IN THE HIGH COURT OF DELHI AT NEW DELHI
%
+
+
Judgment Reserved on: 15.05.2026
Judgment delivered on: 14.08.2026
Judgment uploaded on: 15.08.2026
FAO(OS) (COMM) 132/2024 CM APPL. 37358 /2024
FAO(OS) (COMM) 136/2024 CM APPL. 37716/2024
SSANGYONG ENGINEERING AND CONSTRUCTION CO. LTD.
.....Appellant
versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA
.....Respondent
Advocates who appeared in this case
For the Appellant
:
Mr. Navin Kumar, Ms. Surbhi Agarwal, Ms.
Rashmeet Kaur, Ms. Aarti Mahto, Advs.
For the Respondents
:
Mr. Ankur Mittal and Mr. Arpit Sharma,
Advs.
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA
JUDGMENT
MANMEET PRITAM SINGH ARORA, J.
1.
FAO(OS) (COMM) 132/2024 has been filed under Section 37 of the
Arbitration and Conciliation Act, 1996 [‘Act of 1996’] read with Section 13
of the Commercial Courts Act, 2015 assailing the judgment dated
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
08.04.2024 passed by the learned Single Judge [the ‘impugned judgment’]
in exercise of its jurisdiction under Section 34 of the Act of 1996 in
OMP(COMM) No. 340/2021, whereby the Arbitral Award dated 26.06.2021
[‘impugned Award’] has been set aside at the instance of the Respondent,
and the disputes [including claims and counter-claim] have been remanded
back to the Arbitral Tribunal for fresh adjudication.
2.
FAO(OS) (COMM) 136/2024 has been filed assailing the judgment
dated 08.04.2024 passed in Section 34 petition being OMP (COMM) No.
256/2021 filed by the Appellant, on the plea that learned Single Judge failed
to adjudicate the Appellant’s challenge to the impugned Award rejecting the
Appellant’s claim for pre-award and pendente lite period for interest at 10%
per annum on the awarded amount, compounded monthly.
FACTUAL MATRIX
3.
On 30.12.2005, the Appellant was awarded a contract by the
Respondent for the construction of a highway on the Jhansi-Lakhanadon
Section in the State of Madhya Pradesh for about 54 Km. between Km 211
to Km 255 of NH-26 (Contract Package-ADB-II/C-6) [the ‘contract’ or
‘contract package C-6’] at a Contract Price of Rs. 163,87,02,003/-.
4.
It is stated that the contract in question, being a FIDIC1 standard form
contract, stipulated that execution of the contract would be supervised by an
independent third party, i.e., the Engineer.
5.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
Accordingly, as per Clause 2.1 of General Conditions of the Contract
International Federation of Consulting Engineers
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
[‘GCC’], the Respondent/Employer had appointed M/s. Roughton
International to act as ‘the Engineer’.
6.
As per Clause 2.6 of GCC, it was provided that the Engineer shall
have the authority to inter alia give his decision, opinion or consent,
determine value, or otherwise take action which may affect the rights and
obligations of the Respondent/Employer or the Appellant/Contractor. Such
power was to be exercised by the Engineer impartially, having regard to all
circumstances.
7.
It was specifically agreed in terms of the said Clause 2.6 of GCC that
“any such decision (sic. of the Engineer), opinion, consent, expression of
satisfaction, or approval, determination of value or action may be opened up,
reviewed or revised as provided in Clause 67 of COPA (i.e. the Dispute
Resolution Mechanism under the Contract)”.
8.
It is stated that upon substantial completion of work, the project was
to be taken over by the Engineer by issuing a Taking Over Certificate
[‘TOC’] in terms of Clause 49 of GCC, which was also the point of
commencement of the Defects Liability Period [‘DLP’] for a period of 365
days.
9.
It is stated that the Appellant executed the contract under the
instructions of the Engineer. It is stated that as per Sub-Clause 60.1 of the
Conditions of Particular Applications [‘COPA’] the Appellant submitted
monthly statements to the Engineer for each month in respect of the work
executed up to the end of the previous month. It is stated that the monthly
statements were submitted in the form of an Interim Payment Application
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
[‘IPA’]. It is stated that, pursuant to Sub-Clause 60.2 of COPA, the
Engineer, upon verification of the work executed, determined the amount
due to the Appellant under the IPA and issued to the Respondent and the
Appellant the corresponding IPC for payment against the IPA. It is stated
that the Appellant raised several IPAs during the execution of the contract,
and that a total of 72 IPCs were issued by the Engineer, which have been
duly paid by the Respondent to the Appellant.
10.
It is stated that the project was completed on 30.10.2012, as certified
by the TOC dated 06.04.2013. The certificate recorded that the work was
determined as complete as on 12.03.2013. The DLP was completed on
12.03.2014 as certified by the Defects Liability Certificate [‘DLC’] dated
04.04.2014. It is stated that issuance of the DLC constitutes approval of all
works executed under the contract as agreed by the parties under Clause
61.1 of GCC.
11.
Upon completion of the project and the DLP, the Appellant raised its
Draft Final Statement [Draft Final Bill] as per Sub-Clause 60.11 of COPA
on 24.06.2014, for a net value of Rs. 160,71,89,930/- payable in INR and $
5,845,604.72 payable in USD for the evaluation and certification of the
Engineer in terms of Sub-Clause 60.13 of COPA.
Thereafter, the Engineer reviewed the Draft Final Statement.
The Engineer certified the Final Statement, pursuant to its jurisdiction
under Sub-Clause 60.11 of COPA. The Engineer issued the Final Payment
Certificate [‘FPC’] dated 31.08.2014, in terms of Sub-Clause 60.13 of
COPA against the Contractor’s Draft Final Statement for payment for a net
value of Rs. 14,24,50,311/-, wherein payment in INR was of Rs.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
122,802,146/- and payment in USD was $ 446,650.86.
12.
The Arbitral Tribunal, at paragraph no. 26 of the impugned Award,
while considering the nature of the Certificate dated 31.08.2014, recorded
that the Appellant had not furnished the written discharge contemplated
under Sub-Clause 60.12 of COPA and accordingly concluded that the said
Certificate constituted the Final Statement under Sub-Clause 60.11 of COPA
and not an FPC under Sub-Clause 60.13 of COPA. The findings of the
Arbitral Tribunal are not challenged by the Appellant. The Appellant agrees
that the Certificate dated 31.08.2014 is a Final Statement [Final Bill] and not
an FPC.
The Arbitral Tribunal, by its Award dated 26.06.2021, awarded the
Appellant Rs. 6,65,57,179/- and USD 251,858/- towards the balance amount
under the Final Statement, together with future interest at 2% per annum.
However, it declined to adjudicate the Respondent’s challenge to the
correctness of the said Final Statement on the premise that it had not been
challenged under Sub-Clause 67 of COPA read with Clause 2.6 of GCC.
The Arbitral Tribunal also rejected the Respondent’s counter-claim of Rs.
2,76,12,569/- as barred by limitation. The Appellant’s claim for delayedpayment interest under Sub-Clause 60.8 of COPA was also rejected, which
has been separately challenged by the Appellant in OMP (COMM) No.
256/2021.
13.
Thereafter, the Respondent challenged the impugned Award by way
of OMP (COMM) No. 340/2021, inter alia on the ground of violation of
principles of natural justice, contending that the case of the Respondent had
not been considered and that the said Award ignored that no term of the
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
contract provides for payment against a Final Statement.
14.
The learned Single Judge vide Impugned Judgment has set aside the
impugned Award and remanded the matter back to the Arbitral Tribunal for
fresh adjudication on the following three findings: i.
Absolute non-consideration and non-adjudication of the objections of
the Respondent to the Final Statement dated 31.08.2014, which
amounts to non-adherence to the principles of natural justice. Also,
the non-consideration of the pleas of the Respondent vis-à-vis the
errors in the contents of the Final Statement dated 31.08.2014 is a
breach of public policy.
ii.
Since the Final Statement dated 31.08.2014 was not a FPC as
contemplated under Sub-Clause 60.13 of COPA, the relief granted by
the Arbitral Tribunal in favour of the Appellant, directing the
Respondent to make payment as per the Final Statement dated
31.08.2014, was not permissible as per the contract.
iii.
Lastly, contradiction in the impugned Award with a separate award
dated 01.12.2019 with respect to a separate contract package C-5,
wherein the Arbitral Tribunal held the character of the similar FPC
therein to be an Interim Payment Certificate [i.e., as per Sub-Clause
60.9 of COPA] and concluded that such a certificate has not attained
finality. The learned Single Judge also noted that the counter-claim in
the other arbitration had been held to be within limitation and not
time-barred. The learned Single Judge was of the view that the
findings in the impugned Award arising out of contract package C-6
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
were contrary to those in the arbitral award dated [‘award dated
01.12.2019’] arising out of contract package C-5, even though they
arose from identical clauses in the contract.
14.1. The learned Single Judge observed that the composition of the
Arbitral Tribunal presiding over the disputes in contract package C-6 and
contract package C-5 was the same.
14.2. This finding of the learned Single Judge that the composition of the
Arbitral Tribunal was identical has been disputed by the Appellant as a
matter of fact.
We therefore note that the composition of the Arbitral Tribunal which
passed the impugned Award dated 26.06.2021 in contract package C-6
comprised of (i) Shri Prabhat Krishna, Presiding Arbitrator, (ii) Shri A.K.
Yadav, and (iii) Shri Ashok Khurana. Whereas, the composition of the
Arbitral Tribunal, which passed the award dated 01.12.2019 in contract
package C-5 comprised (i) Shri B.V. Tripathi, Presiding Arbitrator, (ii) Shri
Ashok Khurana and (iii) Shri A.K. Yadav. Thus, the composition of the
Tribunal was not identical, though at least two members were common.
However, Shri Ashok Khurana has recorded his dissent in the award dated
01.12.2019, passed in contract package C-5. This issue will be considered
later.
15.
In these facts, the Appellant has instituted the present appeals.
SUBMISSIONS BY THE APPELLANT
16.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
Mr. Navin Kumar, learned counsel for the Appellant contended that
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
the Appellant was entitled to receive the entire payment certified on
31.08.2014 within a period of 84 days as per Sub-Clause 60.8 of COPA.
He stated that the Respondent, in fact, released part-payments to the
Appellant on 03.09.2014, 08.09.2014 and 24.09.2014. The details of the
payments are: “25. It is submitted that as per Sub-Clause 60.8 of COPA, the
Respondent was required to release the payments of the Claimant as
certified by the Engineer in the aforesaid Final Payment Certificate dated
31.08.2014 within a period of 84 days, however, the Respondent released
only a sum of Rs.3,66,92,653/- on 03.09.2014 and Rs.1,68,631282/- on
24.09.2014 against lNR portion and USD 1,62,607.48/- on 08.09.2014
and USD 32,183.95/- on 24.09.2014 against Foreign portion.”
16.1. He stated that in the Statement of Claim2 [‘SoC’] filed before the
Arbitral Tribunal, the Respondent defaulted in making the balance payments
and vide letter dated 15.10.2014 directed the Engineer to undertake
compliance with the Certificate dated 31.08.2014 which was non-contractual
and arbitrary. He stated that the Appellant opposed the aforesaid action of
the Respondent vide its representation dated 01.02.2015, and it called upon
the Respondent to release the due amount of the Final Statement [Final Bill]
certified by the Engineer on 31.08.2014. It is stated that the Respondent
failed to make payment for over two years and therefore the Appellant, vide
letter dated 26.04.2016, issued a reminder for release of the outstanding
payment towards the Final Statement [Final Bill]. He referred to the
Respondent’s response dated 09.05.2016, wherein the Respondent declined
to release the payment until the compliances notified by it had been duly
fulfilled by the Engineer as well as the Appellant.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
Dated 07.10.2017
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
16.2. He stated that in the SoC, the Appellant raised a grievance to the letter
dated 18.08.2016 received from the Office of the Engineer unilaterally
incorporating the corrections in the Statement of Completion and Final
Statement [Final Bill] inter alia making the net payable amount negative and
recommending recovery payment from the Appellant. In the SoC, the
Appellant termed the said action of the Engineer as arbitrary and unjustified.
It is contended that the said action of the Engineer was in violation of the
contract. He relied upon the Appellant’s letter dated 23.09.2016 and
06.10.2016 objecting to the action of the Engineer in seeking to unilaterally
amend the Final Statement [Final Bill] dated 31.08.2014, at the behest of the
Respondent. He took a categorical stand that the amendments made by the
Engineer to the Final Statement [Final Bill] were not acceptable to the
Appellant.
16.3. He contended that since the disputes inter se parties remained
unresolved, on account of the Respondent’s non-payment of the balance
amount in terms of the Final Statement [Final Bill] dated 31.08.2014, the
Appellant invoked Arbitration under Clause 67 of COPA vide its letter dated
07.11.2016 towards its claim for payments under the Final Statement [Final
Bill] dated 31.08.2014.
16.4. He contended that the learned Single Judge, while setting aside the
impugned Award, exceeded the limited scope of interference permissible
under Section 34 of the Act of 1996. He submitted that such an exercise was
impermissible, particularly in the case of an International Commercial
Arbitration.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
16.5. He further contended that the learned Single Judge failed to consider
the Appellant’s principal submission concerning the effect of Clause 2.6 of
GCC and Clause 67 of COPA. It was submitted that the Arbitral Tribunal
had, upon consideration of the contractual provisions, correspondence and
conduct of the parties, held that the Final Statement certified by the Engineer
on 31.08.2014 had attained finality and binding effect, as the Respondent
had failed to avail the contractual mechanism for challenging the said
certification within the prescribed period. He submitted that the finding of
the learned Single Judge that Sub-Clause 60.11 of COPA did not
contemplate payment of the Final Statement amounted to substitution of the
Court’s interpretation for that of the Arbitral Tribunal.
16.6. He also assailed the finding that the pendency of disputes between the
parties disentitled the Appellant from receiving payment under the Final
Statement. He submitted that the Arbitral Tribunal had returned a finding of
fact that the disputes subsequently sought to be raised by the Respondent
pertained to the Final Statement which had already attained finality, and
therefore, the learned Single Judge, impermissibly re-examined the nature of
the disputes and the contractual provisions and treated the Tribunal’s
interpretation as a ‘mistake of law’, though no such ground could justify
interference in the present proceedings.
16.7. He further contended that there was no violation of natural justice or
failure to adjudicate the Respondent’s objections and counter-claims. He
submitted that the Arbitral Tribunal had considered the Respondent’s case
and had first determined the issue of limitation, holding that the counterclaims were barred by time, and having reached such a finding, the Arbitral
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
Tribunal was not required to undertake an elaborate examination of the
merits of claims which were otherwise not maintainable.
16.8. He submitted that the learned Single Judge had also adopted an
impermissibly broad understanding of ‘public policy’ under Section 34 of
the Act of 1996 and had used the said ground to undertake a review of the
Award. It was contended that the Arbitral Tribunal had in fact adjudicated
the disputes and had rejected the Respondent’s counter-claims, inter alia, on
the grounds that there was no contractual basis for reopening the Final
Statement and that the Respondent had failed to challenge the Certificate
within the prescribed period; consequently, the finding that the impugned
Award suffered from a breach of public policy was unsustainable.
16.9. He further submitted that the finding, that the impugned Award
suffered from ‘illegality’ was equally untenable. He contended that the
ground of patent illegality was not available in respect of an International
Commercial Arbitration and, in any event, could not be invoked to reappreciate evidence or revisit the interpretation adopted by the Arbitral
Tribunal.
16.10. He also challenged the reliance placed by the learned Single Judge
upon an alleged contrary view taken by the same Arbitral Tribunal in
another arbitration [contract package C-5]. He submitted that the
composition and factual matrix of the two proceedings were not identical
and that the present Award had to be examined on the basis of the pleadings,
evidence and contractual framework applicable to the present dispute;
comparison with a separate arbitral proceeding could not furnish a
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
permissible ground for setting aside the impugned Award under Section 34
of the Act of 1996.
16.11. He submitted that the learned Single Judge further erred in holding
that the Arbitral Tribunal’s interpretation of the contract was contrary to the
fundamental policy of Indian law. He reiterated that construction of the
contractual provisions was within the domain of the Arbitral Tribunal and
that a different interpretation preferred by the Court could not, by itself,
render the impugned Award contrary to the fundamental policy of Indian
law.
SUBMISSIONS BY THE RESPONDENT
17.
Mr. Ankur Mittal, learned counsel for the Respondent contended that
the learned Single Judge rightly held that the Arbitral Tribunal violated the
principles of natural justice by failing to adjudicate the discrepancies raised
by the Respondent regarding the Certificate dated 31.08.2014.
17.1. He submitted that under Clause 60 of COPA, payments were based on
monthly statements supported by measurements recorded by the Engineer;
the Engineer had approved and Respondent had paid all the IPCs over 7-8
years; however, in the Final Bill dated 24.06.2014, the Appellant
substantially revised the quantities based on as-built drawings, even though
the works had already been measured, certified and paid earlier.
17.2. He submitted that the Respondent sought clarification regarding the
increased quantities certified in the Final Bill; the Appellant responded only
on 01.02.2015 and admitted that the requirements for issuance of a final
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
certificate, including written discharge, had not been fulfilled. He submitted
that the dispute subsequently continued and arbitration was invoked by the
Appellant.
17.3. He contended that since the Appellant had already invoked
arbitration, Respondent was entitled to raise its objections and defences
concerning the correctness of the 31.08.2014 certificate in its Statement of
Defence [‘SoD’] and counter-claim; it was not necessary for the Respondent
to independently invoke arbitration. Reliance was placed on State of Goa v.
Praveen Enterprises3 and National Highway Authority of India v.
Transstroy (India) Ltd.4.
17.4. He contended that the Arbitral Tribunal failed to consider the detailed
calculations and material placed on record demonstrating numerous
discrepancies in the Certificate dated 31.08.2014; despite conducting
approximately 50 hearings, the Arbitral Tribunal did not adjudicate the
correctness of the certificate, which went to the root of the dispute.
17.5. He submitted that Clause 2.6 of GCC permitted the Engineer’s
decision/opinion to be opened, reviewed or revised under Clause 67 of
COPA. He submitted that this power was available irrespective of which
party invoked arbitration and could apply to both claims and defences.
17.6. He submitted that the Respondent had specifically challenged the
quantities and variation-order items and contended that the Appellant’s
claims were theoretical calculations based on as-built drawings rather than
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
(2012) 12 SCC 581
(2022) 15 SCC 91
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
actual site measurements. He submitted that the Respondent placed
extensive pleadings and documents, running into approximately 4,000
pages, before the Arbitral Tribunal, but these were allegedly ignored. He
submitted that the Arbitral Tribunal effectively abandoned its duty to
adjudicate by recording that there was no dispute concerning the amounts
certified on the Certificate dated 31.08.2014.
17.7. He argued that the Arbitral Tribunal itself recognised that
measurements were required to be taken at site and recorded in measurement
books; however, the Certificate dated 31.08.2014 was admittedly based on
as-built drawings rather than actual measurements. He submitted that the
Arbitral Tribunal therefore failed to adjudicate Respondent’s fundamental
objection that the certificate did not correspond with the measurements
recorded during execution.
17.8. He submitted that the Arbitral Tribunal failed to decide whether the
Certificate dated 31.08.2014 was an IPC or an FPC, as the contract did not
contemplate payment of a ‘Final Statement’; payment was contemplated
only through an IPC or FPC under Sub-Clause 60.8 of COPA.
17.9. He submitted that Sub-Clause 60.11 of COPA expressly contemplated
that where the Engineer disagreed with or could not verify any part of the
draft final statement, a dispute would arise and only the undisputed portion
would be certified. Since disputes admittedly existed, the Arbitral Tribunal
ought to have examined the issue rather than treating the certificate as
conclusive.
17.10. He contended that since the certificate was an IPC and not an FPC,
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
Sub-Clause 60.9 of COPA permitted the Engineer to revise or modify it. The
certificate was in fact revised on 13.07.2017 and 31.12.2017. He therefore
contended that the Arbitral Tribunal disregarded the express contractual
terms in treating the earlier certificate as final.
17.11. He further submitted that the Arbitral Tribunal gave findings
inconsistent with another arbitration [contract package C-5] concerning
similar facts, where a common arbitrator Mr. A.K. Yadav, had held that the
relevant payment certificate was an IPC and not an FPC; he argued that
consistency in interpretation of the same contractual provisions should be
maintained.
17.12. He contended that Respondent’s counter-claim arose from mistakes in
the Engineer’s and Appellant’s calculations, which could only be discovered
after detailed examination of the measurement books covering the period
from 2006 to 2014; therefore, limitation could not have commenced merely
from the date of the disputed Certificate dated 31.08.2014.
The revised certificate was issued in 2017, and the counter-claim was
filed on 08.12.2017; he argued that even if limitation were computed from
the date the discrepancies were brought to the Appellant’s notice or
discovered, the counter-claim was within time.
17.13. He submitted that once the Appellant had invoked arbitration,
Respondent was entitled to raise counter-claims in the same proceedings; a
separate invocation would only result in multiplicity of proceedings5.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
State of Goa v. Praveen Enterprises (supra) [Paragraph Nos. 25-33, and 41].
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
FINDINGS AND ANALYSIS
18.
This Court has heard the learned counsel for the parties and perused
the record.
I.
NON-ADJUDICATION OF THE DISPUTE SUBMITTED TO THE
ARBITRAL TRIBUNAL AND RESPONDENT’S DEFENCE
19.
The impugned Award records that the Arbitral Tribunal conducted its
first hearing on 09.08.2017.
20.
The Appellant filed its SoC on 07.10.2017 and raised a claim towards
the balance unpaid amount of Rs. 8,84,22,371/- payable in INR and
$3,391,185 payable in USD along with interest at the rate of 10% from
07.10.2017 till the actual date of payment as per the Certificate dated
31.08.2014. Pertinently, in the SoC, the Appellant narrated the facts which
had transpired between the parties from 31.08.2014 till 07.11.2016
pertaining to the issuance of the Certificate dated 31.08.2014 by the
Engineer and its unilateral modification by the Engineer at the request of the
Respondent, giving rise to the disputes between the parties qua the payments
under the said Certificate, more specifically paragraph nos. 27 to 38 of the
SoC.
21.
A perusal of the SoC clearly shows that all the issues, claims and
differences arising inter se parties out of the Certificate dated 31.08.2014
were made the subject matter of the arbitration proceedings by the
Appellant. In this regard, paragraph no. 38 of the SoC is relevant and is
reproduced hereunder: -
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
“38.
………
Therefore, all issues, claims, differences arising out of the Claimant's
Final Bill as certified by the Engineer are a subject matter of the
present arbitration proceedings and the same are required to be
adjudicated upon by this Hon'ble Tribunal.”
[Emphasis Supplied]
22.
The Respondent filed its SoD and counter-claim dated 08.12.2017,
with the following reliefs:
“(a) Reject the claim of the Claimant as not sustainable in the facts and
circumstances of the case.
(b) Allow the Counter Claim of Respondent of Rs. 2,79,52,299 /-.
(c) Grant pre-arbitration, pendent lite and future interest at the rate of
24%
(d) Cost of the Arbitration proceedings.”
23.
The relevant paragraphs of the SoD and counter-claim read as under: “1. The Present Arbitration proceedings is filed by Claimant seeking
payment of Final Statement of the Claimant dated 24.06.2014 and as
recommended by Engineer vide its payment certification dated
31.08.2014, but the Claimant has conveniently neglected the later
developments including the Revised Certification made by the
Engineer on 18.08.2016. It is important to note that the Engineer
revised his earlier certification, since it was found that there were
some errors, in unsustainable claims made by the Claimant
regarding BOQ and certain rates of the materials etc.,
………
20. The Claimant ought to have raised the Final Statement on or before
12.05.2013 since the Defect Liability Certificate was issued on
04.04.2014, but the Claimant delayed the same. Moreover, Final
Statement should contain all breakup of the details and supporting
documents so that the verification of quantity and other contractual
requirements can be checked by the Engineer as well as by the employer.
It is very important because the Respondent before realizing the Final
Payment has to check each and every claim- of the Claimant to avoid any
over payment of the public money. It is humbly submitted that the
payment for quantities or items of BOQ are payable as per actual
execution of work that site and not as per the quantities of items provided
in BOQ of the contract. Hence, it is clear that as per Good Industry
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
Practice, Final Statement of quantity should have been as per actual
execution of quantities by Claimant, but the Claimant insisted to clear the
Final Statement as per provisions of quantities taken in the contract. It is
pertinent to mention here that actual execution of work at various places
was not executed exactly as per the 'Approved Drawings' and even not as
per 'As Built Drawings'. It is further submitted that for verification of
Final Quantities in Final Statement, the, Respondent sent various notices
to Engineer as well as to the claimant vide letters dated 09.05.2016 and
17.10.2016, but the Claimant did not respond to the said letters of the
Respondent. The Respondent requested the Claimant vide ·its letters
dated 9.05.2016 and 17.10.2016 seeking information for the purpose of
verification of executed Quantity but the Claimant did not provide any
details. The true copy of letters dated 9.05.2016 and 17.10.2016 are
marked and annexed as Annexure R-2(colly).
21. The final Statement dated 24.06.2014 submitted by the Claimant to
the Engineer did not disclose actual quantum of BOQ used in the project
site and it did not disclose the required details for the purpose of
verification of the same.
………
23. Simply submitting that the Final Statement based on contract
quantities does not entitle the contractor to receive those amounts prior to
verification. The Respondent again requested the Claimant vide its letters
dated 9.05.2016 and 17.10.2016 seeking information for the purpose of
verification of executed Quantities but the Claimant did not provide any
detail. The true copy of letters dated 9.05.2016 and 17.10.2016 are
marked as annexures in the above- mentioned para.
………
25. It is submitted that while Respondent was verifying the Final
Statement it released 50% Interim amount of Gross payment as an
Advance i.e. Rs.1,68,63,282/- and USD 162,607.48 in the interest of
progress of work.
………
32. The Claimant without producing the information required by the
Respondent as well as the Engineer, it kept on pressurizing the
Respondent to release the payment as per the final Statement. One such
letter dated 26.04.2016 was sent by Claimant but, the Respondent could
not finalize the verification since the required information was not
provided by Claimant.
………
34. It is incorrect to state that the Respondent somehow wanted to
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
withhold the legitimate claim of the Claimant which became payable in
terms of contract. Infact, the Claimant was in a hurry to get the amount
from Respondent, in excess of the Quantities actually executed & on the
basis of very high Rates than the standard rates. This can be understood
from the conduct of the claimant refusing to produce the relevant
documents including MB’s Measurement Sheets and Test Certificate etc.
………
39. It is incorrect to state that by virtue of the provisions contained in the
contract between the parties; the Respondent is liable to pay a sum of
Rs.6,56,57,179/- payable in INR and $ 2,51,858.57 in USD towards
unpaid Final Statement amount payable to the Claimant as certified by
the Engineer for the works executed by the Claimant. As per modified
final statement (Annexure R-3) submitted by engineer earlier,
respondent is liable to pay net balance sum of INR- 25,06,599/- &
USD 9,711/- only on account of final statement of project.
In fact, the Claimant is liable to pay a sum of Rs. 2,79,52,299/- to
respondent as detailed below(i) Claimant has to make a payment of Rs.2,50,00,000/- to the
Respondent on account of base index taken by the claimant for foreign
inputs as October 2005 in place of September 2005 (28. days prior to bid
submission) annexed as Annexure R-4.
(ii) Claimant has to make a payment of Rs. 29,52,299/- to the Respondent
on account of non- compliance of observations of Vigilance division of
NHAI annexed as Annexure R-5.
[Emphasis Supplied]
24.
A perusal of the SoD and counter-claim shows that the Respondent
specifically disputed its liability to pay the balance amounts claimed by the
Appellant under the Certificate dated 31.08.2014. It challenged the
Certificate dated 31.08.2014, claiming that excess amounts were paid to the
Appellant during the contract and relied upon the Engineer’s revised
Certificate dated 13.07.2017. In addition to the aforesaid challenge to the
Certificate dated 31.08.2014, the Respondent also raised a counter-claim for
recovery of Rs. 2,79,52,299/-, from the Appellant.
25.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
The Respondent thereafter filed an amended counter-claim on
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
13.07.2018 based on another revised Final Bill dated 31.12.2017, claiming
recovery of a lesser amount of Rs. 2,76,12,569/- from the Appellant.
26.
The Arbitral Tribunal, while allowing the claims of the Appellant, has
recorded its findings at paragraph no. 26.0 of the impugned Award. The
findings of the Arbitral Tribunal can be summarised as under: i.
The value of work determined and certified by the Engineer through
IPCs is based on actual executed quantities and the payments were not
released on the basis of estimated quantities included in the Bill of
Quantities [‘BOQ’] as contended by the Respondent in its amended
SoD6.
ii.
The certification done by the Engineer in its monthly IPCs for all the
items of work executed by the Claimant is in accordance with the
drawing approved by the Engineer and is quantified on the basis of
the actual measurements of the various components of work carried
out at the site. Therefore, it represents a milestone-based certification,
and so the quantification done is firm on the date of the issue of the
IPC. The submission of the Respondent that the Engineer was issuing
IPC on a tentative basis was rejected7.
iii.
The monthly certification done by the Engineer in its monthly IPCs,
the quantities of all the items of work executed by the Claimant and
their valuation, as the work proceeded, was available both with the
Engineer and the Respondent, and the Respondent continued to
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
Paragraph 26 (viii) at internal page 42 of the award
Paragraph 26 (x) at internal page 43 of the award
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
release the money based on these certifications. Therefore, the
Respondent could have carried out verification of the quantities
independently, with the assistance of the Engineer or the Claimant or
both, at the stages when IPCs were issued by the Engineer or even
thereafter till they reached a finality through the acceptance of Final
Statement, by both the Engineer and the Claimant8.
iv.
Sub-Clause 60.9 of COPA authorises the Engineer to make by an IPC
any correction or modification in any previous IPC. Engineer also has
the authority to omit or reduce the value of such work in any IPC, if
any work is not being carried out to its satisfaction. Thus, the
Engineer is empowered to make any correction or modification in any
IPC as per Sub-Clause 60.9 of COPA. The Arbitral Tribunal took note
that during the execution of the contract, 72 IPCs have been issued by
the Engineer and the Engineer did not carry out any corrections or
modifications in any of the IPCs. The Arbitral Tribunal concluded
that Sub-Clause 60.9 of COPA is limited to IPCs alone9.
v.
The Arbitral Tribunal categorically held that the submission of the
Respondent that the Engineer could also make corrections or
modifications in the Final Statement agreed between the Engineer and
Claimant under Sub-Clause 60.11 of COPA is not correct10.
vi.
The Arbitral Tribunal held that there was no dispute between the
Engineer and the Claimant on the Draft Final Statement, and so the
Paragraph 26 (xiii) at internal page 44 of the award
Paragraph 26 (xiv) and (xv) at internal pages 44 and 45 of the award
Paragraph 26 (xv) at internal page 45 of the award
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
Final Statement agreed to between the Engineer and the Claimant
became final11.
vii.
The Arbitral Tribunal observed that the Claimant had admittedly
failed to issue any written discharge as required under Sub-Clause
60.12 of COPA. The Tribunal held that in the absence of the written
discharge, the Engineer was not entitled to issue a FPC under SubClause 60.13 of COPA. The Tribunal held that the Engineer had erred
in issuing the FPC12.
viii.
The Arbitral Tribunal held that the Certificate dated 31.08.2014 is not
as per the format of the FPC stipulated in Sub-Clause 10.13 of
COPA13.
ix.
The Arbitral Tribunal14 has observed that as on 24.06.2014 [when the
Appellant submitted the Draft Final Statement] and 31.08.2014 [when
the Appellant submitted the Final Statement], a number of disputes
were pending between the Appellant and the Respondent. It therefore
concluded that the Certificate dated 31.08.2014 issued by the
Engineer is actually NOT the FPC envisaged under Sub-Clause 60.13
of COPA, but was in reality the Final Statement agreed between the
Engineer and the Claimant in terms of Sub-Clause 60.11 of COPA.
The Arbitral Tribunal held that, therefore, the Engineer had termed
the document dated 31.08.2014 incorrectly as the FPC. The Arbitral
Tribunal held that this document, which is signed by both the
Paragraph 26 (xxiii) at internal page 49-50 of the award
Paragraph 26 (xxxi) at internal page 52-53 of the award
Paragraph 26 (xxxii) at internal page 53 of the award
Paragraph 26 (xxii) at internal page 48 of the award.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
Engineer and the Claimant, was Part(a) of the Final Statement agreed
between the Claimant and Engineer under Sub-Clause 60.11 of
COPA, and accordingly it attained finality on 31.08.201415.
x.
The Arbitral Tribunal at paragraph no. 26(xxvii) of the impugned
Award observed that the Respondent has not mentioned the clauses of
the contract which entitle the Respondent or the Engineer to reopen
the Final Statement agreed between the Engineer and the Claimant
and also get it finalised unilaterally by the Engineer without seeking
the consent of the Claimant.
However, the Arbitrator only made an observation and did not
determine the issue as regards the jurisdiction [or lack thereof] of the
Engineer to carry out the modifications to the Final Statement.
xi.
The Arbitral Tribunal held16 that the Final Statement has not been
challenged by any party under Clause 67 of COPA as per
requirements laid down under Clause 2.6 of GCC, and thus, it has
become absolute and has to be implemented. This is the conclusion of
the Arbitral Tribunal which forms the basis of awarding the principal
amount claimed by the Appellant in its SoC on the basis of the
Certificate dated 31.08.2014.
27.
To summarise, the Arbitral Tribunal by its impugned Award decided
the claims raised in the SoC of the Appellant, separately from the counterclaim of the Respondent. The Arbitral Tribunal allowed the claims of the
Appellant for the principal amount and future interest thereon, as per the
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
Paragraph 26 (xxxiii) at internal page 53-54 of the award
Paragraph 26 (xxxiv) at internal page 54 of the award
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
Certificate dated 31.08.2014 issued by the Engineer; however, it rejected the
claim for interest for the period from 31.08.2014 to 07.10.2017 [i.e. the date
of filing of SoC], as well as rejected the claim for interest for the pendente
lite period from 08.10.2017 till 26.06.2021 [i.e. the date of passing of the
award].
The Arbitral Tribunal held that said Certificate dated 31.08.2014 is
actually the Final Statement as contemplated under Sub-Clause 60.11 of
COPA. The Arbitral Tribunal concluded that the said Final Statement was
agreed between the Claimant and the Engineer, and it has attained finality on
31.08.2014, since it has ‘not been challenged’ by any party under Clause 67
of COPA as per the requirement laid down under Clause 2.6 of GCC. The
relevant paragraph no. 26(xxxiv) of the impugned Award reads as under: “xxxiv. Since this part of Final Statement has not been challenged by
any Party under Clause 67 of COPA as per requirements laid down
under Clause 2.6 of the Contract, it has become absolute and has to be
implemented.”
[Emphasis Supplied]
28.
In our considered opinion, the finding of the Arbitral Tribunal at
paragraph no. 26 (xxxiv) of the impugned Award that the Final Statement
has ‘not been challenged’ by any party, appears to be on the premise that
there is ‘no’ formal claim or challenge to the Certificate dated 31.08.2014,
by the Respondent. It appears that the Arbitral Tribunal was of the view that
a formal claim is required under Clause 2.6 of GCC read with Clause 67 of
COPA.
29.
The learned Single Judge has held that the said finding of the Arbitral
Tribunal that the Certificate dated 31.08.2014 ‘has not been challenged’, is
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
contrary to the record as it fails to take into consideration the specific pleas
raised by the Respondent in the SoD, challenging the veracity of the
Certificate dated 31.08.2014. The learned Single Judge held that, in fact, the
Arbitral Tribunal has failed to adjudicate on the elaborate pleas raised by the
Respondent challenging the Certificate dated 31.08.2014. It has therefore
concluded that the failure of the Arbitral Tribunal to adjudicate the pleas of
the Respondent challenging the veracity of the Certificate dated 31.08.2014
had resulted in non-adherence to the principles of natural justice and
amounts to a violation of public policy. The learned Single Judge has
therefore opined that the challenge to the impugned Award is made out
under Section 34 of the Act of 1996.
A.
The issue of correctness (or otherwise) of the Certificate dated 31.08.2014
was, indeed, a dispute referred to the Arbitral Tribunal
30.
Having perused the SoC and the SoD, there is no doubt in our mind
that the cause of action for the Appellant to invoke the arbitration clause was
the dispute which had arisen between the parties with respect to the
correctness [or otherwise] of the Certificate dated 31.08.2014.
31.
The pleadings of the SoC reveal that Appellant was aggrieved that the
Respondent was not releasing balance payments due under the Certificate
dated 31.08.2014. The Appellant was aggrieved by the Respondent’s
objections to the Certificate dated 31.08.2014, and this led to exchange of
several letters between the parties, eroding the binding nature of the said
Certificate. The Appellant was aggrieved that the Engineer, vide
communication dated 18.08.2016, had unilaterally revised the Certificate
dated 31.08.2014, and recorded negative payment as well as recommended
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
recoveries from the Appellant. It was in the backdrop of these unresolved
disputes that the Appellant invoked arbitration vide notice dated 07.11.2016,
and, as expressly stated in paragraph no. 38 of its SoC, submitted for
adjudication of all issues, claims and differences arising out of the
Certificate dated 31.08.2014. In this regard, paragraph no. 38 of the SoC is
relevant and is reproduced hereunder: “38.
………
Therefore, all issues, claims, differences arising out of the Claimant's
Final Bill as certified by the Engineer are a subject matter of the
present arbitration proceedings and the same are required to be
adjudicated upon by this Hon'ble Tribunal.”
[Emphasis Supplied]
32.
In the SoD, the Respondent specifically disputed the correctness of
the computation of value of work done in the Certificate dated 31.08.2014. It
denied its liability to make payment of any balance amount as per the said
Certificate. In addition, it raised a counter-claim for recovery of excess
payments made to the Appellant. The Respondent relied upon the modified
Final Bill issued by the Engineer which, as per the Respondent, superseded
the Certificate dated 31.08.2014. Illustratively, the opening para of the SoD,
which acknowledges the dispute qua the veracity of the Certificate dated
31.08.2014, reads as under: “1. The Present Arbitration proceedings is filed by Claimant seeking
payment of Final Statement of the Claimant dated 24.06.2014 and as
recommended by Engineer vide its payment certification dated
31.08.2014, but the Claimant has conveniently neglected the later
developments including the Revised Certification made by the
Engineer on 18.08.2016. It is important to note that the Engineer
revised his earlier certification, since it was found that there were
some errors, in unsustainable claims made by the Claimant
regarding BOQ and certain rates of the materials etc.”
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
[Emphasis Supplied]
33.
In our considered opinion, the rival pleadings of the parties in the SoC
and SoD expressly acknowledged that the correctness [or otherwise] of the
Certificate dated 31.08.2014, issued by the Engineer, was directly a subject
matter of the challenge in the arbitration proceedings. While the Appellant
undertook the onus to prove the correctness of the Certificate dated
31.08.2014 for seeking the payments due to it, the Respondent as well
undertook the onus to prove its objections to the Certificate dated
31.08.2014. This was the only issue raised by the Appellant in its SoC and
Respondent in the SoD for the consideration of the Arbitral Tribunal. As a
matter of fact, at the arbitral proceedings, the Respondent filed voluminous
evidence to prove its objections to said Certificate. Thus, the correctness [or
otherwise] of the Certificate dated 31.08.2014 was directly an issue arising
for consideration before the Arbitral Tribunal.
However, the Arbitral Tribunal, in a remarkable turn of events, has at
paragraph no. 26(xxxiv) of the impugned Award returned a finding that the
said Certificate dated 31.08.2014 [or Final Statement as characterized by the
Arbitral Tribunal] has not been challenged. We are unable to agree with the
said conclusion of the Arbitral Tribunal. The correspondence preceding the
invocation of Clause 67 of COPA and the commencement of the arbitration
proceedings, read with the rival pleadings of the parties before the Arbitral
Tribunal, leaves little doubt that the Certificate dated 31.08.2014 was the
very subject matter of the dispute inter se parties as contemplated under
Clause 2.6 of GCC.
34.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
As noted above, the Certificate dated 31.08.2014 was sought to be
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
corrected by the Engineer itself on 18.08.2016, and ultimately an amended
Final Bill dated 31.12.2017 was also issued by the Engineer, which showed
that, in fact, the Respondent had to effect recoveries from the Appellant.
Whether the corrections and recoveries proposed by the Engineer on
18.08.2016 or 31.12.2017 were permissible or correct or incorrect were the
issues which were directly arising for consideration and adjudication before
the Arbitral Tribunal. However, the Arbitral Tribunal has abjectly failed to
adjudicate on this issue on the basis of its finding at paragraph no. 26(xxxiv)
of the impugned Award, which is entirely wrong in the facts of this case and
cannot be sustained. Its failure to do so, while proceeding on the erroneous
premise that the Certificate dated 31.08.2014 had not been challenged by the
Respondent, amounts to a failure to adjudicate the disputes falling within the
terms of the submission to arbitration.
35.
It is a settled position of law that the existence of a dispute is a
necessary pre-condition to the invocation of arbitration [Re: Inder Singh
Rekhi v. Delhi
Development
Authority17].
Illustratively,
had
the
Respondent not disputed the Appellant’s entitlement for the balance
payment under the Certificate dated 31.08.2014 and had merely defaulted in
releasing the admitted amount, there would have been no dispute requiring
adjudication by the Arbitral Tribunal. In such a scenario, since the dues
stand admitted, the Appellant would have either filed a writ petition for
release of the admitted dues or filed a suit for recovery. [Re: Surya
Constructions v. State of Uttar Pradesh and Others18]
However, this is not the factual situation in this case, as the
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
(1988) 2 SCC 338 [Paragraph No. 4]
(2019) 16 SCC 794 [Paragraph No. 3]
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
Respondent has been consistently, since 15.10.2014, disputing the veracity
of the Certificate dated 31.08.2014 and disputing the entitlement of the
Appellant to seek payment thereunder. It was to resolve this precise dispute
that the Appellant invoked arbitration vide notice dated 07.11.2016 on the
express contention that the Respondent and the Engineer were wrongfully
disputing the correctness of the Certificate dated 31.08.2014. The Arbitral
Tribunal was thus bound to adjudicate upon the correctness of the Certificate
dated 31.08.2014 before allowing the claims of the Appellant.
The Arbitral Tribunal at paragraph no. 26(xxxiv) of the impugned
Award has wrongly concluded that the Certificate dated 31.08.2014 had not
been challenged by any party, whereas the determination of the correctness
of the said Certificate was actually the core issue in the SoC. The
Respondent’s defence, disputing the correctness of the said Certificate,
challenged the very foundation of the Appellant’s claim to balance payment
under the Certificate dated 31.08.2014 and, therefore, the defence
constituted a material issue requiring adjudication. The Arbitral Tribunal
has, however, failed to adjudicate the Respondent’s substantive defence to
the Appellant’s claim, on its erroneous finding at paragraph no. 26(xxxiv) of
the impugned Award.
36.
The distinction between an erroneous adjudication of an issue, by the
Arbitral Tribunal, and a failure to adjudicate an issue submitted to
arbitration is material. The failure to adjudicate the matters that have been
submitted to the Arbitral Tribunal would make the impugned Award
vulnerable to challenge under Section 34(2)(a)(iv) of the Act of 1996 if it
results in prejudice to the parties to the dispute. In Ssangyong Engineering
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
& Construction Co. Ltd. v. National Highways Authority of India19,
while considering Article 34(2)(a)(iii) of the UNCITRAL Model Law which
corresponds to Section 34(2)(a)(iv) of the Act of 1996, the Supreme Court
cited with affirmation the judgment of Court of Appeal of Singapore, in
CRW Joint Operation v. PT Perusahaan Gas Negara (Persero) TBK20,
which held that the said provision of UNCITRAL Model Law applies not
only where an arbitral tribunal improperly decides matters which had not
been submitted to it, but also where it ‘failed to decide matters that had been
submitted to it’, since in either situation the tribunal has exceeded or failed
to exercise the authority conferred upon it by the parties. The Court of
Appeal at Singapore clarified that failure to deal with every issue referred to
the tribunal would not, by itself, warrant setting aside an award; the crucial
consideration is whether such failure has resulted in real or actual prejudice
to a party. The relevant portion of the judgment reads as under: “61. The Court of Appeal of Singapore, in CRW Joint Operation v. PT
Perusahaan Gas Negara (Persero) TBK, held as follows:
“25. The court's power to set aside an arbitral award is limited to setting
aside based on the grounds provided under Article 34 of the Model Law
and Section 24 of the IAA. As declared by this court in Soh Beng Tee &
Co. (Pte) Ltd. v. Fairmount Development (Pte) Ltd. [Soh Beng Tee &
Co. (Pte) Ltd. v. Fairmount Development (Pte) Ltd.21, SLR(R) para 59
(“Soh Beng Tee”), the current legal framework prescribes that the courts
should not without good reason interfere in the arbitral process. This
policy of minimal curial intervention by respecting finality in the arbitral
process acknowledges the primacy which ought to be given to the dispute
resolution mechanism that the parties have expressly chosen.
26. However, it has also been said (correctly) that no State will permit a
binding arbitral award to be given or enforced within its territory without
(2019) 15 SCC 131
2011 SGCA 33
(2007) 3 SLR (R) 86
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
being able to review the award, or, at least, without allowing the parties
an opportunity to address the court if there has been a violation of due
process or other irregularities in the arbitral proceedings [see Peter
Binder, International Commercial Arbitration and Conciliation in
UNCITRAL Model Law Jurisdictions (Sweet & Maxwell, 3rd Edn.,
2010) at para 7-001].
27. While the Singapore courts infrequently exercise their power to set
aside arbitral awards, they will unhesitatingly do so if a statutorily
prescribed ground for setting aside an arbitral award is clearly
established. The relevant grounds in this regard can be classified into
three broad categories [see generally Nigel Blackaby et al, Redfern and
Hunter on International Arbitration (Oxford University Press, 5th Edn.,
2009) (“Redfern and Hunter”) at paras 10.30-10.86]. First, an award may
be challenged on jurisdictional grounds (i.e. the non-existence of a valid
and binding arbitration clause, or other grounds that go to the
adjudicability of the claim determined by the Arbitral Tribunal). Second,
an award may be challenged on procedural grounds (e.g. failure to give
proper notice of the appointment of an arbitrator), and, third, the award
may be challenged on substantive grounds (e.g. breach of the public
policy of the place of arbitration).”
*
*
*
31. It is useful, at this juncture, to set out some of the legal principles
underlying the application of Article 34(2)(a)(iii) of the Model Law.
First, Article 34(2)(a)(iii) is not concerned with the situation where an
Arbitral Tribunal did not have jurisdiction to deal with the dispute which
it purported to determine. Rather, it applies where the Arbitral
Tribunal improperly decided matters that had not been submitted to
it or failed to decide matters that had been submitted to it. In other
words, Article 34(2)(a)(iii) addresses the situation where the Arbitral
Tribunal exceeded (or failed to exercise) the authority that the
parties granted to it (see Gary B. Born, International Commercial
Arbitration (Wolters Kluwer, 2009) at Vol. 2, pp. 2606-07 and 279899). This ground for setting aside an arbitral award covers only an
Arbitral Tribunal's substantive jurisdiction and does not extend to
procedural matters [see Robert Merkin & Johanna Hjalmarsson,
Singapore Arbitration Legislation Annotated (Informa, 2009)
(“Singapore Arbitration Legislation”) at p. 117].
32. Second, it must be noted that a failure by an Arbitral Tribunal to deal
with every issue referred to it will not ordinarily render its arbitral award
liable to be set aside. The crucial question in every case is whether
there has been real or actual prejudice to either (or both) of the
parties to the dispute. In this regard, the following passage in Redfern
and Hunter ([27] supra at para 10.40) correctly summarises the position:
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
The significance of the issues that were not dealt with has to be
considered in relation to the award as a whole. For example, it is not
difficult to envisage a situation in which the issues that were overlooked
were of such importance that, if they had been dealt with, the whole
balance of the award would have been altered and its effect would have
been different.
(emphasis added)
33. Third, it is trite that mere errors of law or even fact are not sufficient
to warrant setting aside an arbitral award under Article 34(2)(a)(iii) of the
Model Law [see Sui Southern Gas Co. Ltd. v. Habibullah Coastal Power
Co. (Pte) Ltd. [Sui Southern Gas Co. Ltd. v. Habibullah Coastal Power
Co. (Pte) Ltd.22, (2010) 3 SLR 1], SLR paras 19-22]. In the House of
Lords decision of Lesotho Highlands Development Authority v.
Impregilo SpA23, which concerned an application to set aside an arbitral
award on the ground of the Arbitral Tribunal's “exceeding its powers”
[see Section 68(2)(b) of the Arbitration Act, 1996 (c 23) (UK) (“the UK
Arbitration Act”)], Lord Steyn made clear (at [24]-[25]) the vital
distinction between the erroneous exercise by an Arbitral Tribunal of an
available power vested in it (which would amount to no more than a mere
error of law) and the purported exercise by the Arbitral Tribunal of a
power which it did not possess. Only in the latter situation, his Lordship
stated, would an arbitral award be liable to be set aside under Section
68(2)(b) of the UK Arbitration Act on the ground that the Arbitral
Tribunal had exceeded its powers. In a similar vein, Article 34(2)(a)(iii)
of the Model Law applies where an Arbitral Tribunal exceeds its
authority by deciding matters beyond its ambit of reference or fails to
exercise the authority conferred on it by failing to decide the matters
submitted to it, which in turn prejudices either or both of the parties
to the dispute (see above at [31]).”
[Emphasis Supplied]
37.
The obligation of the Arbitral Tribunal under the Act of 1996 to
adjudicate upon the defence raised by the Respondent is enshrined in
Section 18 and Section 34(2)(a)(iii) of the Act of 1996. The Supreme Court
in Associate Builders v. Delhi Development Authority24 held that the said
provisions enshrine the fundamental juristic principles of natural justice.
(2010) 3 SLR 1
(2006) 1 AC 221: (2005) 3 WLR 129: 3 AII ER 789 (HL)
(2015) 3 SCC 49 [Paragraph No. 30].
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
38.
In our considered opinion, the jurisdiction of the Arbitral Tribunal
under Clause 2.6 of GCC to review the Certificate dated 31.08.2014 for its
correctness had been invoked by the Appellant itself in the SoC. The
Respondent consented to this reference to arbitration and submitted its SoD
disputing the correctness of the said Certificate and filing its objections to
the said Certificate. The Arbitral Tribunal was therefore obliged to decide
the issue of the correctness [or otherwise] of the Certificate dated
31.08.2014, on the basis of the pleadings in the SoC and SoD as well as the
documents, even excluding the counter-claim. The absence of a formal
claim by the Respondent challenging the Certificate dated 31.08.2014
cannot be a justification for not adjudicating this issue, as the challenge by
the Respondent to the Certificate dated 31.08.2014 was unambiguous and
clear in the notice dated 07.11.2016 issued by the Appellant invoking
arbitration, and the pleadings. Assuming a formal claim was required, since
all necessary pleadings and evidence were on record, the Arbitral Tribunal
ought to have permitted the Respondent to amend the pleading to include
such a formal claim. However, at the culmination of the arbitral proceedings
which spanned over 50 hearings, where arguments were addressed by parties
on the correctness [or otherwise] of the Certificate dated 31.08.2014, the
Arbitral Tribunal could not have declined to adjudicate this issue on a thin
premise of lack of a formal claim.
39.
In our considered opinion, the Arbitral Tribunal’s conscious omission
to adjudicate upon the correctness [or otherwise] of the Certificate dated
31.08.2014 not only violated the principles of natural justice, as the Tribunal
failed to adjudicate upon the defense of the Respondent, but the impugned
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
Award also violated Section 34(2)(a)(iv) of the Act of 1996 read with
Article 34(2)(a)(iii) of the UNCITRAL Model Law as the Tribunal had
abjectly failed to decide the dispute with respect to the correctness [or
otherwise] of the Certificate dated 31.08.2014 referred to it by the parties.
40.
The Respondent’s challenge to the correctness of the Certificate dated
31.08.2014 questioned and disputed that the Appellant was entitled to the
balance amount claimed on the basis of the said Certificate. By proceeding
on the erroneous premise that the said Certificate had not been challenged,
the Arbitral Tribunal failed to exercise the authority conferred upon it by the
parties, in respect of a material dispute submitted to it, thereby causing
prejudice to the Respondent. The impugned Award, to that extent, is
therefore unsustainable under Section 34(2)(a)(iii) and Section 34(2)(a)(iv)
of the Act of 1996. The non-adjudication of a material defence also violates
the basic requirement of a fair adjudicatory process, and the impugned
Award is in conflict with the public policy of India under Section
34(2)(b)(ii) Explanation (iii) of the Act of 1996.
B.
The findings on limitation governing counter-claim filed by the Respondent
failed to take into consideration correspondence exchanged between the parties
41.
The Arbitral Tribunal in its first hearing on 09.08.2017 had granted
time to the Respondent vide paragraph no. 18(b) of its order to file its SoD
and counter-claim, latest by 11.12.2017.
42.
The Respondent filed its SoD and counter-claim, initially, on
08.12.2017 challenging the correctness of the Certificate dated 31.08.2014
and seeking recovery for a sum of Rs. 2,79,52,299/- as per the modified
Final Bill dated 13.07.2017 certified by the Engineer. The Respondent
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
amended its counter-claim on 13.07.2018 to make a claim for a lesser
amount of Rs. 2,76,12,569/- as per the modified Final Bill dated 31.12.2017
as certified by the Engineer.
43.
The Arbitral Tribunal held that the period for limitation to raise the
counter-claim arose on 15.10.2014, when the Respondent for the first time
acknowledged mistakes in the Certificate dated 31.08.2014. The Arbitral
Tribunal held that the period of three years for filing the counter-claim
expired on 15.10.2017 and therefore held that the counter-claim filed on
08.12.2017 was barred by limitation. The Arbitral Tribunal held that the date
[i.e., 08.12.2017] of filing of the SoD and SoC was the date of reference to
arbitration.
44.
The Respondent has contended that the correspondence on the record
shows that after the Respondent objected to the Certificate dated 31.08.2014,
vide its letter dated 15.10.2014 by pointing out discrepancies and seeking
clarifications, however, the Appellant responded to the said letter for the
first time on 01.02.2015. It contends that various letters were issued by the
Respondent between 2016-17 seeking information for verifying the Final
Bill/Final Statement dated 31.08.2014 and requesting the Appellant for a
written discharge as per Sub-Clause 60.12 of COPA. The Respondent relies
upon Appellant’s letters dated 16.05.2016, 23.09.2016 and 06.10.2016
objecting to the exercise undertaken by the Respondent in verifying the
Certificate dated 31.08.2014. The Respondent also relied upon the letter
dated 18.08.2016 and 19.09.2016 issued by the Engineer carrying out
modifications to the Certificate dated 31.08.2014. The Respondent relied
upon the revised final bill dated 13.07.2017 issued by the Engineer, which
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
was further modified on 31.12.2017 by the Engineer raising a final claim for
recovery of Rs. 2,76,12,569/- from the Appellant, in favour of the
Respondent.
44.1. The Respondent states that since, as per the Arbitral Tribunal, the
Certificate dated 31.08.2014 was not an FPC and was allegedly a Final
Statement, unaccompanied by a written discharge from the Appellant, it
could not have held the counter-claim to be time-barred. The Respondent
states that its limitation to file the counter-claim arose in 2017 when the
revised Final Bill was issued by the Engineer. The Respondent states that
therefore its claims were within limitation.
45.
The Appellant has relied upon the findings of the Arbitral Tribunal to
contend that the counter-claim is barred by limitation.
46.
In our considered opinion, with the setting aside of the Award qua the
claims of the Appellant in the SoC, this part of the Award also needs to be
set aside, as the determination of the character of the Certificate dated
31.08.2014 by the Arbitral Tribunal, on a fresh consideration, will have a
direct bearing on the date of commencement of limitation of the counterclaim. Whether the Certificate will be held to be a final payment certificate
or an interim payment certificate or incorrect, are findings which will have a
material bearing on the issue of limitation. Thus, the issue of counter-claims
being barred or within limitation is intrinsically linked and would also have
to be remanded back.
47.
Also, we note that the Appellant in its letter dated 07.11.2016, while
invoking arbitration, enlisted reference to 16 letters exchanged between the
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
Appellant, Respondent and the Engineer demonstrating dispute. The letter
dated 26.09.2016 issued by the Respondent and enlisted at Sr. No. 4 of this
letter shows that the Respondent issued a recovery demand of Rs. 7,88,687/against the Appellant herein for the subject contract and specifically
disputed any liability to make any further payment under the Certificate
dated 31.08.2014. The Respondent referred to the Engineer’s letter dated
18.08.2016 making corrections to the Certificate dated 31.08.2014.
Similarly, the Engineer, by a letter dated 19.09.2016 [enlisted at Sr. No. 6],
made a further recommendation to the final bill, which was also disputed by
the Appellant vide response letter dated 23.09.2016. The Appellant referred
the disputes between the parties enlisted in the 16 letters enlisted in the
reference to arbitration. The recovery claim of the Respondent in its letter
dated 26.09.2016 on the Appellant, therefore, stood referred to arbitration by
the Appellant itself.
48.
We, however, note that the Arbitral Tribunal while deciding the issue
of limitation has not taken into consideration the effect of the Appellant’s
reference letter dated 07.11.2016 which refers the claim of recovery raised
by the Respondent to arbitration on 07.11.2016. It is apparent that the
counter-claim of the Respondent for recovery stood referred to arbitration by
the Appellant itself. Thus, while computing limitation for the counter-claim,
the Arbitral Tribunal would have to take into consideration the effect of the
letter of reference dated 07.11.2016 [including letter dated 26.09.2016] as
per the judgment of the Supreme Court in State of Goa v. Praveen
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
Enterprises (supra)25.
49.
We are refraining from deciding the issue of limitation in this
judgment, as it would be a finding on merits. We deem it appropriate to
leave the issue open to be decided by the Arbitral Tribunal after duly
considering the facts discussed above. We may note that rejection of the
counter-claims on a wrong finding of bar of limitation would render the
impugned Award vulnerable under Section 34(2)(a)(iii) of the Act of 1996,
as it would lead to wrongful non-adjudication of the counter-claims on
merits.
II.
IRRECONCILABLE
CONTRADICTION
IN
TWO
SEPARATE
ARBITRAL AWARDS, IN TWO SEPARATE CONTRACTS (HAVING
IDENTICAL TERMS AND CONDITIONS), EVEN THOUGH TWO MEMBERS
OF THE TRIBUNAL ARE COMMON
50.
The learned Single Judge set aside the impugned Award dated
26.06.2021 on a finding that in another arbitration proceeding between the
same parties pertaining to contract package C-5, arising out of a contract
containing identical terms and conditions, the award dated 01.12.2019
therein returned contradictory findings, on the identical facts of the contract.
The learned Single Judge noted that two members of the Tribunal were
common.
51.
The impugned Award is dated 26.06.2021 and has been passed in
contract package C-6.
52.
The contradiction, as noted by the learned Single Judge, has arisen
with a prior award dated 01.12.2019 passed in contract package C-5.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
Paragraph 20.
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
53.
The terms and conditions of the contracts, in contract package C-5
and contract package C-6, are identical. The parties are identical. The facts
and issues arising for consideration are near identical.
54.
The impugned Award is subsequent to the award dated 01.12.2019;
however, it contains no explanation from the common members of the
Arbitral Tribunal as regards the basis for returning materially different
findings on identical facts, in an identical contract.
55.
We will now consider the effect, if any, of these contradictions on the
legality of the impugned Award.
56.
In contract package C-5, for disputes arising out of a contract
containing identical terms and conditions, the document issued by the
Engineer, i.e., FPC dated 19.08.2014 therein, has been held by the majority
members of the Arbitral Tribunal as an IPC in the award dated 01.12.2019.
The majority members of the Arbitral Tribunal held that since the draft final
statement dated 12.02.2014 issued by the Contractor [i.e., the Appellant]
was for Rs. 1,16,74,65,455/-, while the Engineer had certified only part
amount of Rs. 9,70,97,582/- against the claimed amount, therefore, the
certification issued by the Engineer on 19.08.2014 for the part amount of
Rs. 9,70,97,582/- cannot be notified as an FPC under Sub-Clause 60.13 of
COPA. The Arbitral Tribunal held that the certificate for the part amount of
Rs. 9,70,97,582/- is only an IPC as per Sub-Clause 60.11 of COPA. The
Arbitral Tribunal took note that since no written discharge had been issued
by the contractor as per Sub-Clause 60.12 of COPA and therefore, in the
absence of the written discharge as well as an agreed final statement
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
between the contractor and the Engineer as per Sub-Clause 60.11 of COPA,
the Engineer could not have issued an FPC on 19.08.2014. The Arbitral
Tribunal therein held that, therefore, the said IPC could be corrected or
revised by the Engineer. The majority members thereafter proceeded to
adjudicate on the objections raised by the Respondent to the correctness of
the certificate dated 19.08.2014. The said arbitral award is in favour of the
Respondent and has been challenged by the Appellant, and is pending
adjudication.
The majority members of the Arbitral Tribunal which took this view
consisted of Mr. B.V. Tripathi, the Presiding Arbitrator and Mr. A.K.
Yadav.
The third member of the Tribunal, Mr. Ashok Khurana, recorded his
dissent and held the Certificate dated 19.08.2014 issued by the Engineer to
be an FPC as per Sub-Clause 60.13 of COPA.
57.
We note that Mr. A.K. Yadav and Mr. Ashok Khurana are both
members of the Arbitral Tribunal, which has passed the impugned Award
dated 26.06.2021 and is the subject matter of this appeal.
58.
In the impugned Award, which is the subject matter of the present
appeal, the Arbitral Tribunal has unanimously held that the document
bearing the nomenclature of an FPC dated 31.10.2014 by the Engineer
cannot be held to be an FPC but it is a Final Statement under Sub-Clause
60.11 of COPA. The Arbitral Tribunal concluded that therefore the Engineer
could not have corrected or revised it.
59.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
The findings in the impugned Award that the Certificate dated
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
31.08.2014 issued by the Engineer is actually a Final Statement under SubClause 60.11 of COPA run contrary to the findings returned by both these
members, Mr. A.K. Yadav and Mr. Ashok Khurana, in their separate
opinions, in the earlier award dated 01.12.2019 in contract package C-5.
60.
Mr. Ashok Khurana and Mr. A.K. Yadav are two members who are
common to the Arbitral Tribunal which decided the Arbitration proceedings
in contract package C-5 and contract package C-6 [subject contract]. The
terms and conditions of the two contracts are identical. The Engineer issued
a Certificate bearing nomenclature Final Payment Certificate dated
19.08.2014 [‘FPC dated 19.08.2014’] under contract package C-5 and a
certificate bearing nomenclature Final Payment Certificate dated 31.08.2014
under contract package C-6 [‘FPC dated 31.08.2014’].
61.
In identical facts and in identical contractual terms, while dealing with
contract package C-5, Mr. A.K. Yadav has held FPC dated 19.08.2014 is an
IPC, which is governed by Sub-Clause 60.9 of COPA and held that the same
can be corrected or revised by the Engineer. However, in contradiction, Mr.
A.K. Yadav, while deciding contract package C-6, has held the FPC dated
31.08.2014 as a Final Statement, which is governed by Sub-Clause 60.11 of
COPA and has opined that the same cannot be corrected or revised by the
Engineer.
There is no distinction discernible on the face of the record to justify
the contradictory findings returned by Mr. A.K. Yadav. The impugned
Award does not disclose any cogent reason for such a departure. Mr. A.K.
Yadav has neither explained the basis on which the earlier finding was
arrived at in the award dated 01.12.2019, nor identified any material
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
distinguishing circumstances in which the subsequent finding was returned
in the impugned Award. In the absence of any such explanation, the
departure from the earlier finding remains unexplained and renders the
reasoning of the impugned Award wholly inconsistent with the award dated
01.12.2019.
62.
Similarly, Mr. Ashok Khurana in his dissent opinion dated
01.12.2019, while dealing with contract package C-5 has held that FPC
dated 19.08.2014 is indeed a final payment certificate in terms of SubClause 60.13 of COPA and therefore cannot be corrected or revised by the
Engineer. However, in contradiction, Mr. Ashok Khurana, in the impugned
Award while deciding contract package C-6, has held that the FPC dated
31.08.2014 is not a final payment certificate as per Sub-Clause 60.13 of
COPA. He held that instead the FPC dated 31.08.2014 is a Final Statement
as per Sub-Clause 60.11 of COPA.
Similarly, there is no distinction discernible on the face of the record
in these contradictory findings returned by Mr. Ashok Khurana in the two
arbitration proceedings. The nuanced shift in the finding is anomalous, and
the Court is unable to appreciate the distinction. There is no explanation
recorded in the impugned award by Mr. Ashok Khurana to justify the
distinct views returned by it on the document titled final payment
certificate[s] as issued by the Engineer.
63.
The contradiction in the findings returned by Mr. A.K. Yadav and Mr.
Ashok Khurana in the arbitral awards concerning contract packages C-5 and
C-6 is, in the facts of the present case, neither justified on appreciation of
evidence nor an alternative interpretation of contractual terms. The
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
impugned Award in contract package C-6 was rendered subsequent to the
award dated 01.12.2019 in contract package C-5. Yet, notwithstanding their
participation in the earlier proceeding, the common members have returned
diametrically opposite findings on the character and legal effect of the
corresponding certificates, without the impugned Award disclosing any
distinguishing feature in the contractual stipulations or the relevant factual
circumstances, or any reason for departing from the position taken in the
earlier proceeding. The distinction in these findings in the two awards has
had dramatically different consequences on the permissibility of subsequent
actions of the Engineer in correcting or revising the certificates on the basis
of the documents and objections raised by the Respondent.
64.
Consistency, certainty and predictability are recognized as the
hallmarks of a sound justice delivery system. The intent which ordinarily
parties have while selecting common members of Tribunals for adjudicating
disputes arising between the same parties, in related disputes, is to ensure
that parties receive consistent decisions from the arbitral tribunal. In the
present case, Mr. A.K. Yadav, who is the nominee member of the
Respondent and Mr. Ashok Khurana, who is the nominee member of the
Appellant, have both returned inconsistent findings in the two arbitral
awards referred above, which are irreconcilable despite the fact that the
contractual terms of the contract and facts in both arbitral proceedings are
identical, or near identical.
65.
There is no justification recorded by the common members in the
impugned Award for taking this diametrically different view. Since the
impugned Award is dated 26.06.2021, it is ex-facie subsequent to the award
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
dated 01.12.2019. The common members of the Arbitral Tribunal are
obliged to justify the different view being taken by them in the subsequently
passed impugned Award.
In this regard, we find it apposite to rely on the dicta in the judgment
of National Highway Authority of India v. Progressive- MVR (JV)26 by
the Supreme Court wherein it was held that, because conflicting arbitral
awards had interpreted the same clause of the contract differently, the
ordinary rule of non-interference with a plausible arbitral view under
Section 34 of the Act of 1996, could not be mechanically applied. The
relevant paragraph reads as follows:
“40. Once we interpret the formula in the manner indicated above, the
necessary consequences would be to hold that the Arbitral Tribunal(s)
did not decide the cases with the correct application of the formula and
further that the claim for price adjustment in respect of bitumen laid by
the contractors was not correct. Therefore, it can be held that the
Award(s) are contrary to the contractual terms. At the same time, this
outcome poses a dilemma inasmuch as in these cases, the Arbitral
Tribunal has taken a particular view and when this was a plausible view,
keeping in mind the parameters of judicial review of the Court in
exercise of powers under Section 34 of the Act, normally the Court
would not interfere with such Awards. However, as already indicated
above, such a situation has arisen because of conflicting Awards
given by the Arbitral Tribunals themselves, which has provoked this
Court to take a final view in the matter, necessitated by the aforesaid
reason. If one takes into consideration the theory that one applies the
principle mechanically i.e. that a plausible view is not to be interfered
with, then it may lead to very anomalous situation. In such an
eventuality, view taken by a particular Arbitral Tribunal in favour of the
Contractor would be upheld as plausible view. Likewise, the Court will
have to uphold the view taken by a particular Arbitral Tribunal in favour
of NHAI as well, as a plausible view. Therefore, the purpose is to avoid
such a situation which cannot be permitted as it would result in
upholding both kinds of arbitral awards interpreting the same
clause, whether they go in favour of the employer or they go in
favour of the contractor. When the exercise is done keeping in view
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
(2018) 14 SCC 688
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
these considerations and outcome thereof is not determined, interest of
justice would also demand that this result has to be applied to the pending
cases, which have not attained finality. Therefore, in these peculiar
circumstances, we hold that the principle of issue estoppel will apply
only in those cases where matters have attained finality and no judicial
proceedings are pending. In all those cases, including the present one,
where awards are challenged on this particular aspect, this judgment will
govern the outcome.”
[Emphasis Supplied]
In our considered opinion, the view expressed by the Supreme Court
in the aforesaid judgment is relevant. The Supreme Court observed that
arbitral tribunals had created an anomalous situation by interpreting identical
contractual terms distinctly in separate awards, which resulted in contrary
awards in favour of the parties. The Supreme Court recognised that this was
not permissible. The Supreme Court held it is imperative that identical
clauses should be interpreted consistently by the arbitral tribunals.
66.
The Appellant has contended that inconsistent views between the two
arbitral awards cannot be a ground for setting aside the impugned Award
under Section 34 of the Act of 1996. The Appellant, on the merits, sought to
contend that the view taken by its nominee member Mr. Ashok Khurana, is
consistent in both the arbitral award[s]. The Appellant has also relied on the
fact that Mr. Prabhat Krishna, the presiding Arbitrator in the impugned
Award, is not common.
In our considered opinion, these pleas of the Appellant are not
meritorious. As discussed above, Mr. Ashok Khurana himself has taken a
distinct view in both the arbitral award[s] and has not given any reasons for
taking a different view. Similarly, Mr. A.K. Yadav, the third member, has
taken two diametrically opposite views in both the award[s] and has not
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
recorded any reasons for taking this opposite view.
67.
The submission of the Appellant that each arbitral proceeding is
distinct and there cannot be comparative review on merits, is a legal plea
which cannot apply to the facts of this case in view of the peculiar facts that
the Arbitral Tribunal members are common, parties are common, contractual
terms interpreted by the Arbitral Tribunal are identical, the facts giving rise
to the disputes are near identical, but the decision in the award[s] is
diametrically opposite.
68.
The Supreme Court in OPG Power Generation Pvt. Ltd. v. Enexio
Power Cooling Solutions India27 held that a ground for interference under
Section 34 of the Act of 1996, and that the expression ‘most basic notions of
justice’ in Clause (iii) of Explanation 1 to Section 34(2)(b)(ii) is attracted
only where the award conflicts with such elementary and fundamental
principles of justice that the violation shocks the conscience of the Court.
In the present case, the same two members of the Arbitral Tribunal
have, in a subsequent proceeding between the same parties and under
identical contractual provisions, adopted irreconcilable positions on
materially similar certificates, without disclosing any reasons for such
departure or identifying any distinguishing circumstance. Such an
unexplained departure from the position earlier adopted by the common
members strikes at the elementary requirement of consistency and reasoned
adjudication and, in the peculiar facts of the present case, is of such a nature
as to shock the conscience of the Court. We are, therefore, of the considered
view that the impugned Award, to this extent, is in conflict with the most
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
(2025) 2 SCC 417
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
basic notions of justice within the meaning of Clause (iii) of Explanation 1
to Section 34(2)(b)(ii) of the Act of 1996.
69.
We therefore hold that the learned Single Judge has rightly set aside
the impugned Award on this ground as well.
70.
Before we part, it is necessary to clarify that the conclusions recorded
in the present judgment are not on the basis of any re-appreciation of the
evidence, re-evaluation of the merits of the rival claims, or substitution of
this Court’s interpretation of the contractual provisions for that adopted by
the Arbitral Tribunal. This Court has consciously refrained from expressing
any opinion on the correctness of the interpretations of the clauses of the
contract, or on the merits of the parties’ respective claims and counterclaims, all of which remain within the exclusive domain of the Arbitral
Tribunal. The findings returned herein are founded upon the Arbitral
Tribunal’s failure to exercise the jurisdiction conferred upon it and the
resultant violation of the principles of natural justice and the statutory
mandate governing arbitral proceedings. The issues pertaining to the
interpretation of the contractual provisions, the correctness of the Certificate
dated 31.08.2014, the legality of the Engineer’s subsequent revisions, and all
other questions on merits are left open for adjudication by the Arbitral
Tribunal in accordance with law.
71.
In view of the foregoing discussion and the findings recorded
hereinabove, we do not consider it necessary to examine in detail the
judgments relied upon by the Appellant, which principally reiterate the
limited scope of judicial interference with arbitral awards and the
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
impermissibility of re-interpreting contractual terms or re-appreciating
evidence under Section 34 of the Act of 1996. The legal propositions
enunciated in the said decisions are well settled and are not in dispute.
However, since the present judgment proceeds on different facts and
circumstances, specifically, the Arbitral Tribunal’s failure to adjudicate a
material dispute referred to arbitration and the consequential jurisdictional
and procedural infirmities, the said authorities do not govern the controversy
arising in the present case. We, therefore, do not find it apposite to deal with
the Appellant’s interpretation of the judgments relied upon by it in the
present judgment.
72.
In view of the aforesaid findings, this Court finds no merit in
interfering with the impugned judgment dated 08.04.2024, including the
direction therein remanding the matter to the Arbitral Tribunal for
consideration and adjudication of the defence raised by the Respondent.
73.
Since we have dismissed the challenge to the direction in the
impugned judgment setting aside the impugned Award, FAO(OS)(COMM)
132/2024 is hereby dismissed. The challenge in FAO(OS)(COMM)
136/2024 to the non-grant of pre-award and pendente lite interest by the
Arbitral Tribunal does not survive for consideration, as we have upheld the
direction passed in the impugned judgment setting aside the impugned
Award.
74.
Accordingly, the appeals are disposed of. Pending applications, if any,
also stand disposed of.
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
MANMEET PRITAM SINGH ARORA, J
V. KAMESWAR RAO, J
AUGUST 14, 2026/hp/mt/AM/aa
Signed By:MOHIT
Signing
Date:15.08.2026 16:05
FAO(OS) (COMM) 132/2024 & FAO(OS) (COMM) 136/2024
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review