WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
THE HIGH COURT OF MEGHALAYA AT
SHILLONG
: ORDER :
WRIT PETITION NO. 39 OF 2017
RCM Infrastructure Ltd., Versus Union of India and Others
Date of Order
::
29.03.2017
PRESENT
HON’BLE SHRI JUSTICE DINESH MAHESHWARI, CHIEF JUSTICE
Shri D. Saikia, Senior Advocate with Shri H Abraham, for the petitioner.
Shri N. Mozika, for the respondents.
BY THE COURT: (ORAL)
The petitioner company, having been awarded a contract by the
respondents for 34 construction works titled “PROVEN OF OTM ACCN
PHASE II AT RUPA” in the state of Arunachal Pradesh at a sum of Rs.
10,98,58,900/- under the acceptance letter dated 12.06.2013, has filed this
writ petition stating grievance against the acts and omissions on the part of
the respondents in not according extension of time for completion of work, in
not releasing the pending bills, and in not considering its representations.
The petitioner has averred that though the aforesaid contract was
awarded under the acceptance letter dated 12.06.2013 but the sites were
handed over much later and the site plans were approved even later. It is
averred that the petitioner started the construction work in the remote site at
Rupa, which is surrounded by hilly terrain with no infrastructure and road
connectivity, which made the work “cumbersome and time consuming”. It is
further averred that the climatic condition of the location was also quite
tough and difficult and there were reduced working hours; and all these
factors led to difficulties and delay in execution of the work. With these
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
nature averments, the petitioner has alleged that the delay has been caused
for the reasons beyond its control but the authorities concerned, instead of
granting extension, were threatening to cancel the contract and were not
even making the payment of the pending running account bills. The
summation of its case by the petitioner is as under:“The facts of the case in brief are that pursuant to a tender process
the petitioner was allotted the Acceptance Letter dated 12.06.13 for
the work „PROVEN OF OTM ACCN PHASE II AT RUPA‟ at a sum of
Rs. 10,98,58,900/- for 34 construction work, Thereafter the
respondent authorities handed over two work site for building
construction in October, 2013 and rest of the building sites were
handed over to the petitioner after a substantial delay, only in
November, 2014 and June, 2015. Further, the site plan was approved
by the respondent authorities only on 10.04.14. Immediately, the
petitioner started the construction work in the remote work site in
Rupa surrounded by hill terrain in the State of Arunachal Pradesh
where there is no proper infrastructure and roadways connecting the
work site causing difficulties in transporting goods, materials,
equipments etc. to the site which made the work cumbersome and
time consuming. That apart, the climatic condition of the said location
is far different from other States. There during the summers the
morning light comes at about 7 A.M. and it sets at about 5 P.M. and
during the winters the morning light come at about 8/9 a.m. and it sets
at about 4 p.m. and thus the workable hours in the said area is only 5
to 6 hours in comparison to other locations where it is minimum 8
hours. Further there is no proper electricity and water supply in that
area and skilled labors are also not available. The materials have to
be procured from other states and transported to the work site by first
unloading in Bhalukpong and then transporting in small vehicles to the
work site due to deplorable road conditions. Incorporating all the
aforesaid facts the petitioner intimated the authorities vide letter dated
10.03.2015 about the reasons for delay in execution of the work.
However, the authorities without considering the matter in its right
perspective warned the petitioner vide letter dated 09.07.15 of
cancelling the work order if the work was not expedited and completed
as per the time schedule. Subsequently, after much persuasion the
respondent authorities vide letter dated 16.12.15 granted extension of
time till 31.07.16. And during this period there were several
correspondences between the petitioner and the respondent
authorities regarding procurement of materials and reinforcement of
labors, which the petitioner complied as per their satisfaction.
Thereafter the petitioner again submitted a letter dated 30.07.16
praying for further extension of reasonable time. On 25.08.16 a
meeting/discussion was held with the Chief Engineer, Eastern
Command Kolkatta and accordingly submitted letter dated 25.08.16
assuring to complete 60% of the work subject to release of RAR bills
and undertook to complete the project work within the specified time
limit mention in the said letter against each work. Considering the said
letter the respondent authorities vide letter dated 04.10.16 granted
final chance till 31.10.16 for completion of target work of 6%.
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
Accordingly, the petitioner after achieving the target of 6% informed
the authorities vide letter dated 05.11.16 about the same and further
prayed for extension of time. However, the respondent authorities with
some malafide intention deliberately under-assessed the progress of
wok of the petitioner as below 6% and threatened to cancel the
contract work. Lastly, in the last week of December the Chief Engineer
MES on his visit to the work site directed the petitioner to stop the
construction work and threatened to issue the cancellation order and
since then, the work is at stand still with all the materials and
machineries lying idle and thereby causing serious prejudice and loss
to the petitioner. The petitioner again submitted a letter/petition dated
12.01.17 before the respondent authorities narrating the reasons for
delay which were beyond the control of the petitioner and prayed for
allowing it to complete the work by further extension of time by one
year and the said petition is pending consideration till date. The
petitioner against all odd was continuing with the construction work
inspite of such difficult terrain and climatic conditions and the delay
has been caused for reasons beyond the control of the petitioner. That
apart there has been substantial delay on the part of the respondent
authorities in handling over the work sites and approval of the site
plan and the revised site plan for which there was delay in
commencement of the construction work and as such the petitioner
cannot be faulted for their lapses. However, the respondent authorities
without considering the above aspects of the matter are initiating steps
for cancellation of the contract and holding up the RAR bills due in a
most arbitrary, illegal, unjust and unreasonable manner which is exfacie illegal and untenable in the eye of law.
Hence the present petition seeking adequate relief.”
The petitioner has also stated its grievance that further work is not
being allowed to be executed, while stating the nature and extent of work
done in the following:“That out of the total 33 work item of the contract work, the petitioner
has already completed substantial work in 13 major construction items
and they are in the verge of completion. As regards work item No. 5
relating to construction of servant quarter, the authorities are yet to
allot the work site. As regards item 17, same will be started as soon as
the officer‟s mess building is complete. Regarding item no. 20
construction of pump house, the authorities are yet to dismantle the
electrical pole and underground electrical cables. Regarding item No.
21 and 22 relating to construction of soak well and septic tank, some
can be started only after completion of the other major office buildings
provided the authorities timely show the area where the lines are to be
placed. Item No. 23 may not be required to execute. Item 24 to 33,
which are petty works, are to be executed only after completion of the
major construction work. Thus, execution of major construction works
is already in the verge of completion and the other work items can be
completed within a short span of time after the major works are over.
As such at this stage if the work order is cancelled/terminated the
petitioner will be highly prejudiced and incur huge loss and same
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
would affect the reputation of the petitioner company. That apart all
the machineries and materials are lying idle in the work site and if they
remain so for a long time they will get damage which will cause
immense loss to the petitioner. Further, after few months the rainy
season will start and it will be difficult to expedite the work due to bad
weather conditions at that time of the season. Thus, it is prayed to
allow continuation of the construction work by grating a reasonable
extension of time considering the bonafide reasons site by the
petitioner and for the greater benefits of the work in hand at large.”
The petitioner has also suggested that the cancellation of contract
would further delay the work in question and, on the contrary, if reasonable
extension was granted to it, the work would be completed within reasonable
time but the authorities were not considering the matter in a just and fair
manner. With these submissions, it is averred that the impugned actions of
the respondents infringe upon the fundamental rights guaranteed under
Articles 14, 19(1)(g) and 21 of the Constitution of India; and the petitioner,
having no alternative efficacious remedy, has approached this Court. The
petitioner has prayed for the reliefs in the following manner:
“Under the aforesaid facts and circumstances, it is, therefore, most
humbly prayed that Your Lordship would be pleased to admit this
petition, call for records, issue a rule calling upon the respondents to
show cause as to why,
i)
a writ in nature of Mandamus should not be issued directing the
respondent authorities not to cancel the contract of the petitioner
allotted vide acceptance letter dated 12.06.13 (Annexure-A) and/or, as
to why,
ii)
a writ in nature of Mandamus should not be issued directing the
respondent authorities to grant reasonable and fair extension of time
of further one year for completion of the contract work, and/or, as to
why,
iii)
a writ in nature of Mandamus should not be issued directing the
respondents to consider the petition/letter dated 15.09.16 and
12.01.17 (Annexure U & Y, pg 80 – 83, 108 – 111), and/or, as to why
iv)
a direction should not be issued to immediately release /pay the
RAR bill amounting to Rs. 93,53,000/- due to the petitioner,
And, after perusal of the records, upon hearing the parties and
after showing cause or causes, if any, make the Rule absolute,
granting full relief to the petitioner as prayed for and/or may pass any
such order/s as Your Lordship may deem fit and proper in the interest
of justice.”
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
This petition was initially considered on 08.03.2017 when, after finding
that the matter related to the execution of work under the contract, the Court
posed the query about existence of arbitration clause in the agreement. In
response, learned counsel for the petitioner though frankly admitted that the
agreement in question carried an arbitration clause, but submitted that the
petitioner has a just and appropriate case to invoke the writ jurisdiction of
this Court. However, at request, the matter was adjourned.
Now, the learned counsel for the petitioner has vehemently argued
that alternative remedy is not of that absolute bar and in the present matter,
even if relating to execution of a contract, grievance of the petitioner
deserves to be examined in the writ jurisdiction. The learned counsel has
particularly emphasised and reiterated on his submissions that no major
factual dispute is involved in the matter and the essential issue being that of
reasonable extension of time for execution, the respondents deserve to be
called upon to submit their reply to the averments taken in the petition. The
learned counsel has referred to and relied upon the decisions of the Hon’ble
Supreme Court in Whirlpool Corporation v. Registrar of Trade Marks,
Mumbai and others : (1998) 8 SCC1; Harbanslal Sahnia and Another v.
Indian Oil Corpn. Ltd. and others : (2003) 2 SCC 107; Union of India and
others v. Tantia Construction Private Limited : (2011) 5 SCC 697; and
Ram Barai Singh and Company v. State of Bihar and others : (2015) 13
SCC 592. The learned counsel has also pointed out that as per the
arbitration clause contained in the agreement between the parties, in the
event of cancellation of the contract, reference cannot be made to the
arbitration until alternative arrangements are made by the Government; and
in the present case, this stage having not arrived, the arbitration clause
cannot be said to be available and operating at this juncture.
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
The learned counsel for the petitioner has strenuously argued that the
petitioner cannot be held solely responsible for all the delays when the
respondents did not hand over and did not clear the sites for a long length of
time and then, took more than one and a half years before giving the
approved plans. The learned counsel has particularly referred to the
representation dated 12.01.2017 (Annexure – Y) as also the previous
representations dated 15.09.2016 (Annexure – U) and dated 05.11.2016
(Annexure – X) to submit that the petitioner had indicated a substantial
execution of work and asked for reasonable extension of time but the
representations have not been attended at and have not been answered by
the respondents. Learned counsel has also attempted to refer to the copies
of certain photographs, allegedly of the sites in question, to suggest that a
substantial work has been carried out and the petitioner deserves to be
given an opportunity to complete the work and the respondents deserve to
be restrained from cancelling the contract. The learned counsel has also
submitted that in any case, a direction deserves to be issued to the
respondents to consider the representations already made by the petitioner.
Learned counsel for the respondents, on the other hand, has
questioned the maintainability of this writ petition with the submissions that
the matter directly involves such questions of facts that cannot be
determined in the writ jurisdiction and then, there exists arbitration clause in
the agreement for resolution of disputes. The learned counsel would submit
that the contract in question was awarded to the petitioner in the month of
June 2013 with the stipulated date of completion as 07.07.2015 but looking
to the various circumstances, one year’s extension was given to the
petitioner until 31.07.2016 and yet further extension was given until
31.10.2016 but the petitioner could not complete the work; and as per his
instructions, as on 31.01.2017, the petitioner had executed only about
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
28.15% of the awarded work and the respondents were taking steps for
cancellation of the contract when this petition came to be filed.
Having given thoughtful consideration to the submissions made with
reference to the law applicable and having examined the record, this Court
is not persuaded to entertain this writ petition.
There remains hardly any doubt that the present matter is clearly the
one concerning execution of a contract work. As noticed from the averments
taken, the petitioner seeks to indicate several so called factors wherefor, the
work in question could not have been executed within the stipulated time
including the allegation that even some of the sites were handed over only in
the month of November, 2014 and June, 2015 and the site plans were
approved only on 10.04.2014. The petitioner has also indicated the factors
that the sites in question are located in remote areas with no proper
accessibility. The petitioner has alleged that for different timings of
availability of sunlight because of location of the sites in the far east, the
working hours were reduced. The petitioner has also alleged that there was
no proper infrastructure in the area and skilled labourers were also not
available. Even while referring to these factors, the petitioner has admitted
that the authorities had indeed granted extension of time by about one year
and until 31.07.2016; and thereafter, the petitioner got another chance until
31.10.2016 for completion of the target work of 6%. It is submitted that after
having achieved the target work, the submissions were made for further
extension of time but the authorities are not granting such extension and
rather, the petitioner is being asked to stop the work. Learned counsel for
the petitioner, while particularly referring to paragraph 11 of the
representation dated 12.01.2017, has argued that the petitioner has
completed a substantial amount of work and deserves to be granted further
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
extension of time. The said paragraph 11 of the representation reads as
under:
“11. We have already completed about 80/90% of works in most of the sites
and the rest of the works are also in full progress and expect to complete
the work within this year if further unwarranted hindrances are not made by
the authorities which effects the smooth execution of the work. In the site
always MES, official are saying that our work will be cancel by which most
labourers are left the site and the progress of work hampered. Thus, it is
prayed for grating further one year time for completion of the work and if
such extension is granted, we undertake to complete the work within the
extended period. In anticipation of your positive response.”
Learned counsel for the respondents, while asserting that the
petitioner has completed only about 28.15 % of the awarded work as on
31.01.2017, has submitted that the suggestions as made in paragraph 11 of
the representation are rather contradicted by the very opening paragraph of
the
same
representation.
This
opening
paragraph
in
the
same
representation dated 12.01.2017, as referred by the learned counsel for the
respondents, could also be taken note as under:
“With due respect we would like to bring to your kind attention that we have
been awarded the PROV OF OTM ACCN (Phase-II) AT RUPA work on
06.07.2013. But the work sites were handed over to us after about one year
as a result there was delay in starting the work. However, inspite of all odds
we have completed about 31% of the awarded work. This completion status
of 31% is based on the total project cost and if we only take civil works, than
our progress is more than 60%. It is pertinent to mention herein that the
building work is only worth Rs. 4 crore, out of the total contract value of Rs.
10.98 crores. We deeply regret the delay caused in the completion of the
work which is for the reasons stated herein below:-”
It is at once clear that the petitioner-company itself has made different
submissions as regards the percentage of work done with reference to the
so called “awarded work” (31%); the so called “civil works” (60%) and “most
of the sites” (80/90%). Learned counsel for the petitioner would submit that
the substantial work executed by the petitioner could be seen from the
copies of the photographs annexed with the petition.
The submissions aforesaid have been taken note of only to indicate
that the matter relates to such basic questions of fact which cannot be
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
determined in the writ jurisdiction of this Court. As to whether the particular
factors were of practical hindrance in execution of the work and whether the
requisite steps were taken by the petitioner to deal with such factors would
entail an enquiry into several aspects concerning facts. This would also
remain a question for consideration as to whether the petitioner would not be
deemed to have taken all the local factors into account while making an offer
for the contract in question. The so called photographs cannot by
themselves make out percentage of work carried out and reference to the
same practically carries no meaning for the purpose of the present petition.
In an overall comprehension of the matter, it is but clear that the
petitioner seeks to suggest existence of certain facts and seeks issuance of
writ of prohibition and mandamus in this contractual matter on that basis but
then, as per the petitioner’s own showing the work has not been completed;
and the petitioner lastly prayed for an extension of time for about one year. It
would always remain a question of fact as to how much work the petitioner
has executed and, if the contract has not been performed as required, who
is to be held responsible for the non-performance and/or breach of contract.
These issues by their very nature, involve determination of the questions of
facts on the basis of evidence; and, ordinarily, such a determination is not
carried out in the writ jurisdiction of this Court.
There cannot be any quarrel with the principles of law enunciated by
the Hon’ble Supreme Court in the decisions referred by the learned counsel
for the petitioner. In the case of Whirlpool Corporation (Supra), the Hon’ble
Supreme Court, even while pointing out that the existence of alternative
remedy is not of that absolute bar and the writ petition can be entertained in
exceptional circumstances, has expounded as followed:
“ 15. Under Article 226 of the Constitution, the High Court, having regard to
the facts of the case, has a discretion to entertain or not to entertain a writ
petition. But the High Court has imposed upon itself certain restrictions one
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
of which is that if an effective and efficacious remedy is available, the High
Court would not normally exercise its jurisdiction. But the alternative remedy
has been consistently held by this Court not to operate as a bar in at least
three contingencies, namely, where the writ petition has been filed for the
enforcement of any of the Fundamental Rights or where there has been a
violation of the principle of natural justice or where the order or proceedings
are wholly without jurisdiction or the vires of an Act is challenged. There is a
plethora of case-law on this point but to cut down this circle of forensic
whirlpool, we would rely on some old decisions of the evolutionary era of the
constitutional law as they still hold the field.
16. Rashid Ahmed v. Municipal Board, Kairana laid down that existence of
an adequate legal remedy was a factor to be taken into consideration in the
matter of granting writs. This was followed by another Rashid case, namely,
K.S. Rashid & Son v. Income Tax Investigation Commission which
reiterated the above proposition and held that where alternative remedy
existed, it would be a sound exercise of discretion to refuse to interfere in a
petition under Article 226. This proposition was, however, qualified by the
significant words, “unless there are good grounds therefor”, which indicated
that alternative remedy would not operate as an absolute bar and that writ
petition under Article 226 could still be entertained in exceptional
circumstances.
17. A specific and clear rule was laid down in State of U.P. v. Mohd. Nooh
as under:
“But this rule requiring the exhaustion of statutory remedies before
the writ will be granted is a rule of policy, convenience and discretion
rather than a rule of law and instances are numerous where a writ of
certiorari has been issued in spite of the fact that the aggrieved party
had other adequate legal remedies”.
18. This proposition was considered by a Constitution Bench of this Court in
A.V. Venkateswaran, Collector of Customs v. Ramchand Sobhraj Wadhwani
and was affirmed and followed in the following words:
“The passages in the judgments of this Court we have
extracted would indicate (1) that the two exceptions which the
learned Solicitor General formulated to the normal rule as to the
effect of the existence of an adequate alternative remedy were by no
means exhaustive, and (2) that even beyond them a discretion
vested in the High Court to have entertained the petition and granted
the petitioner relief notwithstanding the existence of an alternative
remedy. We need only add that the broad lines of the general
principles on which the Court should act having been clearly laid
down, their application to the facts of each particular case must
necessarily be dependent on a variety of individual facts which must
govern the proper exercise of the discretion of the Court, and that in
a matter which is thus pre-eminently one of discretion, it is not
possible or even if it were, it would not be desirable to lay down
inflexible rules which should be applied with rigidity in every case
which comes up before the Court”.
19. Another Constitution Bench decision in Calcutta Discount Co. Ltd, v.
ITO, Companies Distt. 1 laid down:
“Though the writ of prohibition or certiorari will not issue against an
executive authority, the High Courts have power to issue in a fit case an
order prohibiting an executive authority from acting without jurisdiction.
Where such action of an executive authority acting without jurisdiction
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
subjects or is likely to subject a person to lengthy proceedings and
unnecessary harassment, the High Courts will issue appropriate orders or
directions to prevent such consequences. Writ of certiorari and prohibition
can issue against the Income Tax Officer acting without jurisdiction under
Section 34, Income Tax Act.”
20. Much water has since flown under the bridge, but there has been no
corrosive effect on these decisions which, though old, continue to hold the
field with the result that law as to the jurisdiction of the High Court in
entertaining a writ petition under Article 226 of the Constitution, in spite of
the alternative statutory remedies, is not affected, specially in case where
the authority against whom the writ is filed is shown to have had no
jurisdiction or had purported to usurp jurisdiction without any legal
foundation.”
In the case of Tantia Construction Pvt. Ltd., (Supra), the Hon’ble
Supreme Court reiterated the principles that alternative remedy was not that
of absolute bar in exercise of writ jurisdiction while observing as under:
“33. Apart from the above, even on the question of maintainability of the
writ petition on account of the arbitration clause included in the agreement
between the parties, it is now well established that an alternative remedy is
not an absolute bar to the invocation of the writ jurisdiction of the High Court
or the Supreme Court and that without exhausting such alternative remedy,
a writ petition would not be maintainable. The various decisions cited by Mr.
Chakraborty would clearly indicate that the constitutional powers vested in
the High Court or the Supreme Court cannot be fettered by any alternative
remedy available to the authorities. Injustice, whenever and wherever it
takes place, has to be struck down as an anathema to the rule of law and
the provisions of the Constitution.
34.
We endorse the view of the High Court that notwithstanding the
provisions relating to the arbitration clause contained in the agreement, the
High Court was fully within its competence to entertain and dispose of the
writ petition filed on behalf of the respondent Company. We, therefore, see
no reason to interfere with the views expressed by the High Court on the
maintainability of the writ petition and also on its merits.”
Again, in Harbanslal Sahnia‟s case, the Hon’ble Supreme Court
delineated the principles that in an appropriate case, the High Court can still
exercise writ jurisdiction, particularly if the case relates to the enforcement of
fundamental rights, or failure of principles of justice, or where the orders or
proceedings are wholly without jurisdiction or the vires of an Act is
challenged. The Hon’ble Supreme Court, inter alia, observed as under:
“7. So far as the view taken by the High Court that the remedy by way of
recourse to arbitration clause was available to the appellants and therefore
the writ petition filed by the appellants was liable to be dismissed is
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
concerned, suffice it to observe that the rule of exclusion of writ jurisdiction
by availability of an alternative remedy is a rule of discretion and not one of
compulsion. In an appropriate case, in spite of availability of an alternative
remedy, the High Court may still exercise its writ jurisdiction in atleast three
contingencies: (i) where the writ petition seeks enforcement of any of the
fundamental rights; (ii) where there is failure of principles of natural justice;
or (iii) where the orders or proceedings are wholly without jurisdiction or the
vires of an Act is challenged. (See Whirlpool Corpn. V. Registrar of Trade
Marks (1998) 8SCC 1). The present case attracts applicability of the first
two contingencies. Moreover, as noted, the petitioners dealership, which is
their bread and butter, came to be terminated for an irrelevant and nonexistent cause. In such circumstances, we feel that the appellants should
have been allowed relief by the High Court itself instead of driving them to
the need of initiating arbitration proceedings”.”
In the case of Ram Barai Singh and Company (Supra), the Hon’ble
Supreme Court reiterated the law that existence of arbitration clause in an
agreement does not ipso facto render the writ petition not maintainable,
while observing as under:“11.In our view, a constitutional remedy by way of writ petition is always
available to an aggrieved party and an arbitration clause in an agreement
between the parties cannot ipso facto render a writ petition “not
maintainable” as wrongly held by the Division Bench. Availability of
alternative remedy is definitely a permissible ground for refusal by a Writ
Court to exercise its jurisdiction in appropriate cases. But once the
respondents had not objected to entertainment of the writ petition on ground
of availability alternative remedy, the final judgment rendered on merits
cannot be faulted and set aside only on noticing by the Division Bench that
an alternative remedy by way of arbitration clause could have been resorted
to.”
In the case of Joshi Technologies International INC. v. Union of
India and others : (2015) 7 SCC 728, after referring to several of the
landmark decisions including the one in Whirlpool Corporation (Supra), the
Hon’ble Supreme Court has summarised the principles relating to the writ
jurisdiction in the contractual matters in the following:
“69. The position thus summarised in the aforesaid principles has to be
understood in the context of discussion that preceded which we have
pointed out above. As per this, no doubt, there is no absolute bar to the
maintainability of the writ petition even in contractual matters or where there
are disputed questions of fact or even when monetary claim is raised. At the
same time, discretion lies with the High Court which under certain
circumstances, it can refuse to exercise. It also follows that under the
following circumstances, “normally”, the Court would not exercise such a
discretion:
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
69.1. The Court may not examine the issue unless the action has
some public law character attached to it.
69.2. Whenever a particular mode of settlement of dispute is
provided in the contract, the High Court would refuse to exercise its
discretion under Article 226 of the Constitution and relegate the party to the
said mode of settlement, particularly when settlement of disputes is to be
resorted to through the means of arbitration.
69.3. If there are very serious disputed questions of fact which are
of complex nature and require oral evidence for their determination.
69.4. Money claims per se particularly arising out of contractual
obligations are normally not to be entertained except in exceptional
circumstances.”
In the aforesaid decision in Joshi Technologies International (Supra),
the Hon’ble Supreme Court has also pointed out the ordinary course of
action in case of the alleged breach of contract in the following:
“70.6. Ordinarily, where a breach of contract is complained of, the party
complaining of such breach may sue for specific performance of the
contract, if contract is capable of being specifically performed. Otherwise,
the party may sue for damages.”
As noticed, the present matter directly relates to such questions of fact
which would require oral and documentary evidence for determination and
otherwise, there is no public law character involved in the present matter
relating to execution of work under a contract. Thus, looking to the overall
circumstances, this Court is not persuaded to entertain the matter in the writ
jurisdiction. Apart from the above, it is also clear that the agreement
between the parties specifically provides for arbitration as the mode of
resolution of dispute. The arbitration clause in the agreement in question
reads as under:
“70. Arbitration.- All disputes, between the parties to the Contract (other
than those for which the decision of the C.W.E. or any other person is by the
Contract expressed to be final and binding) shall, after written notice by
either party to the Contract to the other of them, be referred to the sole
arbitration of an Engineer officer to be appointed by the authority mentioned
in the tender documents.
Unless both parties agree in writing such reference shall not take
place until after the completion or alleged completion of the Work or
termination or determination of the Contract under Condition Nos. 55,56 and
57 hereof.
Provided that in the event of abandonment of the Works or
cancellation of the Contract under Condition Nos. 52,53 and 54 hereof, such
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
reference shall not take place until alternative arrangements have been
finalized by the Government to get the Works completed by or through any
other Contractor or Contractors or Agency or Agencies.
Provided always that commencement or continuance of any
arbitration proceeding hereunder or otherwise shall not in any manner
militate against the Government‟s right of recovery from the contractor as
provided in Condition 67 hereof.
If the Arbitrator so appointed resigns his appointment or vacates his
office or is unable or unwilling to act due to any reason whatsoever, the
authority appointing him may appoint a new Arbitrator to act in his place.
The Arbitrator shall be deemed to have entered on the reference on
the date he issues notice to both the parties, asking them to submit to him
their statement of the case and pleadings in defence.
The Arbitrator may proceed with the arbitration, exparte, if either
party, inspite of a notice from the Arbitrator fails to take part in the
proceedings.
The Arbitrator may, from time to time with the consent of the parties,
enlarge, the time upto but not exceeding one year from the date of his
entering on the reference, for making and publishing the award.
The Arbitrator shall give his award within a period of six months
from the date of his entering on the reference or within the extended time as
the case may be on all matters referred to him and shall indicate his
findings, along with sums awarded, separately on each individual item of
dispute.
The venue of Arbitration shall be such place or places as may be
fixed by the Arbitrator in his sole discretion.
The award of the Arbitrator shall be final and binding on both parties to the
Contract.”
The learned counsel for the petitioner has argued with reference to
the first proviso in the arbitration clause that in the event of cancellation of a
contract, the arbitration will not take place until finalisation of alternative
arrangement by the Government and thus, at the present stage, the said
clause cannot be said to be applicable. This argument does not make out a
case for entertaining the matter in the writ jurisdiction for the simple reason
that when the arbitration has been chosen as the mode of resolution of
dispute and the particular methodology for invoking the arbitration clause
has been provided in the agreement itself, as to whether the reference could
be made at present or is to wait until the happening of certain events, by
itself, does not render the clause nugatory; and it cannot be said that the
arbitration as a mode of resolution of dispute is not available to the petitioner
in accordance with the Arbitration and Conciliation Act, 1996.
WP (C) NO. 39 OF 2017
RCM Infrastructure Ltd., v. Union of India & Ors
This Court would not make any further comment in the matter
because the issue being considered herein is limited to the question as to
whether the present petition seeking issuance of writ of prohibition and
mandamus be entertained or not? The answer to this question is in the
negative for the reasons already indicated above.
Learned counsel for the petitioner has in the last made a fervent plea
that at least directions may be issued to the respondents to take a decision
on its representations. As noticed, the present one is a matter concerning
contract and in relation to such a contractual matter, it cannot be said that
any statutory representation has been made so as to call for a mandamus to
the respondents for a decision thereupon. In the totality of circumstances of
the case, this Court is not persuaded even to issue any direction to the
respondents in relation to the representation made by the petitioner seeking
further extension of time. In relation to any legal grievance in that regard,
this Court would only leave it open for the petitioner to take recourse to
appropriate proceedings in accordance with law.
For what has been discussed and observed hereinabove, exercise of
writ jurisdiction in this matter is declined and this writ petition stands
dismissed. However, in the interest of justice, it is made clear that none of
the observations herein shall be construed as any expression on the merits
of the case by this Court either way and any recourse to any other remedy
by the petitioner shall be dealt with in the appropriate forum strictly in
accordance with law.
CHIEF JUSTICE
Sylvana
Item No. SL. 1
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review