Date of reserved for orders: --Date of pronouncement :01.07.2026
Date of uploading
:16.07.2026
APHC010536332024
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3331]
WEDNESDAY, THE 1st DAY OF JULY 2026
PRESENT
THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI
WRIT PETITION NO: 28393/2024
Between:
1. RKN PROJECTS PRIVATE LTD, REP BY ITS MANAGING DIRECTOR,
N RAMESH KUMAR, S/O N BALAIAH, AGED ABOUT 58 YEARS,
OCC. CONTRACTOR, R/O D NO 26-2-29, 2ND LANE, RITHWIK,
ENCLAVE, A.K.NAGAR, NELLORE, SPSR NELLORE DISTRICT.
...PETITIONER
AND
1. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL
SECRETARY,
IRRIGATION DEPARTMENT,
SECRETARIAT
BUILDINGS, VELAGAPUDI, AMARAVATI,
GUNTUR DISTRICT,
ANDHRA PRADESH.
2. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL
SECRETARY,
FINANACE DEPARTMENT,
SECRETARIAT
BUILDINGS, VELAGAPUDI, AMARAVATI,
GUNTUR DISTRICT,
ANDHRA PRADESH.
3. THE SUPERINTENDING ENGINEER,
NELLORE, S.P.S.R. NELLORE DISTRICT.
IRRIGATION
4. THE
EXECUTIVE
ENGINEER,
IRRIGATION
VENKATAGIRI, S.P.S.R NELLORE DISTRICT.
CIRCLE,
DIVISION,
...RESPONDENT(S):
Petition under Article 226 of the Constitution of India praying that in the
circumstances stated in the affidavit filed therewith, the High Court may be
pleased to issue a Writ, order or direction more particularly one in the nature
of Writ of Mandamus declaring the action of the Respondents in not paying
the interest amount
of Rs.53,99,368/- to the Petitioner @ 6 percent per
annum for the execution of
the work under Formation of Left Side Flood
Bank Km 37.100 to Km 60.000 and Right Side Flood Bank from Km 39.000 to
60.000 (Near Ravulapadu Village) of Swarnamukhi River in SPSR Nellore
District, with Agreement No. 1SE/2015 - 2016 Dated. 13.04.2015 to the
petitioner is arbitrary, illegal and consequently direct the respondents to pay
the interest amount for i.e., 1) 1105 Days, 2)1105 Days and 3) 151 Days
delay @ 6 percent per annum as per the orders of Honble High Court in
W.A.No.724 of 2021 and batch Dated. 12.10.2023 to the petitioner for the
execution of the above said works on the admitted bill amount from the date
when the bills were submitted by the petitioner for payment to till the date of
final payment and pass
IA NO: 1 OF 2024
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased to
direct the Respondents to pay the interest amount of Rs.53,99,368/- to the
Petitioner @ 6 percent per annum for the execution of the work under
Formation of Left Side Flood Bank Km 37.100 to Km 60.000 and Right Side
Flood Bank from Km 39.000 to 60.000 (Near Ravulapadu Village) of
Swarnamukhi River in SPSR Nellore District, with Agreement No.
1SE/2015-2016 Dated: 13.04.2015 to the petitioner and pass
Counsel for the Petitioner:
1. S SIVA KUMARI
Counsel for the Respondent(S):
1. GP FOR IRRI AND CAD
2. GP FOR FINANCE PLANNING
The Court made the following order:
Heard Sri S.Bhaskar, learned counsel representing Smt. S.Siva Kumari,
learned counsel for the petitioner and Sri Satish, learned Assistant
Government Pleader for Irrigation and Command Area Development, for the
respondents 1 to 4.
2.
The above writ petition was filed to declare the action of the
respondents in not paying the interest amount of Rs.53,99,368/- @ 6% per
annum in relation to the works executed by the petitioner at Swarnamukhi
River in SPSR Nellore District, vide Agreement No.1SE/2015-2016 dated
13.04.2015, as illegal and arbitrary.
3.
The basis of the petitioner’s claim, as seen from the affidavit, is the
order of the Division Bench in W.A.No.724 of 2021 and batch dated
12.10.2023.
4.
Learned Assistant Government Pleader, while referring to the payment
made to the petitioner, relied upon Clause 69 of the Andhra Pradesh Standard
Specifications, and further contended that the contractor is not entitled to
claim interest upon any guarantee fund or payments in arrears or balances.
Learned Assistant Government Pleader placed reliance on the order dated
11.02.2025 in W.A.No.60 of 2025.
5.
The point for consideration is:
Whether the petitioner is entitled to claim interest in the light of clause-
69 of the Andhra Pradesh Standard Specifications by invoking the
extraordinary jurisdiction under Article 226 of the Constitution of India?
6.
Before delving into the facts, it is necessary to refer to Clause 69 of the
Andhra Pradesh Detailed Standard Specifications, which reads as under:
“69. Interest on money due to the contractor:(a) No omission by the Executive Engineer or the Sub-Divisional Officer
to pay the amount due upon certificates shall vitiate or make void the
contract, nor shall the contractor be entitled to interest upon any
guarantee fund or payments in arrear, nor upon any balance which may,
on the final settlement of his accounts, be found to be due to him.
(b) Whenever the withheld amount reaches Rs. 1,000 or a multiple
thereof, the contractor may, at his option, deposit with Executive Engineer
Rs. 1,000 or a multiple thereof, in any of the forms of interest bearing
securities recognized for the purpose by the Andhra Pradesh Public
Works Accounts Code and subject to the provisions therein contained, in
which case in the equivalent withheld amount shall be paid to him
forthwith. The contractor will be permitted to exercise the option in this
clause, subject only to the condition that the rate of progress contained in
the Articles of Agreement is properly maintained.”
7.
In A.P.S.R.T.C. vs. P. Ramanareddi,1 the learned single judge of the
composite High Court interpreted the scope of Clause 69 and observed as
under:
“23. Thus it is clear that this Clause 69 is intended to really prevent
any claim for interest during the running period when final bill is not
settled and also in respect of earnest money deposit or the sum
equal to 2½ % of the total value of the work done till the expiry of
the period of six months. This six months‟ period is called
„observation period‟, so that the Department can see whether the
work was done satisfactorily or not. Clause 69 cannot be construed
as a total prohibition, but it operates a limited period of six months
from the date of the completion of the work and hence I negative
this contention that Clause 69 is a bar to claim interest.
24. It is fairly well settled that the claim for interest can either be
under the agreement, or under the usage of trade having force of
law, or under the provisions of substantive law or under the
provisions of the Interest Act, 1839 or when the Court exercises
equitable jurisdiction as envisaged in the proviso to Sec. 1 of the
said Act. (Vide: Vithal dass v. Rup Chand (AIR 1967 SC 188). So
far as the requirement of Interest Act is concerned, the Supreme
Court in Thawardas v. Union of India (AIR 1955 SC 468) laid down
five conditions:
1. The interest is not payable under any other law.
2. there must be a debt or a sum certain.
3. it must be payable at a certain time or otherwise.
4. these debts or sums must be payable by virtue of some
written instrument.
5. there must have been a demand in writing stating that
interest will be demanded from the date of the demand.”
1988 SCC OnLine AP 343 : (1989) 1 ALT 195
8.
In W.A.No.60 of 2025, the Division Bench, after considering the order in
W.A.No.724 of 2024 on which the petitioner placed reliance, observed as
follows:
“8. It needs to be pointed out that it is no longer res integra as has
been held by a three-Judge Bench of the Apex Court in Union of India
vs. Bright Power Projects (India) (P) Ltd.1 that when parties to a
contract agree that interest would not be awarded on the amount
payable to the contractor under the contract, the contractor in those
circumstances cannot claim interest either before a civil Court or
before an arbitral tribunal. The Apex Court held:
“10. …so far as payment of interest on the amount payable to the
contractor under the contract was concerned, there was a specific
term that no interest was to be paid thereon.
11. When parties to the contract had agreed to the fact that
interest would not be awarded on the amount payable to the
contractor under the contract, in our opinion, they were bound by
their understanding. Having once agreed that the contractor
would not claim any interest on the amount to be paid under the
contract, he could not have claimed interest either before a civil
court or before an Arbitral Tribunal.”
9. In fact, Section 3(3) of the Interest Act, 1978, specifically carves out
an exception and recognizes the right of the parties to contract out of
the payment of interest on any duty or damages by virtue of an
express agreement. Section 3 (3) (a) (ii) of the Act reads thus:
“3 (3) (a)
(i) …
(ii) any debt or damages upon which payment of interest is
barred, by virtue of an express agreement;”
10. In the light of the aforementioned facts and the law as discussed
hereinabove, in our opinion, the judgment and order impugned to the
extent it orders payment of interest @ 6% per annum, in our view, is
unsustainable. The judgment and order to that extent is set aside.
However, we make it clear that this would not prejudice the right of any
of the parties to agitate their respective claims and counter-claims
before an appropriate forum, in accordance with law.”
9.
That being the legal regime, the petitioner’s claim regarding the interest,
unless the petitioner lets in evidence, it may not be possible to determine the
issue. The petitioner has to establish the completion of work within the time
stipulated; non-payment of the amount as per the terms and conditions; and
entitlement to claim interest despite cl. 69 APSS in the contract need to be
examined by a competent authority based upon the evidence. It is a wellsettled law that, in a Writ Petition, a disputed question of fact should ordinarily
not be entertained. The Hon’ble Apex Court in Himmat Singh vs. State of
Haryana,2 held that:
"18. ...In the grounds of a writ petition only a question of law can be
raised and not a statement of fact. No statement has been made in
the body of the writ petition. The statement made in the said
grounds was also not verified in accordance with the writ rules.
Despite the same, as we have noticed hereinbefore, the fifth
respondent in his affidavit denied or disputed the contents thereof.
Whether the statement of the appellant or the fifth respondent was
correct or not could not ordinarily be decided in a writ proceeding. It
is well known that in a writ petition ordinarily such a disputed
question of fact should not be entertained..."
10.
Also in Punjab National Bank vs. Atmanand Singh,3 recently the
Hon’ble Apex Court, restricting the scope of interference under Article 226 of
the Constitution, held that:
"22. We restate the above position that when the petition raises
questions of fact of complex nature, such as in the present case,
which may for their determination require oral and documentary
evidence to be produced and proved by the party concerned and
also because the relief sought is merely for ordering a refund of
money, the High Court should be loath in entertaining such writ
petition and instead must relegate the parties to remedy of a civil
suit. Had it been a case where material facts referred to in the writ
petition are admitted facts or indisputable facts, the High Court may
(2006) 9 SCC 256
(2020) 6 SCC 256
be justified in examining the claim of the writ petitioner on its own
merits in accordance with law."
11.
Thus, the discussion supra, apart from the judgment of the Division
Bench, since Clause 69 of the Andhra Pradesh Standard Specifications is
made part of the contract, the petitioner is not entitled to claim interest. The
petitioner’s entitlement, if any, vis-à-vis the interest, it requires evidence to be
let in. Without proper evidence on record, in the considered opinion of this
court, granting interest in the facts of the case is impermissible.
12.
Given the facts and circumstances of the case, the writ petition is
disposed of, directing the petitioner to approach the appropriate forum
regarding interest. There shall be no order as to costs.
As a sequel, pending miscellaneous petitions, if any, shall stand closed.
___________________________
JUSTICE SUBBA REDDY SATTI
Date: 01.07.2026
SNI
Whether the order is:
Speaking Yes/No / Reasoned Yes/No
Reportable Yes/No / Non-Reportable Yes/No
THE HONOURABLE SRI JUSTICE SUBBA REDDY SATTI
WRIT PETITION NO: 28393 OF 2024
Date: 01.07.2026
SNI
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review