clear from the material on record that the delay in
completion of the work was not attributable to the claimant and
the Arbitral Tribunal was justified in allowing Claim Nos.1, 2, 7, 10
and 14. The Commercial Court has adequately appreciated the
material on record and dismissed the petition filed by the appellant
under Section 34 of the A&C Act.
17.
In view of the aforementioned, it cannot be held that the
Award suffers from patent illegality and is liable to be interfered
with. Hence, the above appeal is dismissed as being devoid of
merit.
18.
Pending applications, if any, stand disposed of.
Sd/(VIBHU BAKHRU)
CHIEF JUSTICE
Sd/(C.M. POONACHA)
JUDGE
ND/-
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review