Reserved on 15.09.2026
Delivered on 23.10.2026
HIGH COURT OF JUDICATURE AT ALLAHABAD
WRIT - C No. - 4285 of 2009
Smt. Pratima Rajpal And Another
.....Petitioner(s)
Versus
State of U.P. and Others
.....Respondent(s)
Counsel for Petitioner(s)
Counsel for Respondent(s)
: Mayank Singh, S. Shekhar, V.K. Singh
: Sunil Kumar Misra, C.S.C., G.P.
Srivastava, S.P. Singh, Satendra P. Singh
Court No. - 40
HON'BLE SARAL SRIVASTAVA, J.
HON'BLE SUDHANSHU CHAUHAN, J.
(Delivered by Hon'ble Sudhanshu Chauhan, J.)
1. Heard Sri V.K. Singh, learned Senior Advocate assisted by Sri Mayank
Singh, Advocate appearing for the petitioners, learned Standing Counsel for
the State respondent and Sri Sunil Kumar Mishra, learned counsel for the
U.P. State Industrial Development Corporation.
2. The present petition has been filed for quashing the order dated
16.10.2008 passed by the Regional Manager, UP State Industrial
Development Corporation, by means of which the petitioner was informed
that the allotment of the industrial plot made in favour of respondent no. 4
had been cancelled on account of failure to bring the unit to production after
allotment and subsequently, in the year 1999, the said plot had been allotted
to respondent no. 5, further a direction has also been sought for the
respondent nos. 2 and 3 to consider the application dated 12.12.1996, for the
transfer of the said plot in favour of the petitioners.
3. The facts of the case are that in the year 1990, Smt Sobha Dhawanrespondent no. 4, was allotted plot no. E-53, Surajpur ,Site 4, Greater Noida,
measuring 800 sq. m., by the U.P. State Industrial Development Corporation
- respondent no. 2, and subsequently respondent no. 4 took possession of the
plot in pursuance of letter dated 30.4.1994. The respondent no. 4, thereafter,
by means of an application dated 16.01.1996, had requested that she required
a larger plot for the project, and in pursuance thereto, the respondent no. 4
was allotted plot no. D-49, having an area of 1,000 sq. m. Once again, the
respondent no. 4, vide application dated 12.04.1996 had requested that her
plot size be reduced from type D to type E, this was in view of the fact that
the husband of the respondent no. 4 had passed away. On this occasion, the
respondent no. 2, while accepting the request so made, vide the letter dated
23.05.1996 had allotted plot no. E30, having an area of 800 sq m in place of
plot no. D59. Thereafter, the respondent no. 4 had deposited a sum of Rs.
17,351/- on 10.06.1996. Consequently, an agreement dated 04.09.1996 was
WRIC No. 4285 of 2009
entered between respondent no.2-corporation and respondent no. 4 in respect
of plot no. E30.
4. However, as respondent no. 4 failed to establish her unit over the plot,
vide the letter dated 12.12.1996, a request was made to transfer the said plot
in favor of the petitioner, and an amount of Rs. 2,000/- was also deposited in
this regard. The respondent no.2-corporation, vide the letter dated
17.07.1997, addressed to the respondent no. 4, had pointed out certain
deficiencies in respect of the transfer of the plot no.E30 in favour of the
petitioners and had called upon the respondent no. 4 to remove the same. It
is the contention of the petitioner that the deficiencies so pointed out were
subsequently removed, as has been pointed out in the letter dated 11.09.1997
of the petitioner, whereas the respondent-corporation denies the receipt of
any such letter. It is further submitted by the petitioner that thereafter the
petitioner repeatedly requested the respondent-corporation to transfer the
plot in question and to hand over the possession thereof but the same was of
no avail. Ultimately, it is only vide the letter dated 16.10.2008 that the
petitioner was informed by respondent no. 3 that the allotment of the plot
made in favour of respondent no. 4 had been cancelled, in view of the fact
that the unit to be set up was not brought into production, and subsequently
the said plot, in the year 1999 had been allotted to Rajesh Kumar respondent no. 5.
5. In the above background, it is contended by the petitioner that the
cancellation is bad and has been passed without affording any opportunity of
hearing. Further, no decision was taken by the respondents on the transfer
application of the petitioner, which remained pending. It is also contended
that the respondents, had cancelled the allotment dated 23.10.1990, which
was in respect of plot no. E53, while respondent no. 4 had been allotted plot
no. E30 on 23.05.1996, which was sought to be transferred to the petitioner.
Hence, the allotment of plot no. E30 had not been cancelled. The alleged
cancellation letter was never communicated to the petitioner, who all this
while had been waiting for the transfer of the plot in her favour, and repeated
requests made by the petitioner in this regard were of no avail, thus, the
respondent corporation had acted in an arbitrary manner.
6. The learned counsel for the petitioner, while relying on the pleadings of
the parties, has contended that the respondents do not dispute the fact
regarding the filing of the transfer application and the project report
submitted by the petitioner. The respondents also do not dispute the fact that
the cancellation of allotment of plot no. E53 had been done, and not that of
plot no. E30. Besides, there is only a bald denial of the fact that no order
cancelling the allotment was ever issued to the respondent no. 4 or to the
petitioner and also the fact that the allotment had been cancelled without
affording any opportunity of hearing.
7. Per contra, it is contended on behalf of the respondent-corporation that
there were certain deficiencies in the application filed by respondent no. 4 in
respect of the transfer of the plot in favour of the petitioner. In this regard,
vide letter dated 07.04.1997, respondent no. 4 was called upon to remove the
deficiencies, and thereafter by means of another letter dated 17.07.1997, it
was stated that the transfer could be processed only after the deficiencies had
been removed. However, it is contended that the deficiencies in the transfer
application were never removed. The respondents further deny the letter
dated 11.09.1997 by means of which the petitioner has alleged to have
WRIC No. 4285 of 2009
removed the deficiencies as pointed out. It is further contended that, the
letter dated 17.07.1997 remained unresponded, thus, it was assumed that the
respondent no. 4 may not have been interested in transferring the plot.
Accordingly, a notice dated 10.07.1998 was issued to the respondent no. 4
for non-utilization of the plot, the same too remained unresponded. A notice
in this regard was also published in the news daily, Dainik Jagran, Delhi
Edition, on 06.10.1998. However, there was no response on the part of
respondent no. 4. Ultimately, vide letter dated 19.12.1998, the allotment of
plot no. E30 made in favour of respondent no. 4, was cancelled.
Subsequently, plot no. E30 was allotted in favour of respondent no. 5, who is
running his unit from the same.
8. It is further contended that the petitioner has not challenged the
cancellation letter dated 19.12.1998, as well as the allotment in favour of
respondent no. 5. Hence, the relief claimed by the petitioner cannot be
granted. It is incorrect to allege that the cancellation of allotment of plot no.
E53 has been issued, while the fact of the matter is that the terms and
conditions of the allotment letter dated 23.10.1990 issued in respect of plot
no. E53 were also applicable to subsequent allotments made, including that
of plot no. E30, the plot in dispute, and it is only the conditions of allotment
that have been relied upon in the order of cancellation of plot no. E30.
Further, the transfer of the plot having never been made in favour of the
petitioner, hence, the petitioner has no right to question the cancellation of
the allotment. The petitioner has also not deposited any amount in pursuance
of the transfer application, and the amount of Rs.2,000/- that had been
deposited was in respect of the processing fee. The respondent no. 4 has
failed to take possession of plot no. E30 and had not started construction
over the same, hence, had breached the conditions laid down in the allotment
letter dated 23.10.1990 and also those of the license agreement dated
04.09.1996. Hence, the cancellation order had been passed in due
accordance with law. Lastly, the petitioner has approached this court after an
inordinate delay, and the writ petition is liable to be dismissed on the ground
of laches.
9. We have perused the records of the case. As far as conditions of the
allotment letter dated 23.10.1990 are concerned, clause 12 provides that the
possession of the plot will be delivered after the execution of the license
agreement, further, before the execution of the license agreement, the
allottee shall have to place firm orders for the purchase of plant and
machinery and submit documentary proof in support of the said claim to the
responden-corporation. Clause 13 provides that the allotment shall remain
valid and effective for a period of 24 months only from the date of allotment,
during which the allottee shall have to take over the possession of the land
after executing the license agreement on completion of all the formalities for
the same, as mentioned in clause 12. Further, clause 15 provides that the
allotment will be cancelled if the allottee fails to execute the lease agreement
and/or take possession of the land as mentioned in clause 12 and 13 within
the time stipulated in the clause, the time being of the essence.
10. Further, clause 1 of the license agreement dated 04.09.1996 provides
that, during the period of 12 months from the date hereof, the licensee shall
have the license and authority to enter upon the plot of land for the purpose
of building and executing work and carrying on the manufacturing and
production thereon. Further, clause 5 of the agreement provides that if the
licensee fails to commence and complete the building fit for use and start the
WRIC No. 4285 of 2009
manufacturing and production in the time and manner hereinbefore provided
(time being of the essence of the contract), or shall not proceed with the
works with due diligence, or shall have failed to observe any of the
stipulations on his part hereof contained, the grantor shall have the right and
power to re-enter upon and resume possession of the said land. Lastly, clause
4(j)of the agreement provides that the licensee will not directly or indirectly
transfer, assign, sell, encumber, or part with its interest under or the benefit
of this agreement in any manner whatsoever without the previous consent in
writing of the grantor, and it shall be open to the grantor to refuse such
consent or grant the same subject to such conditions as may be laid down by
the grantor in that behalf.
11. Thus the undisputed position that emerges from the records is that the
respondent no.4 was the allottee of the plot in dispute being plot no. E30 and
there is nothing on record to demonstrate that the allotment of the plot in
dispute was transferred in favour of the petitioner at any point of time. It is
also evident that the respondent no.4 did not take the possession of the land
in dispute nor established the production unit over the same as provided
under clause 1 of the agreement dated 04.09.1996 read with clause 15 of the
allotment letter dated 23.10.1990. Hence, the respondent no.4 did not
comply with the terms of the allotment letter as well as the agreement and
under these circumstances, the respondent no.2-corporation was very well
within it's rights to cancel the license and resume possession of the plot in
dispute under the provisions of clause 5 of the agreement.
12. Further as far as the contention of the petitioner that no opportunity was
afforded prior to the cancellation of the allotment it has been categorically
stated by the respondent no.2-corporation that a notice dated 10.07.1998 was
issued to the respondent no.4 for non utilization of the plot in dispute and a
public notice dated 06.10.1998 was also published in the news daily, Danik
Jagran. Further although the allottee of the plot in dispute, respondent no.4
has been impleaded as a party in the present writ petition, however, no
counter affidavit has been filed by her to controvert the contention of the
respondent no.2-corporation in this regard. Thus, the contention of the
petitioner that the allotment had been cancelled without affording any
opportunity of hearing does not hold good.
13. As far as the contention of the respondents that the petitioner has no right
to question the cancellation of the allotment of the plot in dispute is
concerned, the perusal of Clause 4(j) of the agreement reveals that the
petitioner had no indefeasible right to get the plot in dispute transferred in
her favour and the discretion in this regard vested with the respondent no.2corporation. Further the petitioner duly admits the letter dated 17.07.1997
issued by the respondent no.3 pointing out certain deficiencies in the transfer
application. However, it is contended by the petitioner that the deficiencies
so pointed out were duly removed and the petitioner in support thereof has
relied upon the letter dated 11.09.1997, which said letter has been denied by
the respondent no.2-corporation. Moreover, there is nothing on record to
demonstrate as to how the aforesaid letter dated 11.09.1997 was served upon
the respondent no.2-corporation. Even otherwise the perusal of the letter
dated 11.09.1997 reveals that it has been asserted in the same that the
petitioner had submitted the revised site plan and project report but the date
of said submission has been left undated in the aforesaid letter. Thus, the
WRIC No. 4285 of 2009
pleadings as well as the evidence in support thereof fail to demonstrate as to
when the deficiencies pointed out by the respondent no.2-corporation vide
letter dated 17.07.1997 had been removed. The averments in the writ petition
that the revised plan was submitted by the petitioner vide letter dated
11.09.1997 is not in conformity with the contents of the letter dated
11.09.1997 wherein the date of submission of revised site plan and project
report has been left blank and no date of submission of revised plans has
been mentioned. Hence, in view of above it can be very well concluded that
the petitioner has failed to demonstrate, as to when the deficiencies pointed
out in the letter dated 17.07.1997 were removed.
14. Even otherwise, the petitioner in the writ petition has not challenged the
letter dated 19.12.1998 by means of which the allotment of the plot in
dispute in favour of respondent no.4 has been cancelled, besides we have a
serious doubts about the locus of the petitioner to challenge the same, in
view of the findings above. Further the petitioner in the present writ petition
has only challenged the order/letter dated 16.10.2008, which is merely a
communication informing that the allotment of the respondent no.4 over the
plot in dispute had been cancelled and the same had been allotted to
respondent no.5 in the year 1999 and the respondent no.5 was duly operating
his production unit over the same. Thus, the petitioner not having challenged
the order dated 19.12.1998 by means of which the allotment of the plot in
dispute in favour of the respondent no.4 was cancelled, no further relief can
be granted in favour of the petitioner.
15. Lastly, it has been contended by the respondents that the present writ
petition is liable to be dismissed on the ground of laches in view of the fact
that the application for transfer of the plot in dispute was filed on 12.12.1996
whereas the present writ petition has been filed in the year 2009 after a lapse
of more than 12 years. In this regard, the contention of the petitioner is that
the petitioner was repeatedly approaching the respondents but the same was
of no avail. However, the perusal of the record reveals that the petitioner
after the issuance of alleged letter dated 11.09.1997 had only submitted two
representations dated 17.05.2008, addressed to the Principal Secretary of the
Chief Minister and the other representation dated 08.09.2008, addressed to
the respondent no.3.
16. Thus, from the records it is evident that the petitioner for the first time
had approached the respondent no.2-corporation vide letter dated 08.09.2008
and in response thereto the impugned letter/order dated 16.10.2008 was
issued by the respondent no.3. Hence it is beyond doubt that the petitioner
had slept over issue for a duration of about 11 years . It is also settled that
filing of repeated representations does not constitute a sufficient cause for
the explanation for delay in approaching this Court. Thus, the present writ
petition is liable to be dismissed on the ground of laches as well.
17. Under these circumstances, the present writ petition lacks merit and is
hereby dismissed. No order as to costs.
October 23, 2026
Gaurav
(Sudhanshu Chauhan,J.) (Saral Srivastava,J.)
High Court of Judicature at Allahabad
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review