COMAP No. 485 of 2024
ST
RESERVED ON 21
JULY 2026
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 16TH DAY OF SEPTEMBER, 2026
PRESENT
THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
AND
THE HON'BLE MRS. JUSTICE K.S. HEMALEKHA
COMMERCIAL APPEAL NO. 485 OF 2024
BETWEEN:
1.
STATE PROJECT DIRECTOR
RASHTRIYA MADHYAMIKA
SHIKSHA ABHIYAN
NEW PUBLIC ANNEX BUILDING
N.T. ROAD, K.R. ROAD
BENGALURU - 560 001
…APPELLANT
(BY SRI KIRAN VASANTH RON, ADDITIONAL ADVOCATE GENERAL
A/W SRI K.S. HARISH, GOVERNMENT ADVOCATE)
AND:
Digitally
signed by K
P SWETHA
Location:
High Court
of Karnataka
1.
M/S. BSR INFRATECH INDIA LTD.,
No.851, D BLOCK, 15TH CROSS
SAHAKARNAGAR
BENGALURU - 560 092
REPRESNTED BY ITS DIRECTOR
SRI J. JAGPATHI CHOUDHARY
2.
SRI JUSTICE K.N. KESHAVANARAYANA
SOLE ARBITRATOR
ARBITRATION AND CONCILIATION CENTRE
BENGALURU (DOMESTIC AND INTERNATIONAL)
KANJIA BHAVANA, RACE COURSE ROAD
BENGALURU - 560 001
…RESPONDENTS
(BY SRI ZULFIKIR SHAFI, ADVOCATE FOR C/R-1)
-2-
COMAP No. 485 of 2024
THIS COMMERCIAL APPEAL IS FILED UNDER SECTION
13(1A) OF THE COMMERCIAL COURTS ACT, 2015 READ WITH
SECTION 37(1)(c) OF THE ARBITRATION AND CONCILIATION ACT,
1996 PRAYING TO SET ASIDE THE JUDGMENT DATED 18.09.2024,
PASSED IN COM.A.P NO.52/2024 ON THE FILE OF HON'BLE LXXXIV
ADDITIONAL CITY CIVIL AND SESSIONS JUDGE, AT BANGALORE &
ETC.
THIS COMMERCIAL APPEAL HAVING BEEN HEARD AND
RESERVED FOR JUDGMENT, COMING ON FOR PRONOUNCEMENT
THIS DAY, JUDGMENT WAS PRONOUNCED AS UNDER:
CORAM: HON'BLE MR. VIBHU BAKHRU ,CHIEF JUSTICE
and
HON'BLE MRS. JUSTICE K.S. HEMALEKHA
C.A.V. JUDGMENT
(PER: HON'BLE MR. VIBHU BAKHRU ,CHIEF JUSTICE)
1.
The
appellant,
the
State
Project
Director,
Rashtriya
Madhyamika Shikshana Abhiyana, has filed the present appeal
under Section 13(1A) of the Commercial Courts Act, 2015 [CC Act]
read with Section 37(1)(c) of the Arbitration and Conciliation Act,
1996 [A&C Act], impugning a judgment dated 18.09.2024
[impugned judgment] passed by the learned LXXXIV Additional
City Civil and Sessions Judge, Commercial Court, Bengaluru
(CCH-85) [Commercial Court] in Com.A.P.No.52/2024. The
appellant had filed the said petition under Section 34 of the A&C
Act seeking setting aside of an arbitral award dated 10.11.2023
-3-
COMAP No. 485 of 2024
[impugned award] rendered by the learned Sole Arbitrator
[Arbitral Tribunal], in A.C.No.107/2021. The learned Commercial
Court found no ground to interfere with the impugned award and
accordingly passed the impugned judgment dismissing the petition.
2.
Respondent No.1, M/s BSR Infratech India Ltd. [BSR], was
the claimant before the Arbitral Tribunal and the appellant was the
respondent. In terms of the impugned award, the Arbitral Tribunal
partly allowed BSR's claims and directed the appellant to pay a
total sum of `2,83,23,688/- (Rupees two crores eighty-three lakhs
twenty-three thousand six hundred and eighty-eight only) together
with future interest at 9% per annum from the date of the award till
payment,
comprising
`1,80,78,950/-
towards
unproductive
overhead charges, as against the claim of `2,32,55,404/- (Claim
No.7(a)); and `1,02,44,738/- towards loss of expected profit, as
against the claim of `2,32,55,404/- (Claim No.8); and `2,00,000/towards costs (Claim No.12), as against the claim of `12,00,000/-.
3.
The present appeal is one of a batch of five appeals,
(COMAP Nos.484/2024 to 488/2024), filed by the appellant against
orders passed by the learned Commercial Court dismissing the
appellant's
petitions
under
Section
of
the
A&C
Act,
-4-
COMAP No. 485 of 2024
(Com.A.P.Nos.48/2024 to 52/2024) assailing separate Arbitral
Awards rendered by the Arbitral Tribunal constituted of a Sole
Arbitrator in respect of the contract of five packages awarded to
M/s. BSR. The arbitral awards rendered are substantially in similar
terms and the issues involved in the said five appeals are also
materially similar.
PREFATORY FACTS
4.
Rashtriya Madhyamika Shikshana Abhiyana [RMSA] is a
centrally sponsored scheme launched in the year 2009-10 by the
Ministry of Human Resource Development, Government of India,
for enhancing access to, and the quality of, secondary education.
The Government of Karnataka [GoK] implemented the scheme
through the appellant and took up 2,024 civil works under 77
packages between 2009 and 2015. The said civil works involved
construction of new school buildings, Adarsha Vidyalayas [model
schools] and girls' hostels, and strengthening and upgradation of
existing schools at an aggregate cost of `1,645.70 crores. The
scheme has since been integrated with Samagra Shikshana
Karnataka in 2018-19.
-5-
COMAP No. 485 of 2024
5.
On 24.09.2012, tenders were invited on a package basis
through the e-procurement portal in respect of works spread over
thirty districts of the State, for a total of 52 packages. BSR
emerged the successful bidder in respect of five packages. The
present dispute pertains to Package A-19 - Construction of
Adarsha Vidyalayas at K.R. Nagar, Mysore, H.D. Kote, Nanjangud,
Hunsur and T. Narasipura, and Girls' Hostel at K.R. Nagar Block, of
Mysore District [the subject package] - comprising six Adarsha
Vidyalayas and one Girls' Hostel spread over seven work sites.
After BSR was declared as the lowest bidder (L1), the parties
entered into negotiations, pursuant to which BSR agreed to a
contract price of `30,74,26,000/- (`3074.26 lakhs).
6.
By Letter of Acceptance dated 18.03.2013 (Ex.C2), the
appellant accepted BSR's offer for the said contract price in respect
of the subject package, and called upon BSR to furnish the
requisite security deposit.
7.
The parties executed a Construction Agreement [the
Agreement] dated 15.05.2013 (Ex.C3) for execution of the works
under Package A-19. Clause 4 of the Agreement stipulates that the
Letter of Acceptance, the Contract Data, the Conditions of
-6-
COMAP No. 485 of 2024
Contract, and the Special Conditions of Contract, among other
documents, formed an integral part of the Agreement.
8.
The notice to proceed with the work was issued on
17.05.2013 (Ex.C4) and the stipulated period of completion was
twenty months therefrom, the tender completion date being
14.01.2015. During execution, additional quantities and EIRL items
were required to be executed. Upon approval of the competent
authority, the parties entered into a Supplementary Agreement
dated 24.03.2017 for the additional work and cost, and the revised
contract value was determined at `3460.09 lakhs as against the
original contract price of `3074.26 lakhs.
9.
There was delay in execution of the works and they were not
completed within the stipulated period. BSR attributed the delay,
inter alia, to (i) delay in handing over sites; (ii) delay in supply of
drawings; (iii) delay in approval of work slips and EIRL items; (iv)
delay in release of payments; and (v) scarcity of materials and
labour on account of the scattered nature of the work sites. BSR
invoked the price adjustment clause of the Conditions of Contract
and raised its claim towards price adjustment; none of the said bills
were paid. The appellant, on the other hand, contended that no
-7-
COMAP No. 485 of 2024
price adjustment clause was applicable to the Agreement in
respect of the subject works.
10.
In the meantime, under Government Order No. ED 49 MCD
2016 dated 16.11.2016, the GoK, while granting administrative
approval to a revised project cost, directed (i) an audit by the
Karnataka Institute of Public Auditors [KIPA] into the causes of and
responsibility for the delay; and (ii) an enquiry into the issue of
price adjustment by a committee headed by an officer of the rank
of Additional Chief Secretary. The committee reported that the
price adjustment clause incorporated in the tender documents for
the RMSA civil works of 2009-10 and 2010-11 was not duly
approved and was not binding on the GoK.
11.
The said Government Order was impugned by three
contractors, namely, M/s Jampana Constructions Pvt. Ltd., M/s
NCC
Ltd.,
and
M/s
KBR
Infratech
Pvt.
Ltd.,
in
W.P.
Nos.38613/2018, 35594/2018 and 34990/2018 respectively. By
orders dated 25.02.2019, a learned Single Judge of this Court
quashed the Government Order dated 16.11.2016 and restrained
the State from acting upon KIPA's reports and suggestions,
observing
that
whether
the
price
adjustment
clause
was
incorporated with approval or inserted unauthorisedly is a disputed
-8-
COMAP No. 485 of 2024
question of fact, and relegated the petitioners to arbitration. The
intra-court appeals were disposed of by a Division Bench of this
Court observing that the parties would be governed by the terms of
the contract entered into by them in respect of the various
packages awarded by the State.
12.
By Government Order dated 30.09.2020 (Ex.R2), the GoK
adopted the recommendations of a Technical Advisory Committee
and directed, among other things, that (i) extension of time and the
resultant penalty be ascertained in respect of each work site
individually, instead of the package as a whole; (ii) the
administration be held responsible for delay caused on account of
reasons beyond the control of the contractor; and (iii) price
adjustment be allowed in respect of the 25 packages whose tender
conditions contained the price adjustment clause. By an order
dated 13.01.2021(Ex.R3), extension of time was granted to BSR
without penalty.
13.
By its letter dated 11.03.2019 (Ex.C40), BSR set out the
causes of delay and its claims and sought favourable consideration
thereof, and sought to invoke the dispute resolution mechanism
under Clause 23 of the Conditions of Contract read with Clause 4
-9-
COMAP No. 485 of 2024
of the Special Conditions of Contract; and by legal notice dated
08.05.2019 (Ex.C41), it invoked the arbitration agreement,
attributing breach of contract to the appellant.
14.
The appellant responded by reply dated 11.06.2019
(Ex.C42), contending, inter alia, that the reference to arbitration
was premature in view of the pendency of the intra-court writ
appeals.
15.
BSR filed an application under Section 11 of the A&C Act,
being C.M.P.No.263/2019, seeking appointment of an Arbitrator.
This Court allowed the same by an order dated 05.11.2020 and
appointed a Sole Arbitrator to adjudicate the disputes between the
parties.
ARBITRAL PROCEEDINGS
16.
BSR filed its Statement of Claims before the Arbitral Tribunal
claiming an amount of `80,03,19,726/- (Rupees eighty crores three
lakhs nineteen thousand seven hundred and twenty-six only) under
thirteen heads, together with interest at 24% per annum from the
date of the claim petition till payment, and costs. The summary of
claims as set out in the statement of claims is reproduced below:
- 10 -
COMAP No. 485 of 2024
SUMMARY OF CLAIMS
Claims
Particulars
Claim No.1
Payment of Price Adjustment/Escalation
Bill
Payment of equitable enhanced rates
executed beyond tender completion
period.
Claim No.2
Claim No.3
Claim No.4
Claim No.5
Claim No.6
Claim
No.7(a)
Claim
No.7(b)
Claim No.8
Claim
No.9(a)
Claim
No.9(b)
Claim
No.10
Claim
No.11
Claim
No.12
17.
Claim
Amount
(Amt. in Rs.)
4,53,24,186
2,91,75,505
Payment of equitable enhanced rates
executed beyond Tender Completion
Period for extra items.
Payment of equitable enhanced rates
executed beyond Tender Completion
Period for quantities of 125%
Refund of Excess Royalty Charges
Payment towards idle men, machinery
and establishment during original tender
period.
Payment of unproductive overhead
charges.
Payment of additional overhead charges.
Payment towards loss of expected profit
on the balance work as on original tender
completion date.
Loss of expected profit due to non-receipt
of profit by tender completion period.
Loss of expected profit due to non-receipt
of profit by actual completion period.
Payment towards additional Bank
Guarantee charges beyond original
agreement period
Payment towards interest on claim
amount calculated upto 31.12.2020 at the
rate of ...........%
Payment of Rs. 12,00,000/- (Rupees
Twelve Lakhs Only) towards Cost of
Litigation.
TOTAL
19,81,088
7,47,95,600
2,32,55,404
56,37,903
2,32,55,404
11,62,77,020
2,73,72,950
5,98,370
45,08,47,944
12,00,000
80,03,19,726
It was BSR's case that after it was declared the successful
bidder, it had reduced its rates by factoring in the price escalation
- 11 -
COMAP No. 485 of 2024
clause and the economies of scale. BSR claimed that the appellant
did not hand over the sites within the stipulated period despite
various requests, and delayed approval of drawings, work slips and
EIRL items, thereby preventing BSR from completing the contract
within time and prolonging the execution of the works. BSR alleged
that the appellant also withheld amounts due to it, which compelled
BSR to seek reference of the disputes to arbitration.
18.
The appellant contended that no price adjustment clause
was applicable to the Agreement in respect of the subject works,
and that, in any event, the conditions of contract as forthcoming in
the e-procurement portal, which were binding on the parties,
specifically excluded price adjustment. The appellant further
contended that the delay, if any, had been suitably compensated
by extension of time granted without imposition of penalty, and that
the
claims,
aggregating
`80,03,19,726/-,
were
fictitious,
unsubstantiated and beyond the scope of arbitration.
19.
On the basis of the pleadings between the parties, the
Arbitral Tribunal framed the following issues:
"1. Whether Claimant proves that non completion of
the works under the contract within the stipulated
period was for the reasons solely attributable to
Respondent, resulting in breach of contract by
- 12 -
COMAP No. 485 of 2024
Respondent, as such, the delay in completion of the
works was solely attributable to Respondent?
2. Whether for the reasons set out in SOC which were
beyond the control of Claimant, he was prevented from
completing the entire scope of work within the
scheduled contract period?
3. Whether Respondent proves that the delay in
completion of the works under the contract within the
original period stipulated under the contract was solely
attributable to Claimant?
4. Whether Respondent proves that as the
requirements of Clause 38.4 of Conditions of Contract
have not been complied with by Claimant, none of the
claims put-forth in SOC is tenable?
5. Whether the Claimant is entitled for payment of
amounts claimed under various heads as put-forth
under claim Nos.1 to 10 of SOC?
6. Whether the Claimant is entitled for payment
towards past interest on the amounts claimed up to
31-12-2020 at 24% PA as claimed under claim No.11
of SOC?
7. Whether Claimant is entitled for current and future
interest at 24% PA on the amount claimed?
8. Whether Claimant is entitled for cost of this arbitral
proceeding?
9. To what order and award the parties are entitled
to?"
20.
The Arbitral Tribunal, after examining the evidence and
materials placed on record, held that the non-completion of the
works within the stipulated period was for reasons solely
attributable to the appellant, resulting in breach of contract by the
appellant. In arriving at the said finding, the Arbitral Tribunal placed
reliance on the Government Order dated 30.09.2020 (Ex.R2) and
- 13 -
COMAP No. 485 of 2024
the order dated 13.01.2021 (Ex.R3), whereunder extension of time
was granted without penalty recording, in respect of each of the
seven work sites, that the delay - ranging from 171 days to 467
days - was for reasons for which the contractor was not
responsible, and no part of the delay was attributed to BSR. The
Arbitral Tribunal held that the said documents amounted to an
admission on the part of the appellant that BSR was not
responsible for the delay. The Arbitral Tribunal further rejected the
appellant's contention that non-compliance with Clause 38.4 of the
Conditions of Contract rendered the claims not tenable. Insofar as
the claim towards price adjustment (Claim No.1) is concerned, the
Arbitral Tribunal held that the price adjustment clause formed part
of the contract; however, it rejected the said claim in its entirety on
the ground that BSR had placed no evidence to substantiate the
amount claimed thereunder.
21.
The Arbitral Tribunal partly allowed Claim Nos. 7(a), 8 and
12. The Arbitral Tribunal also awarded future interest and costs but
rejected the remaining claims, being Claim Nos.1 to 6, 7(b), 9(a),
9(b), 10 and 11, in their entirety.
22.
The dispositive part of the impugned award is set out below:
- 14 -
COMAP No. 485 of 2024
"AWARD
The claims of Claimant as put forth in
Statement of Claim are allowed in part as
under:
(1) Claim Nos.7(a) is allowed in part in a sum
of Rs.1,80,78,950/- only as against claim of
Rs.2,32,55,404/-;
(2) Claim No.8 is allowed in part in a sum of
Rs.1,02,44,738/- only as against the claim of
Rs.2,32,55,404/-;
(3) Respondent is directed to pay to Claimant
a total sum of Rs.2,83,23,688/- as per
Sl.No.(1) and (2) above together with future
interest at the rate of 9% per annum from the
date of this Award till the date of payment;
(4) Claim No.12 is allowed in part in a sum of
Rs.2,00,000/- only as against claim of
Rs.12,00,000/-. Respondent is directed to pay
to Claimant this amount within a period of 3
months from the date of this award failing
which the said amount shall carry interest at
the rate of 9% per annum from the date of
award till the date of payment;
(5) Claim Nos.1 to 6, 7(b), 9(a), 9(b), 10 and
11 are rejected in their entirety;
(6) Claimant shall pay requisite stamp duty on
this award payable as per Karnataka Stamp
Act.
With the pronouncement and publication of
Award, this Arbitral Proceeding stand
terminated as per Section 32(1) of the Act."
23.
The impugned award was assailed by the appellant before
the learned Commercial Court in Com.A.P.No.52/2024 under
Section 34 of the A&C Act. The learned Commercial Court, by the
- 15 -
COMAP No. 485 of 2024
impugned
judgment
dated
18.09.2024,
found
no
infirmity
warranting interference with the impugned award and dismissed
the petition, giving rise to the present appeal.
24.
As noted above, the learned Arbitral Tribunal had partly
allowed Claim No.7(a), which was towards unproductive overhead
charges. The learned Arbitral Tribunal had noted that there were
no averments made in the claim statement to support the said
claim. Further, even in the affidavit tendered by BSR's witness
(P.W.1) had not stated anything in this regard. Paragraph 121 of
the impugned award reads as under:
"121. Respondent in its SO has contended
that these claims are beyond the original
tender period and the overhead charges
are inbuilt for the finished items of works
and that there is no provision in the
agreement for payment of unproductive
overhead charges beyond the original
tender period, therefore, these claims are
beyond the scope of arbitration as such
Claimant is not entitled for these claims."
25.
Although the statement of claims was bereft of any
particulars or the methodology used for quantification of Claim
No.7(a), the learned Arbitral Tribunal partly allowed the claim by
applying the Hudson Formula and assuming that the overheads
charges constituted 10% of the contract price. It is material to note
that BSR had made no such claim. The learned Arbitral Tribunal
- 16 -
COMAP No. 485 of 2024
relied on the cross-examination of P.W.1 during which a
suggestion was put to the witness that the overhead charges were
included in the item rates. In absence of any averments justifying
the said claim and any evidence led by BSR in this regard, the
award for unproductive overhead imposed is unsustainable.
26.
The learned Arbitral Tribunal also allowed the claim for loss
of profits (Claim No.8), inter alia, referring to the decision in the
case of the Supreme Court in A.T.Brij Paul Singh and Others v.
State of Gujarat1. On the said basis, the learned Arbitral Tribunal
accepted that the expected profit was 10% of the contract price.
However, in the present case, the contract was fully performed and
it is evident that BSR had realized the profit as included in the
contract price. Notwithstanding the same, the learned Arbitral
Tribunal awarded 10% per annum of the expected profits included
in the value of work executed after the execution date. BSR had
made no claim on such basis. It had led no evidence as to the
quantum of loss of profits. We find no basis for awarding 10% p.a
of the assured profits as loss of profits for the prolongation of
contract. In this view, the award against claim No.8 is
unsustainable.
(1984) 4 SCC 59
- 17 -
COMAP No. 485 of 2024
27.
Claim No.12 is for costs. The award of costs, is premised on
BSR succeeding in Claim Nos.7 and 8. Since the award against
claim Nos.7 and 8 is set aside, the award against claim No.12 is
also unsustainable.
28.
The impugned award is in the similar terms as the arbitral
award which was subject matter of challenge in COMAP
No.54/2025. The said appeal was allowed by this court by an order
dated 18.08.2026. The reasons set out in the said order fully cover
the issues involved in the present appeal as well. For the sake of
brevity, the same are not repeated in this order but may be read as
a part of the present order as well.
29.
In view of the above, the impugned award insofar as it
awards claim Nos.7(a), 8 and 12 and interest thereon, is set aside.
30.
The appeal is allowed in the aforesaid terms.
Sd/(VIBHU BAKHRU)
CHIEF JUSTICE
Sd/(K.S. HEMALEKHA)
JUDGE
KPS
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review