IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3331]
THURSDAY,THE SIXTEENTH DAY OF APRIL
TWO THOUSAND AND TWENTY SIX
PRESENT
THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI
WRIT PETITION NO: 29586/2023
Between:
1. SHIRDI SAI BABA CONSTRUCTIONS, REP BY ITS MANAGING
PARTNER, T. CHIRANJEEVA REDDY S/O RAMANARAYANA
REDDY, AGED 48 YEARS, OCC .BUSINESS, R/O. D.NO. 13-279, BEHIND CHURCH SCHOOL,
SHIRIDI NAGAR,
ANANTHAPURAM TOWN, ANANTHAPURAM DISTRICT.
...PETITIONER
AND
1. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL
SECRETARY, DEPARTMENT OF PANCHAYAT RAJ AND RURAL
DEVELOPMENT, SECRETARIAT, VELAGAPUDI, AMARAVATI,
GUNTUR DISTRICT.
2. THE SUPERINTENDING ENGINEER, PANCHAYAT
ANANTHAPURAMU, ANANTHAPURAM DISTRICT.
RAJ,
3. THE EXECUTIVE ENGINEER, PANCHAYAT RAJ, PIU DIVISION,
ANANTHAPURAMU, ANANTHAPURAM DISTRICT.
4. THE ENGINEER INCHIEF, PANCHAYAT RAJ DEPARTMENT,
OPP.PWD GROUNDS, BANDAR RAOD, VIJAYAWADA. R4 IS
IMPLEADED AS PER THE ORDER OF THIS COURT,
DT.27.11.2023 VIDE ORDER PASSED IN I.A.2 OF 2023.
...RESPONDENT(S):
Petition under Article 226 of the Constitution of India praying that in
the circumstances stated in the affidavit filed therewith, the High Court
may be pleased to issue an appropriate Writ, order or direction more
particularly one in the nature of WRIT OF MANDAMUS declaring Memo
No. 1929135/Vig. 11/2022, dt. 25-03-2023 issued by the 1st respondent
whereunder directed to blacklist the petitioner for on the allegation of
substandard quality work execution and the proceedings dt. 01.062023 of
the 4th respondent and the consequential letters dt. 17-05-2023 and 2908-2023 of the respondents 2 and 3 whereunder directed me to pay an
amount of Rs.37,074/- and to relay the rejected components of the work
at the cost and risk of the petitioner failing which an amount of Rs.
43,71,676/- will be recovered towards the cost of the rejected
components of work, is illegal, arbitrary and violation of Article 19(1)(g) of
Constitution of India and to pass Prayer is amended as per the Order of
this Court, dt.27.11.2023 vide order passed in I.A.4 of 2023.
IA NO: 1 OF 2023
Petition under Section 151 CPC praying that in the circumstances
stated in the affidavit filed in support of the petition, the High Court may
be pleased to suspend Memo No. 1929135/Vig. 11/2022, dt. 25-03-2023
issued by the 1st respondent whereunder directed to blacklist the
petitioner for on the allegation of substandard quality work execution and
the consequential letters dt. 17-05-2023 and 29-08-2023 of the
respondents 2 and 3 whereunder directed me to pay an amount of
Rs.37,074/- and to relay the rejected components of the work at the cost
and risk of the petitioner failing which an amount of Rs. 43,71,676/- will
be recovered towards the cost of the rejected components of work,
pending disposal of the main writ petition and pass
IA NO: 2 OF 2023
Petition under Section 151 CPC praying that in the circumstances
stated in the affidavit filed in support of the petition, the High Court may
be pleased to permit the petitioner to implead the Engineer in Chief (PR)
as respondent no.4 in the writ petition as he is the proper and necessary
party to these proceedings and pass
IA NO: 3 OF 2023
Petition under Section 151 CPC praying that in the circumstances
stated in the affidavit filed in support of the petition, the High Court may
be pleased to suspend Memo No. 1929135A/ig. II/2022, .dt. 25-03-2023
issued by the 1strespondent whereunder directed to blacklist the
petitionerfor on the allegation of substandard quality work execution and
the proceedings dt.01-06-2023 of the 4threspondent and the
consequential letters dt. 17-05-2023 and 29-08-2023 of the respondents
2 & 3 whereunder directed me to pay an amount of Rs.37,074/- and to
relay the rejected components of the work at the cost and risk of the
petitioner failing which an amount of Rs. 43,71,676/- will be recovered
towards the cost of the rejected components of work, pending disposal
of the main writ petition and pass such other order or orders as this
Hon‟ble Court may deem fit and proper in the circumstance of the case”
in the place of “I further humbly pray that this Hon‟ble Court may be
pleased to suspend Memo No.1929135A/ig. 11/2022, dt. 25-03-2023
issued by the 1 respondent whereunder directed to blacklist the petitioner
for on the allegation of substandard quality work execution and the
consequential letters dt. 17-05- 2023 and 29-08-2023 of the respondents
2 & 3 whereunder directed me to pay an amount of Rs.37,074/- and to
relay the rejected components of the work at the cost and risk of the
petitioner failing which an amount of Rs.43,71,676/- will be recovered
towards the cost of the rejected components of work, pending disposal
of the main writ petition and pass
IA NO: 4 OF 2023
Petition under Section 151 CPC praying that in the circumstances
stated in the affidavit filed in support of the petition, the High Court may
be pleased to permit the permit the petitioner to amend the writ prayer as
“ to issue an appropriate Writ, order or direction more particularly one in
the nature of WRIT OF MANDAMUS declaring Memo No. 1929135A/ig.
II/2022, dt. 25-03-2023 issued by the respondent whereunder directed to
blacklist the petitioner for on the allegation of substandard quality work
execution and the proceedings dt. 01-06-2023 of the 4*^^ respondent
and consequential letters dt. 17-05-2023 and 29-08-2023 of the
respondents 2 & 3 whereunder directed me to pay an amount of
Rs.37,074/- and to relay the rejected components of the work at the cost
and risk of the petitioner failing which an amount of Rs. 43,71,676/- will
be recovered towards the cost of the rejected components of work, is
illegal, arbitrary and violation of Article 19(1 )(g) of Constitution of India in
the place of to issue an appropriate Writ, order or direction more
particularly one in the nature of WRIT OF MANDAMUS declaring Memo
No. 1929135/Vig. 11/2022, dt. 25-03-2023 issued by the 1®„ respondent
whereunder directed to blacklist the petitioner for on the allegation of
substandard quality work execution and the consequential letters dt. 1705-2023 and 29-08-2023 of the respondents 2 & 3 whereunder directed
me to pay an amount of Rs.37,074/- and to relay the rejected
components of the work at the and risk of the petitioner failing which an
amount of Rs. 43,71,676/- will be recovered towards the cost of the
rejected components of work, is illegal, arbitrary and violation of Article
19(1)(g) of Constitution of India and to cost pass
IA NO: 1 OF 2025
Petition under Section 151 CPC praying that in the circumstances
stated in the affidavit filed in support of the petition, the High Court may
be pleased to direct the 4th respondent to register the firm M/s. Shiridi
Sai Baba Constructions as class-1 contractor by considering the
application dt. 25-11-2024, pending disposal of the main writ petition and
pass
IA NO: 1 OF 2026
Petition under Section 151 CPC praying that in the circumstances
stated in the affidavit filed in support of the petition, the High Court may
be pleased to vacate the interim order dated.07.12.202 3 in
WP.No.29586 of 2023 and pass
Counsel for the Petitioner:
1. KOTI REDDY IDAMAKANTI
Counsel for the Respondent(S):
1. GP FOR PANCHAYAT RAJ RURAL DEV
Date on which order was reserved
:
06.04.2026
Date on which order is pronounced
:
16.04.2026
Date on which the order is uploaded
:
16.04.2026
The Court made the following:
ORDER
Heard Sri K.Ashok, learned counsel representing Sri I.Koti Reddy,
learned counsel for the petitioner and Sri P.Rajesh Kumar, learned
Assistant Government Pleader for Panchayat Raj & Rural Development
for the respondents.
2.
Impugning the Memo No.1929135/Vig.II/2022, dated 25.03.2023
(Ex.P1) issued by the 1st respondent, directing the 4th respondent (a) to
recover an amount of Rs.37,074/- from the petitioner towards deficiency
observed in the strength of M-15 Grade concrete of protection wall and
(b) to relay the rejected components of the work at the cost and risk of
the contractor or to recover an amount of Rs.43,71,676/- from the
contractor towards costs of the rejected components of work and further
requested the 4th respondent to blacklist the petitioner as per
G.O.Ms.No.94, dated 01.07.2003, the petitioner filed the above writ
petition.
3.
The 4th respondent, in pursuance of Ex.P1 memo, blacklisted the
petitioner
vide
Saibaba/FC/2016,
proceedings
dated
01.06.2023.
No.AEE(R)/DEE-T/Regn/Shridi
Initially,
the
blacklisting
proceedings were not challenged. Thereafter, the petitioner filed I.A.No.3
of 2023 and the same was ordered on 27.12.2023.
4.
Averments, in brief, as set out in the affidavit, are as follows:
(a) The 1st respondent sanctioned the work of “Package
No.AP021406 providing BT surface to the road from MRL25-Yadiki to
Chandana with an estimated contract value of Rs.2,57,20,292/- under the
scheme of Pradhana Mantri Gramina Sadak Yojana (PMGSY-II)”.
A
tender notification was flouted and the petitioner stood as L1 by quoting
an excess of 4.95% over the estimated contract value. An agreement
No.54/2014-2015 dated 18.12.2014 (Ex.P4) was executed by the
proprietor of the petitioner and the 2nd respondent. As per Clause No.16
of the agreement, the date fixed for completion of work is 12 months.
While executing the work, the 3rd respondent inspected and submitted
the information
to
the
state quality monitor
for
inspection
of
ongoing/completed work on 28.01.2015 and 29.04.2015. The work was
completed. The authorities verified the work and recorded the M-Books
dated 13.12.2015. The total bill amount was paid, withholding 5%, which
would be paid after 5 years.
(b) Be that as it may, the 1st respondent issued a memo dated
25.03.2023 (Ex.P1). Acting upon the said memo, the respondents 2 and
3 issued Exs.P2 and P3. The 1st respondent issued Ex.P1 memo based
on the vigilance report dated 17.12.2022. No vigilance inspection was
made in the presence of the petitioner‟s representative. The Vigilance
and Enforcement Wing submitted the report in November, 2022, after a
lapse of 7 years since the completion of work. The work was completed
in December, 2015. In fact, there are no damages to the road.
5.
An interim order was granted on 07.12.2023 suspending the
blacklisting proceedings dated 01.06.2023, as also Exs.P2 and P3.
6.
a) A counter affidavit was filed on behalf of the 4th respondent. It
was contended, inter alia, that as per the agreement, the defect liability
period is 5 years i.e. 17.12.2020. The contractor has to maintain the
road till completion of the defect liability period. The petitioner completed
the work within the stipulated time, and the final payment was made after
inspection by the state quality monitor of PMGSY on 31.05.2015.
b) The information was given to the Assistant Engineer by the
Executive Engineer, PR PIU Division, Ananthapuramu, regarding
Vigilance & Enforcement Department inspection, and the representative
of the contractor attended the work site during the inspection. The work
was inspected by the Vigilance & Enforcement Department within the
defect liability period. The Vigilance & Enforcement Department, vide
report No.45 (C.No.7515/V&E/Engg/ 2018 Sec-III), dated 17.11.2022,
recommended initiating disciplinary action against the officers and further
recommended to recover the amount from the petitioner as mentioned
supra.
c) The 1st respondent requested the 4th respondent to initiate
action against the petitioner. Acting upon recommendation, the
proceedings Ex.P2, P3 and the blacklisting proceedings were issued and
eventually prayed to dismiss the writ petition.
7.
Learned counsel for the petitioner, as well as learned Assistant
Government Pleader, reiterated the contentions as per the averments in
the writ affidavit and the counter affidavit.
8.
Now, the points for consideration are:
1) Whether the blacklisting proceedings dated 01.06.2023
issued by the 4th respondent are legally sustainable?
2) Whether Exs.P2 and P3, issued by the respondents 2 & 3,
are legally sustainable?
9.
The undisputed facts as seen from the pleadings are that the
Managing Partner of the petitioner and the 2nd respondent entered into
an agreement No.54/2014-2015, dated 18.12.2014 (Ex.P4), in relation to
providing BT surface to the road from MRL25-Yadiki to Chandana. As
per Clause 16 of the agreement, the date fixed for completion of the work
is 12 months i.e. from 18.12.2014 to 17.12.2015. The petitioner
completed the work within the time stipulated, and thereafter the entire
bill amount was paid, withholding 5% amount, till completion of the defect
liability period.
10.
The Vigilance & Enforcement Department submitted a report vide
No.45 (C.No.7515/V&E/Engg/ 2018 Sec-III), dated 17.11.2022, pointing
out sub-substandard in quality.
The authority recommended initiating
disciplinary action against the officers concerned. Insofar as the
petitioner is concerned, the authority recommended blacklisting the firm
as well as the recovery of the amount.
11.
Whether any show cause notice was issued to the petitioner before
blacklisting the petitioner by proceedings dated 01.06.2023? If not, the
proceedings are vitiated?
12.
A perusal of the proceedings dated 01.06.2023 does not indicate
the issuance of a show-cause notice to the petitioner before blacklisting
the petitioner. Blacklisting a contractor or a firm has very serious
consequences. It prevents the contractor or firm from entering into any
lawful
relationships/agreements
with
the
Government
or
other
instrumentalities. Before resorting to such an extreme step, an
opportunity needs to be provided. The law on this aspect is well settled.
13.
In Erusian Equipment and Chemicals Vs. State of West
Bengal1, at Paragraph-20, the Hon‟ble Apex Court observed as follows:
“20. Blacklisting has the effect of preventing a person from the
privilege and advantage of entering into lawful relationship with the
Government for purposes of gains. The fact that a disability is
created by the order of blacklisting indicates that the relevant
authority is to have an objective satisfaction. Fundamentals of fair
play require that the person concerned should be given an
opportunity to represent his case before he is put on the blacklist.”
14.
In Blue Dremz Advertising Pvt. Ltd. & Anr. Vs. Kolkata
MunicipalCorp. & Ors2, the Hon‟ble Apex Court observed as follows:
“1.
In case there exists a genuine dispute between the parties
based onthe terms of the contract, blacklisting as a penalty cannot
be imposed.
2.
The penalty of blacklisting may only be imposed when it is
necessaryto safeguard the public interest from irresponsible or
dishonestcontractors, and
3.
The Corporation being a statutory body, have a higher
threshold tosatisfy before passing such blacklisting order and
therefore, themeasures undertaken by it should be reasonable.”
15.
In this case at hand, no show-cause notice was issued before
blacklisting the petitioner. Regarding a show cause notice, before black
listing, the Apex Court in UMC Technologies (P) Ltd. v. Food
Corporation of India3, at Paragraph-19, observed as follows:
“19. In light of the above decisions, it is clear that a prior showcause notice granting a reasonable opportunity of being heard is an
(1975) 1 SCC 75
2024 INSC 589
(2021) 2 SCC 551
essential element of all administrative decision-making and
particularly so in decisions pertaining to blacklisting which entail
grave consequences for the entity being blacklisted. In these cases,
furnishing of a valid show-cause notice is critical and a failure to do
so would be fatal to any order of blacklisting pursuant thereto.”
16.
Thus, as seen from the material available on record, no show
notice wasissued to the petitioner before blacklisting the petitioner.
Without giving an opportunity, blacklisting the petitioneris not only illegal
but also arbitrary and violative of principles of natural justice.
17.
Apart from that, the 4th respondent did not adhere to the procedure
mandated under G.O.Ms.No.94 dated 01.07.2003, notice and opportunity
of hearing, before blacklisting the petitioner. Thus, the proceedings dated
01.06.2023 are vitiated and liable to be set aside and accordingly, the
proceedings No.AEE(R)/DEE-T/Regn/Shridi Saibaba/FC/2016, dated
01.06.2023 are set aside.
18.
Insofar as the challenge to Exs.P2 and P3, it was specifically
contended in Paragraph-5 of the writ affidavit that no vigilance inspection
was conducted by giving any notice to the petitioner. In Paragraph-6 of
the counter affidavit, it was contended that the work site was inspected
by the Vigilance & Enforcement department within the defect liability
period, and the representative of the contractor attended the work site
during the inspection.
Having pleaded that the representative of the
petitioner attended the inspection and the inspection was done during the
defect liability period, the 4th respondent, for the reasons best known,
failed to indicate the person who attended, and the date of the inspection
in the report.
19.
The Vigilance report is dated 17.11.2022, filed along with the writ
petition (the deponent did not explain the source of securing the
confidential report), does not indicate the date of inspection and the
presence of the representative of the petitioner. The defect liability, as
per the terms of the agreement, is 5 years. The work was completed
within the time stipulated, and the final payment was made after the
inspection by the state quality monitor of PMGSY on 31.05.2015, as per
averments in paragraph-5 of the counter affidavit.
20.
The defect liability period as per the agreement was completed by
17.12.2020. In the absence of any material before the Court regarding
the date of actual inspection by the vigilance & enforcement department,
this Court has to conclude that the alleged inspection, if at all conducted,
would be after expiry of the defect liability period and hence, the
petitioner cannot be held liable for the defects, if any found thereafter.
No show-cause notice was issued to the petitioner prior to the issuance
of Exs.P2 and P3. On that ground, also Exs.P2 and P3 are vitiated and
liable to be set aside. Accordingly, Lr.No.AEE5/DEE/ATP Yadiki
road/V&E
Report/2023
dated
17.05.2023
(Ex.P2)
and
Lr.Notice
No.2/AEE-IV/V & OC Report/Yadiki Road/2023-24, dated 29.08.2023
(Ex.P3), are hereby set aside.
21.
Given the discussion supra, the Writ Petition stands Allowed. No
order as to costs.
As a sequel, pending miscellaneous petitions, if any, shall stand
closed.
__________________________
JUSTICE SUBBA REDDY SATTI
PVD
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review