The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
13. 01.2021 Heard Mr. M. Hemchandra, learned senior counsel assisted by Mr. Juno Rahman, learned counsel for the appellants. Also heard Mr. S. D Singh, learned senior counsel assisted by Mr. T. Momo, learned counsel for the respondent, Mr. N. Kumarjit, learned AG, Manipur assisted by Mr. H. Lenin, learned Addl. AG, Manipur. and Mr. P. Vaiphei, Additional Chief Secretary (Works), Government of Manipur. The respondents/writ petitioners filed a writ petition being WP(C) No. 32 of 2020 challenging the NIT dated 28-12-2019 issued by the Public Works Department, Government of respondents/writ Manipur. petitioners It was the case of the that the Public Works Department, Government of Manipur had issued an NIT dated 18-2-2010 for constructions of Capital Complex (Civil Secretariat Component at Mantripukhri, Imphal). The respondents being eligible had participate in the bid and was successful in getting the works. The letter of Intent dated 5-10-2010 was issued in favor of the petitioner and the period of execution of works was fixed at 36 (thirty-six) months from the date of execution of the Agreement between the parties. The Agreement was signed on 18-102010 and accordingly, the original period for execution of works was scheduled to expire on 17-10-2013. After fulfilling all the terms and conditions, the respondents proceeded with the works. However, there were some difficulties due to n…
13. That, since the task of carrying of the Joint Measurement would not be completed on 04-12-2020, the same was continued on 05-12-2020. However, the joint measurement being could not be completed as the entire task would require more time and it is estimated that the same can be completed only when the measurement is done for more than 15 to 20 days. On the said dates, only the one part of the measurement (Ministerial Block) of the project “Construction of Capital Complex (Civil Secretariat Component) at Mantripukhri, Imphal would be done and the same is yet to be completed. The measurement works of the South & North Block of the said project is yet to commence.” After considering all the matters and keeping in mind the public importance with regard to the completion of Manipur Civil Secretariat , we had directed the parties to go for a joint measurement as already stated herein above. The basic idea of this Court was to settle the matter as early as possible so that the appellants/Government of Manipur can proceed with the construction of the remaining portion of the Manipur Civil Secretariat. Today, while hearing the matter, learned AG, Manipur submits that the Government of Manipur is ready to proceed with another Joint measurement and thereafter finally settle the issue with the respondents/M/S Simplex Projects Ltd. and ensure that the construction of Manipur Civil Secretaria…
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Yumkham Rother
Yumkham Rother
Date: 2021.01.15
11:07:01 +05'30'
Item No. 1
WA No. 39 of 2020
State of Manipur & Ors
....Appellants
-VersusM/s Simplex Project Ltd
....Respondent
BEFORE
HON’BLE MR. JUSTICE LANUSUNGKUM JAMIR
HON’BLE MR. JUSTICE AHANTHEM BIMOL SINGH
(Through Video Conferencing)
13.01.2021
Heard Mr. M. Hemchandra, learned senior
counsel assisted by Mr. Juno Rahman, learned counsel for
the appellants. Also heard Mr. S. D Singh, learned senior
counsel assisted by Mr. T. Momo, learned counsel for the
respondent, Mr. N. Kumarjit, learned AG, Manipur assisted
by Mr. H. Lenin, learned Addl. AG, Manipur. and Mr. P.
Vaiphei, Additional Chief Secretary (Works), Government of
Manipur.
The respondents/writ petitioners filed a writ
petition being WP(C) No. 32 of 2020 challenging the NIT
dated 28-12-2019 issued by the Public Works Department,
Government
of
respondents/writ
Manipur.
petitioners
It
was
the
case
of
the
that
the
Public
Works
Department, Government of Manipur had issued an NIT
dated 18-2-2010 for constructions of Capital Complex (Civil
Secretariat Component at Mantripukhri, Imphal). The
respondents being eligible had participate in the bid and
was successful in getting the works. The letter of Intent
dated 5-10-2010 was issued in favor of the petitioner and
the period of execution of works was fixed at 36 (thirty-six)
months from the date of execution of the Agreement
between the parties. The Agreement was signed on 18-102010 and accordingly, the original period for execution of
works was scheduled to expire on 17-10-2013. After fulfilling
all the terms and conditions, the respondents proceeded
with the works. However, there were some difficulties due to
non-availability of drawings, changes in specifications and
other connected works due to which the work could not be
completed within the prescribed period of 3 (three) years.
The respondents therefore made an application for
extension
of
time as
provided
under
the
contract.
Thereafter, as there was extra works to be executed, the
contract value was also increased to the tune of Rs. 350
crores. There was some dispute between the respondents
and the appellants with regard to payment of bills and as a
result there were communications between the respondents
and the appellants. In the meantime, the respondents came
across a news item in the local newspaper that coercive
action would be taken against the respondents and
therefore, being aggrieved, the respondents filed an
Arbitration Petition being Art. Pet. (J2) No. 1 of 2018 before
this Court and this Court by order dated 8-10-2018 directed
status quo be maintained by the parties. During the
pendency of the Arbitration Petition, a meeting was held
between the parties to resolve the issue amicably and the
appellants accordingly withdrew the termination letter dated
27-9-2018 with the condition that work should be completed
by February, 2019 and the performance Bank Guarantee be
revalidated on or before 6-11-2018. The respondent also
wrote a letter dated 11-11-2018 requesting the appellants to
grant extension up to 30-06-2019 and also to comply with
the terms of the MOU dated 27-10-2018 by releasing the
payments and maintaining cash flow in the project for its
timely completion. The Arbitration Petition
was also
disposed of on 12-10-2018 recording the terms of the
minutes of the meeting as agreed between the parties and
the withdrawal of the termination order.
It was also alleged in the writ petition that the
appellants failed to act as per the MOU dated 27-10-2018
and instead asked the respondents to complete the works of
3 (three) blocks. A Show Cause Notice dated 4-6-2019 was
also issued apprehending that the work would not be
completed by the respondents within the time agreed.
Another Show Cause Notice dated 18-9-2019 was also
issued to which the respondents replied on 25-9-2019
stating that the delay was not attributable to them. A further
Show Cause Notice dated 17-10-2019 was issued to which
the respondents replied on 25-10-2019 highlighting various
reasons causing the delay. However, the appellants in
arbitrary manner terminated the contract by letter dated 211-2019.
Thereafter, the appellants issued the NIT dated
28-12-2019 for execution of the balance and additional work
arising out of the contract. Being aggrieved, the respondents
filed WP(C) No. 32 of 2020.
Learned Single Judge after hearing the parties
and on consideration of the facts and circumstances of the
case disposed of WP(C) No. 32 of 2020 by Judgment and
Order dated 6-3-2020 allowing the writ petition in part and
quashing the NIT dated 28-12-2019 along with the following
directions:
“[10]
For the reasons stated hereinabove, the instant writ
petition is allowed in part and the NIT dated 28-12-2019 (date
wrongly typed as 28-01-2019) is quashed and set aside with the
following directions:
(a) The
respondents
respondent
No.
and
in
shall
particular,
the
carry
the
out
measurement of the balance work of the project
called “Construction of Capital Complex (Civil
Secretariat Component) at Mantripukhri, Imphal”
which remains incomplete at the site within a
week from the date of receipt of a copy of this
judgment and order.
(b) The respondents shall inform the petitioner, in
advance, about the date and time on which the
measurement of the balance work will be
commenced;
(c) The petitioner shall extend full co-operation to
the respondents in the measurement of the
balance work and in the event of the full cooperation not being extended by the petitioner
without any cogent reason, the respondents ae
at liberty to proceed with the measurement of the
balance work in the absence of the petitioner;
(d) After the measurement of the balance work being
carried out by the respondents in the manner as
stated above, the petitioner shall remove all its
belongings
including
the
machineries,
consumable items etc. within a period of fifteen
days from the date of completion of the
measurement of the balance work and shall not
disturb the balance work being undertaken by
any person duly appointed by the respondents.
(e) After the measurement of the balance work
being
ascertained
and
determined
by
the
respondents, it is open to them to issue a fresh
NIT in respect of the balance work so ascertained
and determined;
(f) Keeping
in
mind
the
importance
and
the
requirement of the secretariat building in the
interest of the general public, an endeavor shall
be made by the respondents to ensure that the
balance work is completed with a reasonable
time.”
Being aggrieved with the Judgment and Order
dated 6-3-2020, the present appeal has been filed by the
Government of Manipur as appellants.
In the meantime, several misc cases were filed
by the State of Manipur as well as M/S Simplex Projects
Ltd.
After
consideration
considering
that the
the
matter
and
taking
into
construction of Manipur Civil
Secretariat involves public interest and of great importance
directed the parties to have a joint measurement and
complete the process at the earliest but not later than 3 rd
November, 2020 by an order dated 16-10-2020 passed in
MC(WA) No. 51 of 2020. There were some difficulties in
completion of the joint measurement and therefore, this
Court by another order dated 23-11-2020 directed the
parties to have another joint measurement along with two
senior officers from the Central Public Works Department
preferably in the rank of an Executive Engineer on 4th and
5th December, 2020 along with other observations. The
parties undertook the joint measurement and a Report to
that effect was submitted before this Court by way of an
affidavit dated 16th December, 2020. The respondents/M/S
Simplex Projects Ltd. also filed a misc case being MC(WA)
No. 74 of 2020. The relevant paragraphs of the said misc
case are reproduced herein below:
“12. That in pursuance to the direction passed by this
Hon’ble Court, the respondents’ team led by Shri Suman Ghosh
(Team Leader) and otehr six other members namely, Shri Abhijit
Roy(Expert), Shri Sandip Guha (Expert), Shri Rishikant Irom, Asst.
Engieer (Electrical) Shri Lal Muni Singh, Manager Civil (Q.S &
Bukkubg), Shri Ajay Kumar, Sr. Civil Engineer and Shri Anand
Kumar Dwivedi, Sr. Accountant had reached the concerned site on
04-12-2020 and had joined the PWD Department in carrying out the
Joint Measurement of the balance work of the project namely,
“Construction of Capital Complex(Civil Secretariat Component) at
Mantripukhri, Imphal.
13. That, since the task of carrying of the Joint Measurement
would not be completed on 04-12-2020, the same was continued on
05-12-2020. However, the joint measurement being could not be
completed as the entire task would require more time and it is
estimated that the same can be completed only when the
measurement is done for more than 15 to 20 days. On the said
dates, only the one part of the measurement (Ministerial Block) of
the project “Construction of Capital Complex (Civil Secretariat
Component) at Mantripukhri, Imphal would be done and the same is
yet to be completed. The measurement works of the South & North
Block of the said project is yet to commence.”
After considering all the matters and keeping in
mind the public importance with regard to the completion of
Manipur Civil Secretariat , we had directed the parties to go
for a joint measurement as already stated herein above. The
basic idea of this Court was to settle the matter as early as
possible so that the appellants/Government of Manipur can
proceed with the construction of the remaining portion of the
Manipur Civil Secretariat.
Today, while hearing the matter, learned AG,
Manipur submits that the Government of Manipur is ready to
proceed with another Joint measurement and thereafter
finally settle the issue with the respondents/M/S Simplex
Projects Ltd. and ensure that the construction of Manipur
Civil Secretariat is not delayed. Mr. S.D Singh, learned
senior counsel appearing for the respondents also submits
that they are also ready to have a final joint measurement
and complete the process at the earliest.
Taking into consideration the submissions
made by the parties, we are of the considered opinion that
there is no purpose to keep this writ appeal pending and
accordingly, we dispose of this writ appeal directing the
parties to have a final joint measurement from 18th January,
2021 and complete the same at the earliest but not later
than one week from 18th January, 2021. The State
respondents are also directed to secure the whole new
Secretariat building in order to ensure that there is no
interference from any quarter and the joint measurement is
undertaken and completed peacefully. The State appellants
shall also provide adequate security to the representatives
of the respondents/M/S Simplex Projects Ltd. The State
appellants are therefore directed to ensure the presence of
two
senior
officers
from
the
Central
Public Works
Department preferably in the rank of Executive Engineer
from 18th January, 2021 till the completion of the
measurement. We further direct that all the representatives
of the parties including the two senior officers from the
Central Public Works Department should sign on every
page of the joint measurement. After completion of the joint
measurement, liberty is given to the State appellants to
proceed with the construction of the Manipur Civil
Secretariat Complex by following all the required formalities
and procedures as provided by law.
With the above observations and directions, writ
appeal stands disposed of.
Furnish a copy of this order to the learned
counsel appearing for all the parties through their respective
e-mails.
JUDGE
JUDGE
kim
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.