HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
Reserved on :05.02.2025
Pronounced on:25.02.2025
WP(C) PIL No.12/2023
CM Nos.7653/2023 &
7654/2023
Sugandha Sawhney, Age 29 years
D/O Kamal Sawhney,
Office Address:Ajay Gandotra & Associates
216, Adarsh Enclave-II, Sector I,
Ext. Trikuta Nagar, Jammu.
…..Petitioner
Through: Petitioner-in-person
versus
1. Union of India, through Secretary,
Ministry of Road, Transport & Highways,
Transport Bhawan 1, Parliament Street,
New Delhi – 110001
2. National Highway Authority of India
(NHAI), through Chairman,
G-5 & 6, Sector 10, Dwarka,
New Delhi – 110075
3. Union Territory of Jammu and Kashmir,
through Chief Secretary,
2nd Floor, Main Building,
Civil Secretariat, Jammu 180001
…..Respondents
Through: Mr. Karan Sharma, Advocate
WP(C) PIL No.12/2023
CORAM:
HON’BLE THE CHIEF JUSTICE
HON’BLE MR. JUSTICE M.A. CHOWDHARY, JUDGE
JUDGMENT
(Per Tashi Rabstan – CJ)
1.
The petitioner through the medium of this Public Interest Litigation
seeks a direction to the respondents to exempt the Toll Tax at Lakhanpur Toll
Plaza, Kathua; Thandi Khui Toll Plaza and Ban Toll Plaza, Nagrota, Jammu
till the National Highway commencing from Pathankot to Udhampur under the
project, titled, Delhi-Amritsar-Katra Expressway gets fully operational for
smooth utilization of the public.
2.
It is averred that the stretch of National Highway-44 from District
Pathankot (Punjab) to District Udhampur (UT of J&K) is undergoing
construction under the project Delhi-Amritsar-Katra Expressway and about
60% to 70% of this stretch is under construction since December, 2021, yet the
general public is being charged Toll Tax at Lakhanpur Toll Plaza, Thandi Khui
Toll Plaza and Ban Toll Plaza despite the fact that such collection of fee levied
ought to be commenced within 45 days from the date of completion of the
section of National Highway in terms of Rule 3(1) and 3(2) of National
Highways Fee (determination of Rates and Collection) Rules, 2008. Further, it
is averred that there are grave hurdles, diversions due to complete destruction
of National Highway. Not only this, the daily travel time for the residents in
the region has significantly increased between three to four hours due to the
construction activities leading to improper road availability, which has further
led to extra burden on the fuel consumption in addition to causing wear and
tear to the vehicles. Therefore, it is averred that the respondents in terms of the
WP(C) PIL No.12/2023
rule position cannot charge toll tax at these three Toll Plazas before the
completion of the project.
3.
Objections have been filed on behalf of respondents. It is averred that as
regards collection of toll tax at Thandi Khui Toll Plaza, the same has been
closed with effect from 26.01.2024 by redistributing the influence length from
Lakhanpur to Udhampur among Lakhanpur and Bann Toll Plazas. It is further
averred that only the brown field portion is undergoing widening or
construction of elevated structures wherein service road/diversions have been
provided for the movement of traffic. Further, only 32 km stretch is undergoing
widening from Kunjwani to Udhampur out of the total completed 4-lane
stretch of 80 kms. The project from Pathankot to Jammu commenced on
26.09.2022 and from Jammu to Katra commenced in June 2023. NHAI is
collecting user fee for completed 4-lane stretch of NH-44 from Pathankot to
Udhampur at Lakhanpur, Thandikhui and Bann Toll Plazas at the rates
applicable as per NH Fee Rules. It is further averred that the Government of
India Gazette Notification No.H-25016/2/2011-P&P (Toll) dated 16.12.2013
stipulates reduction of user fee rates by 25% for the stretches under widening.
Further, National Highway Authority of India has reduced the toll rates
separately after damage caused to the Tarhan Bridge over Ujh River in July
2023 and no toll, is being charged for the bridge as well as its 8.8 km long
approach road which was officially closed for the purpose of diversion through
existing BRO road. Also, requisite reduction for stretches under widening to
six lane expressway has already been done. National Highway Authority of
India (NHAI) was collecting user fee for completed 4-lane stretch of NH-44
from Pathankot to Udhampur at Lakhanpur, Thandikhui and Bann Toll Plazas
at the rates applicable as per NH Fee Rules. NHAI acknowledges the
WP(C) PIL No.12/2023
discomfort on account of widening along with existing highway and, therefore,
reduction in toll rates as per MoRTH guidelines to 75% of the applicable rates
has already been done at the toll plazas.
4.
Heard learned counsel appearing for the parties, considered their rival
contentions and also perused the file.
5.
The main thrust of this Public Interest Litigation is for exemption of Toll
Tax at Lakhanpur Toll Plaza; Thandi Khui Toll Plaza and Ban Toll Plaza, till
the National Highway, commencing from Pathankot to Udhampur under the
project - Delhi-Amritsar-Katra Expressway, gets fully operational for smooth
utilization of the public, as currently this particular highway is in a deteriorated
condition.
6.
The stand of respondents is that from Pathankot to Jammu only the
brown field portion is undergoing widening or construction of elevated
structures wherein service road/diversions have been provided for the
movement of traffic; whereas from Kunjwani to Udhampur only 32 km stretch
is undergoing widening out of the total completed 4-lane stretch of 80 kms,
therefore, no question arises for exemption of toll tax at Lakhanpur Toll Plaza
and Bann Toll Plaza. However, requisite reduction for stretches under
widening to six lane expressway has already been done. As regards collection
of toll tax at Thandi Khui Toll Plaza, the same has been closed with effect from
26.01.2024 by redistributing the influence length from Lakhanpur to
Udhampur among Lakhanpur and Bann Toll Plazas.
7.
Now it is to be seen whether the toll tax ought to be exempted or
reduced when National Highway-44 from District Pathankot (Punjab) to
WP(C) PIL No.12/2023
District Udhampur (UT of J&K) is undergoing extensive construction under
the project Delhi-Amritsar-Katra Expressway.
8.
Admittedly, the respondents have themselves asserted that National
Highway-44 from Pathankot to Udhampur is undergoing construction of
elevated structures under the project Delhi-Amritsar-Katra Expressway,
besides many sections of this highway are also being upgraded from four-lane
to six lane. Not only this, at many places Nalas at both sides of the highway are
also being constructed. The respondents have also averred that due to different
nature of construction works being carried out at this highway, service
roads/diversions have been provided for the movement of traffic; meaning
thereby the four-lane National Highway at most of the places has been reduced
to single lane, actually dirt-path has been cleared for the vehicles to use the
only alternative, as a result of which the daily use of this under construction
stretch with such deteriorated conditions adds to wear and tear of vehicles.
Otherwise too, it is not a hidden thing nor the learned counsel appearing for
respondents has denied this that National Highway-44 from Pathankot to Bann
Toll Plaza to Domel (Katra) is in a poor and deteriorated condition, there are
grave hurdles, potholes and diversions due to complete destruction of this
particular National Highway. Thus, the commuters are being unfairly charged
as they are not receiving the value they are paying for in terms of quality
infrastructure. Once this very highway is in bad shape due to different nature of
construction activities, the National Highways Authority of India (NHAI) or
the concessionaire managing the toll road cannot collect toll tax from
commuters using the highway. This is based on the principle that tolls are
collected to provide users with the benefit of well maintained infrastructure. If
this highway is in a deteriorated condition and uncomfortable to drive on, it is
WP(C) PIL No.12/2023
considered unfair for commuters to continue paying tolls, rather the same is
violation of fair service. Certainly, the commuters and drivers must be feeling
frustrated by the poor state of this particular highway they are paying to use.
The basic premise is that tolls should be a form of compensation for road users
in exchange for smooth, safe, and well-maintained highways.
9.
Therefore, due to different nature of construction activities being carried
on this particular highway, it was expected from the Government or the
concerned Ministry or NHAI to suspend the toll collection until DelhiAmritsar-Katra Expressway gets fully operational, but to the utter dismay of
commuters that instead of suspending the toll collection, the respondents have
increased the toll fees at Lakhanpur Toll Plaza and Bann Toll Plaza on the
same day when Thandi Khui Toll Plaza came to be closed on 26.01.2024 in
order to adjust the toll fees of Thandi Khui Toll Plaza. Not only this, hefty toll
fee is being charged from commuters at Bann Toll Plaza, when the fact of the
matter is that the distance between Sarore Toll Plaza to Ban Toll Plaza is near
about 47 kilometers. It seems the general public is being made to suffer on
both counts, i.e., bad highway due to construction activities and hefty toll.
Thus, in this way the general public/commuters are feeling cheated as they are
being forced to pay tolls for the highway which at present is in a poor and
shabby condition that too when in ending June, 2024 Union Minister for Road,
Transport and Highways Mr. Nitin Gadkari at a Global Workshop on Satellitebased tolling said that there is no justification of highway agencies charging
toll, if roads are not in good condition or not upto their standards and people
continue to face problems. He further said that highway agencies are in hurry
to start tolling to collect user fees so as to protect their interest. The Minister
WP(C) PIL No.12/2023
emphasized the agencies to ensure good quality service first before initiating
toll fee collection.
10.
A somewhat similar controversy had arisen before the Apex Court in
Civil Appeal Nos.6781-6782 of 2015 (arising out of SLP(C) Nos.34705-34706
of 2014), titled as, DSC-Viacon Ventures Pvt. Ltd. vs Lal Manohar Pandey, in
which their Lordships vide order dated 27.08.2015, while deciding the question
whether recovery of reduced toll fees at 40% of the earlier rate as stipulated
under Notification dated 02.03.2015 was just and fair, has held as under:
“16. Having said that the question is what should be the extent of
reduction on account of poor maintenance of the road. It is
nobody’s case that the entire length of 26 Kms. is poorly
maintained. At least the report submitted by the Committee does
not suggest so. There are patches which are extensively damaged
and require repair causing inconvenience to the users. That does
not, however, necessarily mean that the entire charge towards toll
must be wiped out. The reduction, in our view, should be
proportionate to the extent of damage suffered by the road or the
failure to maintain the same. Having said that we must hasten to
add that there is no empirical data to indicate the extent of road
length and the resultant inconvenience to the users of the road. A
certain amount of guess work is, therefore, unavoidable in the
matter of determining the extent of relief which the road users
may be entitled to. Keeping all these factors in view, we are of the
opinion that the rate of toll/fee prescribed in terms of notification
dated 02.03.2015 should be reduced to half of what is stipulated in
the notification. This means that instead of 40% levied by the
Government the rate shall be 20% of the rates earlier in force. We
order accordingly. The reduced fee shall be recoverable till such
time the road is repaired and a report certifying the repair to be
satisfactory submitted to the Govt. by a Committee appointed by
the Government of India.”
11.
Further, as per National Highways Fee (Determination of Rates and
Collection) Rules, 2008, the spacing between two adjacent toll plazas should
be 60 kms, i.e., any other fee plaza on the same section of National Highway
and in the same direction shall not be established within a distance of sixty
kilometer. Here, the distance between Sarore Toll Plaza to Bann Toll Plaza
WP(C) PIL No.12/2023
using NH-44 is near about 47 kms, which is certainly against the rule position
and this position has not even been denied by the learned counsel appearing for
respondents. Thus, in this way the respondents and the contractors have
accumulated crores of rupees illegally from the general public.
12.
Further, any commuter/pilgrim, who goes to Katra/Vaishno Devi, if uses
the National Highway-44 from Sarore Toll Plaza in his/her own car upto
Domel, from where he/she has to leave the National Highway-44 to reach
Katra/Vaisho Devi or vice versa, in such a case he/she is bound to cross two
toll plazas, i.e., Sarore Toll Plaza and Bann Toll Plaza and, interestingly, the
distance between Sarore Toll Plaza to Domel is nearly about 54 kilometers;
meaning thereby for covering the distance of just 54 kilometers from Sarore
Toll Plaza to Domel every commuter is bound to pay at two Toll Plazas, i.e.,
Rs.85.00 at Sarore Toll Plaza and Rs.165.00 at Bann Toll Plaza for one side
journey through light motor vehicle – totaling Rs.250.00 for single journey as
on 01.04.2023, which has now been increased. Respondents knew very well
that millions of millions people/pilgrims visit Katra every year to pay
obeisance at the shrine of Mata Vaishno Devi. Therefore, to mint money from
these pilgrims, the respondents have purposefully established Bann Toll Plaza
before Domel without adhering to the rule position regarding spacing between
two adjacent toll plazas at 60 kms. This is nothing but loot of public money
illegally and the commuters are being burdened unduly. Though the Thandi
Khui Toll Plaza came to be closed on 26.01.2024 but on the same very date the
respondents increased the toll fees at Lakhanpur Toll Plaza and Bann Toll
Plaza in order to adjust the toll fees of Thandi Khui Toll Plaza despite the fact
that Bann Toll Plaza was already charging hefty toll fee from the general
public/commuters. Otherwise too, the respondents have not closed/removed the
WP(C) PIL No.12/2023
Toll Plaza at Thandi Khui permanently but the same has been closed
temporarily only due to the construction activities being going on the National
Highway-44 and have not stated that they would not establish new Toll Plaza
near Thandi Khui.
13.
Further, the distance between Nagrota to Domel using NH-44 is just 15
kilometers. Now any commuter or general public residing in Jammu City or
nearby areas/towns/villages if visit Katra/Vaishno Devi or nearby areas in their
own cars, they use only 15 kilometers of NH-44 from Nagrota to Domel, from
where they have to leave the National Highway-44 to reach Katra/Mata Vaisho
Devi/other areas or vice versa. But, for using only 15 kilometers of NH-44 they
are being forced to pay an hefty amount of Rs.165.00 at Bann Toll Plaza for
one side journey through light motor vehicle plus increased toll fee also, which
was imposed by the respondents with effect from 26.01.2024 by redistributing
the influence length from Lakhanpur to Udhampur among Lakhanpur and
Bann Toll Plazas after closing of Thandi Khui Toll Plaza so as to adjust the toll
fee of Thandi Khui Toll Plaza. But, the fact of the matter is that the commuters
from Jammu City and nearby areas never use NH-44 from Thandi Khui Toll
Plaza to reach Katra/Mata Vaishno Devi, then why they are being forced to pay
the increased toll fee for such section of NH-44 which these commuters never
use. This is nothing but highhandedness on the part of respondents for obvious
reasons. One can easily understand such undue enrichment of toll contractors
and why the respondents are levying hefty toll fees arbitrarily. Respondents
must understand the concept of levying toll fee as tolls are a way to make road
users contribute to the costs of maintaining and improving transportation
infrastructure but the same must be fair enough.
WP(C) PIL No.12/2023
14.
During arguments, learned counsel appearing for respondents did not
deny that the distance between Thandi Khui Toll Plaza and Bann Toll Plaza is
much less than 60 kms. Although the learned counsel stated at the Bar that the
respondents would have no objection to return the excess toll fee collected
from the commuters/pilgrims if the distance between both these toll plazas is
less than 60 kms., but how they could find those commuters/pilgrims who have
paid or have been paying excess fees. It is very sorry state of affairs that
though the learned counsel for respondents did not deny that the distance
between Thandi Khui Toll Plaza and Bann Toll Plaza is much less than 60
kms. and that the respondents are ready to return the excess fees, yet, even as
on today they are charging the same toll fee from the general public.
15.
The respondents have filed the toll collection detail which reveals Bann
Toll Plaza collected Rs.659.54 crores during the period 20.03.2015 to
24.12.2024, whereas Lakhanpur Toll Plaza collected Rs.355.77 crores between
the period 22.07.2020 to 24.12.2024 and Thandi Khui Toll Plaza collected
Rs.227.88 crores between the period 11.10.2019 to 26.01.2024.
16.
The toll collection detail reveals that during the aforementioned period
the respondents collected more than rupees 1243 crores from these three toll
plazas. As per the news reports, the toll revenue of National Highway
Authority of India in 2020 was Rs. 24000 crores, and with the facilitation of
FAS Tags from January 2020, toll gate charges or revenue in 2021 was
anticipated to reach Rs. 34000 crores. Though the toll fees at the toll plazas
contribute to the construction, maintenance, enhancement of high quality road
infrastructure, highways, expressways and toll fee is essential for infrastructure
development, however, the respondents must ensure for fair and equitable
WP(C) PIL No.12/2023
tolling fee and that establishment of these toll plazas should not serve merely
as a revenue-generating mechanism or to mint money from the general public.
Further, rapid increase in toll plazas raises several concerns among the general
public. The respondents must ensure that toll plazas are not placed at every
nook and corner of the state. There should not be mushrooming of toll plazas.
17.
It has also come to our notice that the contractors have illegally
employed number of individuals (gunda elements) with criminal backgrounds
at toll plazas. This is a serious matter that involves both law enforcement and
public safety concerns.
18.
Therefore, in view of above discussion, we deem it proper to allow the
present PIL. Accordingly, this PIL is allowed with the following directions:
i.
Respondents are directed to withdraw the order/direction regarding
redistributing the influence length from Lakhanpur to Udhampur among
Lakhanpur and Bann Toll Plazas with effect from 26.01.2024 after the
closure of Thandi Khui Toll Plaza. Respondents to withdraw the said
order/direction positively within a period of one week from today.
ii.
Respondents are directed to levy only 20% of the toll fee with immediate
effect, i.e., the toll fee at Lakhanpur Toll Plaza and Bann Toll Plaza shall
be 20% of the rates earlier in force before 26.01.2024 till the National
Highway from Lakhanpur to Udhampur gets fully operational for
smooth utilization of the public. Respondents to charge the full toll at
both these toll plazas only after the issuance of a certificate in this regard
by an independent surveyor.
iii.
Respondents are directed not to establish any toll within 60 kms of the
National Highway-44. Further, if there is any toll plaza in the UT of
J&K or in the UT of Ladakh within 60 Kms on the National Highway,
respondents to remove the same within two months from today. Further,
there should not be mushrooming of toll plazas in the UT of J&K and
the UT of Ladakh only with the sole aim and objective of minting
money from the general public.
iv.
Further, respondents are charging hefty toll fees at Bann Toll Plaza,
whereas toll fees at other Toll Plazas are also high. Thus, not only the
treasures of NHAI are being filled with thousands of crores of rupees,
the private contractors are also enriching themselves by accumulating
crores of rupees. Since the toll fee must be fair enough for the general
public and should not be a source of revenue-generating mechanism,
WP(C) PIL No.12/2023
respondents, particularly the concerned Union Ministry, are directed to
reconsider levying of fair and genuine toll fees at the toll plazas thereby
slashing the existing toll fees at all the toll plazas as the current toll fees
is at higher side. The decision in the regard be taken positively within a
period of four months from today.
v.
Respondents as well as the contractors of the Toll Plazas are directed not
to employee any person at the toll plazas having criminal background.
Respondents as well as the contractors to deploy the persons at the Toll
Plazas only after verification of such employees by the concerned police
agency. In case of any deviation in this regard, the concerned
SHO/Incharge shall be personally responsible for the same.
19.
Registry to send a copy of this judgment to the concerned Union
Minister, Ministry of Road, Transport and Highways, Government of India.
Jammu
25.02.2025
(M.A. Chowdhary)
Judge
(Tashi Rabstan)
Chief Justice
(Anil Sanhotra)
Whether the order is reportable ?
Whether the order is speaking ?
Anil Sanhotra
2025.02.25 14:42
I attest to the accuracy and
integrity of this document
Yes
Yes
This page is for informational and research purposes only and does not constitute legal advice.