THE HIGH COURT OF MEGHALAYA
AT SHILLONG.
WP(C) No. 92 of 2016
Smt Daplin Umsong
Daughter of (L) Kynjai Pyngrope
Resident of 17th Mile Byrnihat,
Ri-Bhoi District, Meghalaya
:::::: Petitioner
-Versus1. State of Meghalaya,
Represented by Commissioner
Secretary, Govt. of Meghalaya
2. The Collector,
Ribhoi District at Nongpoh
3. The National Highway Authority of
India, Represented by Chairman,
Sector 10 Dwarka, New Delhi-11075
4. Project Director,
National Highway Authority of India,
Suraj Nagar, Mukunola path, G.S. Road,
Khanapara, Guwahati.
:::::: Respondents
WP(C) No. 93 of 2016
Smt Bir Umsong
Daughter of (L) Kynjai Pyngrope
Resident of Lum Nongrim, Byrnihat
Ri-Bhoi District, Meghalaya
-Versus1. State of Meghalaya,
Represented by Commissioner
Secretary, Govt. of Meghalaya
2. The Collector,
Ribhoi District at Nongpoh
3. The National Highway Authority of
India, Represented by Chairman,
Sector 10 Dwarka, New Delhi-11075
:::::: Petitioner
4. Project Director,
National Highway Authority of India,
Suraj Nagar, Mukunola path, G.S. Road,
Khanapara, Guwahati.
:::::: Respondents
BEFORE
THE HON’BLE MR JUSTICE SR SEN
For the Petitioners
:
Mr. R. Kar, Adv.
For the Respondents
:
Capt. Pradeep Kumar, Adv
& Mr. S. Sen Gupta, Addl. Sr. GA.
Date of hearing
:
16.11.2016
Date of Judgment & Order
:
25.11.2016
JUDGMENT AND ORDER
Heard Mr. R. Kar, learned counsel for the petitioner as well as Capt.
Pradeep Kumar, learned counsel for the respondents No. 3 and 4 and Mr. S. Sen
Gupta, learned Addl. Sr. GA for the respondents No. 1 and 2.
2.
The brief fact of the petitioner’s case in a nutshell is that:
―The petitioner is a Khasi Woman, who is an Agriculturist/Horticulturist
having her own plot of land at Byrnihat area of Ri Bhoi District. In the
year 2010 her land was acquired for the purpose of construction of
Jorabat to Lad Umroi portion of the National Highway. As she was paid
inadequate compensation, she had approached the Collector who
referred her case before the Special Judicial Officer at Nongpoh, RiBhoi District. The said case which is referred as LA 12 of 2014 is still
pending.
That in the mean time in the year 2013 additional plot of
her land was acquired under the New Act i.e. The Right to Fair
Compensation & Transparency in the Land Acquisition Act, ReSettlement and Re-Habilitation Act, 2013 which required a separate
parameter to be considered for the purpose of award of the acquired
land. The New Act was enacted to provide a better deal to the farmers.
However though the compensation was paid on the new Act the
quantum of the same was too less and it appears that parameter set
out by the new law was not considered for the purpose of
compensation. The petitioner being aggrieved approached the
authorities to refer her case before the appropriate authority in terms of
Section 51 of the Act, but it appears that the State is yet to constitute
an appropriate authority which has the power to determine fair
compensation. The petitioner‘s case is that Constitution of the authority
is mandatory and as such the respondent State is bound to constitute
the same keeping in view the beneficial nature of the Act i.e. the New
Act of 2013 and non constitution of the authority has adversely affected
her interest as she remains forum less to ventilate her grievance and
hence the petitioner approaches this Hon‘ble High Court under 226 of
the Constitution of India, praying your Lordships intervention into the
matter by directing the state to constitute an authority for the purpose
of adjudication of her claim‖.
3.
The learned counsel for the petitioner submitted that the State
Government had acquired a plot of land at Byrnihat area of Ri-Bhoi District in the
year 2010 for the purpose of construction of Jorabat to Lad Umroi portion of the
National Highway and the petitioner was paid inadequate compensation. And the
matter was pending as L.A. No. 12 of 2014 before the Special Judicial Officer at
Nongpoh, Ri-Bhoi District under the Land Acquisition Act till date.
That in the meantime in the year 2013 additional plot of land was also
acquired from the land of the petitioner under the New Act of 2013. The new Act
was enacted to provide a better deal to the farmers, though the compensation
was paid on the new Act, but the quantum of the same was too less. He also
further argued that, while awarding compensation, the parameter set out by the
new law was not considered. Therefore, the petitioner approached to refer in
terms of Section 51 of the Land Acquisition Act, 2013. The learned counsel
further argued that the Constitution of the authority under the new Act of 2013 is
mandatory and prayed for necessary order.
4.
On the other hand, the learned counsel for the respondents No. 2 and 3
submitted that, 80% of the compensation was awarded as per the assessment
made by the Deputy Commissioner, Ri-Bhoi District, Nongpoh and there is no
question of paying less compensation and further submits that adequate
compensation was paid. So, the petition may be dismissed.
5.
After hearing the submissions advanced by the learned counsel, it is
apparent that the land was acquired under the new Act called “The Right to Fair
Compensation & Transparency in the Land Acquisition Act, Re-Settlement and
Re-Habilitation Act, 2013. It is also an undisputed fact that, 80% of the
compensation was paid to the petitioner.
6.
Now the question which arises before this Court is whether the
compensation so paid is adequate? To answer this question, we will have to
follow the procedure laid down under the new Act, 2013. Section 15 provides the
Submission for Hearing of Objections, Section 28 provides the Parameters to be
considered by Collector in determination of award, Section 51 makes a provision
for Establishment of Land Acquisition, Rehabilitation and Resettlement Authority,
Section 64 makes a clear provision for Reference to Authority.
For ready reference Section 51 of the Act speaks as follows:
―51. Establishment of Land Acquisition, Rehabilitation and
Resettlement Authority. – (1) The appropriate Government
shall, for the purpose of providing speedy disposal of disputes
relating to land acquisition, compensation, rehabilitation and
resettlement, establish, by notification, one or more Authorities to
be known as ―the Land Acquisition, Rehabilitation and
Resettlement Authority‖ to exercise jurisdiction, powers and
authority conferred on it by or under this Act.
(2) The appropriate Government shall also specify in the
notification referred to in sub-section (1) the areas within which the
Authority may exercise jurisdiction for entertaining and deciding
the references made to it under section 64 or applications made
by the applicant under second proviso to 28 sub-section (1) of
section 64‖.
7.
Section 64 further speaks about Reference to Authority which is
reproduced herein below for ready reference:
―64. Reference to Authority.– (1) Any person interested who
has not accepted the award may, by written application to the
Collector, require that the matter be referred by the Collector for
the determination of the Authority, as the case may be, whether
his objection be to the measurement of the land, the amount of
the compensation, the person to whom it is payable, the rights
of Rehabilitation and Resettlement under Chapters V and VI or
the apportionment of the compensation among the persons
interested:
Provided that the Collector shall, within a period of thirty
days from the date of receipt of application, make a reference to
the appropriate Authority:
Provided further that where the Collector fails to make
such reference within the period so specified, the applicant may
apply to the Authority, as the case may be, requesting it to direct
the Collector to make the reference to it within a period of thirty
days.
(2) The application shall state the grounds on which
objection to the award is taken:
Provided that every such application shall be made—
(a) if the person making it was present or represented
before the Collector at the time when he made his
award, within six weeks from the date of the
Collector‗s award;
(b) in other cases, within six weeks of the receipt of the
notice from the Collector under section 21, or within
six months from the date of the Collector‗s award,
whichever period shall first expire:
Provided further that the Collector may entertain an
application after the expiry of the said period, within a further
period of one year, if he is satisfied that there was sufficient
cause for not filing it within the period specified in the first
proviso‖.
8.
On combined reading of Section 51 and Section 64, it is understood that
the Government concerned is bound to notify and to establish the authority to
settle the Land Acquisition, Rehabilitation and Resettlement and Section 64
provides how to make a Reference to Authority.
9.
Since in this case, the land has been acquired under the new Land
Acquisition Act, 2013, the Secretary, Law Department, Government of Meghalaya
is directed to notify and to establish the authority immediately within 15(fifteen)
days from the date of receipt of a certified copy of this judgment and order.
Thereafter, the petitioner will be at liberty to make a reference to the Authority
concerned through the Collector of the District.
10.
Since the facts and circumstances of the WP(C) No. 92 of 2016 and
WP(C) No. 93 of 2016 are similar and equal in nature, both the petitions are
allowed and stands disposed of by this common judgment and order.
11.
No order as to costs.
JUDGE
D. Nary
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review