COMAP No. 488 of 2024
ST
RESERVED ON 21
JULY 2026
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 16TH DAY OF SEPTEMBER, 2026
PRESENT
THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
AND
THE HON'BLE MRS. JUSTICE K.S. HEMALEKHA
COMMERCIAL APPEAL NO. 488 OF 2024
BETWEEN:
1.
STATE PROJECT DIRECTOR,
RASHTRIYA MADHYAMIKA
SHIKSHA ABHIYAN
NEW PUBLIC ANNEX BUILDING
N.T. ROAD, K.R. ROAD
BENGALURU - 560 001
…APPELLANT
(BY SRI KIRAN VASANTH RON, ADDITIONAL ADVOCATE GENERAL
A/W SRI K.S. HARISH, GOVERNMENT ADVOCATE)
AND:
1.
M/S. BSR INFRATECH INDIA LTD.,
NO 851, D BLOCK 15TH CROSS
SAHAKARNAGAR
BENGALURU - 560 092
REPRESNTED BY ITS DIRECTOR
SRI J. JAGPATHI CHOUDHARY
2.
SRI JUSTICE K.N. KESHAVANARAYANA
SOLE ARBITRATOR, ARBITRATION AND
CONCILLIATION CENTRE
BENGALURU (DOMESTIC AND INTERNATIONAL)
KANJIA BHAVANA
RACE COURSE ROAD
BENGALURU - 560 001
…RESPONDENTS
Digitally
signed by K
P SWETHA
Location:
High Court
of Karnataka
(BY SRI ZULFIKIR SHAFI, ADVOCATE FOR C/R-1)
-2-
COMAP No. 488 of 2024
THIS COMMERCIAL APPEAL IS FILED UNDER SECTION
13(1A) OF THE COMMERCIAL COURTS ACT, 2015 READ WITH
SECTION 37(1)(c) OF THE ARBITRATION AND CONCILIATION ACT,
1996 PRAYING TO CONSEQUENTLY SET ASIDE THE JUDGMENT
DATED 18.09.2024, PASSED IN COM.A.P NO.49/2024 ON THE FILE
OF HON'BLE LXXXIV ADDITIONAL CITY CIVIL AND SESSIONS
JUDGE AT BANGALORE & ETC.
THIS COMMERCIAL APPEAL HAVING BEEN HEARD AND
RESERVED FOR JUDGMENT, COMING ON FOR PRONOUNCEMENT
THIS DAY, JUDGMENT WAS PRONOUNCED AS UNDER:
CORAM: HON'BLE MR. VIBHU BAKHRU,CHIEF JUSTICE
and
HON'BLE MRS. JUSTICE K.S. HEMALEKHA
C.A.V. JUDGMENT
(PER: HON'BLE MR. VIBHU BAKHRU ,CHIEF JUSTICE)
1.
The
appellant,
the
State
Project
Director,
Rashtriya
Madhyamika Shikshana Abhiyana, has filed the present appeal
under Section 13(1A) of the Commercial Courts Act, 2015 [CC Act]
read with Section 37(1)(c) of the Arbitration and Conciliation Act,
1996 [A&C Act], impugning a judgment dated 18.09.2024
[impugned order] passed by the learned LXXXIV Additional City
Civil
and
Sessions
Judge,
Commercial
Court,
Bengaluru
[Commercial Court] in Com.A.P.No.49/2024. The appellant had
filed the said petition under Section 34 of the A&C Act seeking
setting aside of an arbitral award dated 10.11.2023 [impugned
award] rendered by the learned Sole Arbitrator [Arbitral Tribunal]
in A.C.No. 105/2021.
The learned Commercial Court found no
-3-
COMAP No. 488 of 2024
ground to interfere with the impugned award and accordingly passed
the impugned order dismissing the petition.
2.
Respondent No.1, M/s BSR Infratech India Ltd. [BSR], was the
claimant before the Arbitral Tribunal and the appellant was the
respondent. In terms of the impugned award, the Arbitral Tribunal
partly allowed BSR's claims and directed the appellant to pay a total
sum of `1,66,24,597/- (Rupees one crore sixty-six lakhs twenty-four
thousand
five
hundred
and
ninety-seven
only),
comprising
`1,06,11,447/- towards unproductive overhead charges (Claim
No.7(a)); and `60,13,150/- towards loss of expected profit (Claim
No.8); with future interest at 9% per annum from the date of the
award till payment; and `2,00,000/- towards costs (Claim No.12).
3.
The present appeal is one of a batch of five appeals, (COMAP
Nos.484/2024 to 488/2024), filed by the appellant against orders
passed by the learned Commercial Court dismissing the appellant's
petitions under Section 34 of the A&C Act, (Com.A.P.Nos.48/2024 to
52/2024) assailing separate Arbitral Awards rendered by the Arbitral
Tribunal constituted of Sole Arbitrator in respect of the contract of
nine packages awarded to M/s. KMV. The arbitral awards rendered
are substantially in similar terms and the issues involved in the said
nine appeals are also materially similar.
-4-
COMAP No. 488 of 2024
PREFATORY FACTS
4.
Rashtriya Madhyamika Shikshana Abhiyana [RMSA] is a
centrally sponsored scheme launched in the year 2009-10 by the
Ministry of Human Resource Development, Government of India, for
enhancing access to, and the quality of, secondary education. The
Government of Karnataka [GoK] implemented the scheme through
the appellant and took up 2,024 civil works under 77 packages
between 2009-10 and 2013-14. The said civil works involved
construction of new school buildings, Adarsha Vidyalayas [model
schools] and girls' hostels, and strengthening and upgradation of
existing schools at an aggregate cost of `1,645.70 crores. The
scheme has since been integrated with Samagra Shikshana
Karnataka (2018-19).
5.
On 24.09.2012, tenders were invited on a package basis
through the e-procurement portal in respect of works spread over
several districts of the State. BSR emerged the successful bidder in
respect of five packages. The present dispute pertains to Package
A-20 — Construction of Adarsha Vidyalaya and Girls Hostel
Buildings at various places in Raichur District [the subject
package], comprising 12 numbers of Adarsha Vidyalaya. After BSR
was declared as the successful bidder, the parties entered into
-5-
COMAP No. 488 of 2024
negotiations, and pursuant to said negotiations, BSR reduced its
quoted rates.
6.
After the negotiation meeting, BSR offered a revised price of
`30,45,05,000/-, being 9.53% above the updated estimate. It is
material to note that BSR stated that it was “ready to execute the
above project considering the inclusion of ‘Price Adjustment Clause’
at the said price. Thereafter, by Letter of Acceptance dated
18.03.2013 (Ex.C2), the appellant accepted the revised offer for a
contract price of `3,045.05 lakhs.
7.
The
parties
executed
a
Construction
Agreement
[the
Agreement] dated 15.05.2013 (Ex.C3), clause 4 of the agreement
stipulates that the letter of acceptance, the contract data, the
General Conditions of Contract and the Special Conditions of
Contract, among other documents, formed an integral part of the
agreement.
8.
Notice to proceed with the work was issued on 17.05.2013
(Ex.C4) and the stipulated period of completion was twenty months
therefrom,
which
expired
on
16.01.2015.
During
execution,
additional quantities and EIRL1 items were required to be executed.
Upon approval of the competent authority, the parties entered into a
Extra Items Rate List: unbudgeted items
-6-
COMAP No. 488 of 2024
Supplementary Agreement dated 24.03.2017 for additional work
and cost.
9.
There was delay in execution of the works it was not completed
within the stipulated period. During the period between 2013 and
2019, BSR addressed several letters to the appellant, inter alia,
alleging (i) delay in handing over sites; (ii) delay in supply of
drawings; (iii) delay in approval of work slips and EIRL items; (iv)
delay in release of payments; (v) non availability of water and power;
and (vi) scarcity of sand.
BSR invoked Clause 39 of the Conditions
of Agreement and raised the price adjustment. None of the said bills
were paid. The appellant, on the other hand, contended that no
price adjustment clause was applicable to the Agreement in respect
of the subject works.
10. In the meantime, under Government Order No. ED 49 MCD
2016 dated 16.11.2016, the GoK, while granting administrative
approval to a revised project cost of `1,717.24 crores excluding
price adjustment, the GoK directed (i) an audit by the Karnataka
Institute of Public Auditors [KIPA] into the causes of and
responsibility for the delay; and (ii) an enquiry into the issue of price
adjustment by a committee headed by an officer of the rank of
Additional Chief Secretary. The committee reported that the price
-7-
COMAP No. 488 of 2024
adjustment clause incorporated in the tender documents for the
RMSA civil works of 2009-10 and 2010-11 was not duly approved
and was not binding on the GoK.
11. The said Government Order and communication were
impugned by three other contractors namely, M/s Jampana
Constructions Pvt. Ltd., M/s NCC Ltd., and M/s KBR Infratech Pvt.
Ltd. in W.P. Nos.38613/2018, 35594/2018 and 34990/2018
respectively. By orders dated 25.02.2019 (Ex.R2), the learned
Single Judge of this Court quashed the Government Order dated
16.11.2016 and restrained the State from acting upon KIPA's reports
and suggestions. The court observed that whether Clause 39 was
incorporated with approval or inserted unauthorisedly is a disputed
question of fact, and relegated the petitioners to arbitration. The
intra-court appeals – W.A. Nos.958/2019, 996/2019 and 1031/2019
by the contractors, and W.A. No.2791/2019 by the State – were
disposed of by the Division Bench of this Court on 20.10.2020,
observing that "the parties would be governed by the terms of the
contract entered into by them in respect of various packages
awarded by the State".
12. By its letter dated 11.03.2019 (Ex.C40), BSR set out the
causes of delay and its claims; and by legal notice dated 08.05.2019
-8-
COMAP No. 488 of 2024
(Ex.C41), it invoked the arbitration agreement under Clause 24 of
the Conditions of Contract read with Clause 4 of the Special
Conditions of Contract.
13. The appellant responded by reply, contending, inter alia, that
the reference to arbitration was premature in view of the pendency
of the intra-court writ appeals.
14. BSR filed an application under Section 11 of the A&C Act
(C.M.P.No.260/2019) seeking appointment of an Arbitrator.
This
Court allowed the same by an order dated 05.11.2020 and
appointed a Sole Arbitrator to adjudicate the disputes between the
parties.
15. In the meanwhile, by Government Order No.EP 89 YYK 2020
dated 30.09.2020 (Ex.R2), the GoK, adopted the recommendations
of the Technical Advisory Committee in supersession of the KIPA
report, ordered that (i) for computing extension of time and penalty,
each work site in a package be treated as a separate unit; (ii) the
administration be held responsible for delays occasioned by causes
beyond the contractor's control; and (iii) price adjustment be allowed
in respect of the 25 packages whose tender conditions contained
the price adjustment clause. Admittedly, the sums due to BSR were
-9-
COMAP No. 488 of 2024
released only thereafter. By an order dated 13.01.2021 (Ex.R3),
extension of time was granted without penalty.
ARBITRAL PROCEEDINGS
16.
BSR filed its statement of claims before the Arbitral Tribunal
claiming an amount of `80,03,19,726/- (Rupees Eighty crores three
lakhs nineteen thousand seven hundred and twenty-six) under
twelve heads. The summary of claims as set out in the statement of
claims is reproduced below.
Claims
Claim amount
(Amt. in Rs.)
Particulars
Claim No.1
Payment
of
Adjustment/Escalation Bill
Price
Claim No.2
Payment of equitable enhanced rates
executed beyond tender completion
period.
Claim No.3
Payment of equitable enhanced rates
executed beyond Tender Completion
Period for extra Items.
4,53,24,186
2,91,75,505
Claim No.4
Payment of equitable enhanced rates
executed beyond Tender Completion
Period for quantities of 125%
Claim No.5
Refund of Excess Royalty Charges
19,81,068
Claim No.6
Payment
towards
idle
men,
machinery and establishment during
original tender period.
7,47,95,600
Claim No.7(a)
Payment of unproductive overhead
charges.
2,32,55,404
Claim No.7(b)
Payment
charges.
overhead
56,37,903
Claim No.8
Payment towards loss of expected
profit on the balance work as on
original tender completion date.
2,32,55,404
of
additional
- 10 -
COMAP No. 488 of 2024
Claim No.9(a)
Loss of expected profit due to nonreceipt of profit by tender completion
period.
11,62,77,020
Claim No.9(b)
Loss of expected profit due to nonreceipt of profit by actual completion
period.
2,73,72,950
Claim No.10
Payment towards additional Bank
Guarantee charges beyond original
agreement period.
5,98,370
Claim No.11
Payment towards interest on claim
amount calculated upto 31.12.2020 at
the rate of 24%.
45,08,47,944
Claim No.12
Payment of Rs.12,00,000/- (Rupees
Twelve Lakhs Only) towards Cost of
Litigation.
12,00,000
Total
17.
80,03,19,726
It was BSR's case that after it was declared a successful
bidder, it had reduced its rates by factoring in the price escalation
clause and the economies of scale. BSR claimed that the appellant
did not hand over the sites within the stipulated period despite
various requests. Thus, BSR was effectively prevented from
completing the contract within time, and the execution of the works
was prolonged. BSR alleged that the appellant also withheld
amounts due to BSR, which compelled BSR to seek reference of
disputes to arbitration.
18.
The respondent contended that the price variation clause
(clause 39) of the conditions of contract was not applicable as the
notice inviting tenders uploaded expressly provided that the said
- 11 -
COMAP No. 488 of 2024
clause be read as deleted. It is contended that this clause was
unauthorisedly included in the Agreement. Thus, the appellant was
not bound by the said price variation clause.
19.
On the basis of the pleadings between the parties, the Arbitral
Tribunal framed the following issues.
"1. Whether Claimant proves that non completion of the
works under the contract within the stipulated period was for
the reasons solely attributable to Respondent, resulting in
breach of contract by Respondent, as such, the delay in
completion of the works was solely attributable to
Respondent?
2. Whether for the reasons set out in SOC which were
beyond the control of Claimant, he was prevented from
completing the entire scope of work within the scheduled
contract period?
3. Whether Respondent proves that the delay in completion
of the works under the contract within the original period
stipulated under the contract was solely attributable to
Claimant?
4. Whether Respondent proves that as the requirements of
Clause 37.3 of Conditions of Contract have not been
complied with by Claimant, none of the claims put-forth in
SOC is tenable?
5. Whether the Claimant is entitled for payment of amounts
claimed under various heads as put-forth under claim Nos.1
to 8 of SOC?
6. Whether the Claimant is entitled for payment towards
past interest on the amounts claimed up to 31-12-2021 at
24% PA as claimed under claim No.9 of SOC?
7. Whether Claimant is entitled for current and future
interest at 24%PA on the amount claimed?
- 12 -
COMAP No. 488 of 2024
8. Whether Claimant is entitled for cost of this arbitral
proceeding?
9. To what order and award the parties are entitled to?"
20.
The Arbitral Tribunal, after examining the evidence and
materials placed on record, found that the non-completion of the
contract within the stipulated period was, in substantial part, for
reasons attributable to the appellant, while also finding that BSR
was partly responsible in certain respects. The Arbitral Tribunal
further rejected the appellant's contention that non-compliance with
Clause 38.4 of the Conditions of Contract rendered the claims not
tenable. However, on a consideration of the material placed on
record, the Arbitral Tribunal did not find merit in BSR's claim for price
adjustment and rejected the same in its entirety.
21.
The Arbitral Tribunal partly allowed claims No. 7(a) and 8
claim No. 12 was allowed in part. The Arbitral Tribunal also awarded
future interest and costs but rejected the remaining claims.
22.
The dispositive part of the impugned award is set out below:
"The claims of Claimant as put forth in Statement of
Claim are allowed in part as under:
(1) Claim No.7(a) is allowed in part in a sum of
Rs.1,06,11,447/- as against claim of Rs.2,32,55,404/-;
- 13 -
COMAP No. 488 of 2024
(2) Claim No.8 is allowed in part in a sum of Rs.60,13,150/only as against the claim of Rs.2,32,55,404/-;
(3) Respondent is directed to pay to Claimant a total sum of
Rs.1,66,24,597/- as per Sl.No.(1) and (2) above
together with future interest at the rate of 9% per annum
from the date of this Award till the date of payment;
(4) Claim No.12 is allowed in part in a sum of Rs.2,00,000/only as against claim of Rs.12,00,000/-. Respondent is
directed to pay to Claimant, this amount within a period
of 3 months from the date of this award failing which the
said amount shall carry interest at the rate of 9% per
annum from the date of award till the date of payment;
(5) Claim Nos. 1 to 6, 7(b), 9(a), 9(b), 10 and 11 are
rejected in their entirety;
(6) Claimant shall pay requisite stamp duty on this award
payable as per Karnataka Stamp Act;
With the pronouncement and publication of Award, this
Arbitral Proceeding stand terminated as per Section
32(1) of the Act."
23.
The impugned award was assailed by the appellant before the
learned Commercial Court in Com.A.P.No.49/2024 under Section 34
of the A&C Act. The learned Commercial Court, by the impugned
judgment
dated
18.09.2024,
found
no
infirmity
warranting
interference with the impugned award and dismissed the petition,
giving rise to the present appeal.
24.
As noted above, the learned Arbitral Tribunal had partly
allowed Claim No.7(a), which was towards unproductive overhead
charges. The learned Arbitral Tribunal had noted that there were no
- 14 -
COMAP No. 488 of 2024
averments made in the claim statement to support the said claim.
Further, even in the affidavit tendered by BSR's witness had not
stated anything in this regard. Paragraph 120 of the impugned
award reads as under:
"120. Respondent in its SO has contended
that these claims are beyond the original
tender period and the overhead charges are
inbuilt for the finished items of works and that
there is no provision in the agreement for
payment of unproductive overhead charges
beyond the original tender period, therefore,
these claims are beyond the scope of
arbitration as such Claimant is not entitled for
these claims."
25.
Although the statement of claims was bereft of any particulars
or the methodology used for quantification of Claim No.7(a), the
learned Arbitral Tribunal partly allowed the claim by applying the
Hudson Formula and assuming that the overheads charges
constituted 10% of the contract price. It is material to note that BSR
had made no such claim. The learned Arbitral Tribunal relied on the
cross-examination of P.W.1 during which a suggestion was put to
the witness that the overhead charges were included in the item
rates. In absence of any averments justifying the said claim and any
evidence led by BSR in this regard, the award for unproductive
overhead imposed is unsustainable.
- 15 -
COMAP No. 488 of 2024
26.
The learned Arbitral Tribunal also allowed the claim for loss of
profits (Claim No.8), inter alia, referring to the decision in the case of
the Supreme Court in A.T.Brij Paul Singh and Others v. State of
Gujarat2. On the said basis, the learned Arbitral Tribunal accepted
that the expected profit was 10% of the contract price. However, in
the present case, the contract was fully performed and it is evident
that BSR had realized the profit as included in the contract price.
Notwithstanding the same, the learned Arbitral Tribunal awarded
10% per annum of the expected profits included in the value of work
executed after the execution date. BSR had made no claim on such
basis. It had led no evidence as to the quantum of loss of profits. We
find no basis for awarding 10% p.a of the assured profits as loss of
profits for the prolongation of contract. In this view, the award
against claim No.8 is unsustainable.
27.
Claim No.12 is for costs. The award of costs, is premised on
BSR succeeding in Claim Nos.7 and 8. Since the award against
claim Nos.7 and 8 is set aside, the award against claim No.12 is
also unsustainable.
28.
The impugned award is in the similar terms as the arbitral
award which was subject matter of challenge in COMAP
(1984) 4 SCC 59
- 16 -
COMAP No. 488 of 2024
No.54/2025. The said appeal was allowed by this court by an order
dated 18.08.2026. The reasons set out in the said order fully cover
the issues involved in the present appeal as well. For the sake of
brevity, the same are not repeated in this order but may be read as
a part of the present order as well.
29.
In view of the above, the impugned award insofar as it awards
claim Nos.7(a), 8 and 12 and interest thereon, is set aside.
30.
The appeal is allowed in the aforesaid terms.
Sd/(VIBHU BAKHRU)
CHIEF JUSTICE
Sd/(K.S. HEMALEKHA)
JUDGE
KPS
This page is for informational and research purposes only and does not constitute legal advice.