Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 10.12.2025
Pronounced on: 23.01.2026
+
FAO(OS) (COMM) 132/2020 & CM APPL. 26984/2020, CM
APPL. 43515/2024, CM APPL. 48931/2025
PRASAR BHARATI
..... Appellant
Through:
Mr.Rajeev Sharma, Sr. Adv.
with Mr.Abhishek Birthray and
Mr.Kartikeya Tripathi, Advs.
versus
STRACON INDIA LTD & ANR.
..... Respondents
Through: Mr.Ashish Dholakia, Sr. Adv.
with
Mr.Gautam
Bajaj,
Mr.Subhoday Banerjee,
Mr.Akash Panwar, Ms.Meghna
Jandu and Ms.Jasleen Kaur,
Advs.
+
FAO(OS) (COMM) 179/2020 & CM APPL. 48929/2025
STRACON INDIA LTD
..... Appellant
Through: Mr.Ashish Dholakia, Sr. Adv.
with
Mr.Gautam
Bajaj,
Mr.Subhoday Banerjee,
Mr.Akash Panwar, Ms.Meghna
Jandu and Ms.Jasleen Kaur,
Advs.
versus
PRASAR BHARATI
Through:
..... Appellant
Mr.Rajeev Sharma, Sr. Adv.
with Mr.Abhishek Birthray and
Mr.Kartikeya Tripathi, Advs.
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
HON'BLE MS. JUSTICE MADHU JAIN
JUDGMENT
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
NAVIN CHAWLA, J.
1.
These cross appeals have been filed by the respective parties,
challenging the Judgment and Order dated 13.03.2020 passed by the
learned Single Judge of this Court in O.M.P. (COMM.) 225/2017,
titled Prasar Bharati v. Stracon India Ltd. & Anr. (hereinafter
referred to as, the „Impugned Order‟), whereby the learned Single
Judge has partly allowed the application filed by Prasar Bharati under
Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter
referred to as, the „A&C Act‟), partly setting aside the Arbitral Award
dated 26.12.2016 (hereinafter referred to as, the „Award‟) passed by
the learned Arbitrator.
2.
As these are cross appeals, for the sake of clarity we shall refer
to Prasar Bharati as the „Appellant‟, and Stracon India Ltd. as the
„Respondent‟. We may also note that the respondent no.2, that is,
Transworld International Inc., is only a pro forma party.
Brief background of facts:
3.
The Board of Cricket Control in India (in short, „BCCI‟), vide
an Agreement dated 25.09.1999 (hereinafter referred to as, the „BCCI
Agreement‟), had granted to the appellant the broadcasting rights for
the cricketing events comprising of domestic and international
matches conducted by the BCCI during the term of the BCCI
Agreement. Clause 2 of the BCCI Agreement specified the term of the
agreement as five years, from 01.10.1999 to 30.09.2004. This Clause
also specified that each cricket season/year is the period from 1 st
October of a year to 30th September of the next year. Clauses 3 and 12
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
of the BCCI Agreement provided that the BCCI would guarantee to
deliver 135 days of International Cricket to the appellant, that is, a
minimum of 27 days of International Cricket in each cricket
season/year. Clause 12.1 of the BCCI Agreement further provided that
if less than 27 days of International Cricket were provided by BCCI in
any cricket season/year, the Appellant would be entitled to a pro-rata
reduction in the consideration, however, this deducted amount shall be
restored to the BCCI if the shortfall in providing 27 days of
International Cricket in a year is made up in the next year.
4.
After the execution of the BCCI Agreement, a cricket series
between India and New Zealand comprising of five One Day
Internationals (ODIs) and three Test Matches, totalling 20 days of
International Cricket was played in October, 1999. A Production &
Marketing Agreement dated 08.10.1999 (hereinafter referred to as, the
„P&M Agreement‟) was entered into between the appellant and the
respondent, whereby, the appellant had granted the marketing rights
for the said series to the respondent.
5.
After the India-New Zealand Series comprising of 20 days of
International Cricket had been played, in January 2000, the appellant
invited bids for marketing of airtime in India and overseas “of the
cricketing events conducted by BCCI in India for the period starting
from 1st January, 2000 to 30th September, 2004”. It is the case of the
appellant that bids were invited for the remainder days of cricket to be
provided by BCCI, that is, 135 – 20 = 115, and an explicit reference to
the BCCI Agreement was made in Clause 1.1 of the Tender. A
tentative list of nine series was also annexed to the Notice Inviting
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Tender („NIT‟).
6.
The respondent won the bid for grant of overseas rights in
response to the said NIT, and thereafter, an Agreement dated
19.02.2000 (hereinafter referred to as, the „Global Rights Agreement‟)
was entered into between the Parties for the grant of global marketing
rights in respect of Domestic and International cricket matches to be
conducted by the BCCI upto 30.09.2004, for a consideration of USD
43.5 million.
7.
In terms of the Clause 9 of the Global Rights Agreement, 5% of
the total consideration was paid by the respondent on 15.02.2000, and
the remaining sum had to be paid in five instalments. Respondent was
also required to submit an unconditional Bank Guarantee for a value
of 15% of the total consideration, on or before 23.02.2004.
8.
Clause 4(a) of the Global Rights Agreement stipulated that the
appellant shall provide to the respondent, the Cricketing Events as
specified in Annexure A of the Agreement. Clause 4(b) of the
Agreement also stipulated that the Respondent shall provide a
minimum of 27 days of International Cricket in each cricket season.
9.
In 2003, dispute was raised by the respondent that there was a
doubt regarding the last two series, that is, between India-Pakistan and
India-Australia,
being
played,
and
therefore,
they
withheld
consideration amounting to USD 6.56 million. On 19.09.2003, the
respondent filed O.M.P. No. 375/2003, seeking interim protection
with respect to the said payment, which was otherwise payable under
the Global Rights Agreement on 30.09.2003. Vide an order dated
26.09.2003, this Court permitted the respondent to deposit the said
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
amount in Court, to be disbursed in accordance with the directions of
the learned Sole Arbitrator.
10.
The dispute was referred to a learned Sole Arbitrator [Justice
B.N. Kripal (Retd.)] for adjudication. By an Award dated 31.08.2004,
the learned Sole Arbitrator held that the dispute raised by the
respondent was premature and should be settled at the stage of final
accounting. Therefore, the respondent was not entitled to withhold the
consideration amounting to USD 6.56 million.
11.
The respondent, claiming that the accounts were to be settled on
31.03.2004, but were not settled by the appellant, again approached
this Court by way of O.M.P. No. 438/2004, to secure a sum of USD
2.18 million, payable by it to the appellant as the last instalment under
the Global Rights Agreement. The said amount was later deposited by
it in Court, in compliance with the order dated 31.11.2004.
12.
Though the amount was lying deposited in Court under the
above referred orders, the appellant, in December 2004, invoked the
Bank Guarantees furnished by the respondent, on account of alleged
non-payment of the consideration due.
13.
The respondent filed I.A. No. 8713/2004, seeking a restraint on
the appellant from encashing the Bank Guarantees.
14.
By a consent Order dated 21.02.2005 passed by this Court, the
amount of USD 6.56 million deposited by the respondent, was
directed to be released to the respondent, while USD 2.8 million was
directed to be released to the appellant. By that time, the appellant had
also received USD 6.56 million by encashing the Bank Guarantees.
By the said consent order, all disputes arising out of the Global Rights
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Agreement, including all claims and counter claims, were also referred
to Arbitration, which culminated into the Arbitral Award, the subject
matter of the challenge in the Impugned Order.
15.
Before the learned Sole Arbitrator, the case setup by the
respondent was that the appellant was supposed to provide nine series
under the Global Rights Agreement, whereas only seven series were
provided, and therefore, they were entitled to a pro-rata reduction in
consideration amounting to USD 9.72 million. It was further claimed
that out of the 27 days of cricket which was to be provided in each
cricketing season, there was a shortfall of 12 and 5 days during
seasons 1 and 4 respectively, for which they were entitled to USD
5.50 million.
16.
The case setup by the appellant before the learned Sole
Arbitrator was that the Global Rights Agreement did not specify any
minimum number of „series‟ to be provided by it; it only provided for
the stipulated days of cricket, in context of matches. It was the case of
the appellant that since BCCI had to provide 135 days of cricket
during the period 01.10.1999 to 30.09.2004, and 20 days of cricket
had been already provided by it in October 1999, that is, before the
parties had entered into the Global Rights Agreement, only 115 days
of cricket was left to be provided by the time the said Agreement was
executed with the respondent. The requirement of providing 27 days
of cricket was for full cricket season and not a part season. As the
agreement was to come into effect from 01.01.2000, that is, in the
middle of the cricket season, there had to be a proportionate deduction
in the same as well.
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
17.
It is also the case of the appellant that the method of valuation
suggested by the respondent was arbitrary. The appellant refuted the
contention of the respondent that USD 43.75 million was the
consideration for nine series, and that the value of a single series
would be USD 4.86 million and that of two series would be USD 9.72
million. It was claimed that the consideration of USD 43.75 million
was for all domestic and international matches conducted by the BCCI
during the term.
Arbitral Award:
18.
The learned Sole Arbitrator, by an Award dated 26.12.2016,
held that the deliverables under the Global Rights Agreement were not
to be counted in terms of series, but were to be counted in terms of the
number of days. The learned Sole Arbitrator further held that 135 days
of International Cricket were to be provided by the appellant under the
Agreement, while only 118 days had been provided. The learned
Arbitrator excluded 10 days of cricket of the India-Australia-New
Zealand Triangular Series, on the ground that the said series was not
part of the Global Rights Agreement, as it was not mentioned in
Annexure-A thereof. The learned Arbitrator, accordingly, held that
there was a shortfall of 17 cricketing days, for which he passed an
Award for USD 5,509,259 million, equivalent to Rs.37,32,79,843/-,
along with interest thereon at the rate of 18% per annum from
19.10.2005 till the date of the Award, in favour of the respondent. The
learned Arbitrator further awarded costs of Rs.35,50,000/- in favour of
the respondent and against the appellant.
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Prior Proceedings:
19.
The Award was challenged by the respondent, vide O.M.P.
(Comm) No. 233/2017, on the limited ground that the learned
Arbitrator had wrongly held that the deliverables were not to be
counted in terms of series. The said challenge of the respondent was
dismissed by the learned Single Judge of this Court, vide its judgment
dated 31.05.2017.
Impugned Order:
20.
By the Impugned Order, the learned Single Judge rejected the
contention of the appellant that since BCCI had to provide 135 days of
cricket during the period 01.10.1999 to 30.09.2004, and 20 days of
cricket had been already provided by it in October 1999, that is, before
the parties had entered into the Global Rights Agreement, only 115
days of cricket, based on pro rata, was to be provided by the appellant
to the respondent, by holding as under:
“58. Petitioner in my view is not right in its
contention that the said 20 days were to be
excluded and therefore it was obliged only to
provide only 115 days in the cricketing season.
The Agreement was entered into between the
parties on 19.02.2000. It was clearly known to
the petitioner on the date of signing the
Agreement that 20 days of cricket had been
played in the year 1999, yet, when the
Agreement was entered into, it was clearly
mentioned that 27 cricket days would be
provided in each season for the 5 cricket
seasons. Had the petitioner intended that these
20 days were to be included, the Agreement
would have read otherwise. It is not open for
the petitioner at this stage to argue contrary to
the terms of the Agreement. My view is further
fortified by Clause 12.1 of the Agreement
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
between the petitioner and the BCCI dated
25.09.1999, where there is a clear provision of
carrying forward of cricket days in case of
shortfall in a particular cricket season. Thus,
this contention of the petitioner has to be
rejected. Thus, the respondents were entitled
to clear 135 days of Cricketing Events in 5
seasons but this would include the 10 days of
Triangular Series. Thus, the part of the Award
which has held that respondents are entitled to
payment for 17 days of shortfall is set aside.
Respondents are only entitled to 7 days of
shortfall and are at liberty to raise this claim
in accordance with law.”
21.
The learned Single Judge also upheld the Award to the extent it
dismissed the Counter Claims of the appellant herein, by holding that
no patent illegality can be noted in the findings of the learned
Arbitrator qua the same.
22.
The learned Single Judge, however, held that the finding of the
learned Arbitrator qua the India-Australia-New Zealand Triangular
Series as not forming part of the Global Rights Agreement, is patently
illegal and cannot be sustained. We quote the relevant paragraphs of
the Impugned Order as under:
“54. Respondents may be right in their
contention that the Triangular Series may not
have earned as much revenue as was expected
from another series between India-Pakistan
and India-Australia, but this argument cannot
be raised by the respondents at this stage.
When the petitioner granted the right to the
respondents to market and telecast the
Triangular Series, the petitioner should have
objected at that stage, instead of telecasting
the series and earning revenue therefrom.
Thus, in my view, the finding of the Arbitrator
allowing the claim of the respondent towards
the shortfall of 10 cricketing days is patently
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
illegal and cannot be sustained, more
particularly in view of the judgment of the
coordinate Bench. To this extent, the Award
deserves to be set aside.”
23.
We may also note that the learned Single Judge, while setting
aside the Award to the extent it found shortfall of 17 Cricketing Days
in favour of the respondent, also reserved liberty with the respondent
to agitate their claim of 7 days shortfall in Cricketing Days in
accordance with law.
24.
Aggrieved of the above, both the parties have filed these cross-
appeals.
Submissions by the learned Senior Counsel for the appellant:
25.
Mr. Rajeev Sharma, the learned senior counsel appearing for
the appellant, submits that the learned Arbitrator has re-written the
contract between the parties by holding that 135 days of cricket was to
be provided by the appellant to the respondent during the five year
period of the Agreement. He submits that the learned Arbitrator has
failed to appreciate that 27 days of cricket was to be provided in each
„Cricket Season‟. Cricket Season in terms of the BCCI Agreement
was from 1st October of a year to 30th September of the next year. As
the Agreement between the appellant and the respondent was signed
on 19.02.2000, that is, in the middle of a Cricket Season, the 27 days
of cricket provided in Clause 4(b) of the Agreement had to be
proportionately reduced. He submits that the learned Arbitrator has, in
fact, not even considered the plea of the appellant with respect to the
proportionate reduction in the number of days of International Cricket
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
to be provided due to the Agreement being for a part of the Cricket
Season. He submits that by not giving any reason for rejection of the
said plea, the Award is patently illegal and is liable to be set aside. In
support, he places reliance on the judgment of the Supreme Court in IPay Clearing Services Private Limited v. ICICI Bank Limited,
(2022) 3 SCC 121.
26.
He submits that even otherwise, the learned Arbitrator has
failed to appreciate that 135 days of cricket was to be provided by the
BCCI to the appellant under the BCCI Agreement which was executed
on 25.09.1999. Prior to the Global Rights Agreement executed
between the appellant and the respondent on 19.02.2000, the IndiaNew Zealand Series had already taken place, therefore, the same,
consisting of 20 days, also had to be excluded from the number of
days of cricket to be provided. He submits that the learned Arbitrator
has, therefore, re-written the Agreement between the parties and for
the said reason, the Award is liable to be set aside. In support, he
places reliance on the judgment of the Supreme Court in PSA Sical
Terminals Private Limited v. Board of Trustees of V.O.
Chidambranar Port Trust Tuticorin & Ors., (2023) 15 SCC 781.
27.
He submits that the learned Single Judge has erred in rejecting
the challenge of the appellant to the Award on the above account only
because the challenge of the respondent to the same by way of
O.M.P.(COMM.) 233/2017 had been rejected by another learned
Single Judge of this Court by its Order dated 31.05.2017. He submits
that the said order cannot act as a res judicata on the challenge laid by
the appellant. He submits that the said challenge of the respondent was
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
based on the plea that for determining its claim, the learned Arbitrator
has wrongly excluded the relevance of the „series‟, while laying
emphasis on the number of days of cricket to be provided. He submits
that the issues were, therefore, different and the said order could not
have acted as res judicata.
28.
The learned senior counsel for the appellant further submits that
the submission of the respondent that the appellant, not having
challenged the order dated 31.05.2017, is bound by the same, is also
fallacious, inasmuch as the said order was in favour of the appellant
and there was no occasion for the appellant to have challenged the
same, therefore, it cannot act as res judicata against the appellant,
only due to the appellant not challenging the same. In support, he
places reliance on the judgment of the Allahabad High Court in Hari
Shankar v. Smt. Jag Deyee, (2000) SCC OnLine All 76, and of this
Court in S. Waryam Singh Duggal v. Smt. Savitri Devi, ILR (1984) 1
Del 214.
29.
He submits that the learned Arbitrator has erred in appropriating
the entire consideration of USD 43.75 million under the Agreement
towards International Cricket. He submits that under the Agreement,
the said consideration was payable for both, the domestic as also
International Cricket, and, therefore, even assuming that there was a
shortfall in the number of Cricketing Days, the amount thereof could
not be determined simply by the mathematical formula adopted by the
learned Arbitrator. He submits that the quantification of the claim
granted in favour of the respondent was, therefore, liable to be set
aside, which the Impugned Order fails to do.
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
30.
On the rejection of the challenge to the Counter Claim no. 1 of
the appellant, the learned senior counsel for the appellant submits that
the claim of damages for the delayed payment of the contractual
amount by the respondent, was wrongly rejected by the learned
Arbitrator by holding that the appellant had not led any evidence in
support of the same. He submits that wrongful deprivation of money
entitles the party to payment of interest as compensation for the loss
caused and no further evidence in support thereof is required. In
support, he places reliance on the judgment of the Supreme Court in
Central Bank of India v. Ravindra and Ors., (2002) 1 SCC 367.
31.
On Counter Claim no.2, that is, a claim on account of broadcast
and marketing of highlights/clippings of BCCI matches by the
respondent within India, he submits that the learned Arbitrator has
erred in rejecting the said claim by holding that it had been raised as
an afterthought. He submits that by the Consent Order dated
21.02.2005 passed by this Court in O.M.P. No.375/2003, all claims
and counter claims had been referred to arbitration. The appellant had
invoked arbitration regarding the said dispute vide Notice dated
19.05.2003, therefore, the Counter Claim raised by the appellant was
within time and could not have been rejected only on the ground of
delay or as having been waived in any manner.
32.
On Counter Claim no.3, the learned senior counsel for the
appellant submits that the learned Arbitrator committed an error in
dismissing the same on ground of constructive res judicata. He
submits that it was only in October, 2003, that is, much after the initial
arbitration, that the appellant came to know of the breach of the
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Agreement committed by the respondent on account of unauthorised
audio/video streaming of matches on internet. Therefore, the same
could not have been made a subject matter of the earlier arbitration.
33.
As regards the reliance on the plea of the appellant in the earlier
round of litigation, and that the said right had been given to the
respondent by a Letter dated 18.02.2000 and, therefore, was not
arbitrable, he submits that the said plea had been rejected not only by
the earlier Arbitrator but also by this Court while dismissing the
challenge of the appellant to the first Award passed by the first
Arbitrator. He submits that the Arbitral Award rejecting the Counter
Claim no. 3 was therefore, liable to be set aside.
34.
The learned senior counsel for the appellant submits that, in any
case, the award of interest at the rate of 18% p.a. in favour of the
respondent by the learned Arbitrator is without any reasons and
without any evidence on how the said rate has been determined. The
same is, therefore, contrary to public policy of India. In support, he
places reliance on the judgments of the Supreme Court in OPG Power
Generation Private Limited v. Enexio Power Cooling Solutions
India Private Limited & Anr., (2025) 2 SCC 417; Vedanta Limited v.
Shenzhen Shandong Nuclear Power Construction Company
Limited, (2019) 11 SCC 465; Krishna Bhagya Jala Nigam Ltd. v. G.
Harischandra Reddy & Anr., (2007) 2 SCC 720, and of this Court in
Steel Authority of India Ltd. (SAIL) v. Primetals Technologies India
Pvt. Ltd., (2020) SCC OnLine Del 2496.
35.
He further submits that the plea of the respondent that in the
application filed by the appellant under Section 34 of the A&C Act,
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
there was no challenge to the rate of interest, is not only factually
incorrect inasmuch as the said challenge was raised as a ground „(R)‟
in the Section 34 application, but even otherwise, the same being
contrary to public policy, is liable to be set aside in terms of Section
34(2)(b)(i) of the A&C Act. The said challenge can also be raised in
the appeal filed under Section 37 of the A&C Act, as held by the
Supreme Court in State of Chhattisgarh & Anr. v. SAL Udyog
Private Limited, (2022) 2 SCC 275.
36.
He submits that only because the appellant had also claimed
interest at the same rate, will not provide justification to the learned
Arbitrator to award an unreasonable rate of interest and that too
without giving any reasons.
37.
He submits that similarly, the reliance of the respondent on the
pre-amended Section 31(7) of the A&C Act, is ill-founded, inasmuch
as the said Section does not do away with the requirement of giving
reasons for the award of interest.
38.
On the challenge of the respondent to the Impugned Order, he
submits that the learned Single Judge has rightly held that the learned
Arbitrator had erred in excluding the India-Australia-New Zealand
Triangular Series from consideration. He submits that the challenge of
the respondent in this regard is ill-founded. He submits that the plea of
the respondent that it could not fully commercialise the said
Triangular Series is also incorrect, inasmuch as not only was this plea
not taken before the learned Arbitrator but also, on facts, it did
commercialise the same by entering into the Agreement with Hutch.
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Submissions by the learned Senior Counsel for the respondent:
39.
On the other hand, Mr. Ashish Dholakia, the learned senior
counsel appearing for the respondent, submits that the learned Single
Judge has erred in interfering with the Arbitral Award by including the
India-Australia-New Zealand Triangular Series in the number of
cricketing days provided by the appellant to the respondent. He
submits that the said finding is in excess of the jurisdiction vested in
the learned Single Judge under Section 34 of the A&C Act.
40.
He submits that the view of the learned Arbitrator that India-
Australia-New Zealand Triangular Series was outside the Agreement,
was a plausible view with which the learned Single Judge has erred in
interfering.
41.
He submits that the learned Arbitrator found that the said series
has no test matches and, therefore, was not a subject matter of the
Agreement, which did not include a pure One Day International series.
The learned Arbitrator held that the “Series” under the Global Rights
Agreement was bi-lateral and having atleast two test matches. He
submits that while the BCCI Agreement included Triangular and
Quadrangular matches, without mandatory test matches in the series,
this was not so in the Global Rights Agreement, which included only
bi-lateral series having test matches as well. It was also not mentioned
in Annexure-A to the Global Rights Agreement, which mentioned the
list of series covered by the Agreement.
42.
He submits that the contention of the respondent that India-
Australia-New Zealand Triangular Series was part of India-New
Zealand Series, was only to answer the submission of the appellant
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
that this was a standalone series provided under the Agreement and
therefore, should be counted as a series provided under the Global
Rights Agreement. In fact, while presenting its claim on basis of the
number of cricket days provided by the appellant, the respondent had
asserted that this series fell outside the scope of the Global Rights
Agreement. He submits that therefore, reliance of the appellant on the
said submission of the respondent, is ill-founded.
43.
He submits that the reliance of the learned Single Judge on the
order passed on the application filed by the respondent under Section
34 of the A&C Act, is incorrect, inasmuch as the same merely
considered the challenge of the respondent that under the Global
Rights Agreement, specified series had to be provided by the appellant
and having failed to do so, it was liable to compensate the respondent.
44.
He submits that as regards the challenge of the appellant to the
finding of the learned Single Judge that in terms of the Agreement,
135 days of cricket had to be provided by it to the respondent, the
same is ill-founded.
45.
He submits that the learned Arbitrator has rightly held that the
obligation of the appellant under the Global Rights Agreement cannot
be modified by relying upon the BCCI Agreement executed between
the appellant and the BCCI.
46.
On the quantification of the damages for non-provision of the
number of cricketing days, the learned senior counsel for the
respondent submits that it was the own case of the appellant before the
learned Arbitrator, as also before the learned Single Judge, that the
consideration was for the „international matches‟. The appellant had
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
also based its Counter Claim on this submission. He submits that
under the Agreement, no list of domestic matches or number of days
thereof was provided, and the said plea is now being taken only as an
afterthought.
47.
Answering the submission of the learned senior counsel for the
appellant on the lack of reasons for award of interest at the rate of
18% p.a., the learned senior counsel for the respondent submits that
the same was never put to challenge by the appellant in its application
under Section 34 of the A&C Act before the learned Single Judge. The
same is, therefore, deemed to have been waived by the appellant. He
submits that the jurisdiction of this Court in exercise of its power
under Section 37 of the A&C Act extends only to examine whether
the learned Single Judge has acted beyond its jurisdiction under
Section 34 of the A&C Act, and not to decide the matter afresh. He
submits that even otherwise the appellant cannot approbate and
reprobate, by first itself demanding interest at the rate of 18% p.a. and,
thereafter, challenging the same. In support, he places reliance on the
judgment of this Court in WAPCOS Ltd. v. C&C Energy Private
Limited, 2022 SCC OnLine Del 3498.
48.
He submits that Section 31(7) of the pre-amended A&C Act
provided for a default rate of 18% interest. The same, therefore,
cannot be said to be violative of public policy. In support, he places
reliance on the judgments of the Supreme Court in Larsen Air
Conditioning and Refrigeration Company v. Union of India & Ors.,
2023 SCC OnLine SC 982, and Sri Lakshmi Hotel (Pvt.) Ltd. & Anr.
v. Sriram City Union Finance Ltd. & Anr., 2025 SCC OnLine SC
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
2473.
49.
As far as challenge to the finding of the learned Arbitrator on
Counter Claims of the appellant is concerned, he submits that
admittedly two of the series mentioned in the Agreement, that is,
India-Australia and India-Pakistan, did not take place. In spite of the
same, the respondent deposited USD 6.56 million in Court on
26.09.2003, that is, before the contractual due date of 30.09.2003. The
respondent subsequently deposited a further sum of USD 2.18 million
for the next instalment. Therefore, not only was the respondent out of
pocket but also the appellant was fully secured of the said amount.
The appellant, after the first Arbitral Award, filed an application
seeking release of the amount so deposited by the respondent. While
the same was pending, the appellant invoked the bank guarantees and
recovered USD 6.56 million on 24.12.2004, thereby, resulting in the
respondent being out of pocket twice-over for the said amount. He
submits that, therefore, the appellant suffered no loss and cannot claim
interest or damages on the same. Placing reliance on the judgment of
the Supreme Court in Gurpreet Singh v. Union of India, (2006) 8
SCC 457, he submits that no interest is payable on the sums deposited
in Court.
50.
He submits that even otherwise, there is no contractual
provision in the Global Rights Agreement entitling the appellant to
claim interest on the delayed payments, nor any notice claiming
interest on the same was issued by the appellant under the Interest Act,
1978.
51.
He submits that the learned Arbitrator and even the learned
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Single Judge have found that the appellant had failed to provide the
committed number of cricket days to the respondent, therefore, being
in default. The appellant, therefore, cannot claim any interest for the
amount allegedly remaining outstanding to be paid.
52.
He submits that this claim was not raised by the appellant in the
first arbitral proceedings and, therefore, the appellant even otherwise
was estopped from raising the same before the learned Arbitrator.
53.
He submits that the appellant could also have invoked the bank
guarantee on 30.09.2003, but waited till 24.12.2004, therefore, its
claim was also barred by the doctrine of mitigation of losses, if at all.
54.
On counter claim no.2, the learned senior counsel for the
respondent submits that the appellant had obtained an injunction
against the respondent on an application filed under Section 9 of the
A&C Act, being O.M.P. 357/2002, which was vacated by the Division
Bench of this Court vide Order dated 24.03.2003, for the failure of the
appellant to appoint an arbitrator and to commence the arbitration
proceedings in this dispute. The appeal was finally dismissed on
21.07.2005 as being infructuous as the Agreement between the parties
had expired on 30.09.2004. The Counter Claim was raised only on
22.07.2006, that is, more than 3 years after the alleged cause of action
arose in October, 2002, and even the purported Notice dated
19.05.2003, receipt of which was denied by the respondent. The
Counter Claim was, therefore, abandoned and was barred by
limitation.
55.
He submits that merely because, by the Order dated 21.02.2005
passed in OMP 357/2002, the appellant was permitted to raise its
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
counter claims, a stale counter-claim would not revive. The said
reference also cannot constitute an invocation or commencement of
arbitration proceedings for such counter claim which even otherwise
was barred by limitation.
56.
He submits that similarly, as far as the Counter Claim no.3 is
concerned, it was the own case of the appellant that such right was
granted to the respondent vide Letter Agreement dated 18.02.2000 and
could not be made a subject matter of arbitration. The said claim was
not raised in the first arbitration proceedings and, therefore, the
learned Arbitrator correctly applied the principles of constructive res
judicata for rejecting the same.
57.
He submits that even otherwise, the said counter claim was not
maintainable as not only the first arbitration, but also the Judgment
dated 17.04.2017 passed by this Court in O.M.P. 426/2008, dismissing
the challenge of the appellant thereto, upheld the multimedia and
internet rights including streaming of the respondent under the Global
Rights Agreement.
Analysis and findings:
58.
We have considered the submissions made by the learned senior
counsels for the parties.
59.
Section 34 of the A&C Act states the grounds for setting aside
an Arbitral Award. So far as it is relevant, for the grounds on which an
Arbitral Award may be set aside by the Court, it reads as under:“Section 34. Application for setting aside
arbitral awards.
*****
(2) An arbitral award may be set aside by the
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Court only if-(a) the party making the application
establishes on the basis of the record of the
arbitral tribunal that-(i) a party was under some incapacity, or
(ii) the arbitration agreement is not valid
under the law to which the parties have
subjected it or, failing any indication thereon,
under the law for the time being in force; or
(iii) the party making the application was not
given proper notice of the appointment of an
arbitrator or of the arbitral proceedings or
was otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not
contemplated by or not falling within the terms
of the submission to arbitration, or it contains
decisions on matters beyond the scope of the
submission to arbitration:
Provided that, if the decisions on matters
submitted to arbitration can be separated from
those not so submitted, only that part of the
arbitral award which contains decisions on
matters not submitted to arbitration may be set
aside; or
(v) the composition of the arbitral tribunal or
the arbitral procedure was not in accordance
with the agreement of the parties, unless such
agreement was in conflict with a provision of
this Part from which the parties cannot
derogate, or, failing such agreement, was not
in accordance with this Part; or
(b) the Court finds that-(i) the subject-matter of the dispute is not
capable of settlement by arbitration under the
law for the time being in force, or
(ii) the arbitral award is in conflict with the
public policy of India.
Explanation 1.--For the avoidance of any
doubt, it is clarified that an award is in
conflict with the public policy of India, only if,(i) the making of the award was induced or
affected by fraud or corruption or was in
violation of section 75 or section 81; or
(ii) it is in contravention with the fundamental
policy of Indian law; or
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
(iii) it is in conflict with the most basic notions
of morality or justice.
Explanation 2.--For the avoidance of doubt,
the test as to whether there is a contravention
with the fundamental policy of Indian law
shall not entail a review on the merits of the
dispute.
(2A) An arbitral award arising out of
arbitrations
other
than
international
commercial arbitrations, may also be set aside
by the Court, if the Court finds that the award
is vitiated by patent illegality appearing on the
face of the award:
Provided that an award shall not be set aside
merely on the ground of an erroneous
application of the law or by reappreciation of
evidence.”
60.
In Ramesh Kumar Jain v. Bharat Aluminium Company
Limited (BALCO), 2025 SCC OnLine SC 2857, the Supreme Court
has explained the restricted jurisdiction of the Court while dealing
with an application under Section 34 of the A&C Act, as under:“27. The Arbitration and Conciliation Act,
1996 avows to provide a speedy, cost-effective
& efficacious mode of alternative dispute
resolution with a policy of minimal judicial
intervention. The same is apparent from the
legislative intent explicitly mandated under
section 5 of A&C Act which envisages an
embargo upon the judiciary to interfere in
arbitral proceedings save in circumstance
expressly stipulated under Part I of the Act.
Hence, it is clear that judicial interference is
circumscribed with only exception being the
statutorily mandated remedies which we find
under section(s) 34 and 37 of the A&C Act.
28. The bare perusal of section 34 mandates a
narrow lens of supervisory jurisdiction to set
aside the arbitral award strictly on the
grounds and parameters enumerated in subsection (2) & (3) thereof. The interference is
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
permitted where the award is found to be in
contravention to public policy of India; is
contrary to the fundamental policy of Indian
Law; or offends the most basic notions of
morality or justice. Hence, a plain and
purposive reading of the section 34 makes it
abundantly clear that the scope of interference
by a judicial body is extremely narrow. It is a
settled proposition of law as has been
constantly observed by this court and we
reiterate, the courts exercising jurisdiction
under section 34 do not sit in appeal over the
arbitral award hence they are not expected to
examine the legality, reasonableness or
correctness of findings on facts or law unless
they come under any of grounds mandated in
the said provision. In ONGC Limited. v. Saw
Pipes Limited, this court held that an award
can be set aside under Section 34 on the
following grounds:“(a) contravention of
fundamental policy of Indian law; or (b) the
interest of India; or (c) justice or morality, or
(d) in addition, if it is patently illegal.”
29. When it comes to section 37 of the A&C
Act it provides for a limited appellate remedy
against an order either setting aside or
refusing to set aside an arbitral award passed
by civil court in exercise of its power under
section
34.
This
court
in MMTC
Ltd. v. Vedanta Ltd., at Paragraph 14
observed that interference with an order made
under section 37 cannot travel beyond the
restrictions laid down in section 34. Further
in Konkan
Railway
Corporation
Limited v. Chenab
Bridge
Project
Undertaking this court at Paragraph 18
observed that the scope of appellate scrutiny
under section 37 is necessarily co-extensive
with the parameters mandated under section
34 of the Act and hence the said provision
does not enlarge the jurisdiction of the
appellate court. Even this court has observed
in Hindustan
Construction
Company
Limited v. National Highways Authority of
India, wherein one of us (Justice Aravind
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Kumar) was part of the bench at Paragraph 26
that the standard of scrutiny of an arbitral
award is very narrow and it is not the judicial
review of an award. Further in Paragraph 27
it was observed that awards which contains
reasons, especially when they interpret
contractual terms, ought not to be interfered
with lightly. This court has also observed
in Larsen Air Conditioning and Refrigeration
Company v. Union of India at Paragraph 15
that the scope of interference in exercise of
appellate power under section 37 is even
narrower to review the findings of the awards,
if it has been upheld or substantially upheld
under section 34. Hence, it is very well settled
that arbitral awards are not liable to be set
aside merely on the ground of erroneous in
law or alleged misappreciation of evidence
and there is a threshold that the party seeking
for the award to be set aside has to satisfy,
before the judicial body could enter into the
realm of exercising its power under section(s)
34 & 37. It is also apt and appropriate to note
that re-assessment or re-appreciation of
evidence lies outside the contours of judicial
review under section(s) 34 and 37. This court
in Punjab State Civil Supplies Corporation
Limited v. Sanman Rice Mills, at Paragraph
12 observed that even when the arbitral
awards may appear to be unreasonable and
non-speaking that by itself would not warrant
the courts to interfere with the award unless
that unreasonableness has harmed the public
policy or fundamental policy of Indian law. It
might be a possibility that on re-appreciation
of evidence, the courts may take another view
which may be even more plausible but that
also does not leave scope for the courts to
reappraise the evidence and arrive at a
different view. This court in Batliboi
Environmental
Engineers
Limited
v.
Hindustan Petroleum Corporation Limited
held that the arbitrator is generally considered
as ultimate master of quality and quantity of
evidence. Even an award which is based on
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
little or no evidence would not be held to be
invalid on this score. At times, the decisions
are taken by the arbitrator acting on equity
and such decisions can be just and fair
therefore award should not be overridden
under section 34 and 37 of the A&C Act on
the ground that the approach of the
arbitrator was arbitrary or capricious.”
(Emphasis Supplied)
61.
In Parsa Kente Collieries Ltd. v. Rajasthan Rajya Viduyt
Utpadan Nigam Ltd., (2019) 7 SCC 236, the Supreme Court held that
construction of terms of contract is primarily for an arbitrator to
decide and unless the arbitrator construes the contract in such a way
that it could be said to be something that no fair-minded or reasonable
person could do so, the interference with the same by a Court
exercising jurisdiction under Section 34 of the A&C Act is not
warranted. We quote from the judgment as under:
“9.1. In Associate Builders v. DDA, this Court
had an occasion to consider in detail the
jurisdiction of the Court to interfere with the
award passed by the Arbitrator in exercise of
powers under Section 34 of the Arbitration
Act. In the aforesaid decision, this Court has
considered the limits of power of the Court to
interfere with the arbitral award. It is
observed and held that only when the award is
in conflict with the public policy in India, the
Court would be justified in interfering with the
arbitral award. In the aforesaid decision, this
Court considered different heads of “public
policy in India” which, inter alia, includes
patent illegality. After referring Section 28(3)
of the Arbitration Act and after considering
the decisions of this Court in McDermott
International Inc. v. Burn Standard Co. Ltd.
and Rashtriya Ispat Nigam Ltd. v. Dewan
Chand Ram Saran , it is observed and held
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
that an Arbitral Tribunal must decide in
accordance with the terms of the contract, but
if an Arbitrator construes a term of the
contract in a reasonable manner, it will not
mean that the award can be set aside on this
ground. It is further observed and held that
construction of the terms of a contract is
primarily for an Arbitrator to decide unless
the Arbitrator construes the contract in such
a way that it could be said to be something
that no fair-minded or reasonable person
could do. It is further observed by this Court
in the aforesaid decision in para 33 that when
a court is applying the “public policy” test to
an arbitration award, it does not act as a court
of appeal and consequently errors of fact
cannot be corrected. A possible view by the
Arbitrator on facts has necessarily to pass
muster as the Arbitrator is the ultimate
master of the quantity and quality of evidence
to be relied upon when he delivers his arbitral
award. It is further observed that thus an
award based on little evidence or on evidence
which does not measure up in quality to a
trained legal mind would not be held to be
invalid on this score.
9.2. Similar is the view taken by this Court in
NHAI v. ITD Cementation (India) Ltd. and
SAIL v. Gupta Brother Steel Tubes Ltd.”
(Emphasis Supplied)
62.
The Supreme Court, in MMTC Ltd. v. Vedanta Ltd., (2019) 4
SCC 163, while interpreting Section 34 of the A&C Act, reiterated
that the Court in exercise of its power under Section 34 of the A&C
Act, does not sit as a Court of Appeal and can interfere on the merits
of the Award only on very limited grounds. It has held as under:
“10. Before proceeding further, we find it
necessary to briefly revisit the existing position
of law with respect to the scope of interference
with an arbitral award in India, though we do
not wish to burden this judgment by discussing
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
the principles regarding the same in detail.
Such interference may be undertaken in terms
of Section 34 or Section 37 of the Arbitration
and Conciliation Act, 1996 (for short “the
1996 Act”). While the former deals with
challenges to an arbitral award itself, the
latter, inter alia, deals with appeals against an
order made under Section 34 setting aside or
refusing to set aside an arbitral award.
11. As far as Section 34 is concerned, the
position is well-settled by now that the Court
does not sit in appeal over the arbitral award
and may interfere on merits on the limited
ground provided under Section 34(2)(b)(ii) i.e.
if the award is against the public policy of
India. As per the legal position clarified
through decisions of this Court prior to the
amendments to the 1996 Act in 2015, a
violation of Indian public policy, in turn,
includes a violation of the fundamental policy
of Indian law, a violation of the interest of
India, conflict with justice or morality, and the
existence of patent illegality in the arbitral
award. Additionally, the concept of the
“fundamental policy of Indian law” would
cover compliance with statutes and judicial
precedents, adopting a judicial approach,
compliance with the principles of natural
justice,
and
Wednesbury
[Associated
Provincial Picture Houses v. Wednesbury
Corpn.,
(1948)
KB
(CA)]
reasonableness.
Furthermore,
“patent
illegality” itself has been held to mean
contravention of the substantive law of India,
contravention of the 1996 Act, and
contravention of the terms of the contract.
12. It is only if one of these conditions is met
that the Court may interfere with an arbitral
award in terms of Section 34(2)(b)(ii), but
such interference does not entail a review of
the merits of the dispute, and is limited to
situations where the findings of the arbitrator
are arbitrary, capricious or perverse, or when
the conscience of the Court is shocked, or
when the illegality is not trivial but goes to
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
the root of the matter. An arbitral award may
not be interfered with if the view taken by the
arbitrator is a possible view based on facts.
(See Associate Builders v. DDA [Associate
Builders v. DDA, (2015) 3 SCC 49 : (2015) 2
SCC (Civ) 204] . Also see ONGC Ltd. v. Saw
Pipes Ltd. [ONGC Ltd. v. Saw Pipes Ltd.,
(2003) 5 SCC 705] ; Hindustan Zinc Ltd. v.
Friends Coal Carbonisation [Hindustan Zinc
Ltd. v. Friends Coal Carbonisation, (2006) 4
SCC 445] ; and McDermott International Inc.
v. Burn Standard Co. Ltd. [McDermott
International Inc. v. Burn Standard Co. Ltd.,
(2006) 11 SCC 181] )
13. It is relevant to note that after the 2015
Amendment to Section 34, the above position
stands somewhat modified. Pursuant to the
insertion of Explanation 1 to Section 34(2), the
scope of contravention of Indian public policy
has been modified to the extent that it now
means fraud or corruption in the making of the
award, violation of Section 75 or Section 81 of
the Act, contravention of the fundamental
policy of Indian law, and conflict with the most
basic notions of justice or morality.
Additionally, sub-section (2-A) has been
inserted in Section 34, which provides that in
case of domestic arbitrations, violation of
Indian public policy also includes patent
illegality appearing on the face of the award.
The proviso to the same states that an award
shall not be set aside merely on the ground of
an erroneous application of the law or by
reappreciation of evidence.
14. As far as interference with an order made
under Section 34, as per Section 37, is
concerned, it cannot be disputed that such
interference under Section 37 cannot travel
beyond the restrictions laid down under
Section 34. In other words, the court cannot
undertake an independent assessment of the
merits of the award, and must only ascertain
that the exercise of power by the court under
Section 34 has not exceeded the scope of the
provision. Thus, it is evident that in case an
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
arbitral award has been confirmed by the
court under Section 34 and by the court in an
appeal under Section 37, this Court must be
extremely cautious and slow to disturb such
concurrent findings.”
(Emphasis Supplied)
63.
Most recently, the Supreme Court in Prakash Atlanta (JV) v.
National Highways Authority of India, 2026 INSC 76, has reiterated
that the findings of an Arbitral Tribunal should not be substituted
merely because an alternative view on construction of contract is
possible. It has held as under:
“59. We may now sum up our conclusion as
under:
xxx
(vi) If an arbitral tribunal’s view is found to be
a possible and plausible one, it cannot be
substituted merely because an alternate view is
possible. Construction and interpretation of a
contract and its terms is a matter for the
arbitral tribunal to determine. Unless the
same is found to be one that no fair-minded
or reasonable person would arrive at, it
cannot be interfered with. If there are two
plausible interpretations of the terms of a
contract, then no fault can be found if the
arbitrator accepts one such interpretation as
against the other. To be in conflict with the
public policy of India, the award must
contravene the fundamental policy of Indian
law, which makes it narrower in its
application.”
(Emphasis Supplied)
64.
We may herein also note that the jurisdiction of the Court under
Section 37 of the A&C Act is limited only to examine if the Court
from which the appeal arises, has erred in applying the principles
applicable to the limited jurisdiction vested in such Court under
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Section 34 of the A&C Act. Section 37 of the A&C Act reads as
under:“Section 37. Appealable orders.
(1) Notwithstanding anything contained in any
other law for the time being in force, an
appeal shall lie from the following orders (and
from no others) to the Court authorised by law
to hear appeals from original decrees of the
Court passing the order, namely:-(a) refusing to refer the parties to arbitration
under section 8;
(b) granting or refusing to grant any measure
under section 9;
(c) setting aside or refusing to set aside an
arbitral award under section 34.
(2) Appeal shall also lie to a court from an
order of the arbitral tribunal-(a) accepting the plea referred to in subsection (2) or sub-section (3) of section 16; or
(b) granting or refusing to grant an interim
measure under section 17.
(3) No second appeal shall lie from an order
passed in appeal under this section, but
nothing in this section shall affect or take
away any right to appeal to the Supreme
Court.”
65.
The Supreme Court in Punjab State Civil Supplies Corpn. Ltd.
& Anr. v. Sanman Rice Mills & Ors., 2024 SCC OnLine SC 2632,
while analysing the scope of Section 37 of the A&C Act, being an
appellate provision, has held as under:
“11. Section 37 of the Act provides for a forum
of appeal inter-alia against the order setting
aside or refusing to set aside an arbitral
award under Section 34 of the Act. The scope
of appeal is naturally akin to and limited to
the grounds enumerated under Section 34 of
the Act.
12. It is pertinent to note that an arbitral
award is not liable to be interfered with only
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
on the ground that the award is illegal or is
erroneous in law that too upon reappraisal of
the evidence adduced before the arbitral trial.
Even an award which may not be reasonable
or is non-speaking to some extent cannot
ordinarily be interfered with by the courts. It is
also well settled that even if two views are
possible there is no scope for the court to
reappraise the evidence and to take the
different view other than that has been taken
by the arbitrator. The view taken by the
arbitrator is normally acceptable and ought to
be allowed to prevail.
*****
14. It is equally well settled that the appellate
power under Section 37 of the Act is not akin
to the normal appellate jurisdiction vested in
the civil courts for the reason that the scope
of interference of the courts with arbitral
proceedings or award is very limited,
confined to the ambit of Section 34 of the Act
only and even that power cannot be exercised
in a casual and a cavalier manner.
*****
20. In view of the above position in law on the
subject, the scope of the intervention of the
court in arbitral matters is virtually
prohibited, if not absolutely barred and that
the interference is confined only to the extent
envisaged under Section 34 of the Act. The
appellate power of Section 37 of the Act is
limited within the domain of Section 34 of the
Act. It is exercisable only to find out if the
court, exercising power under Section 34 of
the Act, has acted within its limits as
prescribed thereunder or has exceeded or
failed to exercise the power so conferred. The
Appellate Court has no authority of law to
consider the matter in dispute before the
arbitral tribunal on merits so as to find out as
to whether the decision of the arbitral
tribunal is right or wrong upon reappraisal of
evidence as if it is sitting in an ordinary court
of appeal. It is only where the court exercising
power under Section 34 has failed to exercise
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
its jurisdiction vested in it by Section 34 or has
travelled beyond its jurisdiction that the
appellate court can step in and set aside the
order passed under Section 34 of the Act. Its
power is more akin to that superintendence
as is vested in civil courts while exercising
revisionary powers. The arbitral award is not
liable to be interfered unless a case for
interference as set out in the earlier part of
the decision, is made out. It cannot be
disturbed only for the reason that instead of
the view taken by the arbitral tribunal, the
other view which is also a possible view is a
better view according to the appellate court.
21. It must also be remembered that
proceedings under Section 34 of the Act are
summary in nature and are not like a fullfledged regular civil suit. Therefore, the scope
of Section 37 of the Act is much more
summary in nature and not like an ordinary
civil appeal. The award as such cannot be
touched unless it is contrary to the
substantive provision of law; any provision of
the Act or the terms of the agreement.
(Emphasis Supplied)
66.
We shall now apply the above tests to the challenge to the
Arbitral Award and to the order of the learned Single Judge laid by the
parties.
67.
The first challenge of the appellant to the Arbitral Award as
also to the Impugned Order of the learned Single Judge is to a finding
that in terms of the Global Rights Agreement, the appellant was to
provide 135 days of International Cricket to the respondent. The
appellant states that the said finding of the Arbitral Tribunal is rewriting the Agreement, inasmuch as it has failed to appreciate that the
Agreement was for part of the cricketing season.
68.
We are unable to accept the said submission of the appellant.
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
The Global Rights Agreement between the parties, though executed
on 19.02.2000, was for the cricketing events from 01.01.2000 to
30.09.2004. Clause 4 of the Agreement defined cricketing events as
under:
“4. CRICKETING EVENTS:
For the purposes hereof, Cricketing Events
shall mean and include the following:(a) The Cricketing Events comprise all
Domestic & International Matches played in
India conducted by the BCCI during the term,
and a list and proposed schedule of both the
Domestic and International Matches (“the
Matches”) is annexed as Annexure A. Any
change in schedules/ timings of the Matches
will not entitle TWI- STRACON for any claim
for damages against Prasar Bharati.
(b) The Cricketing Events, as being provided
by Prasar Bharati, shall comprise of minimum
twenty seven (27) days of international cricket
in each cricket season that would be telecast
live and the same number of highlights of at
least one hour each for each day of the
matches.”
69.
Unlike the BCCI Agreement, the Global Rights Agreement did
not define the term „Cricket Season‟. It did not even state that as the
Agreement was being executed in the middle of a Cricket Season,
there shall be a proportionate reduction of the number of days of
International Cricket for the first season. The definition of Cricket
Season from the BCCI Agreement therefore, cannot be imported into
the Global Rights Agreement to modify the terms thereof.
70.
Clause 9 of the Global Rights Agreement provides for
proportionate reduction in the consideration in case lesser number of
International Matches are played. It reads as under
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
“9. CONSIDERATION
9.1 In consideration for the grant of the
Rights, TWI-/STRACON shall pay to Prasar
Bharati,
the
amount
(hereafter
“Consideration”) of Forty Three Million
Seven Hundred & Fifty Thousand US Dollars.
Payable in Dollars, this consideration shall be
payable subject to the provisions of clause 9.4
and 9.5 hereof. The consideration shall be
payable by TWI-STRACON in the following
instalments;
(a) 5% of the Consideration on 15.2.2000
(receipt of which is hereby acknowledged by
PRASAR BHARATI).
(b) The remaining balance amount of 90% of
the consideration shall be paid in four equal
annual instalments each being 22.5% of the
consideration as follows:
On or before 30 September 2000
22.5%
On or before 30th September 2001
22.5%
On or before 30th September 2002
22.5%
On or before 30th September 2003
22.5%
(c) The balance 5% of the Consideration shall
be paid to PRASAR BHARATI before 30th
November 2004, following settlement of the
final accounts to be carried out before 31
March 2004.
9.2 The final accounts for each year will be
settled before 31st March of each year of the
Term, inter alia, taking into account the
revenue generated through any extra or
additional matches.
9.3 If more or less International matches than
specified in Annexure I are played during the
term, the following shall apply:
9.4.1 If more international Matches are
played, and coverage of such International
match is delivered as stipulated in this
Agreement, then TWI-STRACON will pay
PRASAR BHARATI 50% of the net income
from such additional matches. For these
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
purposes "net income" shall mean sales
income actually received by TWI-STRACON,
after deduction of any applicable withholding
tax and there will be a final reconciliation of
amounts owing at the end of the term, as
referred to in clause 9.2 above.
9.4.2 If less International Matches are played
or coverage of the international matches
stipulated in this agreement is not delivered,
then the consideration for the Rights will be
reduced on a pro rata basis.
9.5 All taxes / levies / charges/ duties
whatsoever relating to or arising out of the
payment of the Consideration of the share of
Net Revenue as aforesaid, by TWI-STRACON
to Prasar Bharati shall be totally on the
account of and shall be solely borne by TWISTRACON.”
71.
Interpreting the terms of the Agreement, the learned Arbitrator,
held that the term of the Agreement being five years, a total of 135
Cricketing Days were to be provided. The learned Arbitrator held that
merely because the Global Rights Agreement commenced from
01.01.2000, as against the BCCI Agreement which commenced from
01.10.1999, the India-New Zealand Series, which took place in
October 1999 (of 20 days), could neither be counted against the
Global Rights Agreement nor could the total number of International
Matches (of 20 days) be reduced from the Global Rights Agreement.
The learned Arbitrator held that the terms of the BCCI Agreement
cannot dictate or modify the terms of the Global Rights Agreement.
This being a matter of interpretation of the contract, which cannot be
stated to be perverse, the same, in exercise of powers under Section 34
of the A&C Act, cannot be interfered with. It was not a case of rewriting the Agreement between the parties but of interpretation
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
thereof.
72.
In fact, applying the same principles for considering a challenge
to an Arbitral Award, the challenge of the respondent to the Arbitral
Award in form of O.M.P. (COMM.) 233/2017 had been rejected by
another learned Single Judge of this Court, vide its judgment dated
31.05.2017. We quote from the same as under:“33. In terms of Clause 4(b), it was agreed
that the Cricketing Events shall comprise of a
minimum of 27 days of international cricket in
which cricketing season. It is apparent from
the above that the expression "Cricketing
Events" would comprise of all domestic and
international matches (as specified in Clause
4(a)) played in India and conducted by BCCI.
Such cricketing events would comprise of
minimum of 27 days of international cricket
(in terms of Clause 4(b)).
34. The term "Cricketing Events" denotes
"Domestic and International Matches" and
thus it is clear that Prasar Bharti had agreed
to provide matches comprising of at least 27
days of international cricket matches in each
cricketing season.
35. In terms of Clause 9.3, if more or less
international matches were played during the
term, the provisions that followed (that is,
Clauses 9.4.1 and 9.4.2) would apply. It is
relevant to note that Clause 9.3 refers to
international matches played during the term,
therefore, the question whether more
international matches or less international
matches were played would have to be
considered with reference to the term of the
Agreement which comprised of five cricketing
seasons. And, the question whether more or
less cricket matches were played would have
to be ascertained on a cumulative basis and
not on an annual basis.
36. As stated above, the expression "Domestic
and International Matches" has been used to
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
define the expression "Cricketing Events" and
thus, Clause 9.4.2 could be understood to
mean that if the Cricketing Events do not take
place or the coverage of the international
matches is not delivered then the consideration
would be reduced on a pro-rata basis.
37. As noted above, the arbitral tribunal had
come to the conclusion that "the word 'series'
is misnomer as it has either to be no. of days of
matches or no. of days of international
cricket". It is apparent that the arbitral
tribunal was of the view that the reduction in
the consideration as contemplated under
Clause 9.4.2 would have to be considered in
reference to the shortfall in providing
Cricketing Events as committed under Clause
4(b) of the Agreement; that is, a shortfall in
providing an aggregate of 135 days of
international cricket during the term. The
arbitral tribunal concluded that the shortfall in
the number of days of international cricket
would also encompass the shortfall in holding
of the Cricketing Events as contemplated
under Clause 4(a). This view cannot by any
stretch be held to be perverse or patently
illegal even if it is accepted that an alternate
view as contended by the petitioners is
possible.
38. The word "series" has not been mentioned
in the Agreement and the only terms used are
"International Matches", "Cricketing Events"
and "Domestic and International Matches".
Annexure A to the Agreement provides for
Cricketing Events. However, Clause 4(a) also
indicates that such events were only 'proposed'
cricketing events. It is also not disputed that
the said list of events was altered as the India
v. Sri. Lanka matches were replaced by India
v. Zimbabwe matches.
39. The arbitral tribunal had also noted that
the duration of cricket matches was variable;
whilst the duration of one-day international
match is only a single day, the duration of test
matches would be more than three days. The
duration of series would also depend on the
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
number of test matches and one day matches.
40. Considering the above, the arbitral
tribunal interpreted the provision of Clause
9.4.2 of the Agreement to stipulate reduction
in the consideration agreed in reference to the
minimum number of days of international
cricket and not "series" as claimed by the
petitioners.
41. The scope of "Cricketing Events" to be
provided to the petitioners is defined in Clause
4 and the language of sub-clauses of Clause 4
of the Agreement clearly indicates that the
assurance of minimum number of Cricketing
Events is stipulated in Clause 4(b) and not
Clause 4(a).
42. The arbitral tribunal had considered the
above and interpreted the Agreement to
stipulate pro-rata reduction in consideration
with reference to the minimum number of days
of international cricket. This being a plausible
view, no interference with the impugned award
is warranted.”
73.
Though the above order would not act as res judicata, inasmuch
as there is no concept of merger applicable to a decision on Section 34
of the A&C Act upholding the Arbitral Award, at the same time, it has
a value of deference to a subsequent challenge to the same Arbitral
Award by the other party.
74.
Now coming to the challenge of the respondent on the inclusion
of the India-Australia-New Zealand Triangular Series to the number of
International Cricket days provided by the appellant, the learned
Arbitrator had excluded the said series by holding that the same was
not a separate series and was not mentioned in Annexure-A to the
Agreement. Once the learned Arbitrator had itself stated that the list of
Series provided in Annexure-A to the Agreement was only tentative
and cannot govern the rights of the parties, to hold that there will be a
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
total exclusion to the Triangular Series between India-Australia-New
Zealand, rights over which had admittedly been availed of by the
respondent, therefore, was a contradiction in the Arbitral Award itself
and has rightly been interfered with by the learned Single Judge in the
Impugned Order. The learned Single Judge has observed as under:
“53. Since the Co-Ordinate Bench has dealt
with the issue of series in entirety and upheld
the Award to that extent, the only issue that
remains to be adjudicated by this Court is the
entitlement of the respondents to their claim of
shortfall of 17 days under clause 4(b). At the
cost of repetition, the Tribunal has allowed the
claim on the ground that the 10 cricketing
days could not have been provided as these
were a part of the Triangular Series, which
were not mentioned in the Schedule. Once the
Co-ordinate Bench has held in its judgment,
which has attained finality, that the list was
only a 'proposed' list and there had been an
earlier change in the India-Sri Lanka matches,
this finding of the Tribunal cannot be
sustained. It is significant to note that when
the India-Sri Lanka matches were replaced,
respondents had not raised any protest and in
fact even when the Triangular Series were
played, the respondents had telecast the same
and exploited the series. They had earned
revenue therefrom, without any demur or
protest.
54. Respondents may be right in their
contention that the Triangular Series may not
have earned as much revenue as was expected
from another series between India-Pakistan
and India-Australia, but this argument cannot
be raised by the respondents at this stage.
When the petitioner granted the right to the
respondents to market and telecast the
Triangular Series, the petitioner should have
objected at that stage, instead of telecasting
the series and earning revenue therefrom.
Thus, in my view, the finding of the Arbitrator
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
allowing the claim of the respondent towards
the shortfall of 10 cricketing days is patently
illegal and cannot be sustained, more
particularly in view of the judgment of the
coordinate Bench. To this extent, the Award
deserves to be set aside.”
75.
We see no reason to interfere with the said findings of the
learned Single Judge.
76.
While making a claim based on number of Series of cricket
provided by the appellant to the respondent, it was the own case of the
respondent that the India-Australia-New Zealand Triangular Series
was a part of the India-New Zealand Series. The learned Arbitrator
accepted the same, however, when coming to the question of number
of International Matches or Cricketing Events provided under the
Agreement, the learned Arbitrator, excluded the same, treating it as a
separate Series and also on the ground that as it did not have any Test
Matches, it could not be counted against the Agreement. Not only was
this finding contradicting the earlier finding of the learned Arbitrator,
but introduction of a Series to necessarily have Test Matches, was
introducing a new term in the Agreement. This was not a simple case
of interpreting the contract, but re-writing the same. We quote from
the Arbitral Award as under:“.......I may also note that an alternate
argument sought to be advanced by Mr
Sharma was that at least eight out of nine
series were provided to claimant. It was
Respondent's submission that India - New
Zealand and India - Australia - New Zealand
triangular series were two separate series. To
buttress this submission, Mr. Sharma relied
upon an agreement between Claimant and
Hutch and also a letter from BCCI to
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Respondent stating that the two were different
series. In response, Mr. Dayal submitted that
the triangular series was an extension of the
India- New Zealand series and that in so far as
in agreement with Hutch is concerned, the
bifurcation was only as regards one day from
test matches.
In my view Respondent cannot place
reliance on Claimant's agreements with third
parties. In any case, once rights have been
granted to Claimant for a particular series,
Claimant may be well within its rights to
further distribute them in whole or in part.
Even in cross-examination, Respondent has
not been able to establish conclusively as to
whether the triangular series was a separate
series or not. Claimant's witness denies the
suggestions and interpretations given by
Respondent (Questions Nos.180 and 181 in
cross-examination of Claimant witness).
Q. No.180. I am suggesting to you that
the statement in para 25 of your affidavit that
the triangular events was a replacement of the
already scheduled India New Zealand series of
October, 2003 is your assumption and is not
based on any records.
Ans. You are not correct. Please refer to
the definition of cricketing events on page 5 of
the agreement which does not exclude any
combination of teams playing in an event. It
also refers to Annexure-A as a list and
proposed schedule and the Annexure-A does
have a proposed schedule for October, 2003 to
November, 2003. The triangular series
matches with both of this.
Q. 181. I am drawing your attention to
the document at page 749 of the respondents
documents which is a letter dated 30th
September, 2003 written by BCCI to the effect
that the India New Zealand series and the triseries wee two separate events. What do you
have to say to that?
Ans. The reference is to a letter from
BCCI to Dordarshan which may have a
relevance the way the events were described in
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Doordarshans agreement with BCCI. It does
not impact the definition used by Doordarshan
in their agreement with Claimant. This
document is marked as Mark X-1 for
identification. I accordingly reject the
submission of Respondent.
*****
A series cannot be one match, described as
Test Matches. Series could have two or more
test matches. A Test Match would ordinarily
mean 5 days of international cricket. As to
how many Test Matches each of the 7 series
were provided to the Claimant has not been
shown by the Claimant. These days as I give
this Award, there is series between England India and there are 5 test matches. On the
other hand Respondent Prasar Bharati has
filed a statement showing the no. of ODIS
(One Day International) and no. of days of
Test Matches in each series. Prasar Bharati
also could not have shown a series between
India - Australia - New Zealand which is not
part of the series mentioned in the schedule to
the agreement, therefore cannot be taken note
of. This way Respondent has provided 118
days international cricket to the Claimant.
*****
It would be seen that last series in the table
between India – Australia - New Zealand is
not part of the series under the agreement. So
10 days of cricket sought to have been
provided to the Claimant has to be ignored.
Thus 118 days cricket would appear to have
been provided to the Claimant as per the table.
There would be thus 17 days of cricket which
Respondent - Prasar Bharati has failed to
provide to the Claimant (135 days - 118 days
= 17 days). Claimant also says that there was
shortfall of 17 days of cricket not having been
provided to it by the Prasar Bharati. As to how
118 days cricket was provided by the Prasar
Bharati to the Claimant, details are given in
the aforementioned table. Claimant has not
given any details of the days of cricket
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
provided to it. In the circumstances, I would
accept the table of the Prasar Bharati showing
how 118 days of cricket was provided to the
Claimant.”
77.
The above quotation would itself show not only the
contradiction in the findings of the learned Arbitrator, but as rightly
contended by the learned senior counsel for the appellant, a new case
dehors the contract being made by the learned Arbitrator in favour of
the respondent contrary to its own pleadings.
78.
Now coming to the issue of giving a monetary value to the less
number of International Cricket days provided by the appellant to the
respondent, we find no merit in the submission of the learned senior
counsel for the appellant that the consideration of USD 43.5 million,
being for both, domestic as also International Cricket, could not have
been ascribed entirely towards International Cricket by the learned
Arbitrator. In this regard, we have already reproduced hereinabove
Clause 9 of the Agreement between the parties. The same, in Clause
9.3 thereof, states that if more or less international matches than
specified in Annexure-A (wrongly typed as „I‟) are played during the
term of the contract, there shall be an adjustment as provided in
Clause 9.4.1 and Clause 9.4.2 respectively. Clause 9.4.2 states that if
less „international‟ matches are played or coverage of the international
matches stipulated in the Agreement is not delivered, „then the
consideration for the Rights will be reduced on a pro rata basis‟.
Therefore, in terms of the Agreement, though rights for both, the
domestic as also international matches, were provided by the appellant
to the respondent, however, the entire consideration under the
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Agreement was ascribed to the international matches. Clause 9.4.2
further stated that if there is a lesser number of international matches
provided, the consideration for the Rights, that is, USD 43.5 million
shall be reduced on a pro rata basis. This again is a matter of
interpretation of the contractual terms by the learned Arbitrator, with
which, much less finding any fault, we do agree, and therefore, find no
merit in the challenge thereto.
79.
The next challenge of the appellant to the Arbitral Award and
the findings of the learned Single Judge are to the rate of interest
awarded by the learned Arbitrator. In this regard, we may only note
that there was no specific challenge to the same made by the appellant
in its application under Section 34 of the A&C Act before the learned
Single Judge. There appears to be no submission in this regard also
made before the learned Single Judge. It is also not denied that the
appellant itself had claimed interest at the rate of 18% p.a. on its
Counter Claim. Once both the parties were claiming the same rate of
interest, we find no error in the learned Arbitrator awarding the same
while allowing the claim of the respondent. The plea of the appellant
that further reasons were required from the arbitrator for the said rate
of interest to be awarded, therefore, does not impress us. While in
normal circumstances, the Arbitral Tribunal must give reasons not
only for the rate of interest but also for the period for which it is
granted, the same rigour may not apply in the facts of the present case
where the appellant itself was claiming interest at the same rate.
80.
In view of the above, the challenge of the appellant to the order
of the learned Single Judge, as far as the claims of the respondent are
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
concerned, we find no merit.
81.
Similarly, we find no merit in the challenge of the respondent to
the finding of the learned Single Judge that the 10 cricketing days for
India-Australia-New Zealand Triangular series also need to be
included while calculating the number of international matches
provided by the appellant to the respondent.
82.
Now coming to the challenge of the appellant to the rejection of
the Counter Claims, the first Counter Claim raised by the appellant
was on account of alleged loss occasioned by delayed payment of
USD 6.56 million, which was payable by the respondent to the
appellant on or before 30.09.2003, but was paid only on 24.12.2004.
The learned Arbitrator rejected the said Counter Claim by holding that
the appellant had failed to lead any evidence in support of the said
claim.
83.
In this regard, we find merit in the contention of the learned
senior counsel for the appellant that once the claim is of delay in
payment of money, the person deprived of the use of money is
legitimately entitled, as a right, to be compensated for such
deprivation, including in form of interest for the delayed period,
however, at the same time, the learned Arbitrator has not based his
rejection on the sole basis of the appellant not leading evidence in
support of its claim of damages. The learned Arbitrator has agreed
with the submission of the respondent that the sum of USD 6.56
million had been deposited by the respondent in this Court, pursuant
to the Order of this Court on 26.09.2003, that is, much before the due
date of 30.09.2003. Later, the appellant filed an application seeking
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
release of the said amount, which was not permitted by the High
Court, vide its Order dated 13.09.2004, while adjourning the said
application to 19.01.2005. An application to advance the date of
hearing was also dismissed by this Court. Thereafter, the respondent
sent a notice to the appellant to settle accounts in terms of the
Agreement and, as the appellant failed to do so, filed another
application under Section 9 of the A&C Act, being O.M.P. 438/2004.
In the said O.M.P., in compliance with the Order dated 30.11.2004
passed by this Court, the respondent deposited USD 2.8 million also
in Court. In spite of the same, the appellant invoked the bank
guarantee and recovered USD 6.56 million on 24.12.2004.
84.
In these peculiar facts, the learned Arbitrator found that the
claim of damages for the alleged delayed payment was not
maintainable.
85.
We do not see any reason to disagree with the said finding of
the learned Arbitrator. In any case, appreciation of the evidence and
the effect thereof on the claim of a party, unless found to be
completely perverse or patently illegal, cannot be interfered with in
exercise of powers under Sections 34/37 of the A&C Act.
86.
Counter Claim no.2 of the appellant was on account of
broadcast and marketing of highlights and clippings of BCCI matches
by the respondent within India. The learned Arbitrator rejected the
said claim of the appellant by holding that though the appellant itself
had raised the said issue, however, it chose not to pursue the same as it
did not appoint an arbitrator to adjudicate the same. The learned
Arbitrator, therefore, held that the appellant was a by-stander who let
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
the train cross the station and cannot be allowed to raise this claim at a
belated stage.
87.
In this regard, we may only note that on an application filed by
the appellant under Section 9 of the A&C Act, the respondent, vide
Order dated 21.02.2003, had been restrained from marketing the
clippings and highlights of the matches within India. The respondent
challenged the same by way of an appeal, being FAO(OS) 129/2003,
and the order of the learned Single Judge was stayed by the Division
Bench, vide order dated 24.03.2003, noting that the appellant had
failed to take concrete steps to appoint an arbitrator. The appellant
now contends that it had invoked the arbitration vide a Notice dated
19.05.2003, receipt whereof is denied by the respondent. Reference of
this notice was not made by the appellant before the learned Arbitrator
or even before the learned Single Judge. Though, by an order dated
21.02.2005, the parties were referred to arbitration, allowing them to
raise their claims and Counter Claims, the said Counter Claim came to
be raised by the appellant only on 22.07.2006, that is, much beyond
the period of limitation. It was in these facts that the learned Arbitrator
held that the same cannot be allowed to be raised at this belated stage.
88.
This again, being a finding of facts, cannot be interfered with by
this Court in exercise of its power under Sections 34/37 of the A&C
Act.
89.
Counter Claim no.3 was raised by the appellant, claiming
unauthorised audio/video streaming of cricket matches on internet by
the respondent. The learned Arbitrator found that the appellant had
contended that these rights had been given to the respondent only by a
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Letter dated 18/19.02.2000, which was a separate Agreement and,
therefore, not subject to the Arbitration Agreement between the parties
contained in the Global Rights Agreement. The learned Arbitrator,
therefore, held that the appellant cannot be allowed to approbate and
reprobate on the same. The learned Arbitrator further held that the
appellant, having not raised this claim in the first arbitration
proceedings, the claim would be barred by the principles of
constructive res judicata.
90.
Though the learned senior counsel for the appellant has
contended that the appellant came to know of this violation of the
Agreement by the respondent only in October, 2003, and that the first
arbitrator had held that the dispute arising from Letter dated
18/19.02.2000 were also arbitrable, we are not impressed with the
challenge laid by the appellant.
91.
As noted hereinabove, the learned Arbitrator has held that the
appellant could have raised this claim in the first arbitration
proceedings. There is no clear answer to this from the appellant. In
fact, it appears that whether the respondent could have exploited its
right on the internet was a subject matter of the first arbitration
proceedings which culminated into an Award, challenge to which was
dismissed by this Court. Invoking of the principles of constructive res
judicata by the learned Arbitrator, therefore, cannot be faulted,
especially in exercise of the powers under Sections 34/37 of the A&C
Act.
92.
With the above, we conclude the challenge to the Arbitral
Award laid by the parties. However, as far as the challenge to the
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Impugned Order of the learned Single Judge is concerned, after the
passing of the Impugned Award, a further development has taken
place which has given rise to a further challenge to the Impugned
Order of the learned Single Judge by the appellant.
93.
As noted hereinabove, the learned Single Judge has held that
the finding of the learned Arbitrator of there being a shortfall of 17
cricketing days, cannot be sustained. The learned Single Judge has
held that the ten days of India-New Zealand-Australia Triangular
Series also need to be counted under the Global Rights Agreement and
therefore, there was a shortfall of only seven days. The learned Single
Judge has further held that for the shortfall of 7 days, the respondent
would be entitled to avail of its remedies in accordance with law.
94.
At the time of the passing of the Impugned Order, the
respondent had already filed an application seeking enforcement of the
Arbitral Award, being O.M.P. (ENF.)(COMM) 232/2018.
95.
A learned Single Judge of this Court, by order dated
15.06.2020, in those proceedings, held that for the 7 days of shortfall,
the Award still sustains and for which the appellant has to make
payment in terms of the Award. We quote from the order as under:
“13. Now coming to the question of
quantification of 7 days shortfall, what
emerges is that the learned Judge vide
deciding O.M.P.(COMM)225/2017 did not
deal with the calculation for either 17 days or
for 7 days, and therefore, left it to the DH to
raise a claim towards the amount payable to
it. This is, evidently, for the reason that the
award granted compensation on a per day
basis and, therefore, the quantification for 7
days shortfall was never really an issue.
Therefore, merely because no quantification
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
has been done by the learned Judge while
upholding a part of the award, it cannot be
said that no amount is payable to the DH. In
fact, the amount payable to the DH for 7 days
shortfall is crystal clear and needs no
determination even by this Court, especially in
view of the order dated 13.12.2018, read with
order dated 18.01.2019 passed in these very
proceedings. Para 13 of the order dated
13.12.2018 reads as under:"13. Therefore, for the moment, I am
inclined to direct Prasar Bharti to
deposit an amount equivalent to seven
(7) cricketing days.
13.1 According to Mr. Sharma, if 7
cricketing days is monetized the
principal amount would be a sum of
Rs.15,37,634.65.
13.2 To be noted, the learned Arbitrator
has also awarded interest at the rate of
18 per cent.
13.3 In my view, for the moment, simple
interest at the rate of 9 percent should
suffice.
13.4 Accordingly, Prasar Bharti is
directed to deposit Rs.15,37,634.65
along with interest at the rate of 9
percent for the period referred to in the
Award."
14. As the aforesaid order contained some
typographical errors regarding the amount,
the same came to be corrected on 18.01.2019,
on which date also, the learned counsel for the
JD did not dispute the figure of
Rs.15,37,634,65/- and accordingly, the JD was
directed to deposit a sum of Rs. 15,37,634,65/along with interest @ 9% p.a. for the shortfall
of 7 days, which is the period for which the
decree holder's claim has been upheld by the
Coordinate Bench. Pursuant to the said order,
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
the JD has duly deposited a sum of
Rs.33,69,94,847/-, seeking release whereof,
the present petition has been filed by the DH
No. 1.
*****
18. In the light of the aforesaid discussion,
specially the admitted position that the JD is
entitled to recover amounts under the 3
arbitral awards from the DH, I am of the view
that
while withholding
a sum of
Rs.22,43,55,126/- for the present, it would be
appropriate to direct release a sum of Rs. 11
crores in favour of the DH No. 1, out of the
sum of Rs.33,69,94,847/- as deposited by the
JD. The Registry is accordingly directed to
remit to DH No.1, a sum of Rs. 11 crores with
proportionate interest accrued thereon, out of
the sum deposited by the JD. The aforesaid
amount be transferred in Account No. CA
000984321151, Bank: Indian Bank, BranchSaket, New Delhi, ISFC: IDIB000S097.”
96.
This has led to a challenge by the appellant, which may be a
little confused. On the one hand the appellant submits that the learned
Enforcement Court cannot go behind the order of the learned Single
Judge and expand its scope in the enforcement proceedings and in this
regard, places reliance on the judgments of the Supreme Court in
Topanmal Chhotamal v. Kundomal Gangaram & Ors., (1959) SCC
OnLine SC 22, and Meenakshi Saxena & Anr. v. ECGC Limited &
Anr., (2018) 7 SCC 479, and on the other hand, it contends that the
learned Single Judge cannot modify the Award and, therefore, the
entire Award, that is even for those 7 days, is deemed to have been set
aside by the learned Single Judge leaving it open to the respondent to
avail of its remedies in accordance with law.
97.
As far as the powers of the Executing Court are concerned, it
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
cannot be disputed that the Executing Court cannot go behind the
Decree or expand its scope in the name of interpreting the Decree.
However, we would not like to go further into this issue, as no appeal
lies under Section 37 of the A&C Act against the order of the
Executing Court.
98.
On the second part of the challenge, however, by the Order
dated 14.09.2020 passed by the Supreme Court in SLP(C) No.
9884/2020, titled Prasar Bharati (Broadcasting Corporation of
India) v. Stracon India Limited & Anr., the Supreme Court has
observed that it is open to both the parties to argue all points in the
appeals that may be filed against the Impugned Order herein.
99.
As the respondent contends that by the Impugned Order, the
claim of the respondent for 7 days, on a pro-rata basis, stands
sustained by the learned Single Judge, we shall, therefore, have to
consider the challenge of the appellant to the Impugned Award on the
same basis.
100. In Gayatri Balasamy v. ISG Novasoft Technologies Limited,
(2025) 7 SCC 1, the Supreme Court has considered the powers of the
Court, under Sections 34/37 of the A&C Act, to modify an Arbitral
Award or to severe the severable part thereof which cannot be
sustained. By a majority, the Court held as under:
“34. To this extent, the doctrine of omne majus
continet in se minus-the greater power
includes the lesser-applies squarely. The
authority to set aside an arbitral award
necessarily encompasses the power to set it
aside in part, rather than in its entirety. This
interpretation is practical and pragmatic. It
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
would be incongruous to hold that power to set
aside would only mean power to set aside the
award in its entirety and not in part. A
contrary interpretation would not only be
inconsistent with the statutory framework but
may also result in valid determinations being
unnecessarily nullified.
35. However, we must add a caveat that not all
awards can be severed or segregated into
separate silos. Partial setting aside may not be
feasible when the "valid" and "invalid"
portions are legally and practically
inseparable. In simpler words, the "valid" and
"invalid" portions must not be interdependent
or intrinsically intertwined. If they are, the
award cannot be set aside in part.
36. The Privy Council, in Ram Protap
Chamria v. Durga Prosad Chamria addressed
this issue with the following pertinent
observations:
"18. ... if, however, the pronouncement of
the arbitrators is such that matters beyond
the scope of the suit are inextricably
bound up with matters falling within the
purview of the litigation, in that case, the
court would be unable to give effect to the
award because of the difficulty that it
cannot determine to what extent the
decision of the subject-matter of the
litigation has been affected and coloured
by the decision of the arbitrators in
regard to matters beyond the ambit of the
suit."
Thus, the power of partial setting aside should
be exercised only when the valid and invalid
parts of the award can be clearly segregated
particularly in relation to liability and
quantum and without any corelation between
valid and invalid parts.”
101. The Court further clarified the difference between setting aside
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
and modification of an award, and recognised a limited power of
modification of the Arbitral Award, by holding as under:
“52. Reference may also be made to the power
of recall, which every court possesses, as
recognised by this Court in Budhia Swain v.
Gopinath Deb. The availability of this power
enables the Court to address various situations
efficiently, rather than remanding the matter
to the Arbitral Tribunal under Section 34(4).
Lastly, one may also refer to the power of
granting interim relief f the circumstances so
warrant.
53. The doctrine of implied power is to only
effectuate and advance the object of the
legislation i.e. the 1996 Act and to avoid the
hardship. It would, therefore, be wrong to say
that the view expressed by us falls foul of
express provisions of the 1996 Act.
54. Under Section 152 of the Code, a court
executing a decree has the power to correct
clerical or arithmetic mistakes in judgments,
orders, or decrees arising from any accidental
slips or omissions. This Court in Century
Textiles Industries Ltd. v. Deepak Jain held
that clerical or arithmetical errors may be
corrected by the executing court, however, the
court must take the decree according to its
tenor and cannot go behind the decree.”
102. Hon‟ble Mr. Justice K.V. Viswanathan, in his dissenting
opinion in the said judgment, however, held that the power to modify
the Award cannot be said to be subsumed in the power to set aside,
nor can any such power be assumed by invoking inherent powers of
the court.
103. Applying the above principles, as laid down in the Majority
judgment, to the facts of the present case, the learned Arbitrator, in the
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
Impugned Award, has held that there was a shortfall of 17 cricketing
days and the same was quantified in terms of money on a pro-rata
reduction of the consideration under the Agreement. The learned
Single Judge held that for 10 days of India-Australia-New Zealand
Triangular Series, the Award cannot be sustained and therefore, the
total period of shortfall in cricketing days will be only 7 days. This
part being severable was, therefore, set aside. The Award for the
remaining 7 days, however, stood sustained.
104. As we have already upheld the Impugned Order on this aspect,
we are of the opinion that the challenge to the upholding of this
severable part of the Arbitral Award has no merit. The quantification
of recoverable amount for these 7 days is calculable on basis of the
Arbitral Award itself. As noted above, the Arbitral Award had held
that the consideration payable under the Global Marketing Agreement
was for 135 cricketing days and any shortfall therein will reduce the
consideration on a pro-rata basis. Therefore, for the 7 days, applying
the pro-rata reduction in the consideration as mentioned by the learned
Arbitrator and upheld by the learned Single Judge, the Award remains
enforceable against the appellant and in favour of the respondent.
Conclusion:
105. In view of the above, we find no merit in the challenge to the
Impugned Order of the learned Single Judge, as laid by the appellant
as also the respondent.
106. The appeals are, accordingly, dismissed. The applications are
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
disposed of as infructuous.
107. There shall be no order as to costs.
NAVIN CHAWLA, J.
MADHU JAIN, J.
JANUARY 23, 2026/ns/VS
Digitally Signed
FAO(OS) (COMM) 132/2020 & FAO(OS) (COMM) 179/2020
By:REYMON VASHIST
18:17:32
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review