Serial No. 17
Regular List
HIGH COURT OF MEGHALAYA
AT SHILLONG
WP(C) No. 106 of 2019
Date of Decision: 04.09.2019
Vs.
Smti Roma D. Sangma
The Union of India & Ors.
Coram:
Hon’ble Mr. Justice H. S. Thangkhiew, Judge
Appearance:
For the Petitioner/Appellant(s):
Mr. K. N. Choudhury, Sr. Adv. with
Mr. A. Mir, Adv.
For the Respondent(s)
Ms. A. Paul, ASG for R 1 & 2.
Mr. B. Bhattacharjee, AAG with
Ms. I. Lyngwa, GA for R 3-8.
Mr. B. Laitmon, Adv. for R 9.
:
i)
Whether approved for reporting in
Law journals etc.:
ii)
Whether approved for publication
in press:
1.
Yes/No
Yes/No
Heard Mr. K.N. Choudhury, learned Sr. counsel assisted by Mr. A.
Mir, learned counsel for the petitioner. Ms. A. Paul, learned ASG for the
respondent No. 1 and 2, Mr. B. Bhattacharjee, learned AAG assisted by Ms.
I. Lyngwa, learned GA for the respondent No. 3 to 8 and Mr. B. Laitmon,
learned counsel for the respondent No. 9.
2.
The brief facts of the case is that the petitioner by way of this writ
petition, has put a challenge to the power and authority of the Directorate of
Tourism to issue NIT dated 05.03.2019. The ground taken is that the NIT
dated 05.03.2019, is inconsistent with, and in violation of letter dated
15.01.2019 of the Ministry of Tourism, Government of India more
particularly Clause 4.6 of the “Swadesh Darshan Scheme Guidelines for
Integrated Development of Theme Based Tourism Circuits in the
Country”. The contention of the writ petitioner is that it is only the
Meghalaya Tourism Development Corporation, which has been designated
as the ‘Implementing Agency’ that has the exclusive power and authority to
issue the NIT dated 05.03.2019.Therefore, according to the petitioner, since
the NIT has been issued without any authority of law by the Directorate of
Tourism, any work order issued pursuant to the impugned NIT dated
05.03.2019 will be non-est and void, for which eligible prospective bidders
such as the Petitioner are apprehensive to participate in. Hence the writ
petition.
3.
Mr. K.N. Choudhury, learned Sr. counsel assisted by Mr. A. Mir,
learned counsel for the petitioner opens his submissions by referring to the
“Swadesh Darshan Scheme Guidelines for Integrated Development of
Theme Based Tourism Circuits in the Country”. He submits that the said
Scheme was launched in the year 2014-2015, to develop tourist centers and
circuits on specific themes, or attracting tourists having special interest in
visiting such places. In this regard, he submits under the said scheme, the
Ministry of Tourism, Government of India had framed guidelines for the
development of theme based tourist circuits. Under the scheme guidelineshe
stated it is provided for a National Steering Committee (NSC) to be headed
by the Minister of Tourism, and for a Central Sanctioning and Monitoring
Committee (CSMC) and this Committee was responsible for the projects
apart from monitoring the progress of implementation.
4.
He submits that the scheme guidelines also stipulated that there will
be a Mission Directorate headed by a Member-Secretary of the National
Steering Committee (NSC) as Nodal Officer. Some of the key
responsibilities of the Mission Directorate was for identification of projects
etc. He submits that the scheme is fully centrally funded and funds are
released to the implementing agency under the scheme.
5.
Learned Sr. counsel for the petitioner draws the attention of this Court
to Clause 4.6 of the scheme guidelines, which deals with implementation of
the projects. He further submits that the implementing agency/executing
agency shall be responsible for timely implementation of the project and that
the Implementing Agency shall be responsible for inviting and finalizing
tender within stipulated time. He further submits that the implementing
agency for the State of Meghalaya is the Meghalaya Tourism Development
Corporation (MTDC).
6.
The learned counsel submits that vide letter dated 15.01.2019 the
respondent No. 1 conveyed the administrative and finance sanction for
project development in various places in the State of Meghalaya. He submits
that as per Clause 4.6 of the scheme guidelines it is specifically provided
therein that the implementing agency shall be responsible for inviting and
finalizing the tender for works approved under the scheme.
7.
He next submits that as per Clause 4.6 of the scheme guidelines, as
aforementioned the implementing agency Meghalaya Tourism Development
Corporation (MTDC) in the instant case, have been given the power and
authority to invite tenders for the said project/works in Meghalaya.
However, he submits in total contravention of the scheme guidelines and the
letter dated 15.01.2019, the Directorate of Tourism has issued the NIT dated
05.03.2019, without any authority of law or jurisdiction.
8.
Learned Sr. counsel for the petitioner also refers to letter dated
15.03.2017 issued by the under Secretary, Government of Meghalaya
Tourism Department which contains Government approval for Meghalaya
Tourism Development Corporation (MTDC) for the selection and execution
of works under the scheme (Swadesh Darshan Scheme) and also to be the
authority to constitute the tender committee.
9.
Learned Sr. counsel then submits that the Petitioner who is a Class - 1
contractor and a prospective bidder had instituted the instant writ proceeding
on being aggrieved by the impugned NIT dated 05.03.2019. He contends
that the writ petition, has been structured primarily on the basis that even
though Meghalaya Tourism Development Corporation (MTDC), is under the
administrative control of Government of Meghalaya, it is a juristic person,
and in discharge of its functions, it is the Board of Directors of the
Corporation who are responsible for the conduct and management of its
business. He submits that the power and authority to issue tenders and to
finalize the same vests with the Meghalaya Tourism Development
Corporation (MTDC) and not upon the Director of Tourism, Government of
Meghalaya. He submits that the respondent No. 7/ Director of Tourism in his
affidavit however, has contended that the Government of Meghalaya had
exclusive authority to issue NIT and that a tender committee had also been
constituted on 21.02.2019 by the Tourism of Department itself.
10.
He further submits that on coming to learn about this development the
writ petitioner had filed another writ petition bearing WP(C) No. 148 of
2019, but on an objection being raised as to its maintainability, the same was
withdrawn on 30.05.2019. He submits that however, the constitution of the
tender committee having a bearing in the matter, the same has been brought
on record by means of an additional affidavit. He contends that in the
present challenge, the petitioner seeks to refer and rely upon a
communication dated 01.07.2016 where upon its evident that the Secretary
Tourism Department, Government of Meghalaya is the Nodal Officer for
implementing and monitoring of the project, whereas Meghalaya Tourism
Development Corporation (MTDC) the implementing agency would execute
the work. The learned Sr. counsel then, draws the Court attention to the fact
that the Articles of Association of the Meghalaya Tourism Development
Corporation (MTDC) provides that the Managing Director is responsible for
the conduct and management of the business of the Corporation subject to
the control and supervision of the Board of Directors. He submits that the
Article 73 (xxiv) of the Articles of Association empowers the Board of
Directors to enter into contracts and therefore it will follow, that it is only
the Board of Directors of the Meghalaya Tourism Development Corporation
(MTDC), which is competent to decide upon issuance of tenders under the
Swadesh Darshan Scheme. He submits that the apprehension of the
petitioneris that the manner and method of award of contract in favour of
prospective bidders, in view of this irregularity, would be flawed and
unsustainable, and as such deserves to be interfered with by this Court. He
lastly, submits that the mandate, which is embodied in the Swadesh Darshan
Scheme, is binding on the Government of Meghalaya and the State cannot
deviate therefrom, in implementing the scheme. As such, he submits that the
order dated 21.02.2019 as well as impugned NIT dated 05.03.2019 are
without any authority of law and the same are liable to be interfered with.
11.
In support of his submissions, learned Sr. counsel relied upon on the
following judgments: (i)
(1988) 2 SCC 602, A.R. Antulay v. R.S. Nayak.
(ii)
(1975) 1 SCC 559, Ramchandra Keshav Adke v. Govind
Joti Chavare.
(iii)
(1972) 2 SCC 788, Bennett Coleman & Co. v. Union of
India.
12.
Mr. B. Bhattacharjee, learned AAG assisted by Ms. I. Lyngwa,
learned counsel on behalf of the respondent No. 3 to 8, in reply to the
submissions of the learned Sr. counsel for the petitioner firstly, submits that
the petitioner has no locus standi to file the instant writ petition as the
scheme of guidelines for implementation of the Swadesh Darshan Scheme
does not confer any individual right or privilege on the petitioner. He
submits that the Swadesh Darshan Scheme is neither an Act nor a Rule, but
is only a guideline, which lays down the mode and manner in which the
Swadesh Darshan Scheme, is to be implemented. He submits, in case any
part thereof is not adhered to, the same is to be brought to the notice of the
Ministry of Tourism, Government of India and there is nothing in the writ
petition to indicate that such steps have been taken by the petitioner before
coming before this Court.
13.
Learned counsel submits that in the implementation of the scheme,
there is also no instance of the Central Government raising any kind of
objection as to the manner in which the scheme is being implemented in the
State. Learned counsel then submits that the term “Implementing Agency”
includes many functionaries, which consist of functionaries of the Union of
India, State Government and the Meghalaya Tourism Development
Corporation (MTDC). He next refers to Clause 4.6 of the scheme, which he
submits, lays down that the implementing agency shall appoint a Nodal
Officer for implementation of project. He submits that by communication
dated 15.01.2019, The Secretary, Government of Meghalaya had been
appointed as the Nodal Officer for implementation and monitoring of the
project by the Under Secretary to the Government of India, Ministry of
Tourism (Swadesh Darshan Division) and not by the Meghalaya Tourism
Development Corporation (MTDC).
14.
He submits that the Meghalaya Tourism Development Corporation
(MTDC) was appointed as the implementing agency only for execution of
the work, as has been given in para 6 of the said letter dated 15.01.2019, and
a plain reading of the contents of the communication, specially paras 4, 6, 8,
9 and 11, will indicate that the State Government remains the overall
implementing and monitoring agency under the guidelines of the scheme.
Learned counsel further submits that the NIT dated 05.03.2019 has been
issued by the Respondent No. 7 in the capacity of the Member Secretary,
Tender Committee constituted by the Government of Meghalaya vide
notification dated 21.02.2019 and that the said constitution dated
21.02.2019, is not under challenge in the instant Writ Petition and as such he
submits, in absence of any challenge to the said notification whereby the
tender committee has been constituted, the NIT dated 05.03.2019 cannot be
said to be illegal or without any authority.
15.
Learned counsel also submits that the respondent No. 9/ MTDC is a
Government Corporation, and for the purpose of execution of Government
work, the MTDC does not stand on a different footing and remains a part
and parcel of the State, which is reflected in the constitution of the Tender
Committee constituted vide notification dated 21.02.2019. Learned counsel
points out that the same consists of representatives from the Tourism
Department, Finance Department and Law Department of the State besides
the officials of the Meghalaya Tourism Development Corporation (MTDC).
He further submits that the Meghalaya Tourism Development Corporation
(MTDC) by itself has no power or authority to constitute a tender committee
consisting of officials of the different departments of the State and it is only
the State, which can constitute the same.
16.
Learned counsel then submits, that with regard to the powers of the
Board of the Meghalaya Tourism Development Corporation (MTDC), the
Governor holds the ultimate power to issue directives and instructions in
relation to matters which include Finance, Conduct of business and Affairs
of the Meghalaya Tourism Development Corporation (MTDC) and the said
NIT dated 05.03.2019, was issued in pursuance to the constitution of the
Tender Committee by the Governor vide notification dated 21.02.2019 and
as such cannot be invalidated.
17.
The next limb of submission of the learned counsel is that the
Meghalaya Tourism Development Corporation (MTDC), which has been
arrayed as party respondent No. 9, has not filed any affidavit, nor raised any
grievance against the constitution of the Tender Committee by the Governor
and the issuance of the NIT by the respondent No. 7, nor is there any
allegation of violation of the terms and conditions of the guidelines for
implementation of Swadesh Darshan Scheme. Learned counsel also brings
to the notice of the Court that the respondent No. 7, is also functioning as the
Managing Director of the Meghalaya Tourism Development Corporation
(MTDC) and as such the petitioner has no valid ground to be aggrieved.
18.
With regard, to the additional affidavit filed by the writ petitioner, the
learned counsel submits that the same had been filed, without taking any
leave or permission of this Court after WP(C) No. 148 of 2019 had been
withdrawn. He then closes his submissions by reiterating that the petitioner
has no locus standi, nor in any manner can be said to be aggrieved and as
such the writ petition being without any merit is liable to be dismissed.
19.
Ms. A. Paul, learned ASG on behalf of the respondent No. 1 and 2
adopts the submissions made by the learned AAG for the respondent No. 3
to 8, and has stressed on the absence of locus of the writ petitioner to
challenge the NIT. She also submits that the Meghalaya Tourism
Development Corporation (MTDC) itself is not aggrieved with the same and
submits that no individual right of the petitioner has been violated in any
manner to warrant any interference by this Court.
20.
I have heard learned counsels for the parties considered their
respective submissions and examined the materials on record. From the
arguments as projected by the petitioner, the only grievance is that the
guidelines as prescribed under the Swadesh Darshan Scheme, have been
violated as the tender had not been floated by the competent authority, and
this being the case it was contended that the entire tender process being
patently illegal stood vitiated and invalid.
21.
The writ petitioner a prospective bidder, has since also taken part in
the tender process by submitting her tender and the factum of such
participation has been placed before this Court by way of an affidavit dated
14.06.2019. Before advancing further, it would be expedient to examine the
scheme in question, especially Clause 4.6, which is quoted herein below: -
“4.6 Implementation:
Swadesh Darshan being a central sector scheme will
be implemented under overall control of Mission
Director.
Experts/Consultants may be engaged by executing
agencies
for
detailed
planning
and
designing/preparing DPR of the works/projects under
the scheme.
The implementing/ executing agency shall be
responsible for timely implementation of the
project/work with quality assurance of assets created.
The implementing agency shall appoint a Nodal
Officer for implementation of project.
The States/ UT Administration shall appoint a State
Level Monitoring Committee for timely implementation
of project.
If there is any escalation/variation from approved
DPR. SGs/ UT Administrations must inform MoT and
seek its approval for the same before commencing
work on the component.
Land to be used for the project must be free from all
encumbrances.
Implementing Agency shall invite and finalize all
tenders within stipulated time to enable MoT to release
of installments of the project.
Work for different phases of the projects shall be
completed within the period stipulated in the
respective sanction letters & monitoring framework.
The Implementing agency shall follow all codal
formalities
while
awarding
contracts
for
works/material/equipment procurement and ensure
complete transparency in its transactions. E-tendering/
e-procurement will be compulsorily followed for all
tenders.
Implementation of WSA/Toilet Block project would be
done as per Annexure 2.”
22.
On a bare perusal of the above quoted clause, it is noted that the
implementing agency, would be responsible for the timely implementation
of the projects/work and further that a Nodal Officer was to be appointed for
implementation of the project. It is also provided that the implementing
agency was to invite and finalize tenders within a stipulated time, to enable
the Ministry of Tourism to release installments for the project. Letter dated
15.01.2019 from the Ministry of Tourism, places on record the fact that the
Meghalaya Tourism Development Corporation (MTDC) was to be the
implementing agency for execution of the aforesaid work, on being
appointed by the State Government, and further that The Secretary
(Tourism) Government of Meghalaya was to be the Nodal Officer for
implementation and monitoring of the project.
23.
The scheme also provides that the State Government would set up a
monitoring committee headed by The Secretary of Tourism, with a member
from the Ministry of Tourism and the implementing agency, to monitor the
physical and financial progress of the sanctioned project. As noted, earlier
the entire case of the petitioner rests on the contention that the Meghalaya
Tourism Development Corporation (MTDC) having been nominated as the
implementing agency, is the sole authority to execute and implement the
project to the exclusion of all other authorities.
24.
The submissions and the contentions of the learned counsel for the
petitioner on this aspect, though attractive at first flush on closer
examination however does not make out a watertight case. Firstly, though
the Meghalaya Tourism Development Corporation (MTDC) is the
implementing agency, the NIT cannot be said to be incompetent, as the same
was issued under the hand of the Director of Tourism and Member Secretary
of the Tender Committee, the authority of which to issue the tender is not in
question herein. Secondly, it is not the case of the writ petitioner that the
Meghalaya Tourism Development Corporation (MTDC) has been totally
divested of its responsibility of being the implementing agency for execution
and supervision of the work as its role remains intact as envisaged under the
scheme. Thirdly, is the fact that the Government remains the overall
implementing and monitoring agency under the guidelines of the scheme
and it is not that the MTDC is the sole authority but is in fact under the
control and supervision of the Government. Fourthly, an aspect, which also
deserves consideration, is that the tender committee is constituted of
representatives from Tourism Department, Finance and Law Departments of
the State, besides, the officials of the Meghalaya Tourism Development
Corporation (MTDC).
25.
The said constitution of the tender committee is also not under direct
challenge in the instant writ petition, but has only been brought to the notice
of this Court by way of an additional affidavit, as WP(C) No. 148 of 2019,
wherein the constitution of the tender committee had been assailed, has since
been withdrawn. No relief being permissible in the instant application
against the said constitution of the Tender Committee, this Court in the
instant proceedings only notes the same.
26.
The Swadesh Darshan Scheme, as it stands cannot come within the
definition of an Act or Rule, a violation whereof, would render the actions
by the respondents arbitrary or illegal. In fact,the scheme is only a guideline,
which lays down the manner and method of implementation of various
projects. Enforceability, of such guidelines by way of a mandamus is also
questionable, as it has to be viewed in the context of an infringement being
caused to the fundamental or legal rights of the petitioner on its noncompliance or non-adherence. The same in the instant case, has not been
occasioned, more so, as no grave illegality or even violation can be
discerned which will render the tender process ‘non-est’ or invalid in the eye
of law. Looking into the totality of the tender process, the irregularities as
highlighted by the petitioner, cannot amount to actions that can be termed as
illegal or vitiated to have adversely affected the rights of the petitioner to
warrant any interference by this Court.
27.
The decisions relied upon by the Learned Senior Counsel will have no
application to the instant case in view of the discussions in para 24 above,
and also the fact that the Scheme is only a guideline not having the authority
of an Act or Rules, added to the fact that the Respondent No. 9 the MTDC
itself, is not aggrieved with the NIT.
28.
Coming to the Locus Standi of the petitioner, it is well established in
administrative law, law of contract and other allied laws that an affected
person would have a cause of action, even in some cases as third party to
bring an action in public interest despite the fact that he may not have
personal interest. But in the instant case, the cause of action would be
personal to the aggrieved party and not a cause of action in rem. Even if
keeping in view the widened scope of jurisdiction under Article 226, and
even if the dictates of law are not strictly applied, it would be still difficult
for this Court to hold that the Petitioner though being an Applicant to the
tender process could maintain the present Writ Petition.
29.
Though the concept of locus standi has since undergone a substantial
change, the basic rule that still holds good and is the bedrock of the concept,
is that, only a person aggrieved or a person directly affected, is the person
who has right to invoke jurisdiction of the Court under Article 226 of the
Constitution. It therefore follows that to sustain the prayer of the writ
petitioner, it must be apparent that the NIT so issued, has adversely affected
the Petitioner's legal right. This situation not being so in the instant case, and
the personal rights of the petitioner having not been infringed in any manner,
the instant writ petition also fails for lack of locus of the petitioner to
maintain the instant petition.
30.
As such in the facts and circumstances of the case and for the
foregoing reasons, the writ petition is accordingly dismissed.
31.
No order as to costs.
Judge
Meghalaya
04.09.2019
“D.Thabah PS”
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review