The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
11. In the present case, admittedly, the allegation is that the appellant-defendant is in possession of the premises as a tenant without paying the electricity charges and the rent. There is also apprehension that the appellant-defendant may create a third-party right over the property. In such circumstances, we are of the considered view that the facts of the case would fall within the meaning of urgent interim relief -9HC-KAR NC: 2026:KHC:48371-DB COMAP No. 407 of 2026 CNR: KAHC010577422026 to be granted without going through the process of premediation/pre-litigation mediation.
12. Accordingly, we find no error in the impugned judgment and order passed by the Commercial Court. This appeal is devoid of merit and substance, and stands dismissed. No order as to costs.
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
-1HC-KAR
NC: 2026:KHC:48371-DB
COMAP No. 407 of 2026
CNR: KAHC010577422026
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 7TH DAY OF SEPTEMBER, 2026
PRESENT
THE HON'BLE MR. JUSTICE D K SINGH
AND
THE HON'BLE MR. JUSTICE H.SHANTHI BHUSHAN
COMMERCIAL APPEAL NO. 407 OF 2026
BETWEEN:
1.
SRI ASHOK SANCHETI
S/O LATE PARASMAL,
AGED ABOUT 55 YEARS,
PROPRIETOR,
M/S. JODHAPURWALA,
NO. 849, 15TH MAIN ROAD,
3RD BLOCK, RAJAJINAGAR,
BENGALURU 560010.
…APPELLANT
Digitally
signed by
VASANTHA
KUMARY B
K
Location:
HIGH
COURT OF
KARNATAKA
(BY SRI. P.N.MANMOHAN FOR
SMT. RACHANA GANESH K., ADVOCATE)
AND:
1.
SRI SATHYA SREE VAVHALE
AGED ABOUT 62 YEARS,
S/O LATE M. GANGADHAR,
R/AT NO.2, SHREEKUNJ,
1ST FLOOR, DARJIPETE ROAD,
RANGASWAMY TEMPLE STREET CROSS,
BENGALURU 560053.
…RESPONDENT
THIS COMAP / COMMERCIAL APPEAL IS FILED UNDER
SECTION 13 (1A) OF THE COMMERCIAL COURTS ACT, 2015
PRAYING TO SET ASIDE THE ORDER DATED.13.08.2026
PASSED BY THE LXXXVIII ADDITIONAL CITY CIVIL AND
-2HC-KAR
NC: 2026:KHC:48371-DB
COMAP No. 407 of 2026
CNR: KAHC010577422026
SESSIONS
JUDGE,
BENGALURU
CITY,
IN
COM.O.S.NO.782/2025 DISMISSING THE IA NO.10 FILED BY
THE APPELLANT UNDER ORDER VII RULE 11(d) READ WITH
SECTION.151 OF THE CPC, 1908 AND SECTION.12A OF THE
COMMERCIAL COURTS ACT, 2015 (PRODUCED AT ANNEXUREG) AND CONSEQUENTLY, ALLOW IA NO.10 FILED BY THE
APPELLANT (PRODUCED AT ANNEXURE-E) AND REJECT THE
PLAINT IN COM.O.S.NO.782/2025 IN THE INTEREST OF
JUSTICE AND EQUITY.
THIS APPEAL, COMING ON FOR ORDERS, THIS DAY,
JUDGMENT WAS DELIVERED THEREIN AS UNDER:
CORAM: HON'BLE MR. JUSTICE D K SINGH
and
HON'BLE MR. JUSTICE H.SHANTHI BHUSHAN
ORAL JUDGMENT
(PER: HON'BLE MR. JUSTICE D K SINGH)
Heard Mr. P.N. Manmohan, learned counsel for the
appellant.
2.
The present Commercial Court appeal has been filed
impugning the order dated 13.08.2026 passed by the Court of
LXXXVIII Additional City Civil and Sessions Judge, Bengaluru in
Commercial
Original
Suit
No.782/2025
on
an
interim
application filed by the respondent-plaintiff seeking urgent
interim relief of temporary injunction.
-3HC-KAR
NC: 2026:KHC:48371-DB
COMAP No. 407 of 2026
CNR: KAHC010577422026
3.
The appellant is the tenant of the commercial
property situated at 25th cross, Rangaswami Temple Street,
Bengaluru measuring 414 sq. ft., as per the averments in the
plaint. The appellant-defendant has not paid the electricity
charges to BESCOM and has also not been paying the rent.
The plaintiff sought, inter alia, (i) damages/mesne profits at the
rate of Rs.2,50,000/- per month from the date of filing of the
suit till the date of vacating and handing over the vacant
possession of the suit schedule property to the plaintiff, with
interest at a commercial rate as contemplated under Order II of
the Code of Civil Procedure, 1908; and
(ii) a decree directing the defendant to vacate and hand
over vacant physical possession of the suit schedule property
and to pay the existing electricity charges along with the
arrears of rent till handing over possession.
4.
In the suit, IA No.1 was filed by the plaintiff under
Order VII Rules 1 and 2 read with Section 26 of the CPC. In
addition, an application under Order 39 Rules 1 and 2 was filed
seeking a temporary injunction restraining the appellantdefendant from creating third-party rights/creating any third-
-4HC-KAR
NC: 2026:KHC:48371-DB
COMAP No. 407 of 2026
CNR: KAHC010577422026
party interest in respect of the suit schedule property by
passing possession to any third party. Considering the urgency,
that if the possession of the suit schedule property is passed to
any third party, it would defeat the very purpose of filing this
suit and the
plaintiff would suffer
untold hardship,
the
Commercial Court passed an order of temporary injunction
restraining the appellant-defendant from creating any thirdparty interest over the suit schedule property.
5.
summons,
On receipt of notice of IA No.1 along with suit
the
defendant
filed
objections
and
also
filed
I.A.No.10 under Order VII Rule 11(d) read with Section 151 of
the CPC and Section 12-A of the Commercial Courts Act, 2015
praying for dismissal of the suit on the sole ground that premediation in respect of the dispute was mandatory and that no
such pre-mediation steps having been taken, the suit was liable
to be dismissed.
6.
The Commercial Court, vide impugned order dated
13.08.2026, rejected the said application. The Commercial
Court held that Section 12-A itself contemplates urgent interim
relief, and therefore, where there is likelihood of the defendant
-5HC-KAR
NC: 2026:KHC:48371-DB
COMAP No. 407 of 2026
CNR: KAHC010577422026
creating third-party rights in respect of the tenanted premises,
such situation would fall within the ambit of urgent interim
relief as contemplated under Section 12-A of the Commercial
Courts Act, 2015.
7.
Mr.
P.N.
Manmohan,
learned
counsel
for
the
appellant, with great felicity has argued that for deciding
whether there exists an emergency/urgency sufficient to
bypass the pre-litigation mediation mandate, the Court must
examine the pleadings and the plaint averments should clearly
disclose such urgency/emergency requiring urgent interim
relief.
8.
He has placed reliance on few judgments including
the case of YAMINI MANOHAR vs T.K.D KEERTHI [(2024)
5 SCC 815] wherein the Supreme Court has held that if the
Court on considering the merits has come to the conclusion
that there is a prima facie case in favour of the plaintiff and
irreparable harm and injury would be caused if the urgent
interim relief is not granted and balance of convenience is in
favour of the plaintiff, the parties need not be directed to
undergo pre-litigation mediation.
-6HC-KAR
NC: 2026:KHC:48371-DB
COMAP No. 407 of 2026
CNR: KAHC010577422026
9.
We have considered the submissions and perused
the judgments relied upon.
10.
Paragraphs
10, 11 and 12 of the said judgment
which are relevant are extracted hereunder:
"10. We are of the opinion that when a plaint
is filed under the CC Act, with a prayer for an
urgent interim relief, the commercial court
should examine the nature and the subjectmatter of the suit, the cause of action, and the
prayer for interim relief. The prayer for urgent
interim relief should not be a disguise or mask
to wriggle out of and get over Section 12-A of
the CC Act. The facts and circumstances of the
case have to be considered holistically from
the standpoint of the plaintiff. Non-grant of
interim relief at the ad interim stage, when the
plaint is taken up for registration/admission
and examination, will not justify dismissal of
the commercial suit under Order 7 Rule 11 of
the Code; at times, interim relief is granted
after issuance of notice. Nor can the suit be
dismissed under Order 7 Rule 11 of the Code,
because
the
arguments,
is
interim
denied
relief,
on
post
merits
and
the
on
examination of the three principles, namely :
-7HC-KAR
NC: 2026:KHC:48371-DB
COMAP No. 407 of 2026
CNR: KAHC010577422026
(i) prima facie case, (ii) irreparable harm and
injury, and (iii) balance of convenience. The
fact
that
the
court
issued
notice
and/or
granted interim stay may indicate that the
court is inclined to entertain the plaint.
11. Having stated so, it is difficult to agree
with the proposition that the plaintiff has the
absolute choice and right to paralyse Section
12-A of the CC Act by making a prayer for
urgent interim relief. Camouflage and guise to
bypass the statutory mandate of pre-litigation
mediation should be checked when deception
and falsity is apparent or established. The
proposition that the commercial courts do
have a role, albeit a limited one, should be
accepted, otherwise it would be up to the
plaintiff alone to decide whether to resort to
the procedure under Section 12-A of the CC
Act.
An
“absolute
and
unfettered
right”
approach is not justified if the pre-institution
mediation under Section 12-A of the CC Act is
mandatory, as held by this Court in Patil
Automation
[Patil
Automation
(P)
Ltd.
v.
Rakheja Engineers (P) Ltd., (2022) 10 SCC 1 :
(2023) 1 SCC (Civ) 545] .
-8HC-KAR
NC: 2026:KHC:48371-DB
COMAP No. 407 of 2026
CNR: KAHC010577422026
12.
The
words
“contemplate
any
urgent
interim relief” in Section 12-A(1) of the CC
Act, with reference to the suit, should be read
as conferring power on the court to be
satisfied. They suggest that the suit must
“contemplate”,
which
means
the
plaint,
documents and facts should show and indicate
the need for an urgent interim relief. This is
the precise and limited exercise that the
commercial courts will undertake, the contours
of which have been explained in the earlier
paragraph(s). This will be sufficient to keep in
check
and
ensure
that
the
legislative
object/intent behind the enactment of Section
12-A of the CC Act is not defeated."
11.
In the present case, admittedly, the allegation is
that the appellant-defendant is in possession of the premises as
a tenant without paying the electricity charges and the rent.
There is also apprehension that the appellant-defendant may
create
a
third-party
right
over
the
property.
In
such
circumstances, we are of the considered view that the facts of
the case would fall within the meaning of urgent interim relief
-9HC-KAR
NC: 2026:KHC:48371-DB
COMAP No. 407 of 2026
CNR: KAHC010577422026
to be granted without going through the process of premediation/pre-litigation mediation.
12.
Accordingly, we find no error in the impugned
judgment and order passed by the Commercial Court. This
appeal is devoid of merit and substance, and stands dismissed.
No order as to costs.
13.
If the parties decide and agree, the matter may be
referred to mediation by the Commercial Court.
Sd/(D K SINGH)
JUDGE
Sd/(H.SHANTHI BHUSHAN)
JUDGE
RKA
List No.: 1 Sl No.: 1
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review