HIGH COURT OF CHHATTISGARH AT BILASPUR
WA No. 763 of 2026
1 - State Of Chhattisgarh Through The Secretary, Department Of Public Relations,
Mahanadi Bhawan, Mantralaya, Nava Raipur, Atal Nagar District Raipur Chhattisgarh
2 - Director Directorate Of Public Relations Indravati Bhawan, Mantralaya, Nava
Raipur, Atal Nagar District Raipur Chhattisgarh
3 - Commissioner, Public Relations Directorate Public Relations Indravati Bhawan,
Mantralaya, Nava Raipur, Atal Nagar District Raipur Chhattisgarh
... Appellant(s)
versus
Govind Maskhare S/o Shri Mohan Lal Maskhare Aged About 50 Years R/o Janta
Colony, Gudhiyari, Raipur Chhattisgarh District Raipur Chhattisgarh
...Respondent(s)
(Cause-title taken from Case Information System)
-----------------------------------------------------------------------------------------------------------------For Appellants
: Shri Prasun Bhaduri, Dy AG
For Respondent
: Shri Jitendra Pali, Advocate
---------------------------------------------------------------------------------------------------------
Hon'ble Shri Ramesh Sinha, Chief Justice
Hon'ble Shri Justice Ravindra Kumar Agrawal
Order on Board
Per Ramesh Sinha, Chief Justice
17.08.2026
1.
Heard Shri Prasun Bhaduri, learned Deputy Advocate General
appearing for the appellants on I.A. No. 1 of 2026, which is an application
for condonation of delay of 60 days in preferring the instant appeal. Also
heard Shri Jitendra Pali, learned counsel appearing for the respondent.
WA 763 of 2026
2.
The appellants have filed this writ appeal against an order dated
08.04.2026, passed by the Hon’ble Single Judge, in WPS No. 2675 of
2021 (Govind Maskhare Vs State of Chhattisgarh and others), by
which the learned Single Judge has allowed the writ petition filed by the
writ petitioner(s).
3.
Learned Deputy Advocate General appearing for the appellants/
State submits that the present writ appeal has been preferred by the
appellants/State against the order dated 08.04.2026 passed in WPS No.
2675 of 2021, by the Hon’ble Single Bench of this Court. He would further
submit that the State is a multi-functioning body and it has to follow the
rules of obtaining sanction etc. for filing an appeal, which took
considerable time due to administrative procedures and multiple levels of
approval. He also submits that the appellants have a strong case on
merits, therefore, the delay if not condoned, would result in grave
miscarriage of justice.
4.
It has been further contended that the State, after obtaining
necessary documents and information with respect to the case, some
delay was occurred due to fulfillment of various departmental formalities
and working of the Government machinery, because the State
Government is a multi functioning body, hence, at times the fulfillment of
departmental formalities takes unexpected long time. Therefore, in some
cases the State is prevented from filing the case within the prescribed
period of limitation, which is bona fide and not deliberate. The instant
appeal is, therefore, being filed after a delay of 60 days from the
WA 763 of 2026
prescribed period of limitation. Reliance has been placed upon the
judgment rendered by Hon’ble Supreme Court in the matter of “State of
Haryana v. Chandra Mani and others” (1996) 3 SCC 132, to buttress
his submissions. As such, the learned State counsel prays that the delay
of 60 days in preferring the petition may be condoned.
5.
Learned counsel for the respondent submits that the writ appeal is
barred by delay and laches and further there is no cogent reason or
explanation has been given in the delay and laches application filed for
condonation of delay. Hence, the appeal is not liable to be entertained.
6.
On a pointed query being made to the learned for the appellants as
to why they have approached this Court against the impugned order
dated 08.04.2026, after an inordinate delay of 60 days, he has not offered
any plausible explanation or any cogent reason for delay in filing the writ
appeal.
7.
The question for determination before this Court, is whether the
provisions of Section 5 of the Limitation Act, 1908 (i.e. Act 9 of 1908 i.e.
the old Limitation Act) would apply to an application for condonation of
delay.
8.
The Hon’ble Supreme Court in the matter of Postmaster General
and others v. Living Media India Limited and another, (2012) 3 SCC
563, has dealt with the limitation issue and held as under:“27. It is not in dispute that the person(s) concerned
were well aware or conversant with the issues involved
including the prescribed period of limitation for taking up
WA 763 of 2026
the matter by way of filing a special leave petition in this
Court. They cannot claim that they have a separate
period
of
limitation
when
the
Department
was
possessed with competent persons familiar with court
proceedings. In the absence of plausible and
acceptable explanation, we are posing a question
why the delay is to be condoned mechanically
merely because the Government or a wing of the
Government is a party before us.
28. Though we are conscious of the fact that in a matter
of condonation of delay when there was no gross
negligence or deliberate inaction or lack of bonafide, a
liberal concession has to be adopted to advance
substantial justice, we are of the view that in the facts
and circumstances, the Department cannot take
advantage of various earlier decisions. The claim on
account of impersonal machinery and inherited
bureaucratic methodology of making several notes
cannot be accepted in view of the
modern
technologies being used and available. The law of
limitation undoubtedly binds everybody including
the Government.
29. In our view, it is the right time to inform all the
government bodies, their agencies and instrumentalities
that unless they have reasonable and acceptable
explanation for the delay and there was bonafide effort,
there is no need to accept the usual explanation that the
file was kept pending for several months/years due to
considerable degree of procedural red-tape in the
process. The government departments are under a
special obligation to ensure that they perform their
duties with diligence and commitment. Condonation of
WA 763 of 2026
delay is an exception and should not be used as an
anticipated benefit for government departments. The
law shelters everyone under the same light and should
not be swirled for the benefit of a few.
30. Considering the fact that there was no proper
explanation offered by the Department for the delay
except mentioning of various dates, according to us, the
Department has miserably failed to give any acceptable
and cogent reasons sufficient to condone such a huge
delay. Accordingly, the appeals are liable to be
dismissed on the ground of delay.”
9.
Recently, the Hon’ble Supreme Court in the matter of State of
Madhya Pradesh v. Ramkumar Choudhary, 2024 INSC 932, while
considering the delay, issued some directions and observed as follows:“5. The legal position is that where a case has been
presented in the Court beyond limitation, the petitioner
has to explain the Court as to what was the "sufficient
cause" which means an adequate and enough reason
which prevented him to approach the Court within
limitation. In Majji Sannemma v. Reddy Sridevi, 2021
SCC Online SC 1260, it was held by this Court that even
though limitation may harshly affect the rights of a party, it
has to be applied with all its rigour when prescribed by
statute. A reference was also made to the decision of this
Court in Ajay Dabra v. Pyare Ram, 2023 SCC Online 92
wherein, it was held as follows:
WA 763 of 2026
"13.
This Court in the case of Basawaraj v.
Special Land Acquisition Officer [(2013) 14 SCC 81]
while rejecting an application for condonation of
delay for lack of sufficient cause has concluded in
Paragraph 15 as follows:
“15. The law on the issue can be summarised
to the effect that where a case has been
presented in the court beyond limitation, the
applicant has to explain the court as to what
was the “sufficient cause” which means an
adequate
and
enough
reason
which
prevented him to approach the court within
limitation. In case a party is found to be
negligent, or for want of bona fide on his part
in the facts and circumstances of the case, or
found to have not acted diligently or remained
inactive, there cannot be a justified ground to
condone the delay. No court could be justified
in condoning such an inordinate delay by
imposing any condition whatsoever. The
application is to be decided only within the
parameters laid down by this Court in regard
to the condonation of delay. In case there was
no sufficient cause to prevent a litigant to
WA 763 of 2026
approach the court on time condoning the
delay without any justification, putting any
condition whatsoever, amounts to passing an
order in violation of the statutory provisions
and it tantamounts to showing utter disregard
to the legislature.”
14. Therefore, we are of the considered opinion that
the High Court did not commit any mistake in
dismissing the delay condonation application of the
present appellant."
Thus, it is crystal clear that the discretion to condone
the delay has to be exercised judiciously based on
facts and circumstances of each case and that, the
expression 'sufficient cause' cannot be liberally
interpreted, if negligence, inaction or lack of bona
fides is attributed to the party.
5.1. In Union of India v. Jahangir Byramji Jeejeebhoy (D)
through his legal heir, 2024 INSC 262, wherein, one of us
(J.B.Pardiwala, J) was a member, after referring to
various decisions on the issue, it was in unequivocal
terms observed by this Court that delay should not be
excused as a matter of generosity and rendering
substantial justice is not to cause prejudice to the
WA 763 of 2026
opposite party. The relevant passage of the same is
profitably extracted below:
“24. In the aforesaid circumstances, we made it
very clear that we are not going to look into the
merits of the matter as long as we are not
convinced that sufficient cause has been made out
for condonation of such a long and inordinate
delay.
25. It hardly matters whether a litigant is a private
party or a State or Union of India when it comes to
condoning the gross delay of more than 12 years.
If the litigant chooses to approach the court long
after the lapse of the time prescribed under the
relevant provisions of the law, then he cannot turn
around and say that no prejudice would be caused
to either side by the delay being condoned. This
litigation between the parties started sometime in
1981. We are in 2024. Almost 43 years have
elapsed. However, till date the respondent has not
been able to reap the fruits of his decree. It would
be a mockery of justice if we condone the delay of
12 years and 158 days and once again ask the
respondent to undergo the rigmarole of the legal
proceedings.
WA 763 of 2026
26. The length of the delay is a relevant matter
which the court must take into consideration while
considering
whether
the
delay
should
be
condoned or not. From the tenor of the approach
of the appellants, it appears that they want to fix
their own period of limitation for instituting the
proceedings for which law has prescribed a period
of limitation. Once it is held that a party has lost
his right to have the matter considered on merits
because of his own inaction for a long, it cannot be
presumed to be non-deliberate delay and in such
circumstances of the case, he cannot be heard to
plead that the substantial justice deserves to be
preferred as against the technical considerations.
While considering the plea for condonation of
delay, the court must not start with the merits of
the main matter. The court owes a duty to first
ascertain the bona fides of the explanation offered
by the party seeking condonation. It is only if the
sufficient cause assigned by the litigant and the
opposition of the other side is equally balanced
that the court may bring into aid the merits of the
matter for the purpose of condoning the delay.
WA 763 of 2026
27. We are of the view that the question of
limitation is not merely a technical consideration.
The rules of limitation are based on the principles
of sound public policy and principles of equity. We
should not keep the ‘Sword of Damocles’ hanging
over the head of the respondent for indefinite
period of time to be determined at the whims and
fancies of the appellants.
xxx xxx xxx
34. In view of the aforesaid, we have reached to
the conclusion that the High Court committed no
error much less any error of law in passing the
impugned order. Even otherwise, the High Court
was exercising its supervisory jurisdiction under
Article 227 of the Constitution of India.
35. In a plethora of decisions of this Court, it has
been said that delay should not be excused as a
matter of generosity. Rendering substantial justice
is not to cause prejudice to the opposite party. The
appellants have failed to prove that they were
reasonably diligent in prosecuting the matter and
this vital test for condoning the delay is not
satisfied in this case.
WA 763 of 2026
36. For all the foregoing reasons, this appeal fails
and is hereby dismissed. There shall be no order
as to costs.
”Applying the above legal proposition to the facts
of the present case, we are of the opinion that the
High Court correctly refused to condone the delay
and dismissed the appeal by observing that such
inordinate delay was not explained satisfactorily,
no sufficient cause was shown for the same, and
no plausible reason was put forth by the State.
Therefore, we are inclined to reject this petition at
the threshold.
6. At the same time, we cannot simply brush aside
the delay occurred in preferring the second appeal,
due to callous and lackadaisical attitude on the part
of the officials functioning in the State machinery.
Though the Government adopts systematic approach
in handling the legal issues and preferring the
petitions/applications/appeals well within the time,
due to the fault on the part of the officials in merely
communicating
the
information
on
time,
huge
revenue loss will be caused to the Government
exchequer. The present case is one such case,
wherein, enormous delay of 1788 days occasioned in
WA 763 of 2026
preferring the second appeal due to the lapses on the
part of the officials functioning under the State,
though valuable Government lands were involved.
Therefore, we direct the State to streamline the
machinery touching the legal issues, offering legal
opinion, filing of cases before the Tribunal / Courts,
etc., fix the responsibility on the officer(s) concerned,
and penalize the officer(s), who is/are responsible for
delay, deviation, lapses, etc., if any, to the value of
the loss caused to the Government. Such direction
will
have
to
be
followed
by
all
the
States
scrupulously.
7. There is one another aspect of the matter which we
must not ignore or overlook. Over a period of time, we
have noticed that whenever there is a plea for
condonation of delay be it at the instance of a private
litigant or State the delay is sought to be explained right
from the time, the limitation starts and if there is a delay
of say 2 years or 3 years or 4 years till the end of the
same. For example if the period of limitation is 90 days
then the party seeking condonation has to explain why it
was unable to institute the proceedings within that period
of limitation. What events occurred after the 91st day till
the last is of no consequence. The court is required to
WA 763 of 2026
consider what came in the way of the party that it was
unable to file it between the 1st day and the 90th day. It is
true that a party is entitled to wait until the last day of
limitation for filing an appeal. But when it allows the
limitation to expire and pleads sufficient cause for not
filing the appeal earlier, the sufficient cause must
establish that because of some event or circumstance
arising before the limitation expired it was not possible to
file the appeal within time. No event or circumstance
arising after the expiry of limitation can constitute such
sufficient cause. There may be events or circumstances
subsequent to the expiry of limitation which may further
delay the filing of the appeal. But that the limitation has
been allowed to expire without the appeal being filed
must be traced to a cause arising within the period of
limitation. (See: Ajit Singh Thakur Singh and Another v.
State of Gujarat, AIR 1981 SC 733).”
10.
Taking into account the facts and circumstances of the present
case, in the light of aforementioned judgments of the Hon’ble Supreme
Court in the matters of Postmaster General (supra) and Ramkumar
Choudhary (supra), it is evident that Government departments are under
a special obligation to discharge their duties with due diligence and
commitment. Condonation of delay is an exception, not the rule, and
cannot be claimed as a matter of right or anticipated privilege by
WA 763 of 2026
Government entities. The law casts its protection equally upon all litigants
and cannot be distorted to confer undue advantage upon a select few.
11.
In the light of the principles of law laid down by the Hon’ble
Supreme Court in the aforementioned judgments (supra), and upon due
consideration of the grounds urged in I.A. No. 1, we find that the delay of
60 days in preferring the writ appeal has not been satisfactorily explained
with any cogent or plausible reason. The appellants have failed to
demonstrate sufficient cause so as to justify condonation of such delay.
Therefore, no ground is made out to exercise our discretion in favour of
the appellants for condoning the delay.
12.
Consequently, I.A. No. 1 seeking condonation of delay is hereby
rejected. As a natural corollary thereto, the writ appeal also stands
dismissed.
Sd/(Ravindra Kumar Agrawal)
Judge
padma
V PADMAVATHI
Date: 2026.08.20
13:46:17 +0530
Sd/(Ramesh Sinha)
Chief Justice
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review