Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
*
IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Date of decision: 20.03.2026
+
O.M.P. (COMM) 221/2023 & I.A. 11873/2023
RITES LTD. THROUGH ITS GROUP GENERAL
MANAGER
.....Petitioner
Through:
Mr. G.S. Chaturvedi, Adv.
versus
M/S APEX CONSTRUCTION CO. & ANR.
.....Respondents
Through: Mr. Ripudaman Bhardwaj,
CGSC with Mr. Kushagra
Kumar, Mr. Amit Kumar Rana
& Ms. Pragati Trivedi, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
AVNEESH JHINGAN, J. (ORAL)
1.
This petition under Section 34 of the Arbitration and
Conciliation Act, 1996 (for short „the Act‟) is against the award dated
11.01.2023.
2.
The grievance is that the unilateral appointment of the arbitrator
is in violation of the amended Section 12(5) of the Act.
The facts in brief are that the respondent was the successful
bidder in tender invited by the RITES Limited (for short „RITES‟) on
behalf of the Delhi Police. The work awarded was for construction for
Delhi Police Housing in Sector 11, Rohini, New Delhi, to be
concluded within twenty four months from the date of handing over
the site and was for approximately Rs. 20.89 crores. Dispute arose
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
between the parties to the lis. Clause 25 of the conditions of the
contract reproduced below provides for settlement of disputes and
arbitration:
“CLAUSE 25
Settlement of Disputes & Arbitration
Except where otherwise provided in the Contract all
questions and disputes relating to the meaning of the
specifications, design, drawings and instructions
hereinbefore mentioned and as to the quality of
workmanship or materials used on the work or as to
any other question, claim, right matter or thing
whatsoever in any way arising out of or relating to the
Contract, designs, drawings, specifications, estimates,
instructions, orders or these conditions or otherwise
concerning the works or the execution or failure to
execute the same whether arising during the progress
of the work or after the cancellation, termination,
completion or abandonment thereof shall be dealt with
as mentioned hereinafter:
1) If the Contractor considers any work demanded of
him to be outside the requirements of the Contract or
disputes any drawings, record or decision given in
writing by the Engineer on any matter in connection
with or arising out of the Contract or carrying out of
the work to be unacceptable, he shall promptly within
15 days request the Engineer-in-Charge in writing for
written instruction or decision. Thereupon, the
Engineer-in-Charge shall give his written instructions
or decision within a period of one month from the
receipt of the Contractor‟s letter.
If the Engineer-in-Charge fails to give his instructions
or decision in writing within the aforesaid period or if
the Contractor is dissatisfied with the Instructions or
decision of the Engineer-in Charge, the contractor may,
within 15 days of the receipt of the Engineer-in-Charge
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
decision, appeal to the Appellate Authority specified in
Schedule „F‟ who shall afford an opportunity to the
Contractor to be heard, if the latter so desires, and to
offer evidence in support of his appeal. The Appellate
Authority shall give his decision within 30 days of
receipt of Contractor‟s appeal. If the Contractor is
dissatisfied with this decision, the Contractor shall
within a period of 30 days from receipt of the decision,
give notice to the Accepting Authority specified in
Schedule „F‟ for appointment of arbitrator failing
which the said decision shall be final binding and
conclusive and liable to adjudication by the Arbitrator.
2) Except where the decision has become final,
binding and conclusive in terms of Sub Para (1) above,
disputes or difference shall be referred for adjudication
through arbitration by a sole arbitrator appointed by the
Accepting Authority. The selection of Arbitrator by the
Accepting Authority will be governed by the fact
whether the dispute is (i) between two Public Sector
Enterprises or (ii) between a Public Sector Enterprise
and a Government Department or (iii) Otherwise.
In case the disputes does not fall under item (i) or (ii)
of this Para the Accepting Authority, shall appoint the
sole Arbitrator within 30 days of receipt of notice from
the Contractor to refer the dispute for Arbitration, the
Accepting Authority stipulated in Schedule F shall
send to the Contractor a list of three serving officers of
RITES of appropriate status depending on the total
value of claim, who have not been connected with the
work under the Contract. The Contractor shall, within
15 days of receipt of this list select and communicate to
the Accepting Authority, the name of one officer from
the list who shall then be appointed as the Sole
Arbitrator. If the Contractor fails to communicate his
selection of name within the stipulated period, the
Accepting Authority shall without delay, select one
officer from the list and appoint him as the Sole
Arbitrator.
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
****
****
****
6) Parties to be impleaded in the arbitration
proceedings.
In case of any claims by the Contractor, the Employer
as well as RITES Ltd acting as Agent to the Employer
will implead themselves as parties to the Arbitration
Proceedings.”
3.1
A notice dated 03.06.2019 under Section 21 of the Act was
issued by the respondent. It was specifically mentioned in the notice
that after amendment of Section 12(5) of the Act, serving official of a
party to the dispute cannot be appointed as an arbitrator without the
consent of both parties and the respondent is not willing to give such
consent. A request was made to intimate three names in terms of
Clause 25 of the conditions of the contract but not being the serving
officials of RITES. The three names suggested by the petitioner vide
communication dated 20.06.2019 were not accepted by the
respondent. Thereafter the respondent was given an option to select
arbitrator from the panel maintained by the petitioner. The matter was
referred to the arbitrator appointed by the petitioner but selected by
the respondent. Aggrieved of the impugned award this petition is filed.
4.
Learned counsel for the petitioner submits that the appointment
of the arbitrator is in violation of Section 12(5) of the Act and the
impugned award is liable to be set aside. Reliance is placed upon the
decision of this court in Railways Board, Ministry of Railways Vs.
Titagarh Rail Systems Limited, 2026:DHC:1720.
5.
Per contra the respondent participated in appointment of the
arbitrator, had selected the arbitrator from the panel of the petitioner
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
and the appointment is not unilateral. The argument is that the final
determination of the arbitrator to be appointed was by the respondent
and not of the petitioner. It is contended that the participation and the
exercise of choice by the respondent in appointment of the arbitrator is
evident from the fact that the respondent rejected the list of three
arbitrators given by the petitioner. The decision relied upon by the
petitioner is stated to be not applicable to the facts of this case.
6.
Before proceeding further, it would be apposite to quote the
following decisions:
6.1
The Supreme Court in Bhadra International (India) Pvt. Ltd.
& Ors. v. Airports Authority of India, 2026 INSC 6 dealt with the
following three issues:
“29….i. Whether the sole arbitrator could be said to
have become “ineligible to be appointed as
an arbitrator” by virtue of sub-section (5) of
Section 12 of the Act, 1996?
ii. Whether the parties could be said to have
waived the applicability of sub-section (5)
of Section 12 of the Act, 1996, by way of
their conduct, either expressed or implied?
iii. Whether the appellants could have raised an
objection to the appointment of the sole
arbitrator for the first time in an application
under Section 34 of the Act, 1996?”
Held:
“123…i.
The principle of equal treatment of parties
provided in Section 18 of the Act, 1996,
applies not only to the arbitral proceedings but
also to the procedure for appointment of
arbitrators. Equal treatment of the parties
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
entails that the parties must have an equal say
in the constitution of the arbitral tribunal.
ii. Sub-section (5) of Section 12 provides that any
person whose relationship with the parties or
counsel, or the dispute, whether direct or
indirect, falls within any of the categories
specified in the Seventh Schedule would be
ineligible to be appointed as an arbitrator.
Since, the ineligibility stems from the
operation of law, not only is a person having
an interest in the dispute or its outcome
ineligible to act as an arbitrator, but
appointment by such a person would be ex
facie invalid.
iii. The words “an express agreement in writing”
in the proviso to Section 12(5) means that the
right to object to the appointment of an
ineligible arbitrator cannot be taken away by
mere implication. The agreement referred to
in the proviso must be a clear, unequivocal
written agreement.
iv.
When an arbitrator is found to be ineligible by
virtue of Section 12(5) read with the Seventh
Schedule, his mandate is automatically
terminated. In such circumstance, an
aggrieved party may approach the court under
Section 14 read with Section 15 for
appointment of a substitute arbitrator.
Whereas, when an award has been passed by
such an arbitrator, an aggrieved party may
approach the court under Section 34 for
setting aside the award.
v.
In arbitration, the parties vest jurisdiction in
the tribunal by exercising their consent in
furtherance of a valid arbitration agreement.
An arbitrator who lacks jurisdiction cannot
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
make an award on the merits. Hence, an
objection to the inherent lack of jurisdiction
can be taken at any stage of the proceedings.”
6.2
The Division Bench of this court in Mahavir Prasad Gupta
and Sons v. Govt. of NCT of Delhi, 2025 SCC OnLine Del 4241
dealt with the following issues:
“74…a)
When a party itself has unilaterally appointed the
arbitrator, whether that party can object to the
unilateral appointment of the arbitrator at any
stage during or after the arbitration proceedings?
b)
If a party has unilaterally appointed an arbitrator,
can that party be deemed to have given express
waiver in writing under Section 12(5) of the Act
while making the appointment itself?”
The court concluded:
“84….a)
Mandatory Requirement: Any arbitration
agreement providing unilateral appointment of
the sole or presiding arbitrator is invalid. A
unilateral appointment by any party in the
arbitrations seated in India is strictly prohibited
and considered as null and void since its very
inception.
Resultantly,
any
proceedings
conducted before such unilaterally appointed
Arbitral Tribunal are also nullity and cannot
result into an enforceable award being against
Public Policy of India and can be set aside under
Section 34 of the Act and/or refused to be
enforced under Section 36 of the Act.
b) Deemed Waiver: The proviso to Section 12(5)
of the Act requires an express agreement in
writing. The conduct of the parties, no matter
how
acquiescent
or
conducive,
is
inconsequential and cannot constitute a valid
waiver under the proviso to Section 12(5) of the
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
Act. The ineligibility of a unilaterally appointed
arbitrator can be waived only by an express
agreement in writing between the parties after
the dispute has arisen between them. Section
12(5) of the Act is an exception to Section 4 of
the Act as there is no deemed waiver under
Section 4 of the Act for unilateral appointment
by conduct of participation in the proceedings.
The proviso to Section 12(5) of the Act requires
an „express agreement in writing‟ and deemed
waiver under Section 4 of the Act will not be
applicable to the proviso to Section 12(5) of the
Act.
c)
Award by an Ineligible Arbitrator is a
Nullity: An award passed by a unilaterally
appointed arbitrator is a nullity as the
ineligibility goes to the root of the jurisdiction.
Hence, the award can be set aside under Section
34(2)(b) of the Act by the Court on its own if it
„finds that‟ an award is passed by unilaterally
appointed arbitrator without even raising such
objection by either party.
d) Stage of Challenge: An objection to the lack of
inherent jurisdiction of an arbitrator can be taken
at any stage during or after the arbitration
proceedings including by a party who has
appointed the sole or presiding arbitrator
unilaterally as the act of appointment is not an
express waiver of the ineligibility under proviso
to Section 12(5) of the Act. Such objection can
be taken even at stage of challenge to the award
under Section 34 of the Act or during the
enforcement proceedings under Section 36 of the
Act.”
7.
After amendment of Section 12(5) of the Act an employee of
the party in dispute can neither be appointed arbitrator nor can
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
nominate or appoint any other person as an arbitrator. The unilateral
appointment in absence of express agreement in writing between the
parties to waive applicability of Section 12(5) of the Act is void ab
initio. The filing of the claim statement or participation in the
arbitration proceedings cannot be construed to be waiver under the
proviso to Section 12(5) of the Act. The unilateral appointment of the
arbitrator can be objected to for the first time under Section 34 of the
Act.
8.
Clause 25(2) of the conditions of the contract provides for
resolution of disputes except where the decision has attained finality
under clause 25(1). In case the disputes are not between two Public
Sector Enterprises or between a Public Sector Enterprise and a
Government Department, the Accepting Authority i.e. RITES within
thirty days on receipt of notice from the contractor is to send list of
three serving officers of RITES to be appointed as arbitrator. The
contractor within fifteen days of receipt of the list has to communicate
one of the names from the list. In case of failure of the contractor to
select the candidate within the stipulated period, RITES shall appoint
arbitrator from the list.
9.
The law is well settled that the official of a party to the dispute
can neither be appointed arbitrator nor appoint an arbitrator. In the
case in hand, the arbitrator was appointed by the petitioner from the
panel maintained by it. The Supreme Court in Central Organisation
for Railway Electrification v. ECI SPIC SMO MCML (JV), (2025)
4 SCC 641 held that curating a panel of arbitrators by one of the
parties to the dispute and requiring the other party to exercise its
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
choice from such a panel affects the freedom of the party to appoint
the arbitrator, thereby raising a reasonable doubt. The relevant
paragraphs are reproduced below:
“132. In Voestalpine [Voestalpine
Schienen
GmbH v. DMRC Ltd., (2017) 4 SCC 665 : (2017) 2
SCC (Civ) 607] and CORE [Central Organisation for
Railway
Electrification v. ECI-SPIC-SMO-MCML
(JV), (2020) 14 SCC 712] , one of the parties curated a
panel of arbitrators and mandated the other party to
select their arbitrator from the panel. Since the curation
of the list is exclusively undertaken by one party, the
other party is effectively excluded from the process of
curating the panel from which exclusively, the
appointment of an arbitrator is to be made. The other
party has to mandatorily select its arbitrator from a
curated panel, restricting their freedom to appoint an
arbitrator of their choice. This is against the principle
of equal treatment contained under Section 18. In this
situation, there is no effective counterbalance because
both parties do not participate equally in the process of
appointing arbitrators. The party curating the panel can
restrict the choice of the party only to a person who is
on the panel selected by the other party and to no other
person.
133. Many PSUs are regularly involved in arbitration
disputes and constantly need the services of arbitrators.
Such institutions often maintain a pool of potential
arbitrators with the sole object of having a ready pool
of qualified professionals who have committed their
time and consented to act as arbitrators for fixed fees.
The Arbitration Act does not prohibit parties to an
arbitration agreement from maintaining a curated panel
of potential arbitrators. However, the problem arises
when the PSUs make it mandatory for other parties to
select their nominees from the curated panel of
arbitrators. When a PSU exercises its discretion to
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
curate a panel, the very factor that the PSU is choosing
only a certain number of persons as potential
arbitrators and not others will raise a reasonable doubt
in the mind of a fair-minded person. The PSUs may
conceivably have nominated a person on the panel of
potential arbitrators because they have a certain
predisposition in favour of the former. This doubt is
reinforced when the other party is given no choice but
to select its arbitrator from the curated panel.
134. In CORE [Central Organisation for Railway
Electrification v. ECI-SPIC-SMO-MCML (JV), (2020)
14 SCC 712] , the three-member tribunal was sought to
be constituted in the following manner : (i) the
Railways would suggest at least four names of retired
railway officers; (ii) the contractor would select two
names out of the panel for appointment as their
arbitrator; (iii) The General Manager (of the Railways)
would thereafter choose at least one person out of the
two to be appointed as the contractor's arbitrator; and
(iv) The General Manager would proceed to appoint
the balance arbitrators from the panel or outside the
panel and also indicate the presiding arbitrator.
135. Such an arbitrator-appointment clause is likely to
give rise to justifiable doubts as to the independence
and impartiality of arbitrators for two reasons : (i) the
contractor is restricted to choosing its arbitrator from
the panel of four arbitrators nominated by the party
who is a disputant; and (ii) the contractor's choice is
further constrained because it is made subject to the
decision of the General Manager who will choose one
among the two persons suggested by the party. Since
the contractor has to select its arbitrator from a curated
panel, the arbitration clause does not allow the
contractor equal participation in the appointment of
their arbitrator. Moreover, the clause allows the
General Manager to appoint the balance arbitrators
from either the panel or outside the panel. Thus, the
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
process of appointing the arbitrators is unequal because
the General Manager can go beyond the panel of four
potential arbitrators, while the contractor is bound by
the names enlisted in the panel.”
10.
In view of the law laid down by the Supreme Court in Bhadra
International (India) Pvt. Ltd. (supra) and the decision of this Court
relied upon by the learned counsel for the petitioner, the appointment
of the arbitrator is in violation of the amended provisions of Section
12(5) of the Act.
11.
The issue now to be determined is as to whether after the
dispute arose was there an express waiver in writing by the parties that
the provisions of Section 12(5) of the Act will not apply.
12.
The Supreme Court in Bhadra International (India) Pvt. Ltd
(supra) held that waiver involves a conscious decision to abandon the
existing legal right and can be made only by a person fully aware of
such right. A legal right cannot be taken away by implications. The
waiver has to be an unequivocal expression and it cannot be lost sight
of that by such waiver the restriction imposed by Section 12(5) of the
Act is sought to be overcome.
13.
There is no prescribed format under the proviso to section 12(5)
of the Act for an express agreement in writing but it shall not mean
that the waiver can be inferred by implication or through conduct. It
would be relevant to quote the following paragraph from Bhadra
International (India) Pvt. Ltd. (supra):
“84. Undoubtedly, the statute does not prescribe a
format for the agreement. However, the absence of a
prescribed format cannot be construed to mean that
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
the waiver may be inferred impliedly or through
conduct. We say so because the legislature has
consciously prefaced the term “agreement” with the
word “express” and followed it with the phrase “in
writing”. This semantics denote the intention of the
legislature that the waiver under the proviso to
Section 12(5) must be made only through an express
and written manifestation of intention.”
14.
The respondent in the notice dated 03.06.2019 expressly stated
that after amendment of Section 12(5) of the Act, serving official of
RITES cannot be appointed arbitrator without consent of both the
parties and the respondent is not giving this consent. Once there is no
express consent in writing given under proviso to Section 12(5) of the
Act, the rigours of the amended provisions of Section 12(5) of the Act
are applicable. The option given to the respondent to select arbitrator
from the panel list of arbitrators being maintained by the petitioner is
not enough for wriggling out of the provisions of Section 12(5) of the
Act. The Supreme Court in Central Organisation for Railway
Electrification (supra) held that making the other party to select an
arbitrator from a curated panel is against the principle of equal
treatment contained in Section 18 of the Act.
15.
The matter needs to be considered from another angle. The
express consent in writing under proviso to Section 12(5) of the Act
has to be of both the parties. It is not a case set up by the respondent
that the petitioner consented for waiver of applicability of Section
12(5) of the Act. The waiver has to be expressed and cannot be
construed or inferred through conduct. The Division Bench of this
court in Mahavir Prasad Gupta and Sons (supra) held that an
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
appointment of an ineligible person as an arbitrator is void ab-initio
and can be challenged by the party making such appointment. The
relevant paragraphs of the judgment are:
“81. Accordingly, the party that unilaterally
appointed the arbitrator cannot be deemed to
have agreed in writing to waive the ineligibility
of the arbitrator by act of appointment. When
appointment itself is ineligible under the
provisions of Section 12(5) of the Act read with
Seventh Schedule of the Act, it does not take
away the right of the party to challenge such an
appointment merely because that party had made
the appointment in absence of express agreement
in writing between the parties to waive the
applicability of Section 12(5) of the Act.
82. Hence, a party which unilaterally appointed
the arbitrator has right to object to such
appointment irrespective of fact that that party
itself made the appointment of the arbitrator.
Mere fact of making appointment in writing will
not make the ineligible appointment a valid
appointment unless there is express agreement in
writing waiving such ineligibility.
83. Although it appears disingenuous, a party
appointing an the sole or presiding arbitrator
unilaterally can challenge the award on the
ground that the award has been rendered in
contravention of Section 12(5) of the Act read
with
Seventh
Schedule
of
the
Act
notwithstanding that the said party itself made
such an appointment. When the Arbitral
Tribunal inherently lacked jurisdiction to act, the
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
arbitration proceedings are void ab initio,
rendering the award unenforceable irrespective
of which party made such unilateral
appointment. The arbitral proceedings and an
award made by an unilaterally appointed sole or
presiding arbitrator, who is de jure ineligible to
be appointed as an arbitrator by virtue of the
Seventh Schedule of the Act are void ab initio.
The waiver under the proviso to Section 12(5) of
the Act must be express and subsequent to the
disputes having been arisen between the parties.
Hence, the party which appointed the sole or
presiding arbitrator unilaterally can also
challenge the award under Section 34 of the Act
on the ground of such ineligibility.”
16.
In the absence of compliance of proviso to Section 12(5) of the
Act by the parties, the appointment of the arbitrator by the petitioner is
vitiated as it violates Section 12(5) read with Seventh Schedule of the
Act. The appointment of the arbitrator is void ab-initio and renders the
impugned award nullity.
17.
The petition is allowed and the impugned award is set aside.
Pending application is also disposed of.
AVNEESH JHINGAN, J
MARCH 20, 2026/Pa
Reportable:- Yes
O.M.P. (COMM) 221/2023
Signed By:CHANCHAL
15:15:34
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review