IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 24.09.2026
#
CNR No. DLHC010827972025
+
FAO (COMM) 300/2025, CM APPL. 67104/2025 & CM
APPL. 19367/2026
RAVINDER KUMAR TYAGI
Through:
.....Appellant
Mr. Sunil Dutt Dixit & Mr.
Amit Mishra, Advs.
versus
POONAM MATHARU & ORS.
.....Respondents
Through: Mr. Manoj Kumar, Adv. for R1, 2 & 4 (through VC).
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
HON'BLE MS. JUSTICE SHAIL JAIN
AVNEESH JHINGAN, J. (ORAL)
1.
This appeal under Section 37 of the Arbitration and
Conciliation Act, 1996 (for short ‘the Act’) is filed against the order
dated 28.08.2025 (for short ‘impugned order’) passed by the learned
District Judge (Commercial Court) Tis Hazari Courts, Delhi
(hereinafter ‘the commercial court’) dismissing the objections under
Section 34 of the Act (hereinafter referred to as ‘objections’) as timebarred.
BRIEF FACTS
2.
The brief facts are that a dispute relating to sale and purchase of
Signed By:HONEY FAO (COMM) 300/2025
ARORA
16:56:06
a plot was referred to arbitration at the instance of Sh. Om Prakash,
respondent no.4. The appellant was impleaded in the arbitration
proceedings. The grievance that impleadment of the appellant was a
misjoinder was rejected on 31.10.2014. The arbitration proceedings
culminated in award dated 15.01.2015. The copy of the award was
served to the appellant on 29.01.2015. The objections were filed
before this court on 26.05.2015 and the registry on 27.05.2015 pointed
out defects but neither the defects were removed nor the objections
were re-filed.
2.1
On 17.05.2024, the appellant received summons from the
executing court. On 06.07.2024, the appellant filed objections before
the commercial court along with an application for condonation of
delay. On 24.07.2024, another objection petition was filed before this
court but the registry on 25.07.2024 prepared a scrutiny report and
raised an issue of maintainability.
2.2
The commercial court after calling for the record from this court
passed the impugned order dismissing the objections being timebarred.
SUBMISSIONS OF THE PARTIES
3.
Learned counsel for the appellant contends that the commercial
court erred in dismissing the application for condonation of delay. The
contention is that it was not considered that the counsel through whom
the objections were filed before this court on 26.05.2015 had neither
communicated the status of the proceedings nor rectified the defects
pointed out by the registry. The argument is that on receipt of the
Signed By:HONEY FAO (COMM) 300/2025
ARORA
16:56:06
summons from the executing court on 17.05.2024 the appellant
approached the earlier counsel to check the status of the objections.
On return of the original case file by learned counsel on 10.06.2024,
within reasonable time the objections along with an application for
condonation of delay were filed before the commercial court on
06.07.2024.
3.1
It is emphasised that enhancement of the pecuniary jurisdiction
of this court to rupees two crores on 26.10.2015 added to the
confusion as to whether the objections were to be filed before this
court or before the commercial court. The submission is that the initial
filing on 26.05.2015 was not non-est and should be considered for
condoning the delay.
3.2
It is canvassed that there was no arbitration agreement between
the appellant and respondent no.4, it is a case of fraud and in the
absence of an arbitration agreement the award cannot be enforced. The
submission is that there is no limitation in a case of fraud. Reliance is
placed upon the decision of the Supreme Court in State of Uttar
Pradesh & Anr. v. R.K. Pandey & Anr. 2025 INSC 48.
3.3
The decision of the Supreme Court in Rafiq & Anr. Vs.
Munshilal & Anr. (1981) 2 SCC 788 is pressed into service to fortify
the contention that the appellant should not be made to suffer due to
the conduct of the counsel.
4.
Per contra, this court has the power to condone the delay only
up to thirty days beyond the period of three months prescribed under
Section 34(3) of the Act. The delay is of more than nine years and
Signed By:HONEY FAO (COMM) 300/2025
ARORA
16:56:06
there is no just explanation for it. The submission is that the appellant
was negligent in pursuing the remedy and adopted delaying tactics to
harass the other party and to keep the property in dispute in litigation.
ANALYSIS
5.
Before proceedings further, it would be relevant to reproduce
Section 34(3) of the Act:
“34. Application for setting aside arbitral award.
***
***
***
(3) An application for setting aside may not be made
after three months have elapsed from the date on which
the party making that application had received the
arbitral award or, if a request had been made under
section 33, from the date on which that request had been
disposed of by the arbitral tribunal:
Provided that if the Court is satisfied that the applicant
was prevented by sufficient cause from making the
application within the said period of three months it may
entertain the application within a further period of thirty
days, but not thereafter.”
6.
Section 34(3) of the Act is unambiguous that an application
under Section 34 of the Act is to be filed within three months from the
date of receipt of the award. The court may upon sufficient cause
being shown, entertain the application within a further period of thirty
days but not thereafter. Reference in this regard be made to the
following decisions of the Supreme Court:
6.1
In P. Radha Bai & Ors. Vs. P. Ashok Kumar & Anr, (2019) 13
SCC 445 held as under:
“33.2. The proviso to Section 34(3) enables a court to
Signed By:HONEY FAO (COMM) 300/2025
ARORA
16:56:06
entertain an application to challenge an award after the
three months' period is expired, but only within an
additional period of thirty days, "but not thereafter". The
use of the phrase "but not thereafter" shows that the 120
days' period is the outer boundary for challenging an
award. If Section 17 were to be applied, the outer
boundary for challenging an award could go beyond 120
days. The phrase "but not thereafter" would be rendered
redundant and otiose. This Court has consistently taken
this view that the words "but not thereafter" in the
proviso of Section 34(3) of the Arbitration Act are of a
mandatory nature, and couched in negative terms, which
leaves no room for doubt.
6.2
In Simplex Infrastructure Ltd. V. Union of India, (2019) 2
SCC 455 held as under:
“18. A plain reading of sub-section (3) along with the
proviso to Section 34 of the 1996 Act, shows that the
application for setting aside the award on the grounds
mentioned in sub-section (2) of Section 34 could be made
within three months and the period can only be extended
for a further period of thirty days on showing sufficient
cause and not thereafter. The use of the words “but not
thereafter” in the proviso makes it clear that the extension
cannot be beyond thirty days. Even if the benefit of
Section 14 of the Limitation Act is given to the
respondent, there will still be a delay of 131 days in filing
the application. That is beyond the strict timelines
prescribed in sub-section (3) read along with the proviso
to Section 34 of the 1996 Act. The delay of 131 days
cannot be condoned. To do so, as the High Court did, is
to breach a clear statutory mandate.
(emphasis supplied)
7.
The award was received by the appellant on 29.01.2015. The
objections were filed before this court on 26.05.2015. The defects
Signed By:HONEY FAO (COMM) 300/2025
ARORA
16:56:06
pointed out in scrutiny by the registry on 27.05.2015 were neither
removed nor the objections were re-filed. The appellant took no steps
in the matter for about nine years. On receipt of summons from the
executing court in 2024, earlier objections filed were not pursued but
fresh objections were filed before the commercial court along with an
application for condonation of delay. Even thereafter, another fresh
objection petition was filed before this court on 24.07.2024. The
objection regarding maintainability raised by the registry on
25.07.2024 was not rectified and the petition was not re-filed. This
court cannot condone the delay beyond thirty days. The appellant after
remaining inactive for about nine years and not bringing the
objections filed in 2015 to logical end cannot take advantage of the
earlier filing to overcome the period of limitation for the fresh filing of
objections before the commercial court in 2024.
8.
The contention of the appellant that there is no limitation in a
case of fraud cannot be gone into as there are no requisite pleadings of
fraud in the objections. The contention that there was no arbitration
agreement between the parties is an issue on merit to be considered if
the objections are entertained after condoning the delay. Once the
award was received by the appellant the period prescribed under
Section 34(3) of the Act commenced.
9.
The reliance on the decision of the Supreme Court in R.K.
Pandey & Anr. (supra) does not advance the case of the appellant. In
that case, the Supreme Court considered the validity and
enforceability of arbitral awards in the context of execution
Signed By:HONEY FAO (COMM) 300/2025
ARORA
16:56:06
proceedings under Section 47 of the Code of Civil Procedure, 1908.
The decision does not deal with condonation of delay beyond the
period prescribed under Section 34(3) of the Act.
10.
Another aspect is that the original case file was returned by the
earlier counsel on 10.06.2024 but the objections filed in 2015 were not
even thereafter re-filed instead, fresh objections were filed before the
commercial court in July 2024. Even the fresh objections filed before
this court on 24.07.2024 were not pursued.
11.
The contention of the learned counsel for the appellant that the
initial filing dated 26.05.2015 was not a non-est filing is of no avail. It
is not a case of condoning delay in re-filing but a case where the
objections filed were left unattended and after more than nine years
the appellant chose to file fresh objections.
12.
The submission regarding enhancement of the pecuniary
jurisdiction of this court on 26.10.2015 does not explain the failure of
the appellant to re-file the objections after removing the defects
pointed out by the registry on 27.05.2015. The change in pecuniary
jurisdiction took place after the objections had already been returned
for removal of defects and for nine years the appellant remained in
slumber.
13.
The commercial court rightly held that it had no jurisdiction to
condone the delay beyond thirty days. Even otherwise, there is no
reasonable explanation for condoning the delay of nine years. The
Supreme Court in Oriental Aroma Chemical Industries Limited v.
Gujarat Industrial Development Corporation & Anr., (2010) 5 SCC
Signed By:HONEY FAO (COMM) 300/2025
ARORA
16:56:06
459 held that though a liberal approach may be adopted in considering
short delays but a stricter approach is to be taken where the delay is
inordinate. The relevant para of the judgement is reproduced below:
“15. The expression "sufficient cause" employed in
Section 5 of the Limitation Act, 1963 and similar other
statutes is elastic enough to enable the courts to apply the
law in a meaningful manner which subserves the ends of
justice. Although, no hard-and-fast rule can be laid down
in dealing with the applications for condonation of delay,
this Court has justifiably advocated adoption of a liberal
approach in condoning the delay of short duration and a
stricter approach where the delay is inordinate-Collector
(L.A.) v. Katiji, N. Balakrishnan v. M. Krishnamurthy
and Vedabai v. Shantaram Baburao Patil.”
(emphasis supplied)
14.
The reliance on the decision of the Supreme Court in Rafiq
(supra) is not applicable to the facts of the present case. The appellant
remained inactive for nine years after the defects were pointed out by
the registry. The Supreme Court in Rajneesh Kumar & Anr. V. Ved
Prakash, 2024 SCC OnLine SC 3380 after considering the case of
Rafiq (supra) held that negligence of the counsel by itself cannot be a
ground to condone long and inordinate delay. The litigant is also
required to remain vigilant about the rights and proceedings. The
relevant paragraph of the judgment is reproduced below:
“10. It appears that the entire blame has been thrown on
the head of the advocate who was appearing for the
petitioners in the trial court. We have noticed over a
period of time a tendency on the part of the litigants to
blame their lawyers of negligence and carelessness in
attending the proceedings before the court. Even if we
Signed By:HONEY FAO (COMM) 300/2025
ARORA
16:56:06
assume for a moment that the concerned lawyer was
careless or negligent, this, by itself, cannot be a ground to
condone long and inordinate delay as the litigant owes a
duty to be vigilant of his own rights and is expected to be
equally vigilant about the judicial proceedings pending in
the court initiated at his instance. The litigant, therefore,
should not be permitted to throw the entire blame on the
head of the advocate and thereby disown him at any time
and seek relief.”
(emphasis supplied)
DECISION
15.
In view of the above, no case is made out for interference under
Section 37 of the Act. The appeal is dismissed.
16.
Pending applications also stand dismissed.
AVNEESH JHINGAN, J
SHAIL JAIN, J
SEPTEMBER 24, 2026
‘ha’
Reportable: Yes
Signed By:HONEY FAO (COMM) 300/2025
ARORA
16:56:06
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.