Page No.# 1/7
GAHC010080902026
2026:GAU-AS:17378-DB
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WA/147/2026
SURAJIT RABHA
S/O- TANGUN RABHA, VILLAGE- GERUAPAR
P.O.- DONGPAR DIST- BAKSA ASSAM- 781368.
-VERSUS1: THE BODOLAND TERRITORIAL COUNCIL AND 5 ORS. REPRESENTED BY
THE PRINCIPAL SECRETARY BODOLAND TERRITORIAL COUNCIL (BTC)
BODOLAND SECRETARIAT COMPLEX BODOFA NWGWR KOKRAJHAR783371.
2:THE SECRETARY BODOLAND TERRITORIAL COUNCIL (BTC)
ENVIRONMENT AND FOREST DEPARTMENT BODOLAND SECRETARIAT
COMPLEX BODOFA NWGWR KOKRAJHAR- 783371
3:THE ADDITIONAL CHIEF CONSERVATOR OF FOREST CUM CHD
BODOLAND TERRITORIAL COUNCIL KOKRAJHAR- 783371
4:THE DIVISIONAL FOREST OFFICER BAKSA FOREST DIVISION
DEPARTMENT MUSHALPUR BTR BAKSA- 781372
5:THE EXECUTIVE MEMBER BODOLAND TERRITORAIL COUNCIL
BODOFA NWGWR KOKRAJHAR-783371
6:SRI. DINESH BORO
S/O. SRI MAINA RAM BORO R/O. VILL.- NATHKUCHI
P/O. NIZ-DEFELI DIST. TENGAJHAR PIN-781364
For the Appellant(s)
: Mr. R. Majumdar, Advocate.
For the Respondent(s)
: Ms. B. Bhuyan, Sr. Advocate/Standing Counsel, BTC, assisted by Ms.
R. Saloi, Advocate.
Page No.# 2/7
–B E F O R E –
HON’BLE THE CHIEF JUSTICE MR. ASHUTOSH KUMAR
HON’BLE MR. JUSTICE KAUSHIK GOSWAMI
23.11.2026
(Ashutosh Kumar, CJ)
We have heard Mr. R. Majumdar, learned Advocate for the
appellant and Ms. B. Bhuyan, learned Senior Advocate/Standing
Counsel, BTC, assisted by Ms. R. Saloi, learned Advocate for the
respondent Nos.1 to 5.
2.
The bid of the appellant against the NIT issued by the Divisional
Forest Officer, Baksa Forest Division for settling Barnadi Sand Mahal No.13
for sand mining contract period for 7(seven) years from 2025 to 2032, was
returned as the highest offer. The Bid Committee recommended the
tender of the appellant, which recommendation was ultimately
approved by the Secretary, BTC and was formally communicated by the
Additional Principal Chief Conservator of Forests-cum-Council Head of
the Department, BTC, Kokrajhar with a specific direction to complete the
settlement as per the provisions of the Assam Minor Mineral Concession
Rules, 2013 (hereinafter to be referred as the “Rules of 2013”).
However, because of the objection of an Executive Member of
the BTC, the recommendation in favour of the appellant was rejected
and a further decision was taken to re-process the tender and to allot the
Mahal to one Dinesh Boro (respondent No.6), who had not even
participated in the original bid.
3.
This was questioned by the appellant before the learned Single
Judge vide WP(C) No.6863/2025. Later, during the pendency of the
afore-noted writ petition, the entire tender was withdrawn with a decision
Page No.# 3/7
of the BTC to re-process the entire tender by e-auction mode, as
mandated under the Rules of 2013.
4.
Before the Writ Court, the appellant had contended that when
the tender was floated, no Rule provided necessarily for e-auction. Any
decision to put every auction under the e-auction mode was a later
development, which could not have been applied in the case of the
appellant, especially when he had been found to be technically and
financially responsive to the bid and the only thing left was the formal
conclusion of the contract and issuance of work order to the appellant.
5.
The learned Single Judge, however, vide the impugned
judgment dated 02.04.2026, took the view that once a decision has been
taken to cancel the tender in its entirety and adopt the e-auction/
procurement mode for work of any value, then no interference was
required but observed that if any earnest money is still lying with the BTC,
that must be returned to the appellant forthwith.
6.
The appellant has doubted such a decision on the ground that
the requirement of e-auction/ procurement was not necessary in all
tenders and that such requirement was introduced post the floating of
the tender. Thus, that could not have been the sole reason for cancelling
the tender. It was also contended by the appellant that the BTC never
adopted such resolution or decision to put every work to e-tender,
regardless of the work value.
The contention, therefore, is that the cancellation of tender in its
entirety was arbitrary and procedurally unjust. It also suffered from
arbitrariness.
Page No.# 4/7
7.
The afore-noted contentions are based on the fact that tender
for other Sand Mahals floated contemporaneously without the e-auction
mode were taken to its conclusion and were settled with the highest
bidders. Thus, the only reason for not accepting the tender of the
appellant at such a belated stage was the desire of one of the Executive
Members of the BTC to have the work allotted in favour of the
respondent No.6. When this ploy did not succeed, the entire tender was
withdrawn.
8.
This precipitate action by the BTC, therefore, is not only arbitrary
but also a colourable exercise of power.
However, the afore-noted grounds do not weigh heavily with us
at this stage when the entire tender has been withdrawn as no
enforceable right in favour of the appellant can be said to have been
created only on the recommendation of the bid of the appellant for final
contract.
9.
This issue has been debated a number of times before the
judicial forums and it is no mere semantics whether at a stage prior to
conclusion of contract can lead to any claim for enforcement of such
contract. At any stage, before the conclusion of the contract with the
party, the process remains inchoate, conditional and perhaps only an
expression of intent that the party selected would become the
concessionaire.
10.
In Rajasthan Co-operative Dairy Federation Limited -Vs- Maha Laxmi
Mingrate Marketing Services (P) Limited & Ors. :: (1996) 10 SCC 405 ; Dresser
Rand S.A. -Vs- Bindal Agro Chemicals Limited :: (2006) 1 SCC 751 and Level-9
Page No.# 5/7
Biz Private Limited -Vs- H.P. Housing and Urban Development Authority ::
Manu/SC/0258/2024, the Supreme Court has consistently held that a
decision to enter into a contract with a party in a tender does not
tantamount to the contract itself but it only remains a “promise in
embryo”. No doubt it is capable of maturing into an enforceable
contract and justifiably a bidder may expect that the formal contract will
follow, which is quite in sync with the commercial nature of these
proceedings but such expectations do not galvanized into entitlement.
11.
The ground taken by the BTC to cancel the tender in its entirety
and the impugned judgment, which defends such a decision, have been
assailed by the appellant as arbitrary and unjust.
From the arguments advanced on behalf of the parties, we are
of the view that had the contract not been given to the appellant but to
the respondent No.6, who was not even a bidder, because of the choice
of the BTC, it would have been absolutely unjust and a faulty decision
making. However, we are not in a position to find fault with the process,
especially when the entire tender has now been withdrawn on the
principle of State having the freedom to contract.
12.
In Jagdish Mandal -Vs- State of Orissa & Ors. :: (2007) 14 SCC 517 ,
the Supreme Court made a cautionary observation that, perhaps, a Writ
Court ought not to interfere in such matters unless the action of the State
is so arbitrary that no responsible authority acting reasonably and in
accordance with the relevant law could have reached. There must be a
nuanced understanding of the circumstances. Though the decision not to
finally enter into a contract with the appellant was imbued with a motive
Page No.# 6/7
which cannot be called just and proper but with the withdrawal of the
entire tender for the purpose of re-processing it, it would be difficult for us
to record that this process also was adopted to somehow benefit the
respondent No.6 or anyone else in place of the appellant. There was an
element of unreasonableness prima facie when the respondent No.6 was
named by the BTC. The error perhaps was remedied when a decision was
taken to withdraw the entire tender for the purposes of floating a fresh
tender.
13.
In any case, with our inability to hold the entire cancelation to be
vitiated only on the ground of the requirement of e-auction not
mandated at the time when the tender was floated, this Court could
have only thought of remanding the matter to the competent authority
for reconsideration of the question whether that could be a ground for
cancellation of the tender but nothing beyond. We find from the
circumstances of this case that such calibrated remedy would serve no
good purpose when the decision has already been taken by the BTC to
float a fresh tender where there would be no proscription on the
appellant to participate.
14.
That apart, we find that there should not be any dispute now with
respect to necessity of e-auction as such requirement is only regulatory in
nature, which ought not to be subjected to any dialectical debate as to
whether the requirement could have a retrospective operation. The
cancellation of the entire tender, which appear to be arbitrary, was later
remedied by a decision to put it to a fresh tender.
15.
Mr. Majumdar, learned Advocate for the appellant has drawn
Page No.# 7/7
our attention of this Court towards the observations of the Supreme Court
in Subodh Kumar Singh Rathour -Vs- Chief Executive Officer & Ors. :: (2024)
15 SCC 461, wherein it has been held that tenders are in the nature of
public contract, whose sanctity would surely be compromised if they are
withdrawn unnecessarily or for no plausible reason and that it would be
no fallacy to entertain legitimate expectation for such process to be
concluded.
16.
There is no denial to the afore-noted propositions but in the
current set of facts and circumstances of the case, we find that no useful
purpose would be served in reversing the judgment impugned.
17.
Thus, while upholding the judgment impugned, we reiterate that
the appellant shall be returned the earnest money forthwith, which Mrs.
Bhuyan, learned Senior Advocate representing the BTC submits, has
already been done. It will be open for the appellant to encash the
Demand Draft and if the Demand Draft has expired, ask for renewal of
such Demand Draft from the respondent/BTC. It would be open for the
appellant to participate in fresh tender.
18.
The appeal stands dismissed.
19.
No order as to costs.
JUDGE
Comparing Assistant
CHIEF JUSTICE
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review