Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Reserved on: 05th February, 2026
Pronounced on: 16th June, 2026
+
RFA 546/2024
SUNIL VADEHRA
S/o Shri Sohan Lal Vadehra,
R/o C-34, Nizamuddin East,
New Delhi
Through:
.....Appellant
Mr. S. C. Anand Advocate.
versus
AITHENT TECHNOLOGIES PVT. LTD.
Through its Chief Executive Officer,
A-186, Okhla Industrial Area, Phase-I,
New Delhi-110020.
.....Respondent
Through: Ms. Venancio D'Costa and Ms. Gauri
Goel, Advocates.
CORAM:
HON'BLE MS. JUSTICE NEENA BANSAL KRISHNA
J U D G M
E N T
NEENA BANSAL KRISHNA, J.
1.
The present Regular First Appeal under Section 96 read with Order
XLI of the Code of Civil Procedure, 1908 (hereinafter referred to as
“CPC”) has been preferred by the Appellant/Plaintiff, Sunil Vadhera,
assailing the Judgment and Decree dated 18.04.2024, whereby the Suit for
Recovery of Rs.8,89,381/- filed by the Appellant/Plaintiff has been
dismissed, by the learned District Judge, Delhi.
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
2.
The Appellant/Plaintiff instituted the CS DJ No.13354/2016 for
recovery of Rs.8,89,381/- (principal amount of Rs.6,54,733/- and interest of
Rs. 2,34,648).
3.
Briefly stated, the case of the Appellant/Plaintiff was that he joined
the services of the Respondent Company on 01.04.1995 and continued in
employment till 19.11.2003. At the time of his resignation, he was serving
as Director and General Manager of the Company and was drawing a gross
monthly salary of Rs.1,42,333/-.
4.
During the financial year 2002-2003, the Respondent Company faced
financial difficulties on account of substantial investments in infrastructure
and delayed payments from its overseas affiliated entities. Consequently, in
March 2002, the Defendant Company decided to defer a portion of the
salaries payable to employees drawing salaries above Rs.12,000/- per
month,for the financial year 2002–2003 on a graded scale of 15%, 20%,
25% and 30% depending upon the salary range. The employees were also
promised one month’s salary, as bonus compensation, to offset the financial
hardship occasioned by the deferment of salaries. The deferred salary was to
be paid, on 01.04.2003.
5.
The deferment was implemented on a graded scale, and since his
salary exceeded Rs.60,000/- per month, 30% of his gross salary amounting
to Rs.42,700/- per month, was deferred from April, 2002 till March, 2003.
The deferred component aggregating to Rs.5,12,400/-, was agreed to be paid
on 01.04.2003.
6.
The Appellant/Plaintiff further asserted that as per the policy of
deferment, he was also entitled to Rs.1,42,333/- i.e. one month’s salary, as
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
bonus compensation. Hence, a total amount of Rs. 6,54,733/- was due and
payable to the Plaintiff, as on 01.04.2003.
7.
Appellant/Plaintiff stated that during an Open-House Meeting held on
09.08.2002, the Management announced restoration of salaries of certain
category of employees i.e. lowest salary group of Rs.12,000/- to Rs.20,000
per month, with effect from 01.10.2002, and assured that the cases of other
employees would also be reviewed and their deferred salaries, would be
released.
8.
As per the Appellant/Plaintiff, the said announcement had been made
with the approval of the CEO of the Defendant Company, who had sent an
e-mail dated 09.07.2002 to Mr. Raju Ahluwalia, with copies to Mr. Ajay
Malik and the Appellant/Plaintiff regarding the preponement of the decision
to restore salaries to the earlier levels.
9.
While the original salary of the Appellant/Plaintiff of Rs.1,42,333/-,
stood restored w.e.f. 01.04.2003, the management sought more time to pay
the arrears of the deferred salary along with the compensation bonus. The
Plaintiff has also relied upon a communication dated 05.04.2004, issued by
the CEO of the Respondent Company assuring clearance of his dues by
31.05.2004. However, payment of the deferred salary and compensation
bonus, continued to be postponed, despite repeated requests.
10.
Despite subsequent e-mails sent by the Plaintiff asking about his dues,
the Respondent Company failed to release the claimed amount.
11.
The Appellant/Plaintiff instituted the present Suit seeking recovery of
Rs.8,89,381/- inclusive of interest (Rs. 6,54,733/- plus interest of
Rs.2,34,648/-).
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
12.
The Defendant/Respondent Company in its Written Statement,
raised a preliminary objection regarding territorial jurisdiction.
13.
On merits, it was contended that there was no deferment of salary and
that the salary structure of employees had merely been restructured, in view
of prevailing business circumstances.
14.
The Respondent Company denied that any Agreement existed
whereby the reduced portion of salary was to be repaid, at a future date. It
was further asserted that the Appellant/Plaintiff himself was part of the
Management team which had participated in the decision-making process
relating to restructuring of salaries.
15.
The Respondent Company admitted that one month's salary had been
discussed as a “loyalty incentive”, but asserted that the same was neither a
contractual commitment nor a legally enforceable obligation.
16.
The Respondent Company further denied that any amount remained
due and payable to the Appellant/Plaintiff, at the time of cessation of his
employment and prayed for dismissal of the Suit.
17.
On the basis of the pleadings of the parties, the learned Trial Court
framed the following Issues, on 26.04.2008:
“1. Whether the plaintiff is entitled for the suit amount?
OPP
2. Whether the plaintiff is entitled to interest, if any, then
at what rate and to what extend? OPP
3. Relief.”
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
18.
The Appellant/Plaintiff examined himself as PW-1 and tendered his
affidavit Ex.PW-1/A. He relied upon the salary certificate, income tax
records, e-mail communications, correspondence exchanged between the
parties and other documents Ex. PW-1/1 – Ex. PW – 1/7.
19.
PW-2, Shri Sanjay Verma, former Vice-President of the Respondent
Company, supported the case of the Appellant/Plaintiff regarding deferment
of salaries and the subsequent assurances extended by the Management.
20.
DW-1, Shri Bunty Bisht, Manager of defendant Company,
reiterated the stand taken in the Written Statement and denied existence of
any agreement regarding deferred salary.
21.
The learned Trial Court, upon appreciation of the evidence led by the
parties, concluded that the Appellant/Plaintiff had failed to establish any
contractual arrangement, whereby the reduced component of salary was to
be repaid at a later date or that one month's salary was contractually payable
as bonus. Consequently, the Suit was dismissed vide Judgment and
Decree dated 18.04.2024.
22.
Aggrieved by the said Judgment and Decree dated 18.04.2024, the
present Appeal has been preferred by the Appellant/Plaintiff.
23.
The grounds of challenge primarily are that Plaintiff was serving as a
Director of the Respondent Company and his remuneration could not have
been adversely altered, in the absence of any Resolution passed in the
Annual General Meeting. It is contended that the Respondent failed to place
on record any AGM Resolution, authorizing reduction of the remuneration
payable to the Appellant.
24.
It is further submitted that the learned Trial Court erred in treating the
Appellant merely as an employee and failed to appreciate that his
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
remuneration was governed by decisions of the shareholders, in the Annual
General Meeting.
25.
It is further contended that the decision in Dale & Carrington Invt.
(P) Ltd. v. P.K. Prathapan,(2005) 1 SCC 212: 2004 SCC OnLine SC 1067
pertains to the requirement of Board Resolutions and disputes relating to
powers of Directors and do not consider the liability of a Company arising
from commitments allegedly made by its Directors to employees, and were
inapplicable to the facts in hand.
26.
Further, the communication dated 05.04.2004 issued by the CEO of
the Respondent Company, established the case of the plaintiff/Appellant.
27.
The Appellant has accordingly, prayed that the impugned Judgment
and Decree dated 18.04.2024 be set aside and the Suit be decreed.
28.
The Respondent in its Written Submissions, has contended that the
salary reduction during the Financial Year 2002-2003, was a restructuring of
remuneration, necessitated by the financial constraints faced by the
Company and not a deferment of salary. This is evident from the
communication dated 01.04.2002 itself, which referred to restructuring of
remuneration, and did not contain any promise for payment of the reduced
component of salary, on a future date.
29.
It is further submitted that the Appellant, who was himself a part of
the senior management of the Company, continued in service even after
restoration
of
salary
w.e.f.
01.04.2003
and
did
not
raise
any
contemporaneous claim for the alleged arrears. Reliance has also been
placed upon the Judgment dated 06.08.2018 passed by this Court in M/s
Aithent Technologies Pvt. Ltd. v. Archana Verma (RFA 608/2014), wherein
claims arising out of the salary restructuring exercise, were rejected.
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
30.
The Appellant in his Written Submissions, has reiterated the grounds
taken in the Appeal.
Submissions heard and Record perused.
31.
It is the case of the Plaintiff/Appellant, Mr. Sunil Vadera, that he
joined the Defendant Company as a General Manager on 01.04.1995 and
was subsequently entrusted with the role of Head of Operations in India. On
02.05.1999, he was inducted onto the Board of Directors as a Director, while
continuing to discharge his functions as General Manager. The Plaintiff
tendered his resignation from both positions vide letter dated 14.11.2003,
which was accepted by the Defendant Company on 19.11.2003.
32.
He further deposed that he was drawing a gross salary of
Rs.1,42,333/- per month from 01.04.2003 until 11.11.2003, shortly before
tendering his resignation. In support thereof, he relied upon the Salary
Certificate dated 18.10.2005, exhibited as Ex. PW-1/1. He further stated that
with effect from 12.11.2003, he proceeded on leave without pay for a period
of six months pursuant to mutually agreed terms contained in the
Defendant’s letter dated 11.11.2003, which also contemplated an option for
him to resign. The Plaintiff thereafter, submitted his resignation vide letter
dated 14.11.2003.
33.
The Plaintiff further stated that prior to the reduction in salary, he was
drawing a monthly salary of Rs.1,20,000/- along with an annual component
of Rs.10,00,000/-. Thereafter, his salary was revised and increased to
Rs.1,42,333/- per month, which continued up to 31.03.2002.
34.
The Plaintiff further deposed that he was drawing a gross salary of
Rs.1,42,333/- per month during the months of January and February, 2002,
i.e., during the financial year from 01.04.2001 to 31.03.2002. In support of
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
the same, he relied upon his Form-16 and Income Tax Returns, which were
marked as PW-1/A and PW-1/B respectively. For the intervening Financial
Year 01.04.2002 to 31.03.2003, he has also filed his Form-16, which is
marked PW-1/C.
35.
The entire controversy in the present case centres around the
reduction of the Plaintiff’s salary for one year from 01.04.2002 till
31.03.2003. It is an admitted case that with effect from 01.04.2002, the
Plaintiff’s salary was reduced from Rs.1,42,333/- per month to Rs.84,000/per month and continued at the reduced level until 31.03.2003. It is further
undisputed that with effect from 01.04.2003, the Plaintiff’s salary was
restored to Rs.1,42,333/- per month. Thus, there was an admitted reduction
in the Plaintiff’s salary for one year i.e. the period from 01.04.2002 to
31.03.2003.
36.
The circumstances leading to reduction in salary for Financial Year
2002-03, were explained by the Plaintiff in his testimony, wherein he stated
that the Defendant Company was a wholly owned subsidiary of Aithent Inc.,
New York, USA with effect from 01.01.2001. He stated that the Defendant
Company had advanced an interest-free loan of Rs.739 lakhs to Aithent Inc.,
which increased to Rs.808 lakhs as on 31.03.2003.
37.
The Plaintiff further stated that two affiliated entities, namely Canyon
Blue and Velos, were amongst the principal clients of the Defendant
Company. A substantial number of technical resources of the Defendant
Company, were deployed for development and maintenance of products for
these entities. However, the said entities failed to make timely payments for
the services rendered, resulting in significant outstanding receivables.
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
Despite the accumulation of such dues, the Defendant Company continued
to provide services, particularly to Canyon Blue.
38.
The aforesaid circumstances adversely impacted the financial position
of the Defendant Company and resulted in dwindling of available reserves
with the Defendant Company. Towards the end of March, 2002, discussions
were held within the management regarding the measures to address the
situation The Plaintiff, who was then a Director of the Defendant Company,
along with Mr. Venu Gopal (CEO), Mr. H.R. Ahluwalia (Vice President –
HR), Mr. Sanjay Verma (Vice President – Technology) and Mr. Rajiv Gupta
(Assistant Vice President – Technology), deliberated upon the issue. It was
thereafter, decided that the prevailing situation should be shared with the
employees and their cooperation sought. Consequently, an open General
House Meeting of all employees was convened, wherein all the employees
had been invited.
39.
At the said meeting, Mr. Venu Gopal, CEO, and the Plaintiff
addressed the employees, and explained the financial difficulties being faced
by the Defendant Company, particularly on account of non-receipt of
payments from affiliated entities, and expressed the expectation that the
situation would improve in the coming months. He sought the cooperation
of the employees in helping to tide over this temporary difficulty. The
Plaintiff stated that he, in turn, explained the measures proposed by the
Management Team in detail.
40.
The proposed measure involved deferment of a portion of the
employees’ salaries on a graded scale, for a period of up to twelve months. It
was represented that upon expiry of the said period, the salaries would be
restored to their original levels. It was further stated that if any employee left
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
the organisation during this period, the deferred salary together with gratuity
benefits would be paid, at the time of final settlement.
41.
In cases where employees were receiving both monthly and annual
remuneration components, the two components were merged with effect
from 01.04.2002 to mitigate hardship.
42.
The employees agreed to the proposed arrangement and extended
their cooperation to the management in overcoming the financial difficulties
faced by the Defendant Company. The Management also promised a special
bonus equivalent to one month's salary to each employee.
43.
As per the Plaintiff, under the aforesaid arrangement, the Defendant
Company agreed with employees drawing a gross salary above Rs.20,000/per month to defer a portion of their salary for Financial Year 2002-2003,
till April 2003. The deferred portion of the salary was determined on a
graded scale, namely 15%, 20%, 25% and 30% for employees drawing gross
monthly salaries in the ranges of Rs.12,000/- to Rs.20,000/-, Rs.20,000/- to
Rs.30,000/-, Rs.30,000/- to Rs.60,000/- and above Rs.60,000/- respectively.
44.
Consequently, the amount of deferred salary attributable to the
Plaintiff for Financial Year 2002-2003 was Rs.5,12,400/-. Upon adding the
promised bonus equivalent to one month's salary, the Plaintiff claimed that a
total sum of Rs.6,54,733/- became due and payable to him, which was not
paid by the Defendant Company.
45.
The Defendant Company, on the other hand, contended that the
arrangement was not one of deferment of salary and that no promise had
been made to pay the reduced salary amount with effect from 01.04.2003 to
the employees. In fact, owing to the financial difficulties being faced by the
Company, the salaries of employees were restructured for a period of one
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
year. It was, therefore, asserted that there was no question of any deferred
salary becoming payable to the Plaintiff or any other employee.
46.
Although the Plaintiff sought to characterize the arrangement as one
involving deferment of salary, his testimony and admissions during crossexamination indicate that the arrangement emerged from internal
discussions within the management, in which he himself played a significant
role and a mechanism had been worked out to sail through the financial
difficulties of Defendant Company.
47.
The admissions made by the Plaintiff further reveal that there was no
formal written agreement, board resolution or other contemporaneous
document recording any obligation on the part of the Defendant Company to
repay the reduced salary at a future date. It is quite evident from the
comprehensive reading of the entire testimony of PW-1, that there may have
been an internal understanding amongst the members of the Management
and CEO that employees who supported the Company during its financial
difficulties, would be compensated in the future by payment of the deferred
salary. However, no such understanding was formally documented in the
Company records, the arrangement continued to be reflected as a
restructuring of salary. The Plaintiff himself admitted that no board
minutes, resolution or other formal record exist, to show that the
arrangement was one of deferment rather than restructuring.
48.
Much emphasis has been placed by the Appellant on the absence of an
AGM Resolution, approving the reduction in his remuneration as a Director.
However, the present Suit is not one challenging the validity of such
reduction. The case of the Appellant is that the reduced salary was deferred
and remained payable.
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
49.
In the absence of any formal document evidencing a deferment of
salary, the Plaintiff, who admittedly played a leading role in formulating and
implementing the arrangement, has not successfully been able to prove that
there was any Policy of deferred salary, to be paid along with the restored
salary from 01.04.2003.
50.
Another aspect, which is of immense importance, is that the Plaintiff,
as per his own testimony, resigned from the Defendant Company on
19.11.2003. At that time, admittedly, all his claims and dues were settled.
51.
Significantly, the document dated 11.11.2003 Ex. DW-1/P3, was
executed at that stage when the Appellant/Plaintiff ceased to actively serve
the Respondent Company. The said document specifically records the
financial arrangement governing the relationship between the parties and the
benefits payable upon separation. The same is produced as under:
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
52.
Significantly, the said document is completely silent regarding the
alleged deferred salary of Rs.5,12,400/- or the alleged compensation bonus
of Rs.1,42,333/-. Though the document bears the signatures of the
Appellant/Plaintiff in token of acceptance, there is no acknowledgment of
any outstanding liability or reference to any deferred salary arrangement.
53.
If it was indeed a case of deferment, and not restructuring, as alleged
by the Plaintiff, there is no reason, why he would not have protested,
insisted or claimed his outstanding dues, on account of alleged deferment of
the salary.
54.
The conduct of the Plaintiff, in not insisting on any outstanding dues
at the time of his resignation and his filing of the Suit only after two years of
his resignation, also lends support that it was not a formal agreed policy of
the Defendant Company to pay the deferred salary.
55.
The Appellant/Plaintiff has also placed reliance upon the letter dated
05.04.2004 Ex. PW-1/3, wherein the CEO of the Respondent Company
stated
that
he
remained
committed
to
clear
the
dues
of
the
Appellant/Plaintiff. The same is reproduced as under:
“April 5, 2004
Dear Sunil,
Aithent has a history of valuing employees as partners in its growth.
Our philosophy all through has been to achieve organizational
objectives by dovetailing employees' personal growth plans and
ambitions with organizational business objectives. The management
acknowledges your valuable contribution in building Aithent and
helping it achieve its business goals.
In recent times Aithent was impacted by certain environmental factors
on which the management did not have control. Consequently, Aithent
passed through a rough patch and despite our sincere efforts and
intentions, we could not meet some of the financial commitments that
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
we had made to you. As a result of this delay, you have gone through
hardship in the past few months and I am thankful to you for your
patience and thereby your exemplary support to the organization in
this hour of need.
However, this was a temporary phase and we have crossed the
troubled waters. I stand committed to honor all my commitments and
clear all your dues by May 30"', 2004. In case these dues are not
settled by May 31 2004, Aithent would pay an interest on the unpaid
dues @5% per annum for the
period of delay w.e.f June I, 2004.
I once again thank you for your unflinching support and patience.
Wishing you the best in your professional and personal endeavours.
Sincerely,
N Venn Gopal
CEO”
56.
However, the said communication neither quantifies the alleged dues
nor identifies their nature. There is no reference to the reduced salary for
Financial Year 2002-2003, no mention of any compensation bonus and no
recital that the salary reduction was merely a deferment to be repaid at a
future date.
57.
It is not disputed that there were discussions regarding payment of a
one month's salary bonus, to employees. However, the Appellant/Plaintiff
has failed to place on record any material to establish that the said bonus
crystallized into a binding contractual obligation. The consistent stand of the
Respondent has been that the same was contemplated only as an incentive
and not as a legal commitment. In the absence of any document or other
cogent evidence demonstrating that the bonus became payable as a matter of
right, the claim towards compensation bonus cannot be sustained.
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
58.
The Plaintiff has relied upon the aforesaid communication Letters, Ex.
PW 1/3, but from these Letters there is no admission of there being any
deferment of salary or the entitlement of the Plaintiff for the same.
59.
This conclusion also finds support from the judgment of a Coordinate
Bench of this Court in M/s Aithent Technologies Pvt. Ltd. v. Archana Verma
(RFA 608/2014 decided on 06.08.2018), arising out of the same salary
restructuring exercise undertaken by the Respondent Company, during the
Financial Year 2002-03. The Coordinate Bench, while examining a similar
claim of deferred salary, observed that there was no material on record to
establish any arrangement of deferment and consequently, set aside the
decree granted by the Trial Court.
60.
The learned Trial Court has appreciated the evidence brought on
record and has rightly concluded that while reduction of salary during the
relevant period stands admitted, the Appellant/Plaintiff failed to establish
that such reduction merely constituted a deferment creating a legally
enforceable obligation to repay the amount at a later date.
61.
There is no merit in the present Appeal, which is hereby, dismissed
along with pending Applications.
(NEENA BANSAL KRISHNA)
JUDGE
JUNE 16, 2026/R
Signed By:VIKAS
ARORA
18:04:50
RFA 546/2024
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review