RFA NO. 1 OF 2016
THE HIGH COURT OF MEGHALAYA AT
SHILLONG
: ORDER :
RFA NO. 1 OF 2016
Shri Nikson Nongrum
::: Appellant
Versus
Meghalaya Tourism Development Corporation
Limited
::: Respondent
Date of Order
::: 21.11.2017
PRESENT
HON’BLE SHRI JUSTICE DINESH MAHESHWARI, CHIEF JUSTICE
Shri S Chakrawarty Sr. Adv. with Shri HL Shangreiso, for the Appellant.
Shri B Baruah, for the respondent.
BY THE COURT: (ORAL)
PRELIMINARY
This first appeal is directed against the judgment and decree dated
05.12.2014 as passed in Money Suit No. 7 (H) of 2000 whereby, the learned
Assistant District Judge, Shillong has dismissed the suit filed by the
plaintiff/appellant, essentially on the ground that the same was barred by
limitation.
Learned
counsel
for
the
parties
have
advanced
elaborate
submissions on the question of limitation and that being the basic point for
determination in this appeal, the facts and background aspects may be
noticed in brief, to the extent relevant for the present purpose.
THE BACKGROUND ASPECTS
On 18.06.1997, the original plaintiff Smti. Isabell Nongrum (since
deceased and represented by her son in the present appeal) filed the suit
leading to this appeal, for declaration and money recovery, in the Court of
RFA NO. 1 OF 2016
the Assistant to the Deputy Commissioner at Shillong that was registered as
Title Suit No. 12 (T) of 1997. It was, however, found that the suit had been
filed in the wrong forum and hence, the plaint was returned to the plaintiff on
12.04.2000 and the same was, thereafter, presented in the Court of the
Assistant District Judge, Shillong where the matter came to be registered as
Money Suit No. 7 (H) of 2000. In this suit, the plaintiff claimed the following
reliefs:― The plaintiff, therefore, prays
(a)
for a declaration that the letter No. MTDC/TB/CS/42/85/45, dated
18.11.86 imposing a penalty of Rs. 31,350/- (Rupees Thirty One
thousand three hundred fifty) onluy on the plaintiff in respect of
sanitary fitting and Internal Water supply work is illegal and void.
(b)
for a declaration that letter No. MTDC/TB/CS/42/85/46, dated
18.11.86 imposing a penalty of Rs. 1,94,740/- (Rupees One lacs
ninety four thousand Seven hundred forty) only on the plaintiff in
respect of Civil Work is illegal and void.
(c)
for a decree of Rs. 65,59,855/- (Rupees sixty five lacs fifty none
thousand eight hundred fifty five and paise eighty( only against the
defendant.
(d)
for a decree of interest 23%p.a. w.e.f. 01.10.96, till realisation, on the
aforesaid amount of Rs. 65,59,855/- ( Rupee Sixty five lacs fifty-nine
thousand eight hundred fifty five & paise eighty) only.
(e)
for a declaration that the letter No. MTDC/TB/CS/85/47, dated19/11/86 alleging the works executed by the plaintiff to be of low
quality, sub-standard and technically defective is illegal and
technically defective is illegal and void.
(f)
for any other relief/reliefs as the plaintiff may be found entitled to in
law and equity.
(g)
for cost of the suit.‖
On the basic facts, the plaintiff averred that in her capacity as Class I,
P.W.D. Contractor, she had submitted her offer in response to the Notice
Inviting Tender dated 31.05.1985 for the work of “Construction of the
Remaining Apartments (Basement) etc., Phase – II Construction of the
Tourist Lodge Building at Shillong”; and after negotiations, the work was
allotted to her at 49.8% above the schedule of rates under the work-order
RFA NO. 1 OF 2016
dated 19.07.1985. The plaintiff pointed out that the estimated value of the
work was Rs. 19,47,000/- (Rupees nineteen lakhs and fourty-seven
thousand) and the work was to be completed within seven months. It was
further pointed out that a supplementary work of sanitary installation and
internal water supply in the same construction was also awarded to her at
the negotiated rate of 42.5% above the schedule of rates; the estimated
value whereof was Rs. 3,13,500/- (Rupees three lakhs thirteen thousand
and five hundred) and this supplementary work was to be completed within
three months. The plaintiff also pointed out that she had deposited the
security amount of Rs. 97,500/- (Rupees ninety-seven thousand five
hundred) towards the main construction work and another Rs. 13,500/(Rupees thirteen thousand five hundred) towards the supplementary work.
The plaintiff averred that with her sincere efforts, the major portion of
the work was completed but due to inapt handling of the project by the
defendant, progress of the work slowed down and even some of the
executed work had to be dismantled when there were several alterations
and modifications of the original drawings. After lengthy details of the
deviations or shortcomings on the part of the defendant, the plaintiff averred
that she asked for extension of time upto 30.06.1986 for completion of the
work and for enhancement of the rates as also for payment of extra amount
towards modified items of work; but the defendant only extended the time
upto 15.05.1986. The plaintiff further averred that though the work was
completed within the extended period and the completed building was to be
handed over but the defendant further ordered modification over the already
completed work, which required her to spend yet further and extra amount in
execution. While omitting the other details, suffice it is to notice that
RFA NO. 1 OF 2016
according to the plaintiff, ultimately, the completed construction was handed
over to the defendant on 03.10.1986.
The plaintiff alleged that after handing over the building, the
defendant started finding faults with the work executed, with the intention of
causing harm and financial loss to her. After a reference to the
correspondence exchanged, the plaintiff pointed out that she approached
the High Court by way of a writ petition, which was registered as Civil Rule
No. 127 of 1987 wherein, by the order dated 30.11.1989, the High Court
directed the defendant to release a sum of Rs. 2,76,429/- (Rupees two lakhs
seventy-six thousand four hundred and twenty nine) in her favour.
The plaintiff further averred that during the pendency of the said writ
petition, the parties attempted to settle the matter amicably and the
defendant, by the letter dated 17.04.1996, sent a draft Memorandum of
Understanding [„MOU‟] to her for comment and consideration upon which
she suggested a few amendments. The contents of this draft MOU, having
their relevance, shall be noticed hereafter later. The plaintiff averred that
Clause-8 of the said MOU required her to withdraw the Court case and
hence, on 04.06.1996, she made the prayer for withdrawal which was
granted by the High Court while allowing her to seek appropriate remedy
under the law, if so required. This order dated 04.06.1996 shall also be
referred a little later.
It is noticed from the record that on 30.10.2000, the plaint was
amended with insertion of paragraphs 36-A, 36-B, 36- C and 37-A as also
with amendment of paragraph 42. The relevant plaint averments, having
direct correlation with the question of limitation, could be usefully noticed as
under:―36. That during the pendency of the said civil Rule the parties here to
attempted to settle the matter amicably outside the court and all efforts were
RFA NO. 1 OF 2016
made in this direction by the plaintiff as she knocked the door of ministers,
political leaders including Chief Minister and Chief Secretary besides the
officers of the defendant office. In the meantime the said writ petition
remained pending in the court.
36 A. That all through there was a negotiation of compromise between the
plaintiff and the defendants which was initiated by the defendant, but due to
some reason or other best known to the defendant no settlement could be
arrived at though the plaintiff was always willing to settle the matter
considering the greater public interest involved.
36 B. That the defendants by their commitment of settlement of the
disputed issues involved in the suit has legally acknowledged the claim of
the plaintiff and therefore kept the matter alive till the settlement is reached.
36 C. That the defendant after thread bear discussion held on different
dates told the plaintiff that they shall prepare a draft memorandum of
settlement and the same shall officially be given to the plaintiff for her
acceptance.
37.
That finally the defendant vide his letter No. MTDC/TB/CS/42/85-/97
dated 17.04.96 sent a draft Memorandum of understanding to the plaintiff
for her comment and consideration, upon which the plaintiff being eagerly
interested to settle the matter amicably suggested few amendments in the
said memorandum of understanding as the draft did not touch the basic
issues.
A copy of the letter dated 17.04.96 alongwith MOU are at AnnexureX.
37 A. That on the issue of the letter No. MTDC/TB/CS/42/85/97 dated
17.04.96, by which the draft memorandum of understanding was remitted to
the plaintiff the defendant acknowledged the claim of the plaintiff and given
fresh cause of action regularizing the period of limitation involved in the suit.
Besides this the plaintiff all through was pursuing the matter and her interest
was subjudice before the various court including the High Court and hence
the right of plaintiff was never extinguished by any law applicable to the
case.
38.
That the clause-8 of the aforesaid MOU required the plaintiff of
withdraw the court case pertaining to the work and as such to facilitate and
early and amicable settlement of the case the plaintiff withdrew the said
Civil Rule on 04.06.96 and accordingly an order permitting withdrawal of the
case passed by the Hon’ble High Court permitting the plaintiff to seek
appropriate remedy under law if so required.
A copy of the order dated 04.06.96 is enclosed at Annexure-Y.
******
******
******
*****
42.
That the cause of action for the suit arose on 31.05.85, 19.07.85,
06.11.85, 06.12.85, 26.02.86, 31.05.86, 04.08.86, 04.03.86, 15.05.86,
15.09.86, 30,09,86, 03.10.86, 10.10.86, 14.12.86, 17.10.86, 18.10.86,
24.10.86, 03.11.86, 05.11.86, 18.11.86, 19.11.86, 04.06.96, 28.10.96, and
on various prior, in between and subsequent dates which is still continuing
within the jurisdiction of this hon’ble court.‖
RFA NO. 1 OF 2016
The plaintiff gives out the details of the work done by her and while
assailing the action of the defendant, prayed for reliefs as noticed at the
outset.
The defendant in its written statement, while refuting the other plaint
averments, averred that the suit was barred by limitation and that no fresh
cause of action arose by the MOU, as alleged. The defendant, inter alia,
averred as under:
―34. That the statements made in paragraph 37 A of the plaint is not
admitted and hereby denied. The Defendant say that the instant suit is
barred by limitation and no fresh cause of action had arisen by the M.O.U.
as alleged, which, in any view, of the matter, is only a draft proposal at the
instance of the plaintiff.‖
On the pleadings of the parties, the Trial Court framed as many as 14
issues. Issue No. 3 was precisely framed on the question if the suit was
barred by limitation. In evidence, the plaintiff examined two witnesses
whereas the defendant examined three witnesses. The plaintiff exhibited as
many as twenty-eight documents whereas the defendant exhibited four
documents.
Perusal of the record makes out that the Trial Court initially proceeded
to decree the suit on 13.06.2003 without even determining the question of
limitation. The judgment and decree so passed by the Trial Court was
challenged by the defendant in the jurisdictional High Court in RFA No. 14 of
2004. The appeal so filed by the defendant was allowed by the High Court
on 22.11.2007 and the matter was remanded to the Trial Court to decide the
issues in accordance with law. Strangely, after such remand, the learned
Trial Court, chose to decide only Issue No. 3 and that too ex-parte against
the defendant; and again decreed the suit in favour of the plaintiff on
26.04.2013. The defendant preferred yet another appeal, being RFA No. 1
of 2014 that was considered and allowed by the learned Single Judge of this
RFA NO. 1 OF 2016
Court on 10.09.2014 while disapproving the judgment and decree dated
26.04.2013; and the matter was remanded to the Trial Court over again.
IMPUGNED JUDGMENT AND DECREE DATED 05.12.2014
Pursuant to the order so passed by this Court, the Trial Court heard
and decided the matter afresh by the impugned judgment and decree dated
05.12.2014.
It appears that as regards the question of limitation, the basic
contention urged on behalf of the plaintiff was that she was pursuing her
remedy in the High Court in Civil Rule No. 127 of 1987, which was
subsequently renumbered as Civil Rule No. 54 (SH) of 1989 and therein,
she was granted liberty to seek appropriate remedy under the law, if so
required; and hence, the time spent in the High Court was required to be
excluded for the purpose of limitation; and similarly, the time spent in the
Court of Assistant to the Deputy Commissioner, Shillong was also required
to be excluded as the plaintiff was prosecuting in the wrong forum and the
plaint was returned on 12.04.2000.
The Trial Court referred to the order passed by the High Court in Civil
Rule No. 127 of 1987 [renumbered Civil Rule No. 54 (SH) of 1989] and the
ratio in the decision of the Hon‟ble Supreme Court in the case of Deena
(Dead) Through LRs v. Bharat Singh: (2002) 6 SCC 336 on the
interpretation of Section 14 of the Limitation Act, 1963 and found that the
plaintiff was not entitled to the benefit of Section 14 of the Act of 1963 in the
following:―Applying the ratio in Deena versus Bharat Singh reported in (2002)
6 SCC 336 to the facts of the instant case, there is no pleading nor
evidence led, that the cause of action in the Civil rule filed before the
Hon’ble High Court and the instant suit are the same. It is also not the
plaintiff’s case that civil rule was dismissed due to defect of jurisdiction or
other cause of like nature as contemplated under section 14 of the
Limitation Act 1963.
In the absence of any evidence that the cause of action in the Civil
Rule and the instant suit are the same and that the failure of the prior
RFA NO. 1 OF 2016
proceeding was due to defect of jurisdiction or other cause of like nature, I
am constrained to hold that the plaintiff is not entitled to benefit of section
14 of the Limitation Act 1963.
In view of the forgoing discussions, I am of the considered view that
the suit is clearly barred by limitation and this issue is decided in the
affirmative.‖
In view of the above and in view of other findings, the Trial Court
found that the suit was hopelessly barred by limitation and then, while
determining other issues, dismissed the suit essentially on the ground of
limitation by the impugned judgment and decree dated 05.12.2014.
It is noticed that as per the applications moved in this matter, the
original plaintiff expired on 05.01.2015. Hence, her son has preferred this
first appeal as the appellant.
RIVAL CONTENTIONS
Learned senior counsel Shri S Chakrawarty appearing for the
appellant has strenuously argued that the matter in question was clearly
covered by Section 14 of the Limitation Act, 1963 [„the Act of 1963‟] for the
reason that the proceeding relating to the same matter in issue was being
prosecuted in good faith in the High Court in the aforesaid writ petition and
such proceeding was in the civil court and was of the civil nature; and the
appellant withdrew from such proceeding in view of the proposition of
settlement between the parties. Learned counsel has referred to the
decision of the Hon‟ble Rajasthan High Court in the case of Bhupendra
Singh v. Gulab Singh: AIR 1966 Rajasthan 92 to contend that Section 14
of the Act of 1963 is required to be liberally applied so as to exclude the time
spent in the said writ petition.
The learned counsel has yet further argued that the letter dated
07.04.1996 with its accompanying Memorandum of Understanding (Ext. 27)
clearly amounted to an acknowledgement for the purpose of Section 18 of
the Act of 1963. Learned counsel has particularly referred to Clauses 7 and
RFA NO. 1 OF 2016
8 of the draft MOU with the submissions that the said Clauses clearly make
out by necessary implication that there were pending claims of the plaintiff–
contractor, which were to be settled after the proposed re-measurements.
Learned counsel has referred to and relied upon the decisions of the
Hon‟ble Supreme Court in the cases of Lakshmiratan Cotton Mills, Co.
Ltd. V. The Aluminium Corporation of India Ltd. : AIR 1971 SC 1482,
Shapoor Fredoom, Mazda v. Durga Prosad Chamaria and Others: AIR
1961 SC 1236 and that of the Hon‟ble Patna High Court in the case of
Sarangdhar Singh v. Lakshmi Narayan : AIR 1955 Patna 320.
Per contra, learned counsel for the respondent Shri B Baruah has
emphasized on the submissions that Section 14 of the Act of 1963 does not
apply in the present case for the reason that neither any such pleadings
were taken in the plaint nor any evidence was led in that regard by
producing a copy of the petition filed in the High Court. Thus, according to
the learned counsel, there is nothing on record for the Court to examine, if
the earlier proceeding related to the same matter in issue. This apart,
learned counsel would further argue that the plaintiff voluntarily withdrew
from the proceeding taken up in the High Court and hence, it cannot be said
that the Court did not proceed with the said petition for any defect of
jurisdiction of any other cause of the like nature. Learned counsel would
submit that the expressions „the other cause of a like nature‟ are required to
be read ejusdem generis with the principal words “defect of jurisdiction” as
explained by the Hon‟ble Supreme Court in the case of Deena (Supra); and
in the present case, the proceedings in the writ petition having not
terminated for any defect of dissolution or other cause of like nature, the
plaintiff is not entitled to seek exclusion of time spent in prosecuting the writ
petition; and hence, the suit for which the cause of action arose way back in
RFA NO. 1 OF 2016
the year 1986, even if taken to have been filed in the year 1997, was
hopelessly barred by limitation.
As regards the submissions that there had been an acknowledgement
on the part of the defendant/respondent, learned counsel has argued that by
way of an unexecuted proposed Memorandum of Understanding, it can
never be deduced that there was any acknowledgement of liability on the
part of the defendant/respondent. Learned counsel would further submit that
an acknowledgement for the purpose of Section 18 of the Act of 1963, if at
all, has to be unequivocal and that too before the expiration of the
prescribed period of limitation but, in the present case, such communication
dated 17.04.1996 was made only at the instance of the plaintiff without any
admission of liability on the part of the defendant; and in any case, on the
date of this communication, the period of limitation for filing the suit had
already gone by and, therefore, this communication hardly enures to the
benefit of the plaintiff. Learned counsel had relied upon the case of State of
Kerela v. T.M.Chacko: (2000) 9 SC 722.
Having given thoughtful consideration to the rival submissions and
having examined the record, this Court is clearly of the view that the
decision of the learned Trial Court on the issue relating to limitation is
perfectly in accord with law and calls for no interference.
THE PLAINTIFF IS NOT ENTITLED TO THE BENEFIT OF SECTION 14
OF THE ACT OF 1963
The main plank of the case of the plaintiff had been that the time
spent in prosecuting the matter in the High Court in Civil Rule No. 127 of
1987 and that spent in the Court of the Assistant to the Deputy
Commissioner at Shillong in Title Suit No. 12 (T) of 1997 was required to be
excluded. Such exclusion of time spent in prosecuting other civil proceeding
RFA NO. 1 OF 2016
in other Court/s is envisaged by Section 14 of the Act of 1963. The question
is as to whether the plaintiff is entitled to the benefit of Section 14 of the Act
of 1963 in the present case? For appropriate consideration of the matter, the
provisions contained in sub-sections (1) and (3) of Section 14 of the Act of
1963 may be noticed as under:―14. Exclusion of time of proceeding bona fide in court without
jurisdiction.(1) In computing the period of limitation for any suit the time during which
the plaintiff has been prosecuting with due diligence another civil
proceeding, whether in a court of first instance or of appeal or revision,
against the defendant shall be excluded, where the proceeding relates to
the same matter in issue and is prosecuted in good faith in a court which,
from defect of jurisdiction or other cause of a like nature, is unable to
entertain it.
***
***
***
(3) Notwithstanding anything contained in rule 2 of Order XXIII of the Code
of Civil Procedure, 1908 (5 of 1908), the provisions of sub-section (1) shall
apply in relation to a fresh suit instituted on permission granted by the court
under rule 1 of that Order where such permission is granted on the ground
that the first suit must fail by reason of a defect in the jurisdiction of the
court or other cause of a like nature.
***
***
***”
For ready reference, the forerunner of the present Sub-section (1) of
Section 14, that is, sub-section (1) of Section 14 of the Limitation Act, 1908
[„the Act of 1908‟] may also be taken note of as under:―14. Exclusion of time of proceeding bona fide in court without
jurisdiction.(1) In computing the period of limitation prescribed for any suit, the time
during which the plaintiff has been prosecuting with due diligence another
civil proceeding, whether in a Court of first instance or in a Court of appeal,
against the defendant, shall be excluded, where the proceeding is founded
upon the same cause of action and is prosecuted in good faith in a court
which, from defect of jurisdiction, or other cause of a like nature, is unable
to entertain it.
***
***
***”
Noticeable it is that in Section 14 (1) of the Act of 1908, the previous
civil proceeding was required to be founded upon “the same cause of
action” whereas, in Section 14 (1) of the Act of 1963, such proceeding ought
to be relating to “the same matter in issue”. Be that as it may, such
RFA NO. 1 OF 2016
difference in the two provisions of the Act of 1908 and the Act of 1963 is not
of much relevance for the present case, which would, obviously, be
governed by the Act of 1963. These two provisions have been indicated for
proper appreciation of the decision of the Hon‟ble Rajasthan High Court in
the case of Bhupendra Singh (supra), as relied upon by the learned counsel
for the appellant. In the said case, the plaintiff had earlier instituted his claim
before the Court of Wards with whom the estate of defendant was placed
under. However, the plaintiff could not recover any amount and later on filed
the suit for money recovery on 02.02.1952; and on the question of limitation,
exclusion of the period spent before the Court of Wards was claimed. The
High Court found that the Court of Wards was a “Court” within the meaning
of Section 14 of Act of 1908; and that due to peculiarity of such Court, the
time spent in the proceedings therein was required to be excluded. In the
given context, the High Court said,―There is abundant authority for the proposition that the expression ―from
defect of jurisdiction or other cause of a like nature‖ should receive a liberal
interpretation. Thus in Mathura Singh v. Bhawani Singh, ILR 22 All 248, it
was held that the principle behind S.14, broadly speaking, was to give
protection against the bar of limitation to a man honestly doing his best to
get his case tried on merits but failing through the Court being unable to
give him such a trial, and, therefore, it was clearly applicable not only to
cases in which a man brings his suit in the wrong Court, that is a Court
having no jurisdiction to entertain it but also where he brings his suit in the
right Court but is nevertheless prevented from getting trial on the merits by
something which, though not a defect of jurisdiction, is analogous to that
defect.‖
On the other hand, the Hon‟ble Supreme Court has expounded on the
principles governing the operation of the Section 14 of the Act of 1963 in the
case of Deena (supra) as under:―13. From the provisions it is clear that it is in the nature of a proviso to
Order 23 Rule 2. The non obstante clause provides that notwithstanding
anything contained in Rule 2 of Order 23 of the Code of Civil Procedure the
provisions of sub-section (1) of Section 14 shall apply in relation to a fresh
suit instituted on permission granted by the court under Rule 1 of Order 23.
RFA NO. 1 OF 2016
For applicability of the provision in sub-section (3) of Section 14 certain
conditions are to be satisfied. Before Section 14 can be pressed into service
the conditions to be satisfied are: (1) both the prior and subsequent
proceedings are civil proceedings prosecuted by the same party; (2) the
prior proceeding had been prosecuted with due diligence and good faith; (3)
the failure of the prior proceeding was due to defect of jurisdiction or other
cause of like nature; (4) the earlier proceeding and the later proceeding
must relate to the same matter in issue; and (5) both the proceedings are in
a court.
14. The main factor which would influence the court in extending the
benefit of Section 14 to a litigant is whether the prior proceeding had been
prosecuted with due diligence and good faith. The party prosecuting the suit
in good faith in the court having no jurisdiction is entitled to exclusion of that
period. The expression ―good faith‖ as used in Section 14 means ―exercise
of due care and attention‖. In the context of Section 14 the expression
―good faith‖ qualifies prosecuting the proceeding in the court which
ultimately is found to have no jurisdiction. The finding as to good faith or the
absence of it is a finding of fact. This Court is in the case of Vijay Kumar
Rampal v. Diwan Devi observed: (AIR p. 1670, para 3)
―The expression good faith qualifies prosecuting the proceeding in
the court which ultimately is found to have no jurisdiction. Failure to
pay the requisite court fee found deficient on a contention being
raised or the error of judgment in valuing a suit filed before a court
which was ultimately found to have no jurisdiction has absolutely
nothing to do with the question of good faith in prosecuting the suit
as provided in Section 14 of the Limitation Act.‖
15. The other expressions relevant to be construed in this regard are
―defect of jurisdiction‖ and ―or other cause of a like nature‖. The expression
―defect of jurisdiction‖ on a plain reading means the court must lack
jurisdiction to entertain the suit or proceeding. The circumstances in which
or the grounds on which, lack of jurisdiction of the court may be found are
not enumerated in the section. It is to be kept in mind that there is a
distinction between granting permission to the plaintiff to withdraw the suit
with leave to file a fresh suit for the same relief under Order 23 Rule 1 and
exclusion of the period of pendency of that suit for the purpose of
computation of limitation in the subsequent suit under Section 14 of the
Limitation Act. The words ―or other cause of a like nature‖ are to be
construed ejusdem generis with the words ―defect of jurisdiction‖, that is to
say, the defect must be of such a character as to make it impossible for the
court to entertain the suit or application and to decide it on merits. Obviously
Section 14 will have no application in a case where the suit is dismissed
after adjudication on its merits and not because the court was unable to
entertain it.‖
(Underlining supplied for emphasis)
After examining the present case in the light of the principles
aforesaid, this Court has no hesitation in concluding that the plaintiff is not
entitled to the benefit of Section 14 of the Act of 1963 so as to exclude the
time spent in prosecuting the writ petition. It may be observed that so far the
time spent in the Court of Assistant to the Deputy Commissioner at Shillong
in Title Suit No. 12 (T) of 1997 is concerned, the same could, of course, be
RFA NO. 1 OF 2016
excluded for the reason that the said Court had no jurisdiction to deal with
the matter and the plaint was returned for presentation in the proper forum.
However, the suit was filed in the Court of Assistant to the Deputy
Commissioner at Shillong only on 18.06.1997; and the plaint was returned
to the plaintiff on 12.04.2000 and the same was, thereafter, presented in the
Court of the Assistant District Judge, Shillong where the matter came to be
registered as Money Suit No. 7 (H) of 2000. Thus, for the present purpose, it
may be assumed that the suit was filed on the date of initial filing, may be in
the wrong Court, i.e., 18.06.1997 but then, the cause of action for filing this
suit for declaration and money recovery arose way back in the year 1986
(when the building was handed over on 03.10.1986 and the impugned
orders imposing penalty were issued on 18.11. 1986); and if, at all a part
payment be also taken into consideration (as was made under the order of
the High Court dated 30.11.1989), it is but clear that as on 18.06.1997, the
period of three years for filing the suit had expired a long back. The question
is as to whether the time spent in prosecuting the writ petition could be
excluded for the purpose of Section 14 of the Act of 1963?
Learned counsel for the defendant/respondent appears to be correct
in his basic submissions that there had not been any pleadings for invoking
Section 14 of the Act of 1963; and all the necessary ingredients thereof are
not established in the present case that the plaintiff had been prosecuting
the earlier proceeding in good faith, which was not entertained for defect of
jurisdiction of the Court concerned or of any cause of the like nature. Even if
want of pleadings is ignored for a moment, on the admitted facts it is but
clear that the plaintiff had earlier filed a writ petition in High Court and the
same was ultimately dismissed for the plaintiff/petitioner expressing the
desire not to prosecute the same. In fact, the Court did not decline to
RFA NO. 1 OF 2016
entertain the said petition for want of jurisdiction or any other cause of like
nature; rather, the petition came to be dismissed as infructuous with the
following order dated 04.06.1996:―Mr. Siddique submits that the matter is amicably settled and the
Memorandum of Understanding is being prepared and accordingly he is not
pressing the petition at this stage.
The petition is dismissed as infurctuous.
The disposal of this writ petition shall not preclude the petitioner to seek
appropriate remedy under the law if it is so required.‖
It is at once clear that the writ petition was not dismissed due to defect
of jurisdiction or any other alike reason. The plaintiff chose not to press on
the same while suggesting that the matter was being amicably settled and
MOU was being prepared; and the petition was dismissed as infructuous. Of
course, the Court left it open for the plaintiff to seek appropriate remedy
under the law but such observations do not in any manner result in
enlarging the period of limitation. Looking to the nature of the submissions
made and the order thereupon passed by the High Court, it cannot be said
that the said petition was not entertained for want of jurisdiction of the High
Court or for any cause of like nature.
In the given set of facts and circumstances of the present case, the
decision in Bhupendra Singh’s case (Supra) does not help the case of the
plaintiff. Whatever liberal interpretation is put to the expressions occurring in
Section 14 of the Act of 1963 and howsoever liberally this provision is
applied, it cannot be said by any stretch of imagination that the High Court
was unable to entertain the writ petition or declined to proceed with the
same for want of jurisdiction or for any other cause of this nature. It was the
voluntary act of the plaintiff not to proceed with the writ petition. Thus, an
attempt to maintain a civil suit for declaration and money recovery in the
same matter and on the same issue could not have been countenanced, if
the limitation for filing such suit had already expired.
RFA NO. 1 OF 2016
On the facts and in the circumstances of the present case, this Court
is clearly of the view that the plaintiff is not entitled to the benefit of Section
14 of the Act of 1963 so as to exclude the time spent in prosecuting the writ
petition.
THE PLAINTIFF IS NOT ENTITLED TO THE BENEFIT OF SECTION 18
OF THE ACT OF 1963 EITHER
The other submission on behalf of the plaintiff/appellant seeking the
benefit of Section 18 of the Act of 1963, as urged in this matter for the first
time in appeal, does not carry even a remote substance. This Court has not
an iota of doubt that the letter dated 17.04.1996 and the draft Memorandum
of Understanding (Ext. 27) cannot be read as an acknowledgement for the
purpose of Section 18 of the Act of 1963. Section 18 reads as under:
―18. Effect of acknowledgment in writing.— (1) Where, before the
expiration of the prescribed period for a suit of application in respect of any
property or right, an acknowledgment of liability in respect of such property
or right has been made in writing signed by the party against whom such
property or right is claimed, or by any person through whom he derives his
title or liability, a fresh period of limitation shall be computed from the time
when the acknowledgment was so signed.
(2) Where the writing containing the acknowledgment is undated, oral
evidence may be given of the time when it was signed; but subject to the
provisions of the Indian Evidence Act, 1872 (1 of 1872), oral evidence of its
contents shall not be received.
Explanation. – For the purpose of this section,(a) an acknowledgment may be sufficient though it omits to specify the
exact nature of the property or right, or avers that the time for payment,
delivery, performance or enjoyment has not yet come or is accompanied by
refusal to pay, deliver, perform or permit to enjoy, or is coupled with a claim
to set-off, or is addressed to a person other than a person entitled to the
property or right,
(b) the word ―signed‖ means signed either personally or by an agent duly
authorised in this behalf, and
(c) an application for the execution of a decree or order shall not be deemed
to be an application in respect of any property or right.‖
In the decision relied upon by the learned counsel for the appellant,
the Hon‟ble Supreme Court has expounded on the principles governing
RFA NO. 1 OF 2016
such plea of acknowledgement and fresh period of limitation from such
acknowledgement that a liberal construction is required to be put on any
such statement of acknowledgement but with a caveat that such statement
should be of present subsisting liability; must indicate the existence of jural
relationship; and of course, must be unequivocal and clear in its terms. In
the case of Lakshmiratan Cotton Mills (supra), the Hon‟ble Supreme Court
has, inter alia, held as under:
―11. It is clear that the statement on which the plea of acknowledgement is
founded must relate to a subsisting liability as the section requires that it
must be made before the expiration of the period prescribed under the Act.
It need not, however, amount to a promise to pay, for an acknowledgement
does not create a new right of action but merely extends the period of
limitation. The statement need not indicate the exact nature or the specific
character of the liability. The words used in the statement in question,
however, must relate to a present subsisting liability and indicate the
existence of jural relationship between the parties, such as, for instance,
that of a debtor and a creditor, and the intention to admit such jural
relationship. Such an intention need not be in express terms and can be
inferred by implication from the nature of the admission and the surrounding
circumstances. Generally speaking, a liberal construction of the statement
in question should be given. That of course does not mean that where a
statement is made without intending to admit the existence of jural
relationship, such intention should be fastened on the person making the
statement by an involved and far-fetched reasoning.‖
In the case of Shapoor Fredoom Mazda (supra), the Hon‟ble Supreme
has, inter alia, observed as under:
―(6) It is thus clear that acknowledgement as prescribed by S. 19 merely
renews debt; it does not creat a new right of action. It is a mere
acknowledgement of the liability in respect of the right in question; it need
not be accompanied by a promise to pay either expressly or even by
implication. The statement on which a plea of acknowledgement is based
must relate to a present subsisting liability though the exact nature or the
specific character of the said liability may not be indicated in words. Words
used in the acknowledgement must, however, indicate the existence of jural
relationship between the parties such as that of debtor and creditor, and it
must appear that the statement is made with the intention to admit such
jural relationship. Such intention can be inferred by implication from the
nature of the admission, and need not be expressed in words. If the
statement is fairly clear then the intention to admit jural relationship may be
implied from it. The admission in question need not be express but must be
made in circumstances and in words from which the court can reasonably
inferred to refer to a subsisting liability as at the date of the statement. In
construing words used in the statement made in writing on which a plea of
acknowledgement rests oral evidence has been expressly excluded but
surrounding circumstances can always be considered. Stated generally
courts lean in favour of a liberal construction of such statements though it
RFA NO. 1 OF 2016
does not mean that where no admission is made one should be inferred, or
where a statement was made clearly without intending to admit the
existence of jural relationship such intention could be fastened on the maker
of the statement by an involved or far-fetched process of reasoning.‖
In the case of Sharangdhar (supra), the Hon‟ble Patna High Court
has, inter alia, held as under:
―A question of an acknowledgement saving limitation must be treated on its
own merits, and the language expressed has to be examined in every case
to decide whether the acknowledgement was a conditional or an
unconditional one. An acknowledgement of liability need not be express; it
may be by implication although that implication must in all cases be a
necessary implication from which an acknowledgement, clear and
unequivocal, can be inferred.
A bare look on the facts of the present case makes it clear that
Section 18 does not apply by any stretch of imagination. The basic
requirement of Section 18 is that the acknowledgement has to be before
expiration of the prescribed period of limitation for the suit in question. As
Section 14 does not apply and does not enure to the benefit of the plaintiff,
on the date of making such communication i.e., 17.04.1996, the period of
limitation for the suit for declaration and money recovery i.e., the period of
three years, had expired long back.
Apart from the above, the significant aspect of the matter is that the
Memorandum of Understanding in question cannot be in any manner be
said to be of acknowledgement of liability by the defendant/respondent,
whether in explicit terms or by way of any implication. The letter dated
17.04.1996 (Ex. 27) makes it clear that the same was sent by the defendant
to the plaintiff with reference to her letter dated 28.02.1996. The defendant
stated in this letter as under:―
With reference to your letter dt. 28.2.96 a copy of the Draft MOU is
forwarded herewith as per directive of the Managing Director for your
examination and consideration.
Your comments may kindly be communicated at your earliest
convenience.‖
RFA NO. 1 OF 2016
With the said letter dated 17.04.1996, only a draft of Memorandum of
Understanding was sent that reads as under:―MEMORANDUM OF UNDERSTANDING
THIS MEMORANDUM OF UNDERSTANDING arrived at BETWEEN the
Managing Director of Meghalaya Tourism Development Corporation Ltd
with its registered office at Polo Ground Road Shillong 793001 (herein after
called ―the Owner‖) of the one part, AND Smt. I Nongrum wife of/daughter
of ..............................resident of Jaiaw ................ Shillong 793002. by
profession contractor etc herein after called ―the Contractor‖) of the other
part.
WHEREAS the Contractor was alloted the construction work of Phase II of
the R.C.C. Tourist Lodge Building in Shillong vide work orders No.
MTDC/TB/CS/42/85/12
dated
19th
July
and
No.
MTDC/TB/CS/102/85/8 dated 6th November 1985; AND WHEREAS
differences arose between the parties with regard to time of completion of
the work, quality and finishing of the alloted works leading to litigation
between the parties AND WHEREAS owner and the contractor have now
agreed to resolve their differences and disputes mutually.
NOW THEREFORE the parties by this Memorandum of Understanding
agree as follows :1.
The work executed by the contractor shall be measured in details by
an Engineer who was not associated with the works when it was
executed.
2.
The Engineer shall be appointed/nominated by the Owner (who shall
be paid by the Owner and 50% of such payment to the Engineer
shall be borne by the Contractor.
3.
The detailed measurement arrived at by the said Engineer shall be
final and binding on both the parties.
4.
The Engineer shall carry out the detailed measurement in the
presence of the Representative of the Owner and the Contractor or
any other person appointed by the Contractor in writing addressed to
the Owner.
5.
The Engineer shall carry out the detailed measurement on the basis
of the documents and records maintained by the Owner.
6.
The Engineer shall record the detailed measurement in the
Measurement Book to be provided by the Owner which shall be
signed by the Representative of the Owner and the Contractor or any
other person appointed by the Contractor in writing addressed to the
Owner.
7.
The Contractor’s claims for payments to the Owner or Owner’s
counter claims for refund/reimbursement by the Contractor shall be
based on the detailed measurement recorded in the Measurement
Book so provided by the Owner and so signed by both the Parties
i.e. Representative of the Owner and the Contractor or any other
person appointed by the Contractor in writing addressed to the
Owner.
RFA NO. 1 OF 2016
8.
The Contractor shall withdraw all suits, cases and proceedings
pending in any court pertaining to the works carried out by the
Contractor in persurance to the work orders mentioned above on
execution of this MEMORANDUM OF UNDERSTANDING.
IN WITNESS WHEREOF the parties have hereto signed this Memorandum
of Understanding on .....................day of ......... 1996 in presence of the
attesting withnesses.‖
Thus, what could at the best be deduced out of this proposed
Memorandum of Understanding is that at the request of the plaintiffcontractor, the defendant proposed that fresh measurements may be taken
and then, the contractor may make the claim on the basis of such
measurements. There had not been any commitment on the part of the
defendant that any amount was being acknowledged as due to the
contractor and only the quantum of dues was to be work out by way of such
measurements. On the contrary, it is noticed on the factual aspects placed
on record that in fact, the defendant/respondent was conversely seeking to
make recoveries against the plaintiff and as such, the matter of recovery
had also been a matter in issue. In the give scenario, it is difficult to say that
there
had
been
any
acknowledgement
of
liability
by
the
defendant/respondent so as to compute a fresh period of limitation. It gets
per force reiterated that even the said so-called MOU was not signed by any
one on behalf of the defendant/respondent. In fact, the said MOU was never
signed by the plaintiff either and that remained only of the suggested
propositions that never crystallised into any definite form and never took the
shape of acknowledgement in writing for the purpose of Section 18 of the
Act of 1963.
In view of the above, the contention seeking benefit of Section 18 of
the Act of 1963 is also required to be, and is, rejected.
RFA NO. 1 OF 2016
CONCLUSION
For what has been discussed hereinabove, the submissions made by
the learned counsel for the appellant fail and stand rejected and the findings
of the Trial Court stand affirmed. This being the position, this appeal is
required to be dismissed.
Accordingly and in view of the above, this appeal fails and is,
therefore, dismissed. However, in the circumstances, the parties are left to
bear their own costs.
CHIEF JUSTICE
Sylvana
Item no. 5
This page is for informational and research purposes only and does not constitute legal advice.