Item No. 24
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
CRP (C.R.P. ART. 227) No. 9 of 2018
1. Shri Moshhilpa Maring, aged about 63 years, s/o
late Kodul Maring, Ex-Chairman Leibi Village
Authority, by caste Christian occupation farmer,
and a resident of Leibi Maring Village, under P.S.
Moreh, in Tegnoupal Sub-Division of Chandel
District, Manipur.
2. Shri Khudak Kothil Maring, aged about 62 years,
s/o late Angdul Maring, by caste Christian, Chief of
Leibi Maring Village of the same place.
3. Shri Thangsa Angkha Maring, aged about 67
years, s/o late Kothil Maring, by caste Christian, by
occupation business, Chairman of Leibi Village
Authority of the same place.
……. Petitioners
- Versus –
1. Angom Amu Singh, aged about 69 years, s/o late
A. Lila Singh, by caste Christian, Chairman,
Village Authority, Kwatha, by occupation business
and a resident of Kwatha alias Goatha Village
under P.S. Moreh in Tegnoupal Sub-Division of
Chandel District, Manipur.
2. Kshetrimayum Yaima Singh, aged about 65 years,
s/o late Ksh. Tepui Singh, by caste Christian,
Secretary, Village Authority, Kwatha, by
occupation farmer and a resident of the same
place.
…. Respondents
BEFORE
HON’BLE THE CHIEF JUSTICE MR. RAMALINGAM SUDHAKAR
For the petitioners
For the respondents
:
:
Mr. S. Sachindra, Advocate
Mr. N. Umakanta, Advocate
Date of Order
:
13.09.2018
ORDER
[1]
Heard Mr. S. Sachindra, learned counsel appearing for the
petitioners; and Mr. N. Umakanta, learned counsel appearing for the
respondents.
[2]
This civil revision petition has been filed challenging the order of
the Civil Judge Senior Division, Imphal East in Execution Case No. 2 of
2010/3/2011/1/2013/22/2014/1/2016 Ref: O.S. No. 8/2003/18/2013.
[3]
The respondents/petitioners/plaintiffs/decree holders filed the
suit to demarcate the injunction suit against the present revision
petitioners/defendants. The suit was decreed on 28.12.2009 in the following
manner :1.
“For the aforesaid observations, reasons and findings, it is
ordered and decreed that the boundaries of Kwatha Village are and
shall be those that are given in Ext. 6 i.e. order dated 17-01-1924
passed by the Hon‟ble Court of the President of Manipur State Darbar
in Hill Misc. Case No. 116 of 1923-24. Parties are directed to maintain
these boundaries for all time to come. The boundaries as per Exbt. 6
will be demarcated and identified. Defendants‟ counter claim is
accordingly disposed of. Composite decree be prepared accordingly.
But no costs.
Sd/(M. Ibohal Singh)
Addl. District Judge
(Fast Tract Court), Manipur West.”
[4]
The decree was prepared on the basis of the judgment dated
28.12.2009 on same day and it reads as follows:2.
“That in pursuance of the judgment and order dated 28-122009, a decree dated 28-12-2009 was prepared by the Addl. District
Judge (Fast Tract Court), Manipur West as follows:
“For the aforesaid observations, reasons and findings, it
is observed and decreed that the boundaries of Kwatha
Village are and shall be those that are given in Ext. i.e. order
dated 17-01-1924 passed by the Hon‟ble Court of the
President of Manipur State Darbar in Hill Misc. Case No. 116
of 1923-1924. Parties are directed to maintain these
boundaries for all time to come. The boundaries as per Exbt.6 will be demarcated and identified. Defendants‟ counter
claim is accordingly disposed of. Composite decree be
prepared accordingly.
It is further ordered and decreed that parties will bear
their own costs.
Given under my hand and seal of the Court, this day
the 28th December, 2009.
Sd/(M. Ibohal Singh)
Addl. District Judge
(Fast Tract Court), Manipur West.”
[5]
In effect, the judgment and decree primarily relied upon Ext. 6
in the order dated 17.01.1924 passed by the Court of President of Manipur
State Darbar in Hill Misc. Case No. 116 of 1923-24, and the same is set out
for better clarity :
3.
“For more clarity, the operative portion of Ext. 6 i.e. order dated
17-01-1924 passed by the Court of the President of Manipur State
Darbar in Hill Misc. Case No. 116 of 1923-24 is hereinafter reproduced :
“In future the boundary between LEIBI + GOATHA will
be MIMANG LOK (main LAIREM LOKSHA).
The field at the head of this Lok will go to Leibi. The
boundary is at the place where there are four “U Tangji” trees
growing together.
P.M.S.
17.1/1924
[6]
P.M.S.
17/1/1924”
Based on the judgment and decree, an Execution Case being No.
No. 2 of 2010 came to be filed to execute the decree dated 28.12.2009
passed by the Additional District Judge (Fast Tract Court), Manipur West in
O.S. No. 8 of 2009. In the execution case, 2 (two) orders were passed on
23.03.2010 and 28.06.2010. By this order, the Deputy Commissioner,
Chandel, who is the head of the administration of the district wherein the
two villages, and the parties who are fighting for the demarcation of the
boundary are situated, was directed to take up the task of demarcation. In
the order, it was pointed out that the plaintiffs belong to “Meitei” community
and the defendants belong to “Maring” community, and in order to avoid
communal feud at the time of demarcation, sufficient staff, members should
be taken and the police authorities should be involved to avoid law and
order situation. However, this order of the Execution court did not result in
any fruitful action, forcing the decree holders to file W.P. (C) No. 427 of
2010 before the Gauhati High Court, Imphal Bench, seeking to execute the
judgment and decree dated 28.12.2009, and the writ petition was disposed
of on 09.08.2010, directing the Deputy Commissioner, Chandel(respondent
4) and the Superintendent of Police, Chandel(respondent 5) to take steps for
executing the lawful decree passed by the competent Civil Court in
Execution Case No. 2 of 2010. The relevant portion of the order reads as
follows:
“Upon hearing both sides, the Hon‟ble Gauhati High Court, Imphal
Bench was pleased to dispose of Writ Petition being W.P. (C) No. 427 of
2010 on 09-08-2010 redirecting Ld. Deputy Commissioner, Chandel
(Respondent 4) and Superintendent of Police, Chandel (respondent 5)
with the following directions and observations:“Accordingly, this writ petition is disposed of by directing the
respondents-4 and 5 to take up necessary steps for executing the
said lawful decree as per the order of the Competent Civil Court
dated 23-03-2010 and 28-06-2010 passed in Execution Case No.
2/10.
It is made clear that the respondents 4 and 5 shall give
necessary notice to the affected parties in case of taking
necessary steps for execution of the lawful decree of the
competent Civil Court”
Sd.
TNK SINGH
JUDGE, GAUHATI HIGH COURT”
[7]
Thereafter, the case was taken up by the Deputy Commissioner,
Chandel as Demarcation Case No. 1 of 2011, and he passed the order on
30.04.2011. A detailed order was placed before the Execution Court, and
after considering the data submitted by the Deputy Commissioner in his
Demarcation Case No. 1 of 2011, the Execution Court rendered the finding
as follows :5. “ Findings of the Court:
This Court perused the whole order dated 30th April, 2011 passed
by Ld. Deputy Commissioner, Chandel in the light of Hon‟ble Gauhati
High Court‟s order dated 09-08-2010.
On plain reading of the order dated 17-01-1924 passed by the Ld.
President of Manipur State Darbar in Hill Misc. Case No. 116 of 192324, it is very clear and unequivocal that MIMANG LOK should be the
boundary between LEIBI village and GOATHA/Kwatha village.
In this context, the observation and understanding of Ld. Deputy
Commissioner Chandel is very much right in making an attempt to find
“from where to where" the Lairam Lok flows and then from where
MIMANGLOK rises and at what exact point MIMANGLOK flows into.
As per observation of the Court of the Ld. President of Manipur
State Darbar, the head/maru/rising point of MIMANGLOK is
specifically given as the place where there are four "U TANGJI" trees
growing together, which is shortly called “U Tangji Haubi Point”.
This landmark is very important in the sense that starting from this
point upto the exact point where MlMANGLOK flows into will be the
boundary line between Leibi Village and Kwatha Village. The Manipur
State Darbar was also clear to the extent that a field lying at the
head/rising point/maru of MIMANGLOK shall be the land of Leibi
village meaning thereby northern portion of the field contiguous to
southern portion of Leibi village starting from U Tangji Haubi point
will the land of Leibi village.
There is no point of contention so far as the boundary line i.e. the
course of MIMANGLOK which is still in existence. The main
contention between the two villages is in regard to the rising
point/maru/head of MIMANGLOK. This point of contention is also
again simplified by the very clarification made by Manipur State
Darbar which indicated a landmark i.e. the place where there are four
”U TANGJI” trees growing together.
Ld. Deputy Commissioner, Chandel was correct in relying on
certain acceptable and understandable tools for identification of the
exact point which was given by Manipur State Darbar by illicsiting
information from different sources including conducting field
inspection, taking comments/opinions from neighbouring villages,
proper identification of rising point of Lairam Lok and the Mimanglok
by using scientific methods with the help of scientists/experts of
MARSAC.
Moreover, being the head of Administration in the District, Ld.
Deputy Commissioner, Chandel has both responsibility and
accountability to prevent any untoward incident likely to arise between
the contesting villages on account of boundary dispute and he did
nothing wrong in organizing precautionary measures during the
execution process. In this regard, the Ld. Counsel for the respondent
was quite exaggerating in alleging that the manner of execution
process was biased and was with predetermined mindset. Had Deputy
Commissioner, Chandel not done proper homework, the execution
process could not have been completed. The non-co-operative nature
and violent acts/designs of Leibi Villagers is clearly visible right from
day one when staffs of District Administration went for a field visit at
the disputed site. Relevant portion of the order/report of Deputy
Commissioner, Chandel is reproduced herewith:
“…...on reaching the disputed site, it was reportedly found that
Leibi Villagers were present in large numbers and were also
armed with sticks, doas, catapult & knives etc. and they
insisted upon the officials that the boundary point as given by
them should be accepted as the boundary point between the
two Villages failing which no co-operation or participation
will be given to the field visit and also further threatened that
the District officials team will not be allowed to go to the
boundary point as claimed by the Kwatha Village which lies
little ahead of the boundary point claimed by the Leibi
Village.”
It seems that Leibi Village never wanted the demarcation to
proceed as per law. They simply wanted to impose their will upon the
visiting Revenue officials by forcing them to fix the boundary at the
exact point where they wanted and same is absolutely absurd and
condemnable. The following extract of Deputy Commissioner‟s order
verifies their true intention:
“........ the second visit by the official team led by ADC, Moreh
on 09.03.2011 could also not complete the demarcation due to
insistence by the Leibi villagers that the boundary between
Leibi and Kwatha should be at the very spot pointed out by
them and where a temporary shed was constructed by them for
holding of discussion with their representatives,
representatives of Kwatha village and the visiting officials.
They prohibited further movement along the road to inspect
the other spots claimed by Kwatha Villagers as the correct
boundary from their point of view as well as the land marks
mentioned in successive orders of Manipur State Darbar,
Hon‟ble Addl. District Judge(FTC), Manipur West and the
Hon'ble High Court. Thus, the second attempt made by the
officials to execute the Orders and Decree of the competent
Courts was also scuttled due to the unreasonableness and
scant regard of the due processes of law by Leibi villagers.”
Further, the following relevant portions of Ld. Deputy Commissioner‟s
order will make the real situation under which the officials of District
Administration undertook the execution process:
“........ However, the representatives of Leibi village plainly
refused to extend any cooperation. The Ld. Counsel also
declined to accompany the official team seemingly on his
clients‟ instruction in the visit to the contentious spots claimed
and counter claimed by the contesting villages and for which
latitudes and longitudes have been determined by MARSAC
and the particular point where the boundary (final) peg will be
placed is proposed to be pointed out. They also blatantly
threatened the Kwatha villagers from proceeding beyond the
said point with dire consequences. The Ld. Counsel of Kwatha
village Shri N. Umakanta Singh and his associates could
however accompany the undersigned.
AND WHEREAS, there is only one approach road to reach the
relevant spots of ground positions „C‟ and „D‟ and a
Shaktiman truck was parked in a narrow stretch of the road
purportedly being out of order and could not be moved, a fact
which seemed highly suspicious and motivated under the
circumstances. As such, the official vehicles could not proceed
to the sites/points on vehicles. The whole team of officials and
security personnel had therefore to move on foot to first see the
furthest ground spot „D‟ which is at the head of the main
Lairam Lok i.e. maru and while returning, the boundary (final)
peg was put at the ground spot „C‟ as decided by the
undersigned for which the rationale have been presented in the
above paragraphs in the presence of the Ld. Counsel of
Kwatha village, his accompanying Advocates as well as all the
accompanying officials and security personnel.
AND WHEREAS on the return journey towards Ground
position „B‟ where the vehicles of the visiting team was parked,
the undersigned and his team where assaulted by Leibi
Villagers with sticks, catapult, knives, stones and firearms and
necessary report has been lodged with the Moreh P.S.”
Under such circumstances, the point put forward by Ld.
Counsel for the Respondents that the District Administration was quite
biased right from the beginning is simply a wild allegation. It was, in
fact, not the District Administration but the Leibi Villagers who were
without a clean hand right from the beginning. They simply wanted to
sabotage the execution process right from the beginning. The complete
disregard of due process of law by Leibi Villagers in the execution
process is quite unfortunate.
Upon hearing both the sides, Ld. Deputy Commissioner,
Chandel identified three points:
1. “B” (denoting the latitude 240 21‟31.60230” N and longitude
94015‟35.03190”E) is the spot claimed by Leibi village as the
boundary interpreting it as the tip of the masa of the Lairam Lok.
2. “C” (denoting 24°22‟31.48361 "N and longitude
94°15‟19.82663"E) signifies the Spot which is claimed to be the
Lairam Lok Maru by Leibi Village but contrary to which Kwatha
village claims to be the Lairam Lok masa where the U Tangji
trees grew and is therefore the boundary point between the two
villages.
3. “D” (denoting 24°23‟1 7.71345 "N and longitude
94°15‟22.37864E") is claimed to be the head of the Lairam Lok
maru by Kwatha village.
Ld. Deputy Commissioner, Chandel discarded_the point „B‟ by
giving reasons. Relevant portion of the order/report of Deputy
Commissioner, Chandel is reproduced herewith:
“AND WHEREAS, from study of the loks or streams system
depicted in the map in Annexure-A, it is observed that the Iok
emanating from ground position „B‟ does not connect with the
Namchet Lok river directly implying thereby that the said lok is
not a tributary of the Namchet Lok river and cannot therefore be
accepted to be the main Lairam Lok. Instead, the said lok is seen
to be a tributary of Lairam Lok. The above finding does not
support the contention of Leibi village that spot „B‟ is the point
where Lairam Lok masa begins and Where the U Tangji trees
grew. In fact, there is no probable physical evidence whatsoever
where the U Tangji trees could have grown. Nor are there any
sign of growth of U Tangji trees or forests in the hillocks in the
vicinity of the spot depicted by „B‟. Furthermore, it is difficult to
identify any area which could be interpreted to be the field at the
head of the Lok as mentioned in the order of President, Manipur
State Darbar. Therefore, the contention that „B‟ is the boundary
is not convincing. It may also be added that the stream flowing
from point „B‟ is quite insignificant and cannot be construed to
be the Lairam Lok.”
Ld. Counsel for the Respondents also alleged that the rising
point/maru of LAIRAM LOK is the spot “C” and insisted that it the
place where Four U Tangji trees once grew together. On the other
hand the Kwatha village claim that spot “C” is tip/head/maru “of
MIMANGLOK. Claims are claims motivated by self interest. Court has
a special duty to examine the tools relied upon by Ld. Deputy
Commissioner, Chandel in coming to the conclusion that Point “C" is
the exact rising point/maru of MIMANGLOK where Four U Tangji
trees once grew together. The extract of the order dated 30-04-2011 of
Ld. Deputy Commissioner, Chandel is reproduced herewith.
“AND WHEREAS, ground positions denoted by „C‟ and 'D‟
belong to the some water system or stream which directly falls
into the Namchet Lok. Furthermore, „D‟ being the furthermost
point would be the head i.e. maru of the system and „C' would
be the starting point of the masa. This is the most prominent
water system which finally joins with the Namchetlu river (or
Namchet Lok). This system is accordingly identified as the
Lairam Lok river with the point „D‟ as the head or maru and
„C' as its masa. It is also a tributary of the Namchet Lok.
Further, the existence of a discernible field between ground
positions „C‟ and „D‟ lend credence to the claim of Kwatha
Village. Besides, many „U‟ Thanji trees are still seen to grow
in the Hillock immediately adjacent but on the southern side
of ground position „C‟. All these findings fit with the order
passed by the President, Manipur State Darbar. Accordingly,
the logical conclusion is that ground position „C‟ is the
boundary between Leibi village and Kwatha village and
where the four „U‟ Thanji trees once grew.”
Moreover, spot “C" (denoting 24°22'31.48361"N) is on the
southern side of spot “D” (denoting 24°23'17.71345"N) as per
Satellite imagery report conducted by MARSAC. There is a field
between spot “C” and spot “D” which as per findings of Ld. Deputy
Commissioner, Chandel shall go to Leibi and same is contiguous to
Leibi Village. It clearly shows that there is no shadow of doubt that
point “C” should be the U tangji Haubi Point as there are still U
Tangji trees grow at the vicinity of spot “C”. In other sense, putting
boundary peg at spot “D” may cost more land of Leibi Village.
Accordingly, the logical conclusion of Ld. Deputy Commissioner that
ground position „C‟ is the boundary between Leibi village and Kwatha
village and where the four „U‟ Thanji trees once grew is right without a
shadow of doubt.
The conclusion of Ld. Deputy Commissioner, Chandel was
further corroborated/endorsed by the comments/opinions of chiefs of
neighbouring villages who are well informed about the past history of
neighbouring villages. There is no conflicting opinion as regards the
Four U Thanji Haubi Point of the neighbouring villages who are also
Scheduled Tribes like the Leibi Village. Fact is fact and it cannot be
manipulated based on communal considerations. The relevant portion
of the order 30-04-2011 of Ld. Deputy Commissioner, Chandel is
reproduced herewith.
"AND WHEREAS, taking into consideration the opposition
and non-co-operative nature shown by the Leibi Villagers, it
was felt that a still more deeper enquiry was required to be
carried out before fixing another date to visit the disputed site
to execute the Hon‟ble High Court‟s Judgment and Order; the
ADC, Moreh detailed the concerned Head Lambu to make
detailed enquiry with a view to ascertain the real and correct
boundary between the two Villages by making field enquiry
and also for taking opinions and comments from members of
other Villages settled near or around the two contesting
Villages.
AND WHEREAS, the Head Lambu of the SDC Circle, Moreh
accordingly submitted his enquiry report on 24-11-2010
wherein it has been stated that the Chiefs of the
neighbouring Villages endorsed/corroborated the claim of
Kwatha Villages with regard to the boundary dispute to be
the true one. In other words, they supported the spot on the
ground claimed by Kwatha Villagers as the correct
boundary between Kwatha Village and Leibi Village.”
Ld. Counsel for Respondents argued that Ld. Deputy
Commissioner, Chandel had gone beyond the power given to him as an
executing agency of the Hon‟ble Court‟s order by alleging that the
Leibi Village was never given due notice about the demarcation
process. This argument is also not acceptable as the chain of events
indicates otherwise. It is evident from the fact of service of notice and
summons to Chairman/Chiefs of the two contesting villages vide the
ADC, Moreh vide his letters bearing No. ADC(MRH)I3IHMC/2010
dated 27-10-2010. The relevant portion of the order 30-04-2011 of Ld.
Deputy Commissioner, Chandel is reproduced herewith.
“AND WHEREAS, proper Notices and Summons were served
on the Chairman/Chiefs of the two contesting villages for
participation and co-operation in the spot/field visit for
verifying the boundary between the two Villages at the disputed
site by the ADC, Moreh Vide his letters bearing No.
ADC(MRH)I3IHMC/2010 dated 27-10-2010.”
Moreover, further notice was served to all the contesting parties
and chiefs of neighbouring villages on the day i.e. 28‟" April, 2011
actual demarcation was done after an extensive research by the
District Administration, Chandel. It is evident from the fact that a
massive arrangement was made Ld. Deputy Commissioner, Chandel on
28'h April, 2011 by inviting all chiefs/leaders of neighbouring villages.
The relevant portion of the order 30-04-2011 of Ld. Deputy
Commissioner, Chandel is reproduced herewith.
“AND WHEREAS, the following representatives of Leibi village
and Kwatha village and officials were present at the temporary
shed constructed at the same spot indicated by Leibi villagers to
be the correct spot/boundary which is represented by point „B‟in
the map for the discussions for proceeding further with the
demarcation:
Leibi village:
U. Duidang, Advocate, Counsel of Leibi Village
Kh. Medar Dangsak, Chairman, Leibi Village Authority
K. Angdou, Leibi Village leaders/authorities members
Th. Angkham, Leibi Village leaders/authorities members
Moshilpha, Leibi Village leaders/authorities members
Th. Angkha, Leibi Village leaders/authorities members
DL. Mosesm, Leibi Village leaders/authorities members
Leithilkham, Leibi Village leaders/authorities members
Kwatha Village
N. Umakanta, Advocate and his associates, Counsel of Kwatha Village
A. Amu Singh, Chairman, Kwatha Village Authority
Ksh. Yaima Singh, Secretary, Kwatha Village Authority
T. Nando Singh, Kwatha Village leaders/authorities members
Ksh. Kesho Singh, Kwatha Village leaders/authorities members
N. Shangujao Singh, Kwatha Village leaders/authorities members
L. Kokngang Kwatha Village leaders/authorities members
Nearby villages Organisations:
Doujathang Baite, Chief of Bongjang
Mangkhopao Haokip, Chief of Yangoutubi
Zangkholun, Secretary. Khudengthabi Village
Letngam Luphing, Vice President, Kuki Chiefs Association, Moreh Block
Ngamkholun Kipgen, General Secretary, Kuki Chiefs Association, Moreh Block
Officials:
Lunminthang Haokip, ADC, Moreh
Md. A. Salam Khan, AS&S0
L. Nganba, Scientist (MARSAC)
Kusheshwor Longjam. Scientist (MARSAC)
Singhajit Maibam, Scientist (MARSAC)
S. Biswajeet Singh, Mandol
Md. Amir Khan, Mandol”
The presence of huge number of Leibi Villagers in all the
attempts for field inspection/demarcation speaks for itself that both the
villages, specially Leibi village were well informed and due notice was
served and there is no question surpassing the order of the Hon‟ble
Gauhati High Court wherein it was directed that due notice be given to
the affected parties.
Ld. Counsel for the Respondents further submitted that the
execution process done by Deputy Commissioner, Chandel was not
complete as only one peg was fixed at the spot “C". This Court, in this
regard, had already observed that there is np point of contention so far
as the boundary line i.e. the course of MIMANGLOK. The main
contention between the two villages is in regard to the rising
point/maru/head of MIMANGLOK. Ld. Deputy Commissioner,
Chandel did no wrong in putting/fixing the boundary peg at spot „C‟
only as the rest of the boundary Is MIMANGLOK itself.
I have also perused the relevant case laws submitted by the Ld.
Counsel for the Respondents in support of his arguments. In close
examination of case laws discussed therein, it has no bearing in the
present case. There was no technical defect in the execution process.
The District Administtation did a great job by exercising due diligence
and application of mind and same was not done for “namesake”. The
involvement of huge number of chiefs/leaders of neighbouring villages
ranging from Bongyang to Moreh speaks for itself that at no point of
time the District Administration had a biased and predetermined
mindset and that Ld Deputy Commissioner, Chandel allowed himself of
public scrutiny, if any. Except the respondent village, all the village
leaders/chiefs endorsed the mode of execution of Ld. Deputy
Commissioner, Chandel. Moreover, demarcation in the hilly areas
cannot be equated with demarcation in valleys which are already
surveyed. Ld. Deputy Commissioner, Chandel did extensive homework
before doing actual demarcation and there is nothing wrong in it. Had
there not been extensive homework done by Ld. Deputy Commissioner,
Chandel, the execution process would have been sabotaged by Leibi
Villagers.
In view of what has been discussed above, I hereby approve and
accept the order/report dated 30th April 2011 passed/submitted by Ld.
Deputy Commissioner, Chandel. Starting from spot ’C’ (denoting
24°22’31.48361"N) where boundary peg was fixed by Ld. Deputy
Commissioner, Chandel upto the exact point where MIMANGLOK
flows into Namchetlu River will be the boundary line between Leibi
Village and Kwatha Village.
Ld. Deputy Commissioner, Tengnoupal is requested to prepare a
fresh sketch map on the basis of the order dated 30th April 2011 passed
by Ld. Deputy Commissioner, Chandel thereby clearly indicating the
respective boundaries of Leibi and Kwatha Village and necessary
orders may be issued in this regard by vividly indicating the schedule
of land of the respective villages.
Ld. Deputy Commissioner, Tengnoupal and the Superintendent of
Police, Tengnoupal are further requested to take up all necessary steps
for observing peaceful co-existence between two villages and also for
preventing any sort of unwanted incident/communal feud between the
villages in future.
Accordingly, the present Execution Case No. 2/2010 is hereby
closed.
Let a copy of this Order be sent to the DGP, Manipur for
information.
Let a copy of this Order be sent to the Commissioner (Revenue),
Government of Manipur for information.
Let a copy of this Order be sent to the Deputy Commissioner,
Tengnoupal for information and for doing the needful.
Let a copy of this Order be sent to the Superintendent of Police,
Tengnoupal for information and for doing the needful.
Let a copy of this Order be sent to the Addl. S.P., Moreh for
information and for doing the needful.
Let a copy of this order be made available to each of the parties
as prayed for.
(Y. Somorjit Singh)
Civil Judge,
Senior Division,
lmphal East.
[8]
The Execution Court, after considering the detailed order passed
in the demarcation case, rejected all the objections raised by the present
revision petitioners, and accepted the opinion and views of the Deputy
Commissioner, Chandel and directed him to prepare a fresh sketch map on
the basis of his order dated 30.04.2011, thereby making it clear that the
boundary of village Leibi and Kwatha should be redrawn on the basis of
report for the use of the respective villages. He closed the Execution Case,
with a further direction to other officers for implementing it in letter and
spirit. This order of the Execution Court is under challenge.
[9]
Mr. S. Sachindra, learned counsel appearing for the petitioners/
defendants in the suit impressed upon the Court that the proceedings of the
Deputy Commissioner, Chandel in Demarcation Case No. 1 of 2011 suffered
from serious errors of fact. In that, he has misconstrued the location of the
„maru‟ equivalent to „head‟ and „masa‟ the tributary in relation to Lairam Lok
also known as Mimanglok from the main river Namchetlu.
[10]
To highlight this point, learned counsel appearing for the
petitioners, referred to the three points identified by the Deputy
Commissioner, Chandel for the purpose of demarcation by identifying „maru‟
equivalent to „head‟ and „masa' tributary as follows:
6. “Upon hearing both the sides, Ld. Deputy Commissioner, Chandel
identified three points:
1. “B” (denoting the latitude 240 21‟31.60230” N and longitude
94015‟35.03190”E) is the spot claimed by Leibi village as the
boundary interpreting it as the tip of the masa of the Lairam Lok.
2.
“C”
(denoting
24°22‟31.48361
"N
and
longitude
94°15‟19.82663"E) signifies the Spot which is claimed to be the
Lairam Lok Maru by Leibi Village but contrary to which Kwatha
village claims to be the Lairam Lok masa where the U Tangji trees
grew and is therefore the boundary point between the two villages.
3. “D” (denoting 24°23‟1 7.71345 "N and longitude
94°15‟22.37864E") is claimed to be the head of the Lairam Lok
maru by Kwatha village.”
[11]
According to the learned counsel appearing for the petitioners,
the spot claimed by Leibi Village will be the tip of the „masa‟ of Lairam Lok
whereas according to the Kwatha village the „maru‟ is at spot „D‟ and „masa‟
is at spot „C‟. In other words, the Lairam Lok also known as Mimanglok
tributary in connection with Namchetlu River, has his head point at „D‟ and
the tributary „masa‟ point at „C.‟ This view of the Deputy Commissioner,
Chandel, is based on not only the proceedings of the data found in the order
dated 17.01.1924 passed by the President of Manipur State Darbar in Hill
Misc. Case No. 116 of 1923-24, but also on the basis of a specialized study
using Manipur Remote Sensing Applications Centre (MARSAC) to identify the
location of the spot in relation to Namchetlu River and the boundaries of the
two villages in relation to the tributary Lairam Loksha @ Mimanglok.
[12]
In the report of the Deputy Commissioner, specific details of the
growth of U Tangji trees as was reflected in the Hill Misc. Case No. 116 of
1923-24, was also indicated. The Deputy Commissioner, Chandel, on the
basis of both scientific as well as old existing records of the Manipur State
Darbar‟s order, was clearly of the view that point „D‟ will be the maru head
and point „C‟ will be the „masa‟ tributary. This demarcation was done in the
presence of persons concerned, but it appears that the petitioners/Leibi
Villagers had some confrontation at the time of demarcation which led to
some law and order situation. Nevertheless, the Deputy Commissioner,
Chandel, proceeded on the basis of all relevant datas available in the old
records as well as the separate map furnished by MARSAC, copies of which
has been enclosed with his order. Clear and cogent reason has been given
by the Deputy Commissioner, Chandel as to how he is fixing the „maru‟ head
at point „D‟ and „masa‟ tributary at point „C‟. He has also given reasons as to
why he is rejecting point „B‟ as totally untenable. In fact, he clearly makes a
point that the study of local stream depicted in map to his report that the
Lok emanating from ground position „B‟ does not connect with Namchetlu
river (Namchet Lok), directly implying thereby that the Lok is not a tributary
at Namchetlu river (Namchet Lok), and therefore, cannot be accepted to be
main Lairem lok. This method, apparently, is scientific and based on the spot
study. The reasoning and finding are specific.
Relevant portion reads as follows:
“7. AND WHEREAS, from study of the loks or streams system depicted
in the map in Annexure-A, it is observed that the lok emanating from
ground position „B‟ does not connect with the Namchet Lok river
directly implying thereby that the said lok is not a tributary of the
Namchet Lok river and cannot therefore be accepted to be the main
Lairam Lok. Instead, the said lok is seen to be a tributary of Lairam
Lok. The above finding does not support the contention of Leibi village
that spot „B‟ is the point where Lairam Lok masa begins and where the
U Tangji trees grew. In fact, there is no probable physical evidence
whatsoever where the U Tangji trees could have grown. Nor are there
any sign of growth of U Tangji trees or forests in the hiIlocks in the
vicinity of the spot depicted by „B‟. Furthermore, it is difficult to identify
any area which could be interpreted to be the field at the head of the
Lok as mentioned in the order of President, Manipur State Darbar.
Therefore, the contention that „B' is the boundary is not convincing. It
may also be added that the stream flowing from point „B‟ is quite
insignificant and can not be construed to be the Lairam Lok.
AND WHEREAS, ground positions denoted by „C‟ and „D‟ belong to the
same water system or stream which directly falls into the Namchet Lok.
Furthermore, „D‟ being the furthermost point would be the head i.e.
maru of the system and „C' would be the starting point of the masa. This
is the most prominent water system which finally joins with the
Namchetlu river (or Namchet Lok). This system is accordingly identified
as the Lairam Lok river with the point „D‟ as the head or maru and „C'
as its masa. It is also a tributary of the Namchet Lok. Further, the
existence of a discernible field between ground positions „C‟ and „D‟
lend credence to the claim of Kwatha Village. Besides, many „U' Thanji
trees are still seen to grow in the Hillock immediately adjacent but on
the southern side of ground position „C‟. All these findings fit with the
order passed by the President, Manipur State Darbar. Accordingly, the
logical conclusion is that ground position ‟C' is the boundary between
Leibi village and Kwatha village and where the four 'U‟ Thanji trees
once grew.
And whereas, having deduced from all the available evidences and
having arrived at the conclusion that ground spot „C' is the boundary
point which is at a point along the Khudengthabi-Leibi Jeepable Road,
the undersigned fixed the 28th April, 2011 for personally visiting the
disputed site for identification and demarcation along with the
SP/Chandel, AS&SO of DSLR and officials of MARSAC after following
due process for informing the Ld. Counsel of both Parties and
representatives of the contesting villages and that of neighbouring
villages.”
[13]
On the basis of this clear and specific report, the Execution
Court had no other option except to accept the report because it is based
not only on the loaction specified in the Court of President of Manipur State
Darbar in Hill Misc. Case No. 116 of 1923-24 dated 17.01.1924, but also on
scientific application of MARSAC. Besides, there has been specific on spot
verification at the time of demarcation by the authorities in the presence of
large number of villagers. If the revision petitioners did not participate, it is
their peril. They cannot turn around and find fault with the proceedings of
the Deputy Commissioner. Therefore, factually, there appears to be no error
apparent on the face of record in the proceedings of the Deputy
Commissioner, Chandel, and the order of the Civil Judge impugned, who has
correctly approved the same in the Execution Case and closed the same with
a direction to prepare a fresh sketch map on the basis of the order dated
30.04.2011.
[14]
The scope of interference by the Court, more particularly, this
Court against the order passed by the Execution Court has been discussed
by different High Courts. The following judgments may be relevant to
highlight the scope and power of the High Court while interfering the orders
of the Execution Court:
(i) Gopal Ch. Paul Vs. Smt. Amala Mondal : reported in A.I.R. 1990
Calcutta 105. Relevant para reads as follows:
“36. With regard to the submission of Mr. Dasgupta that within the
scope of S. 47 of the Code of Civil Procedure it is not open to the
executing court to go into the question of the validity of the decree
passed by the competent Court, unless it will be shown that there was
any legal impediment to pass such a decree. In my view, true under
the law, an executing court cannot go behind the decree. But if it
could be shown that the decree was a nullity certainly the executing
court can go into this question and hold that the decree was a nullity
and could not be executed. It is firmly established principle that
decree is passed on which the court has no jurisdiction, is a nullity. In
the instant case, because of the legal fiction arising out of the
extension of the West Bengal Non-Agricultural Tenancy Act 1949 with
retrospective effect to the area in question, the decree which was
validly passed by the Trial Court has been rendered invalid and
inoperative as the Court had no jurisdiction to pass a decree as the
ground for decree did not conform with the grounds mentioned in the
West Bengal Non-Agricultural Tenancy Act.”
(ii) Ganapathi And Anr. V. Balasubramania Gounder: reported in AIR
1987 MAD 124. Relevant portion at para 10 reads as follows:
“It is difficult to see how defendants 4 and 5 who are the legal
representatives of the deceased Thanikachalam could now raise only
question with regard to the liability of the decrial property to sale in
execution of the mortgage decree. It is an established proposition of
law that the executing Court must execute the decree as it stands and
it cannot go into the correctness or validity of the decree except when
the decree is a nullity. Since the decree is of a Court with jurisdiction,
the executing Court is bound to execute the decree as it stands. The
relief which the revision petitioners in these two revision petitions are
substantially asking is that the decree must be so modified as to make
it ineffective and inoperative in respect of certain properties. In other
words, the argument comes to this i.e., in so far as the properties in
respect of which the petitioners are contending that these properties
are not liable to be sold, the decree is invalid.”
[15]
The Execution Court in this case has proceeded to pass orders
based on the decree and the demarcation order which is backed by a direction
of this Court. The order is within the scope of the decree which is reflected in
the demarcation order.
[16]
In the above factual matrix, this Court does not find any serious
error in the demarcation report of the Deputy Commissioner, Chandel, as all
records and materials required by law has been taken into consideration, and
the best practice adopted. Principles of natural justice have been scrupulously
followed. It is also based on the direction of this Court. A comprehensive report
has been filed giving each and every factual details possible in exactitude to
justify the demarcation order. Therefore, this Court does not find any error with
the order of the Deputy Commissioner. The order of the Execution Court which
is under challenge has also analyzed the demarcation order in detail and tested
it on the basis of the decree. The order of the Execution Court is in consonance
with the decree. Hence, it cannot be faulted.
[17]
The petitioner has not been able to establish any good ground to
interfere with the order of the Execution Court. The factual dispute raised
appears to be superficial challenge to the decree which has become final. The
Execution Court cannot go beyond the decree.
[18]
For all the above reasons, this Court does not find any good lawful
reason to interfere with the order impugned.
[19]
In the result, inding no merits, revision petition stands dismissed.
CHIEF JUSTICE
FR/NFR
Sandeep
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review