Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
-1-
COMAP No. 486 of 2024
ST
RESERVED ON 21
JULY 2026
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 16TH DAY OF SEPTEMBER, 2026
PRESENT
THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
AND
THE HON'BLE MRS. JUSTICE K.S. HEMALEKHA
COMMERCIAL APPEAL NO. 486 OF 2024
BETWEEN:
1.
STATE PROJECT DIRECTOR
RASHTRIYA MADHYAMIKA
SHIKSHA ABHIYAN
NEW PUBLIC ANNEX BUILDING
N.T. ROAD, K.R. ROAD
BENGALURU - 560 001
…APPELLANT
(BY SRI KIRAN VASANTH RON, ADDITIONAL ADVOCATE GENERAL
A/W SRI K.S. HARISH, GOVERNMENT ADVOCATE)
AND:
1.
M/S. BSR INFRATECH INDIA LTD.,
NO 851, D BLOCK, 15TH CROSS
SAHAKARNAGAR
BENGALURU - 560 092
REPRESNTED BY ITS DIRECTOR
SRI J. JAGPATHI CHOUDHARY
2.
SRI JUSTICE K.N. KESHAVANARAYANA
SOLE ARBITRATOR, ARBITRATION AND
CONCILIATION CENTRE BENGALURU
(DOMESTIC AND INTERNATIONAL)
KANJIA BHAVANA
RACE COURSE ROAD
BENGALURU - 560 001
Digitally
signed by K
P SWETHA
Location:
High Court
of Karnataka
…RESPONDENTS
(BY SRI ZULFIKIR SHAFI, ADVOCATE FOR C/R-1)
-2-
COMAP No. 486 of 2024
THIS COMMERCIAL APPEAL IS FILED UNDER SECTION
13(1A) OF THE COMMERCIAL COURTS ACT, 2015 READ WITH
SECTION 37(1)(c) OF THE ARBITRATION AND CONCILIATION ACT,
1996 PRAYING TO SET ASIDE THE JUDGMENT DATED 18.09.2024,
PASSED IN COM.A.P NO.51/2024 ON THE FILE OF THE HON'BLE
LXXXIV ADDITIONAL CITY CIVIL AND SESSIONS JUDGE AT
BANGALORE & ETC.
THIS COMMERCIAL APPEAL HAVING BEEN HEARD AND
RESERVED FOR JUDGMENT, COMING ON FOR PRONOUNCEMENT
THIS DAY, JUDGMENT WAS PRONOUNCED AS UNDER:
CORAM: HON'BLE MR. VIBHU BAKHRU ,CHIEF JUSTICE
and
HON'BLE MRS. JUSTICE K.S. HEMALEKHA
C.A.V. JUDGMENT
(PER: HON'BLE MR. VIBHU BAKHRU ,CHIEF JUSTICE)
1.
The
appellant,
the
State
Project
Director,
Rashtriya
Madhyamika Shikshana Abhiyana, has filed the present appeal
under Section 13(1A) of the Commercial Courts Act, 2015 [CC Act]
read with Section 37(1)(c) of the Arbitration and Conciliation Act,
1996 [A&C Act], impugning a judgment dated 18.09.2024
[impugned order] passed by the learned LXXXIV Additional City
Civil and Sessions Judge, Commercial Court, Bengaluru (CCH-85)
[Commercial Court] in Com.A.P.No.51/2024. The appellant had
filed the said petition under Section 34 of the A&C Act seeking
setting aside of an arbitral award dated 10.11.2023 [impugned
-3-
COMAP No. 486 of 2024
award] rendered by the learned Sole Arbitrator [Arbitral Tribunal]
in A.C. No. 106/2021. The learned Commercial Court found no
ground to interfere with the impugned award and accordingly
passed the impugned order dismissing the petition.
2.
Respondent No.1, M/s. BSR Infratech India Ltd. [BSR], was
the claimant before the Arbitral Tribunal and the appellant was the
respondent. In terms of the impugned award, the Arbitral Tribunal
partly allowed BSR's claims and directed the appellant to pay a
total sum of `1,18,99,858/- (Rupees one crore eighteen lakhs
ninety-nine thousand eight hundred and fifty-eight only), comprising
`75,85,656/- towards unproductive overhead charges (Claim
No.7(a)); and `43,04,202/- towards loss of expected profit (Claim
No.8); with future interest at 9% per annum from the date of the
award till payment; and `2,00,000/- towards costs (Claim No.12).
3.
The present appeal is one of a batch of nine appeals,
(COMAP Nos.484/2024 to 488/2024), filed by the appellant against
orders passed by the learned Commercial Court dismissing the
appellant's
petitions
under
Section
of
the
A&C
Act,
(Com.A.P.Nos.48/2024 to 52/2024) assailing separate Arbitral
Awards rendered by the Arbitral Tribunal constituted of Sole
-4-
COMAP No. 486 of 2024
Arbitrator in respect of the contract of nine packages awarded to
M/s. BSR. The arbitral awards rendered are substantially in similar
terms and the issues involved in the said nine appeals are also
materially similar.
PREFATORY FACTS
4.
Rashtriya Madhyamika ShikshanaAbhiyana [RMSA] is a
centrally sponsored scheme launched in the year 2009-10 by the
Ministry of Human Resource Development, Government of India,
for enhancing access to, and the quality of, secondary education.
The Government of Karnataka [GoK] implemented the scheme
through the appellant and took up civil works under 77 packages
from 2013-14. The said civil works involved construction of new
school buildings, Adarsha Vidyalayas[model schools] and girls'
hostels, and strengthening and upgradation of existing schools.
The scheme has since been integrated with SamagraShikshana
Karnataka (2018-19).
5.
On 24.09.2012, tenders were invited on a package basis
through the e-procurement portal, for construction of model schools
and upgrading and strengthening of existing government high
schools in several districts of the State, for a total of 52 packages.
-5-
COMAP No. 486 of 2024
BSR was awarded works under 4 packages by way of the prequalification tender, and a further package (Package A-2) by way of
open tender, aggregating to 5 packages comprising 45 work sites.
The present dispute pertains to one such package, namely
Package A-16 — construction of Adarsha Vidyalaya at Kustagi,
Gangavathi and Yelaburga Blocks, and Girls' Hostels at Kustagi,
Gangavathi, Yelaburga and Koppa Block, Koppal District [the
subject package]. After BSR was declared as the successful
bidder, the parties entered into negotiations, and pursuant to said
negotiations, BSR reduced its quoted rates.
6.
The negotiated price of `2,316.94 lakhs offered by BSR in
respect of Package A-16 was accepted, and work was awarded to
BSR by Letter of Acceptance dated 18.03.2013 (Ex.C2), for the
said contract price.
7.
After BSR furnished the requisite security deposit by way of
bank guarantees, the parties executed a Construction Agreement
[the Agreement] dated 15.05.2013 (Ex.C3), comprising General
Conditions of Contract and Special Conditions of Contract, for
execution of the works under Package A-16.
-6-
COMAP No. 486 of 2024
8.
The notice to proceed with the work was issued on
07.05.2013 (Ex.C4), and the stipulated period of completion was
twenty months therefrom. During execution, additional quantities
and EIRL1 items were required to be executed. Upon approval of
the competent authority the parties entered into a Supplementary
Agreement dated 24.03.2017, inclusive of the additional cost,
pursuant to which the percentage of the amount earlier withheld
from BSR came to be released.
9.
There was delay in execution of the works, and they were not
completed within the stipulated period. BSR addressed several
letters to the appellant, inter alia, alleging (i) delay in supply of
agreement copies and signing of conditions of contract; (ii) delay in
handing over sites; (iii) delay in performance of pooja; (iv) delay in
supply of drawings; (v) non-availability of water and power; (vi)
scarcity of sand; (vii) increase in quantity; (viii) delay in payment;
(ix) delay in approval of work slips/EIRL items; (x) increase in cost
of material due to shortage; (xi) loss of working season; and (xii)
extension of bank guarantees. BSR invoked the price adjustment
clause of the Conditions of Contract and raised its claim towards
price adjustment; none of the said bills were paid. The appellant,
Extra Items Rate List: unbudgeted items
-7-
COMAP No. 486 of 2024
on the other hand, contended that no price adjustment clause was
applicable to the Agreement in respect of the subject works.
10.
In the meantime, under Government Order No.ED 49 MCD
2016 dated 16.11.2016, the GoK, while granting administrative
approval to a revised project cost directed (i) an audit by the
Karnataka Institute of Public Auditors [KIPA] into the causes of,
and responsibility for, the delay; and (ii) an enquiry into the issue of
price adjustment by a committee headed by an officer of the rank of
Additional Chief Secretary. The committee reported that the price
adjustment clause incorporated in the tender documents for the
RMSA civil works of 2009-10 and 2010-11 was not duly approved
and was not binding on the GoK. By a communication dated
17.07.2018, the State Project Director informed the contractors that
price adjustment would not be paid and that extension of time
would be considered only upon giving up their contractual claims in
that behalf.
11.
The said Government Order was impugned by three other
contractors, namely M/s. Jampana Constructions Pvt. Ltd., M/s.
NCC
Ltd.
and
M/s.
KBR
Infratech
Pvt.
Ltd.,
in
W.P.
Nos.38613/2018, 35594/2018 and 34990/2018 respectively. By
-8-
COMAP No. 486 of 2024
orders dated 25.02.2019 (Ex.R4, R5 and R6), the learned Single
Judge of this Court quashed the Government Order dated
16.11.2016 in W.P.No.38613/2018, and disposed of the other two
writ petitions in similar terms. As of the appellant's letter dated
11.06.2019, the intra-court appeals against the said orders — W.A.
Nos.958/2019, 996/2019 and 1031/2019 by the contractors, and
W.A. No.2791/2019 by the State — were stated to be pending
before the Division Bench of this Courton 20.10.2020, observing
that "the parties would be governed by the terms of the contract
entered into by them in respect of various packages awarded by
the State".
12.
By its letter dated 11.03.2019, BSR called upon the appellant
to consider its claims and to invoke the dispute resolution
mechanism under Clause 24 of the Conditions of Contract read
with Clause 4 of the Special Conditions of Contract. As the
appellant did not respond, BSR issued a legal notice dated
08.05.2019, invoking the arbitration agreement under the same
clauses.
-9-
COMAP No. 486 of 2024
13.
The appellant responded by letter dated 11.06.2019,stating
that the claims stood rejected in its earlier office communication,
and that reference to arbitration was premature in view of the
pendency of the intra-court writ appeals.
14.
BSR filed an application under Section 11of the A&C Act
(C.M.P.No.262/2019), seeking appointment of an Arbitrator. This
Court allowed the same by order dated 05.11.2020 and appointed
a Sole Arbitrator to adjudicate the disputes between the parties.
15.
In the meanwhile, by Government Order No. EP 89 YYK
2020 dated 30.09.2020, the GoK adopted the recommendations of
the Technical Advisory Committee in supersession of the KIPA
report, ordered, inter alia, that (i) for computing extension of time
and penalty, each work site in a package be treated as a separate
unit; (ii) the administration be held responsible for delays
occasioned by causes beyond the contractor's control; and (iii)
price adjustment be allowed in respect of the 25 packages whose
tender conditions contained a price adjustment clause — a
category which, as noticed in paragraph 8 above, did not include
Package A-16. By an order dated 13.01.2021, extension of time
was granted to BSR without levy of penalty.
- 10 -
COMAP No. 486 of 2024
ARBITRAL PROCEEDINGS
16.
BSR filed its Statement of Claims [SOC] before the Arbitral
Tribunal claiming an amount of `80,03,19,726/- (Rupees Eighty
crores Three lakhs Nineteen thousand Seven hundred and Twentysix only) under twelve heads. together with interest at 24% per
annum from the date of the claim petition till payment, and costs.
The summary of claims as set out in the statement of claims is
reproduced below:
Claims
Particulars
Claim Amount
(Amt. in Rs.)
4,53,24,186
Claim No.1 Payment of Price
Adjustment/Escalation Bill
Claim No.2 Payment of equitable enhanced rates
executed beyond tender completion
period.
Claim No.3 Payment of equitable enhanced rates 2,91,75,505
executed beyond Tender Completion (Claims 2-4)
Period for extra Items.
Claim No.4 Payment of equitable enhanced rates
executed beyond Tender Completion
Period for quantities of 125%
Claim No.5 Refund of Excess Royalty Charges
19,81,068
Claim No.6 Payment towards idle men, machinery 7,47,95,600
and establishment during original
tender period.
Claim
Payment of unproductive overhead
2,32,55,404
No.7(a)
charges.
Claim
Payment of additional overhead
56,37,903
No.7(b)
charges.
Claim No.8 Payment towards loss of expected
2,32,55,404
profit on the balance work as on
original tender completion date.
Claim
Loss of expected profit due to non11,62,77,020
- 11 -
COMAP No. 486 of 2024
No.9(a)
Total
receipt of profit by tender completion
period.
Loss of expected profit due to non2,73,72,950
receipt of profit by actual completion
period.
Payment towards additional Bank
5,98,370
Guarantee charges beyond original
agreement period
Payment towards interest on claim
45,08,47,944
amount calculated up to 31.12.2020 at
the rate of 24%.
Payment of Rs.12,00,000/- (Rupees 12,00,000
Twelve Lakhs Only) towards Cost of
Litigation.
80,03,19,726
17.
It was BSR's case that after it was declared the successful
Claim
No.9(b)
Claim
No.10
Claim
No.11
Claim
No.12
bidder, it had reduced its rates by factoring in the price escalation
clause and the economies of scale. BSR claimed that the appellant
did not hand over the sites within the stipulated period despite
various requests, and delayed approval of drawings, work slips and
EIRL items, thereby preventing BSR from completing the contract
within time and prolonging the execution of the works. BSR alleged
that the appellant also withheld amounts due to it, which compelled
BSR to seek reference of the disputes to arbitration.
18.
The appellant contended that no price adjustment clause
was applicable to the Agreement in respect of the subject works,
and that, in any event, the conditions of contract as forthcoming in
- 12 -
COMAP No. 486 of 2024
the e-procurement portal, which were binding on the parties,
specifically excluded price adjustment. The appellant further
contended that the delay, if any, had been suitably compensated
by extension of time granted without imposition of penalty, and that
the
claims,
aggregating
Rs.80,03,19,726/-,
were
fictitious,
unsubstantiated and beyond the scope of arbitration.
19.
On the basis of the pleadings between the parties, the
Arbitral Tribunal, on 04.02.2022, framed the following issues.
"1. Whether Claimant proves that non completion of
the works under the contract within the stipulated
period was for the reasons solely attributable to
Respondent, resulting in breach of contract by
Respondent, as such, the delay in completion of the
works was solely attributable to Respondent?
2. Whether for the reasons set out in SOC which
were beyond the control of Claimant, he was
prevented from completing the entire scope of work
within the scheduled contract period?
3. Whether Respondent proves that the delay in
completion of the works under the contract within the
original period stipulated under the contract was
solely attributable to Claimant?
4. Whether Respondent proves that as the
requirements of Clause 38.4 of Conditions of
Contract have not been complied with by Claimant,
none of the claims put forth in SOC is tenable?
- 13 -
COMAP No. 486 of 2024
5. Whether the Claimant is entitled for payment of
the amounts claimed under various heads as put
forth under Claim Nos.1 to 10 of SOC?
6. Whether the Claimant is entitled for payment
towards past interest on the amounts claimed up to
31-12-2020 at 24% PA as claimed under Claim
No.11 of SOC?
7. Whether Claimant is entitled for current and future
interest at 24% PA on the amount claimed?
8. Whether Claimant is entitled for cost of this arbitral
proceeding?
9. To what order and award the parties are entitled
to?"
20.
The Arbitral Tribunal, after examining the evidence and
materials placed on record, found that non-completion of the
contract within the stipulated period was, on account of delay in
handing over sites in several locations comprised in Package A-16
and delay in issuing drawings and revised drawings, was for
reasons attributable to the appellant, resulting in breach of contract
by the appellant.
21.
The Arbitral Tribunal partly allowed Claim Nos. 7(a), 8 and
12. The Arbitral Tribunal also awarded future interest and costs but
rejected the remaining claims, being Claim Nos.1 to 6, 7(b), 9(a),
9(b), 10 and 11, in their entirety.
- 14 -
COMAP No. 486 of 2024
22.
The dispositive part of the impugned award is set out below:
"The claims of Claimant as put forth in Statement of
Claim are allowed in part as under:
(1) Claim No.7(a) is allowed in part in a sum of
Rs.75,85,656/- as against claim of Rs.2,32,55,404/-;
(2) Claim No.8 is allowed in part in a sum of
Rs.43,04,202/- only as against the claim of
Rs.2,32,55,404/-;
(3) Respondent is directed to pay to Claimant a total
sum of Rs.1,18,99,858/- as per Sl.No.(1) to (2)
above together with future interest at the rate of 9%
per annum from the date of this Award till the date of
payment;
(4) Claim No.12 is allowed in part in a sum of
Rs.2,00,000/only
as
against
claim
of
Rs.12,00,000/-. Respondent is directed to pay to
Claimant, this amount within a period of 3 months
from the date of this award failing which the said
amount shall carry interest at the rate of 9% per
annum from the date of award till the date of
payment;
(5) Claim Nos.1 to 6, 7(b), 9(a), 9(b), 10 and 11 are
rejected in their entirety;
(6) Claimant shall pay requisite stamp duty on this
award payable as per Karnataka Stamp Act,
With the pronouncement and publication of Award,
this Arbitral Proceeding stand terminated as per
Section 32(1) of the Act."
- 15 -
COMAP No. 486 of 2024
23.
The impugned award was assailed by the appellant before the
learned Commercial Court in Com.A.P.No.51/2024 under Section 34
of the A&C Act. The learned Commercial Court, by the impugned
judgment
dated
18.09.2024,
found
no
infirmity
warranting
interference with the impugned award and dismissed the petition,
giving rise to the present appeal.
24.
As noted above, the learned Arbitral Tribunal had partly
allowed Claim No.7(a), which was towards unproductive overhead
charges. The learned Arbitral Tribunal had noted that there were no
averments made in the claim statement to support the said claim.
Further, even in the affidavit tendered by BSR's witness (P.W.1) had
not stated anything in this regard. Paragraph 121 of the impugned
award reads as under:
"121. Respondent in its SO has contended
that these claims are beyond the original
tender period and the overhead charges
are inbuilt for the finished items of works
and that there is no provision in the
agreement for payment of unproductive
overhead charges beyond the original
tender period, therefore, these claims are
beyond the scope of arbitration as such
Claimant is not entitled for these claims."
- 16 -
COMAP No. 486 of 2024
25.
Although the statement of claims was bereft of any particulars
or the methodology used for quantification of Claim No.7(a), the
learned Arbitral Tribunal partly allowed the claim by applying the
Hudson Formula and assuming that the overheads charges
constituted 10% of the contract price. It is material to note that BSR
had made no such claim. The learned Arbitral Tribunal relied on the
cross-examination of P.W.1 during which a suggestion was put to
the witness that the overhead charges were included in the item
rates. In absence of any averments justifying the said claim and any
evidence led by BSR in this regard, the award for unproductive
overhead imposed is unsustainable.
26.
The learned Arbitral Tribunal also allowed the claim for loss of
profits (Claim No.8), inter alia, referring to the decision in the case of
the Supreme Court in A.T.Brij Paul Singh and Others v. State of
Gujarat2. On the said basis, the learned Arbitral Tribunal accepted
that the expected profit was 10% of the contract price. However, in
the present case, the contract was fully performed and it is evident
that BSR had realized the profit as included in the contract price.
Notwithstanding the same, the learned Arbitral Tribunal awarded
10% per annum of the expected profits included in the value of work
(1984) 4 SCC 59
- 17 -
COMAP No. 486 of 2024
executed after the execution date. BSR had made no claim on such
basis. It had led no evidence as to the quantum of loss of profits. We
find no basis for awarding 10% p.a of the assured profits as loss of
profits for the prolongation of contract. In this view, the award
against claim No.8 is unsustainable.
27.
Claim No.12 is for costs. The award of costs, is premised on
BSR succeeding in Claim Nos.7 and 8. Since the award against
claim Nos.7 and 8 is set aside, the award against claim No.12 is
also unsustainable.
28.
The impugned award is in the similar terms as the arbitral
award which was subject matter of challenge in COMAP
No.54/2025. The said appeal was allowed by this court by an order
dated 18.08.2026. The reasons set out in the said order fully cover
the issues involved in the present appeal as well. For the sake of
brevity, the same are not repeated in this order but may be read as
a part of the present order as well.
29.
In view of the above, the impugned award insofar as it awards
claim Nos.7(a), 8 and 12 and interest thereon, is set aside.
- 18 -
COMAP No. 486 of 2024
30.
The appeal is allowed in the aforesaid terms.
Sd/(VIBHU BAKHRU)
CHIEF JUSTICE
Sd/(K.S. HEMALEKHA)
JUDGE
KPS
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review