-1NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 2ND DAY OF JUNE, 2026
BEFORE
THE HON'BLE MR. JUSTICE S SUNIL DUTT YADAV
WRIT PETITION NO. 27181 OF 2024 (LA-RES)
C/W
WRIT PETITION NO. 13078 OF 2025 (LA-RES)
IN W.P. No. 27181/2024
BETWEEN:
1.
SRI N R NARAYANAPPA
S/O RAMACHANDRAPPA
AGED ABOUT 71 YEARS,
2.
SRI. MOHAN
S/O K.THIMMAPPA
AGED ABOUT 35 YEARS,
3.
SRI. G.R.MANJAPPA
S/O RAMAPPA
AGED ABOUT 55 YEARS,
4.
SMT. LALITHA
W/O N.R.NARAYANAPPA
AGED ABOUT 50 YEARS
MOHANKUMAR
B SHELAR
MOHANKUMAR B SHELAR
Location: High Court of
Karnataka, Dharwad Bench
Date: 2026.06.02 17:43:57
+0530
ALL RESIDENTS OF
GUDDEMANE VILLAGE,
TALAGUPPA, SAGARA TALUK
SHIVAMOGGA DISTRICT - 577 430
… PETITIONERS
(BY SRI. M SHIVAPRAKASH., ADVOCATE)
-2NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
AND:
1.
THE UNION OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS,
REPRESENTED BY ITS DIRECTOR/SECRETARY
NEW DELHI - 100 001.
2.
THE DEPUTY COMMISSIONER
SHIVAMOGGA DISTRICT
SHIVAMOGGA - 577 210
3.
THE ASSISTANT COMMISSIONER
SAGARA SUB DIVISION
SAGARA- 577 401.
4.
THE CHAIRMAN
NATIONAL HIGHWAY AUTHORITY OF INDIA
OFFICE AT GURGAON,
G5 AND 6, SECTOR-10, DWARKA,
DELHI - 110 075.
5.
THE SPECIAL LAND ACQUISITION OFFICER
AND COMPETENT AUTHORITY
NH. 206, SHIVAMOGGA
SECTION NO.611-368/368/1
2ND FLOOR, CENTRAL AVENUE
NEAR SBI BANK, NT. ROAD
SHIMOGA - 577 202.
EMAIL: SLAONH206SMG@GMAIL.COM
… RESPONDENTS
(BY SRI. AJAY PRABHU M., CGC FOR R1;
SRI HARISH A.S., AGA FOR R2, R3 AND R5;
V/O DATED 10.02.2025, R4 IS DELETED)
-3NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA, PRAYING TO,
CALL FOR THE ENTIRE RECORDS IN RESPECT OF THE
NOTIFICATION
NO.CG-DL-E-13102023-249380
DATED
11/10/2023, CG-DL-E-24062024-254900 DATED 24.06.2024
AND FINAL NOTIFICATION NO. CG-DL-E-09082024-256202
DATED
07.08.2024
NOTIFIED
THE
LANDS
BETWEEN
THALAGUPPA - MARATHUR AND TO PLACE THE TRUE FACTS
BEFORE THIS HON'BLE COURT AND ETC.
IN W.P. NO. 13078/2025
BETWEEN:
1.
SRI GANAPATHI
S/O KRISHNAPPA
AGED ABOUT 67 YEARS
2.
SRI MANJAPPA
S/O KOLLURAPPA
AGED ABOUT 58 YEARS
3.
SMT POORNIMA M
C/O KRISHNAPPA S N
AGED ABOUT 43 YEARS
4.
SRI K N KESHAVAMURTHY
W/O NAGARAJA
AGED ABOUT 51 YEARS
5.
SRI C NAGAPPA
S/O CHANNABASAPPA
AGED ABOUT 79 YEARS
6.
SRI NAGARAJA J
S/O JAYARAM P
AGED ABOUT 38 YEARS
-4NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
7.
SRI E NARAYANA
S/O HUCHAPPA
AGED ABOUT 74 YEARS
8.
SRI KOLLURAPPA
S/O KOLLUR NAIK
AGED ABOUT 78 YEARS
9.
SRI H T KOLLURAPPA
S/O TIRUPATI
AGED ABOUT 80 YEARS
10. SMT SARASWATHI
W/O ANNEPPA
AGED ABOUT 60 YEARS
11. SRI NAGARAJA
S/O MANNA NAYAK
AGED ABOUT 78 YEARS
12. SMT MYLAMMA
W/O KANNAPPA
AGED ABOUT 80 YEARS
13. SMT K NAGARATHNA
W/O PRAKASH
AGED ABOUT 62 YEARS
14. SRI K JAYAPRAKASH
S/O K THIMMAYYA
AGE ABOUT 78 YEARS
15. SRI PARASHURAMA
S/O BHADRAVALLI SANNAPPA
AGED ABOUT 54 YEARS
-5NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
16. SRI LINGARAJU J
S/O JAYARAMA P
AGED ABOUT 41 YEARS
ALL RESIDENTS OF
MARATHUR AND TALAGUPPA
SAGARA TALUK
SHIVAMOGGA DISTRICT-577 430
... PETITIONERS
(BY SRI. SHIVAPRAKASH M., ADVOCATE)
AND:
1.
THE UNION OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS,
REPRESENTED BY ITS DIRECTOR/SECRETARY
NEW DELHI - 100 001.
2.
THE DEPUTY COMMISSIONER
SHIVAMOGGA DISTRICT
SHIVAMOGGA - 577 210
3.
THE ASSISTANT COMMISSIONER
SAGARA SUB DIVISION
SAGARA- 577 401.
4.
THE CHAIRMAN
NATIONAL HIGHWAY AUTHORITY OF INDIA
OFFICE AT GURGAON,
G 5 AND 6, SECTOR-10, DWARKA,
DELHI - 110 075.
... RESPONDENTS
(BY SRI. B.M. KUSHALAPPA, CGC FOR R1;
SRI HARISH A.S., AGA FOR R2 AND R3;
-6NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF THE CONSTITUTION OF INDIA, PRAYING TO,
CALL FOR THE ENTIRE RECORDS IN RESPECT OF THE
NOTIFICATION
NO.CG-DL-E-13102023-249380
DATED
11/10/2023,
CG-DL-E-24062024-254900
DATED
24.06.2024 AND FINAL NOTIFICATION NO. CG-DL-E09082024-256202 DATED 07.08.2024 NOTIFIED THE
LANDS BETWEEN THALAGUPPA - MARATHUR AND ETC.
THESE WRIT PETITIONS HAVING BEEN HEARD AND
RESERVED ON 24.04.2026 AND COMING ON FOR
PRONOUNCEMENT OF ORDER AT DHARWAD BENCH
THROUGH VIDEO CONFERENCING THIS DAY, THE COURT
MADE THE FOLLOWING:
CORAM:
HON'BLE MR. JUSTICE S SUNIL DUTT YADAV
CAV ORDER
In light of the petitioners in both the petitions
challenging the validity of the same preliminary and final
notification with identical grievances, both the petitions
are taken up together and disposed of by a common order.
2. The petitioners are residents of the village
Guddemane.
It
is
asserted
that
the
village
of
the
petitioners is connected to the Bangalore-Honnavara Road
through the Marathur-Talaguppa road which is stated to
have been in use for the past eight to nine decades.
-7NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
3.
It is the case of the petitioners that their lands
have benefit of irrigation facilities and are near water canal
which feeds water from the Gowri Kere.
It is submitted
that the proposal of the respondent National Highways
Authority of India (NHAI) to form a By-pass and thereby
abandoning the earlier Marathur-Talaguppa road and such
formation of By-pass would involve acquisition of fertile
and irrigated lands of the petitioners is sought to be
challenged.
4. It is asserted by the petitioners that the existing
Marathur-Talaguppa
road
serves
the
purpose
of
connectivity and no case is made out for laying of the
By-pass road.
5. It is further submitted that Marathur to Talaguppa
road has been in use since 1915 and was upgraded to a
State Highway in 1977 and subsequently upgraded to a
National Highway in 1999. It is specifically contended that
illegal constructions encroaching the right of way have
been put up in 2019 and if such illegal encroachments are
-8NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
removed, the width of the existing road would be sufficient
and there would be no need to consider construction of a
new By-pass.
6. The National Highways Authority of India (NHAI)
have
filed
their
Statement
of
Objections
and
have
specifically contended that the Ministry of Road Transport
and Highways (MoRTH) after deliberation with the Ministry
of Railways has taken a decision to replace all level
crossings with Road over Bridge (ROB). It is asserted that
there is existing level crossing No.152 (Talaguppa) at
Kilometer 73.250 on NH-69 (Old NH-206 HonnavaraChithur Section).
It is submitted that the Road over
Bridge is proposed to facilitate smooth and fast traffic flow
and reduce the possibility of accidents.
7. It is further submitted that Option-I of the
Alignment has been selected and preceded by technical
and administrative sanction.
-9NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
8. It is further asserted that procedure stipulated
under the National Highways Act, 1956 (for short 'the Act')
has been strictly adhered to as contemplated under
Section 3A, 3B, 3C and 3D.
9.
The public hearing inviting objections were held
on 11.01.2024 and 20.01.2021 and no objections were
received during the relevant point of time. It is specifically
asserted that out of the beneficiaries numbering 87 at
Talaguppa and 54 at Marathur, only 20 of them have filed
the writ petition and none of them have filed objections
within the time stipulated.
10.
It
is
also
asserted
that
once
Section
3D
notification is passed, land is vested with the Central
Government and challenge to land acquisition at this
belated point of time does not arise.
11. It is also asserted that the demand for exploring
alternative reliefs was also resorted to and the Deputy
Commissioner
has
furnished
a
detailed
report
after
- 10 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
carrying
out
inspections
and
has
opined
that
it
is
appropriate to implement the Project as per alignment
approved by the Central Government and reliance is
placed on the report at Annexure-R2.
12. The State Government has also filed their
detailed statement of objections.
13.
It
is
asserted
that
the
existing
National
Highway-69 (NH-69) in the Talaguppa stretch passes
through the municipal area and consists of commercial
establishments and residential structures as well as water
body adjoining the Highway.
It is also stated that there
are two Railway Level Crossings LC-110 (Hosur) at
Kilometer 108.525 and LC-152 (Talaguppa) at Kilometer
73.250. Accordingly, it is asserted that the By-pass would
serve the purpose of avoiding passing of road through
municipal area and would avoid Railway Level Crossings.
14.
It is asserted that Option No.1 is found to be
more suitable and has been chosen after taking note of all
- 11 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
factors.
The assertions of NHAI had been adopted.
Accordingly, it is prayed that the petition be rejected.
15.
It is necessary to take note that this court by
order dated 24.01.2025 had directed respondent no.2 and
3 to examine the feasibility of expanding the existing
National Highway and to submit a report. The order dated
24.01.2025 at para 6 reads as hereunder:
"6. Respondent No.2 and 3 shall examine
the possibilities /feasibilities of expanding the
existing National Highway as submitted by
learned counsel for the petitioners and to
submit
a report regarding
its possibilities/
feasibilities by the next date of hearing. It
should
also
take
into
consideration
if
the
proposed acquisition can be avoided. Such
report shall be filed on before 10.02.2025."
16. Pursuant to such direction, the State has placed
before the court sketches showing re-alignment as well as
the report of the Deputy Commissioner dated 29.09.2025.
The Deputy Commissioner has unequivocally affirmed the
- 12 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
alignment finalised by the Central Government pointing
out that there was a sharp bend at the Railway Level
Crossing 152 amongst other grounds. It was also pointed
out that the widening of the existing road in Talaguppa
would result in removal of commercial buildings, religious
structures, Government buildings, houses and prominent
market places.
It is asserted that such removal had stiff
opposition from the public.
17. Heard both sides.
18. The challenge by the petitioners is to the validity
of the notifications passed by the NHAI for the purpose of
laying a By-pass road.
19. The preliminary notification under Section 3A is
dated
11.10.2023
and
objections
were
also
invited
(Annexure-'J' in W.P.No.27181/2024). Subsequently, the
competent authority had sent its report to the Central
Government and thereafter there is a declaration pursuant
to the power conferred under Section 3D, notification is
- 13 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
issued on 07.08.2024 declaring the land to be vested in
the Central Government.
20. Though the petitioners have challenged the
validity
of
the
notifications,
the
grievance
of
the
petitioners is as regards the necessity of the By-pass itself,
as the petitioners specifically assert that the existing road
between Talaguppa-Marathur if freed from encroachment
would be sufficient.
21. The representations only if made before the
Notification under Section 3D i.e., before 07.08.2024 could
have been considered.
For the consideration of the
representation in terms of the statutory scheme, it is
necessary that the objections ought to have been filed
before the competent authority. The objections stated to
have been filed have been enclosed along with Synopsis
on 24.04.2026.
- 14 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
22. The representation made are as follows:
The representation dated 05.11.2022 addressed to:
a) Minister for Road Transport and Highways
b) Prime Minister, Chief Minister of Karnataka
c) Members of Legislative Assembly at Soraba and
Sagara Constituency.
d) National Highways Authority of India, New Delhi.
The representation is not acknowledged, nor is it
addressed to the competent authority.
23.
Amongst the other representations, most of
them are dated 30.08.2024 and highlight the common
concern of the farmers losing irrigated land. Considering
that Section 3D notification is dated 07.08.2024, such
representations submitted to the Special Land Acquisition
Officer and the Competent Authority after the Section 3D
Notification are not obliged to be considered in law. Once
the lands are vested with the Central Government,
representations made to the competent authority are of no
- 15 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
relevance. Such objections filed without adherence to the
time schedule under Section 3 (C) (1) of the Act do not
call for consideration. In law as well, the only objections
that could be made is as regards its use for the purpose
enumerated under Section 3A.
24. The legality of the Notification subsumes all the
grievances of the petitioners as raised regarding the
necessity of the By-pass.
25.
petitioners
As discussed
have
not
supra, the objections of the
been
filed
within
time
and
accordingly, the notification cannot be challenged on the
basis of grounds raised in their representations.
26. Even otherwise, their grievance raised regarding
the necessity of a By-pass has received adequate attention
and has been turned down after due consideration. It is
also to be clarified that such grievance cannot be raised
de hors the notification.
- 16 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
27. This court did call upon the respondent nos.2
and 3 (in W.P.No.27181/2024) by order dated 24.01.2025
to examine feasibility of expanding the existing National
Highway and avoiding the proposed acquisition.
28.
A detailed report was filed by the Executive
Engineer, National Highways Division, Shivamogga, copy
of which was produced by the State along with the memo
dated 11.03.2026 in W.P.No.27181/2024.
29.
The
report
dated
14.07.2025
is
extracted
below:
"Subject:
"Construction of ROBs at LC 79 (Kumsi),
LC 11O (Hosuru) and LC 152 (Thalaguppa of
NH-206 and LC 105 (Ananpuram) of NH-766C
in the State of Karnataka under NH (O) on EPC
Mode - Approved under Annual Plan for the
year 2022-23" - Alignment Approval - Reg.
- 17 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
Reference: WP 27181 of 2024 (LA-RES)
N.R.Narayanappa and Others Vs. The Union of
India
Technical Feasibility for Proposed ROB for
LC-152 at TALAGUPPA
1. The existing road alignment is nonstandard
as
per
National
Highway
geometric
requirements for safety and to support higher
speeds,
attached
herewith
the
reference
satellite imageries as exhibits.
2. Existing road has sharp curves at the level
crossing, making it not feasible provide road
over bridge (ROB) as an alternative to existing
level crossing.
RDSO (Research Designs and
Standards Organisation) has specific guidelines
for Road Over Bridges (ROBs) that aim to
minimize skew angles to improve structural
integrity and ease of construction.
3. Though futuristic traffic of NH69 cannot be
sustained by existing road as the right of way
is narrow and built-up areas are developed
along the route.
- 18 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
4. A cemetery is encountered on the existing
route of NH69.
5.
Existing road passing over a narrow tank
bund
as
shown
in
the
attached
satellite
Subsequently,
the
Deputy
Commissioner,
imageries."
30.
Shivamogga District has addressed a detailed report to the
Principal
Secretary,
Department
of
Public
Works
on
29.09.2025, detailing the reasons for acceptance of the
alignment approved by the Central Government.
31. The report refers to a site inspection in the
presence of the following Officers:
i)
Assistant Commissioner and Special Land Acquisition
Officer, Sagara Sub-Division, Sagara.
ii)
Executive Engineer,
Shivamogga.
National
Highways
iii)
Senior Division Engineer, SWR, Shivamogga.
iv)
Tahsildar, Sagara
Division,
- 19 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
v)
Assistant Executive Engineer,
Sub-Division, Shivamogga.
National
Highways
vi)
Assistant Director of Land Records, Sagara.
vii)
Assistant Director, Taluk Panchayat, Sagara.
viii) Respective Chairman and Members of the Talaguppa
and Marathur Gram Panchayats.
ix)
Public of the Talaguppa and Marathur Village.
32. The prominent observations made in the report
are as follows:
i)
The existing Highway consists of sharp
turns. Construction of Road Over Bridge
is filled with technical difficulties.
ii)
Even
if
a
Railway
Over
Bridge
is
constructed it would pass through heavily
populated areas.
iii)
The existing Highway is 14 Meters to 20
Meters in width at many places.
The
existing road abuts Government lake,
67 commercial buildings, 15 Government
- 20 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
buildings, 04 religious structures and 36
residential sites / houses.
iv)
One
of
the
writ
petitioner
viz.,
N.R.Narayanappa, S/o Ramachandrappa
who
is
the
owner
of
property
in
Sy.No.8/4 has voiced his opinion that he
has no objection for acquisition of his
land for construction of a By-pass if the
road were to be constructed at one end.
33.
Finally, after taking note of various factors at
points (i) to (iv), it is concluded that the alignment as
proposed by the Central Government is appropriate.
34. The details contained in the Table which is a part
of the report is extracted as below:
Sl.
No.
CA±ÀUÀ¼ÀÄ
Existing road
end to end
width
ªÀgÀ¢
from Existing road for a length of
3.23 km width varies from
5.50 m to 7.00 m (in Talaguppa
village limit)
Traffic intensity on this road As
per
National
Highway
Authority
recorded
in
DPR
Passenger Car Unit (PCR) on
NH-69 road is 7034
No. of shops and structures a) A Tank exist at Talaguppa
existing from end to end Sy.No.166 with an extent of
- 21 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
and its type
36.23 Gunta
b) 67 Commercial Buildings
c) 15 Government Structures
like Hospitals, Bus Stand, Police
Station,
Panchayat
Office,
Veterinary
Hospital,
Library,
Govt.
Quarters,
Railway
property.
d) 4 Religious structures like
Temple, Church, Mosque and
Grave Yard.
e)
36 Habitant areas out of
which
are
authorized
properties, 07 Alianated sites,
Unauthorised
properties
found to be verified.
Clear opinion on whether As per site inspection dated
the 28 mtr. Road width is 22.08.2025 the existing width
available.
available varies from 14.00 m to
20.00 m along the stretch.
Whether
structures
or 36 Habitant areas, out of which
encroachment
have 23 are authorized properties, 07
Khata/GP Permit
Alianated sites, Rest found
unauthorised.
No. of persons who raised No one has raised any objection
objections
during
award during award process
process
No. of persons who filed As
per
the
Writ
Petition
Writ Petition
No.27181/2024, 04 members
have filed petition.
Extent of Government Land
Extent of Government land is
1.214 Hectare on existing road.
Map on above details to be Enclosed.
submitted
- 22 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
35. The conclusion drawn in the report is:
a)
If the National Highway is constructed within the
Talaguppa town, it would involve the demolition/removal
of commercial buildings, religious structures, Government
buildings, residential structures and prominent market
places.
b)
For removal of structures as stipulated above, there
was opposition from the public and accordingly it was not
practicable to execute works in the existing road.
c)
At the Railway Level Crossing No.152, the National
Highway takes a sharp turn. If the Highway is constructed
at the same site inclusive of a Road Over Bridge, nearly
half of the Talaguppa town will have to be acquired.
d)
If expansion of the existing National Highway near
the Gowri Kere (Lake) is resorted to near Sy.No.66, this
would require acquisition that would be impermissible in
terms of the regulations of NHAI.
- 23 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
e)
Accordingly, taking note that Section 3(A), 3(D) and
3 (G) notifications are already passed, at the stage of
execution of the project, it would be appropriate to
implement the project in terms of the Central Government
approved alignment.
36. The detailed statement of objections filed by the
respondent no.1 makes out Option-1 of the alignment
options
for
realignment
as
has
been
approved
on
05.08.2022.
37. It is observed that such alignment has been
chosen keeping in mind "intensity of existing utilities and
trees". It is further stipulated that such decision has been
taken pursuant to the decision of the MoRTH (Ministry of
Road Transport and Highways) to replace all the level
crossings with Road over Bridge (ROB). It is averred that
keeping in mind such policy decision, it was resolved to
have Road over Bridge to By-pass the existing Level
- 24 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
Crossing No.152 (Talaguppa) at Kilometer 73.250 on
NH-69 (Old NH-206 Honnavara-Chithur Section).
38. The petitioners have objected to the report by
the Government authorities contending that, the widening
of the existing road is opposed on various grounds
including that, the Government properties are built beyond
75 feet, that there are unauthorised constructions within
the road margin of the existing National Highway.
39. However, the Court cannot sit in judgment over a
decision taken regarding construction of a By-pass rather
than
widening
the
existing
National
Highway.
Such
decisions are essentially policy decision that has been
taken keeping in mind policy issues as detailed at para 32
which envisages avoiding of sharp turns, avoiding railway
level crossing, having road over bridge etc.
40. It is to be noted that the decision taken to
choose a particular option of a re-alignment to have
By-pass and give up altering the existing road is a decision
- 25 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
taken by the requisite authority way back in the year 2022
itself. Such decision taken after considering all factors as
detailed at para 32 and 33 is a decision taken by an Expert
Body and Courts should seldom interfere with such
decisions.
The Apex Court's observation in the case of
Union of India v. Kushala Shetty and Others1 would
be of relevance and is extracted as below:
"28. Here, it will be apposite to mention
that
NHAI
is
a
professionally
managed
statutory body having expertise in the field of
development
and
maintenance
of
national
highways. The projects involving construction
of
new
highways
and
widening
and
development of the existing highways, which
are vital for the development of infrastructure
in the country, are entrusted to experts in the
field of highways. It comprises of persons
having vast knowledge and expertise in the
field
of
highway
development
and
maintenance. NHAI prepares and implements
projects
(2011) 12 SCC 69
relating
to
development
and
- 26 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
maintenance
of
national
highways
after
thorough study by experts in different fields.
Detailed project reports are prepared keeping
in view the relative factors including intensity
of heavy vehicular traffic and larger public
interest. The courts are not at all equipped to
decide upon the viability and feasibility of the
particular project and whether the particular
alignment would subserve the larger public
interest. In such matters, the scope of judicial
review is very limited. The court can nullify the
acquisition of land and, in the rarest of rare
cases, the particular project, if it is found to be
ex facie contrary to the mandate of law or
tainted due to mala fides. In the case in hand,
neither has any violation of mandate of the
1956 Act been established nor has the charge
of malice in fact been proved. Therefore, the
order under challenge cannot be sustained."
41. The allegations made by the petitioners that the
authorities were not considering widening of the existing
National Highway due to vested interests is a sweeping
allegation. The question whether the authorities feel that
- 27 NC: 2026:KHC:25828
WP No. 27181 of 2024
C/W WP No. 13078 of 2025
HC-KAR
a new By-pass would be better than widening the existing
National Highway is a decision, the correctness of which
cannot be a subject matter of re-look by the courts unless
there is any illegality.
42. The limits of the power of judicial review does
not permit the courts to sit in appeal over such decision of
expert bodies.
Further, all legality has merged in the
notification and with no ground made out to set aside the
notification,
efforts
notification
by
to
aspects
re-open
the
relating
to
validity
of
the
alignment
is
impermissible.
43.
Accordingly, no grounds are made to for
allowing the writ petitions and the same are dismissed.
Sd/(S SUNIL DUTT YADAV)
JUDGE
Np/LIST NO.: 19 SL NO.: 1
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review