Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
THE HIGH COURT OF MEGHALAYA
AT SHILLONG.
WP(C) No. 246 of 2016
Shri Ombormi L. Tariang,
S/o (L) Bik Pajat,
R/o Bataw Village
East Jaintia Hills District,
Meghalaya
… Petitioner
- Versus 1.
The State of Meghalaya
Represented by the Commissioner
Secretary, Water and
Sanitation Mission, Government
of Meghalaya, Shillong.
2.
The Executive Engineer (PHE)
RWS Division, Jowai,
Cum Member Secretary
District Water and Sanitation
Mission Jowai.
… Respondents
BEFORE
THE HON’BLE MR JUSTICE SR SEN
For the Petitioner
:
Mr. S. Dey, Adv.
For the Respondent s
:
Mr. A.H. Hazarika, GA.
Date of hearing
:
07.09.2016
Date of Judgment & Order :
07.09.2016
JUDGMENT AND ORDER (ORAL)
Heard Mr. S. Dey, learned counsel for the petitioner as well as Mr. A.H.
Hazarika, learned GA for the respondents.
2.
The brief fact of the petitioner’s case in a nutshell is that:
“That the Petitioner is the citizen of India and he is entitled to all the rights
and privileges guaranteed under the Constitution of India and the Laws
framed there-under. The Petitioner is the member of the Executive
Committee of the Bataw Village and also the Secretary of the Village
Water and Sanitation Committee, Bataw Village which was constituted by
the Office of the Dorbar Shnong Bataw. In the year 2011 Village Water
and Sanitation Committee, Bataw Village was constituted and the date of
established of the said Committee was 18.03.2011. The Headman of the
Bataw village vide No-Objection Certificate dated 8th July 2011 has
confirmed that the village dorbar has No-Objection with regard to the
Bataw “Village Water and Sanitation Committee”, and further the said
Headman was also given his NOC to the said Committee to move forward
with their work. On 11.07.2011 village dorbar shnong meeting was held at
the premises of Government L.P. School, Bataw Nengshnong and on the
said meeting some resolutions were passed and as per one of the
resolution the members of the VWSC were selected. Thereafter on the
same day an application was submitted before the Joint Registrar of
Societies, Jaintia Hills District, Jowai for registering the said Committee.
On 27th July, 2011 the Joint Registrar of Societies, Jaintia
Hills District, Jowai issued the Registration Certificate to the said
Committee under the Registration of Societies Act XXI of 1860 and the
VWSC Bataw village was also allotted Registration No. SR/JH/VWSCB1057/39 of 2011 under the above mentioned Act.
Again on 25.04.2015 the said dorbar shnong held another
meeting and on the said meeting the members and Office bearer of
“Village Water and Sanitation Committee” Bataw village, were selected
for a term of (3) three year i.e. from 2015 to 2018. The members of the
Dorbar Shnong on the said meeting has decided to open a current Bank
Account in the name of the said Committee and it was further decided in
the said meeting to authorize the Chairman and Secretary (Petitioner) of
the said Committee to operate the said bank account. As per the said
resolution current bank account was open in the name of the “VILLAGE
WATER & SANITATION COMMITTEE (VWSC) BATAW” with the
Meghalaya Rural Bank, Jowai and to that effect bank pass-book was
issued vide dated 06.05.2015 and the said bank account is being operated
by the Chairman and the Secretary (Petitioner) of the said Committee.
On 01.09.2015 an amount of Rupees 20, 96, 000/- was
released as the 1st installment for construction of I.H.H.L by the
Respondent No. 2. The project was proposed for the benefits of the
villagers by the VWSC, Bataw village and the Durbar Shnong and
moreover proposal was also given to the villagers/ beneficiaries by the
members of the dorbar shnong and VWSC that who ever want to construct
the latrine by themselves the said Committee will provide the materials for
the construction. The amount which was allotted to the said committee
was withdrawn by the Chairman and the Petitioner from the said bank,
thereafter the material for construction were purchased by the members of
the VWSC for distribution from Rymbai Marble House, Lad Nartiang
Mihmyntdu Jowai vide cash memo Sl. No. 287 dated 29.09.2015 and
Genesis Hardware Sore, Mooralong, Ladthadlaboh, Jowai vide cash
memo Sl. No. 29 dated 02.10.2015, the total amount of money which was
spend for purchasing the said materials is Rs 8,65,595/- only. After the
materials were purchased and the same was duly distributed to all the
beneficiaries of the said village who wanted to construct the latrine by
themselves. However in between the execution of the said work
unfortunately the Petitioner’s father fall ill and his condition was very
serious, the Petitioner immediately admitted his father at NEIGRIMS
hospital, Shillong. As per the report of the doctors of NEIGRIMS hospital
issued on 19th September 2015 the Petitioner’s father namely Shri Bik
Pajat was suffering from Chronic Liver disease with Protal Hypertension.
The Petitioner’s father died on 14.11.2015 at his resident.
While the construction works was going on the Petitioner
was utter shock and surprise to learned that the Executive Engineer (PHE)
RWS Division, Jowai cum Member Secretary District Water and Sanitation
Mission Jowai lodged an First Information Report with the Officer InCharge of Ladrymbai Outpost, East Jaintia Hills District and a case was
registered against him vide Khliehriat P.S. case No. 96 (4) of 2016 under
Section 409 IPC. As per the said FIR the Respondent No. 2 alleged that
the Petitioner have misuse the fund amounting to Rs. 14,84,950/- only
which was meant for construction of 262 numbers of Latrine in their
village, the said Respondent also alleged that the 1st installment
amounting to Rs. 20,96,000/- only was released to the VWSC since 1st
September 2015 and the same has been already withdrawn by the
Petitioner, moreover it was further alleged that on enquiry it was found out
that only Rs. 6, 11,050/- only have been utilized by the Petitioner for
purchase of materials and the balance amount is lying with him. It is to
mention herein that joint account was operated by the Chairman and
Secretary (Petitioner) of the said Committee. Neither the amount as
alleged by the Respondent No 2 was withdrawn by the Petitioner alone nor
the Petitioner was ever asked to show cause as to why action against him
should not be initiated for non utilization of the said amount/failure to
construct 262 numbers of latrine.
The Petitioner along with the Chairman of the said
Committee has purchased the material for distribution to the beneficiaries
from Rymbai Marble House, Lad Nartiang Mihmyntdu Jowai vide cash
memo Sl. No 287 dated 29.09.2015 amounting Rs. 4,77,135/- only,
Genesis Hardware Sore, Mooralong, Ladthadlaboh, Jowai vide cash
memo Sl. No 29 dated 02.10.2015 amounting Rs 3,88,460/- and vide letter
dated 17.02.2016 which was issued by Mr S. Sumer that he has received
an amount of Rs. 5, 38,000/- from the Petitioner for supplying of PPC
Cements to Bataw VWSC. The total amount which was spend by the
Petitioner and the Chairman was Rs. 14,03,595/- only for purchasing the
materials for the construction of 262 number of latrine. Moreover the said
allegation levelled by the Respondent is totally false, fabricated and said
FIR dated 11th April 2016 was lodged due to personal feeling of
resentment of the Respondent and also of the President of FKJGP Bataw
unit, which is apparent from the FIR dated 11th April 2016 itself which show
that the Respondent No.2 has also send a copy of the said FIR to the
President of FKJGP, Bataw unit. It is to point out that the said FIR was
lodged at the instant and initiative of the President of FKJGP, Bataw unit
since he wanted to supply the material at a higher cost than that of the
market price. The Petitioner after learning about the said FIR dated 11 th
April 2016, the Petitioner moved an Application under Section 438 Cr.P.C.
before the Learned Court of the Additional Deputy Commissioner (Judicial)
at Khliehriat on 15th April 2016, however the same was rejected on
26.04.2016, after both the parties were heard and after perused the I.O.
report. Thereafter Petitioner prayed before the said Respondent to grand
him another 15(fifteen) days time so that the pending construction works
can be completed in due time. It is pertinent to mention herein that a copy
of the same was also submitted to the Ladrymbai Police Outpost, East
Jaintia Hills District, Meghalaya for information.
Even after a period of more than 3(three) months the said
Respondent No 2 did not disposed the application of the Petitioner,
however in number of time the Petitioner approached and requested
verbally to the said Officer to dispose his application dated 05.05.2016, but
till date the said Officer did not disposed the application of the Petitioner.
The action of the Respondent No. 2 is unconstitutional and contradictory to
the law of the land and is violative of Principle of natural justice. Hence this
Petition.”
3.
The learned counsel for the petitioner contended that the petitioner could
not complete the project under I.H.H.L due to the sudden demise of his father on
14.11.2015. So, he made a Representation on 05.05.2016 praying for extension of
time of 15(fifteen) days to complete the said project, but the same is pending with
the Office of the Executive Engineer (PHE) RWS Division, Jowai Cum Member
Secretary, District Water and Sanitation Mission Jowai. Hence, this instant writ
petition for necessary direction.
4.
I have perused the Representation dated 05.05.2016 which is at
Annexure-17 of the writ petition, wherein it appears that the petitioner could not
complete the project within the time framed due to the sudden demise of his father
and prayed for extension of time for 15(fifteen) days. In my view, the Executive
Engineer (PHE) RWS Division Jowai Cum Member Secretary, District Water and
Sanitation Mission Jowai should have considered the prayer of the petitioner on
sympathetic and humanitarian ground. The Executive Engineer (PHE) RWS
Division Jowai Cum Member Secretary, District Water and Sanitation Mission Jowai
is hereby directed to allow the petitioner 15(fifteen) days’ time to complete the said
project from the date of receipt of a certified copy of this judgment and order.
5.
With this observation and direction the instant writ petition is allowed and
stands disposed of.
JUDGE
D. Nary
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review