IN THE HIGH COURT OF JAMMU & KASHMIR AND
LADAKH AT SRINAGAR
Reserved on:
10.07.2025
Pronounced on: 14.08.2025
CRM(M) No.729/2024
c/w
CRM(M) No.721/2024
RAMAN PURI
HINDUSTAN CONSTRUCTION COMPANY LTD.
... PETITIONER(S)
Through: - Mr. Z. A. Shah, Sr. Advocate, with
Mr. Arif Sikandar, Advocate (in CRM(M) No.721/2024)
Mr. Syed Faisal Qadiri, Sr. Advocate, with
Mr. Salih Pirzada, Advocate (in CRM(M) No.729/2024)
Vs.
SENIOR SUPERINTENDENT OF POLICE
AND OTHERS
…RESPONDENT(S)
Through:-
Mr. Mohsin Qadiri, Sr. AAG, with
Ms. Nadiya Abdullah, Assisting Counsel, vice
CORAM:
HON’BLE MR. JUSTICE SANJAY DHAR, JUDGE
JUDGMENT
1)
Through the medium of this common judgment,
afore-titled two petitions filed under Section 528 of BNSS
challenging FIR No.23/2024 for offences under Section
5(1)(d) read with 5(2) of J&K Prevention of Corruption Act
[for short “the PC Act”] and Section 120-B of RPC
registered with Police Station Anti-Corruption Bureau,
Srinagar, are proposed to be disposed of. Petition bearing
CRM(M) No.721/2024 has been filed by M/S Hindustan
Construction Company Ltd whereas petition bearing
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
CRM(M) No.729/2024 has been filed by Shri Raman Puri,
retired Chief Engineer.
2)
As per the impugned FIR, communication dated
15.09.2023 along with a communication from the office of
Advocate General, J&K, relating to award of payments in
respect to construction of Mughal Road from Bafliaz to
Shopian
Pulwama
was
received
by
the
respondent
Investigating Agency. Vide the said communication, it was
conveyed that Arbitral Tribunal has passed an award to
the tune of Rs.21,52,66,414/ on account of principal sum
along with interest to the tune of Rs.11,27,40,624/
against which the State has filed a petition under Section
34 of the Arbitration and Conciliation Act. It was further
conveyed that
during pendency of the case, when the
matter was argued by the learned Advocate General before
the High Court, it was noticed that the claimant company
has based its entire claim upon a letter dated 18.10.2014
wherein the then Chief Engineer purportedly had admitted
the claims of the company which was controverted by the
Department. It was further conveyed to the respondent
Investigating Agency that the matter involves serious
financial stake resulting in huge loss to the government
exchequer.
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
3)
The respondent Investigating Agency conducted a
preliminary
verification
and
during
the
course
of
verification, it came to the fore that on 15.03.2005,
tenders for construction of
through
Joint
Mughal Road were floated
Commissioner,
Works/Chief
Engineer,
Mughal Road Project, PWD(R&B) Department and after
following due procedure, the work for the an estimated
amount of Rs.2.14,40,00,000/ was allotted to
M/S
Hindustan
after
Construction
approval/recommendation
Company
of
the
Ltd.
State
Contract
Committee. Accordingly, an agreement to this effect was
executed vide agreement No.61-PW(R&B) of 2006 on
06.02.2026, wherein the date of commencement of works
was mentioned as 01.03.2006 and the date of completion
was fixed as 36 months i.e. 28.02.2009. It was also found
that
a
supplementary
agreement
was
drawn
on
25.01.2010 for an estimated amount of Rs.126.64 crores
with the date of completion as 31.03.2011. The extension
of time in completion of the project was granted upto
15.02.2012. It was also found that when the petitioner
company could not complete the project within the
prescribed time limit, it raised the issue with regard to
grant of extension of time for its reference to the Arbitrator
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
and, accordingly, the matter was referred to the Arbitral
Tribunal.
4)
During verification, it was revealed that the critical
document, on the basis of which award for claim
No.(iii)was granted by the Arbitral Tribunal, was a
communication dated 18.10.2014 of M/S Hindustan
Construction Company upon which
the
then Chief
Engineer, Shri Raman Puri, had recorded his remarks
pertaining to certain conditions which were bearing his
signatures. It was found that Shri Raman Puri was
interacting/meeting with the representatives of M/S
Hindustan Construction Company Ltd. outside his office.
The aforesaid communication was treated as mutual
acceptance of conditions contained therein by the Arbitral
Tribunal. It was found that these mutual conditions were
casually processed without following codal procedure with
an intention to extract undue benefit in the form of claim
No.(iii) which was conceived by drafting the conditions
clandestinely in violation of the terms of the agreement. It
was also found that the then Chief Engineer in connivance
with
M/S Hindustan Construction Company Ltd. took
undue advantage of prior escalation clause and signed a
letter which was drafted on the letter head of the
Construction
Company
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
thereby
agreeing
to
mutual
conditions including acceptance of prior escalation for the
period with effect from 15.02.2012 to 31.12.2012, which
resulted in arbitration award of Rs.21.52 crores plus
11.27 crores in favour of M/S Hindustan Construction
Company Ltd. and corresponding loss to the government
exchequer.
5)
It is alleged in the impugned FIR that by acting in the
aforesaid manner, the then Chief Engineer, PWD(R&B),
Shri Raman Puri (petitioner in CRM(M) No.729/2024), by
abuse of his official position and in conspiracy with
beneficiary company, exceeded his power/competence and
accepted the terms and conditions of the contractor M/S
Hindustan Construction Company Ltd. (petitioner in
CRM(M) No.721/2024) which formed basis of the award
dated 28.03.2019 passed by the Arbitral Tribunal thereby
conferring undue benefit to the company with extension
of time for which no prior order/communication was
issued. It is alleged that by this action of petitioner Raman
Puri,
the
State
was
prevented
from
imposition
of
liquidated damages to the tune of Rs.54.00 crores on the
petitioner company for its inability to complete the
projected within the stipulated time. Thus, according to
the Investigating Agency, offences under Section 5(1)(d)
read with Section 5(2)of the J&K PC Act and Section120-B
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
of RPC stand established against petitioner Raman Puri,
the then Chief Engineer, Mughal Road Project, PWD(R&B)
and petitioner-M/s Hindustan Construction Company
Limited.
6)
The
petitioner
M/S
Hindustan
Construction
Company Ltd. has challenged the impugned FIR and the
proceedings emanating therefrom on the grounds that the
material
on
record
establishes
that
there
was
no
conspiracy between the petitioner company and the Chief
Engineer.
It
has
been
further
contended
that
the
respondent Investigating Agency has suppressed the
material documents, which, in fact, prove that there was
no conspiracy between the petitioner company and the
Chief Engineer. It has been further contended that the
issues raised by the respondent Investigating Agency in
the impugned FIR were adjudicated upon by the Arbitral
Tribunal, whereafter an arbitral award came to be passed
in favour of the petitioner company, which is presently
under challenge before the Court of learned Principal
District Judge, Srinagar. According to the petitioner
company, lodging of the impugned FIR is nothing but an
abuse of process of law as respondent No.2-Department is
trying to wriggle out of the arbitral award passed against
it. It has been contended that no undue benefit has
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
accrued to the petitioner company on the basis of the
mutually
agreed
terms
contained
in
letter
dated
18.10.2014.
7)
It has been further contended that the aforesaid
letter was within the knowledge of respondent No.2 (the
complainant) ever-since the year 2015 but in spite of this,
it did not lodge any complaint with regard to authenticity
of the said letter during all these years and it is only after
having suffered the arbitral award, that communication
dated 15.09.2023 came to be addressed by it to the
respondent Investigating Agency. It has been contended
that the object of lodging impugned FIR is only to scuttle
the arbitration proceedings which are pending at the stage
of
challenge
under
Section
of
Arbitration
and
Conciliation Act.
8)
It has also been contended that the contentions
raised in the impugned FIR have been adjudicated upon
by the learned Arbitral Tribunal and, as such, the
respondent Investigating Agency cannot sit over the award
passed by the learned Arbitral Tribunal. Finally, it has
been contended that the dispute which is subject matter
of the impugned FIR is purely of civil nature and that
there is delay of nine years in lodging the complaint by
respondent
No.2
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
which
has
not
been
satisfactorily
explained and, therefore, the impugned FIR and the
proceedings emanating therefrom deserve to be quashed.
9)
Petitioner Raman Puri has, besides challenging the
impugned FIR and the proceedings emanating therefrom
on the aforesaid grounds, further contended that the
terms and conditions contained in communication dated
18.10.2014 have not been refuted by the Government
during arbitration proceedings and vide communication
dated 21.09.2016, the Government has only disputed
point
No.(ii)
contained
in
communication
dated
18.10.2014. It has been further contended that the entire
discussion on record was within the knowledge of the
Government and petitioner Raman Puri had conveyed the
same to the Government vide his communication dated
19.05.2015.
10)
The respondents in their reply to the petitions,
besides narrating the allegations made in the impugned
FIR, have submitted that that during the course of
investigation,
the
record
pertaining
to
verification
conducted, on the basis of which impugned FIR was
lodged, was seized. It has been submitted that the
statements of the witnesses are to be recorded and the
records are to be sought from the petitioner company and
the Presiding Arbitrator. It has been contended that the
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
final extension of time was granted to the petitioner
company upto 15.02.2012 and despite there being
no
further extension, the petitioner company continued to
execute the work upto 31.12.2012. Thus, there was a
delay of approximately ten months in execution of the
work. It has been submitted that as per the terms and
conditions of the contract, it was the responsibility of the
department to assess the delay and implement the
penalties in the form of liquidated damages for the period
beyond 15.02.2012. However, no such penalty was
enforced on account of the terms contained in letter dated
18.10.2014. It has been submitted that the said letter
raises concerns about its legitimacy. It has been further
submitted that until 19.05.2015, when petitioner Raman
Puri addressed his communication to the government, no
formal response or clarification was sought by him and
this inaction of the department allowed the petitioner
company to rely on communication dated 18.10.2014 and
it
pursued
the
arbitration
proceedings
by
misrepresentation of facts.
11)
According to the respondents, the scope of the
criminal investigation initiated against the petitioners is
beyond the scope and ambit of arbitration and because
cognizable offences are, prima facie, disclosed against the
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
petitioners, as such, the criminal proceedings have to go
ahead.
It
has
been
contended
that
the
criminal
proceedings operate in a separate domain and are not
barred merely because there is a civil suit or arbitration
proceedings going on. It has also been contended that the
findings of the Arbitral Tribunal are not determinative of
criminal
liability
Investigating
and,
Agency
as
such,
cannot
be
the
respondent
precluded
from
undertaking investigation of the case.
12)
Regarding delay in lodging the FIR, the respondent
Investigating Agency
has submitted that it was made
aware about the allegations of criminal misconduct only
on 15.09.2023 when it received vital documents and
information
from
the
respondent
department
and
immediately thereafter, verification of the allegations was
undertaken, thus, there is no delay in lodging of the FIR.
It has been contended that petitioner Raman Puri was not
having
authority
and
competence
to
enter
into
negotiations with the construction company so as to alter
the terms and conditions of the contract and it is only
with the approval of the competent authority that he could
have entered into negotiations for altering the terms and
conditions of the contract. Therefore, petitioner Raman
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
Puri has clearly abused his official position with a view to
confer undue benefit upon the petitioner company.
13)
I have heard learned counsel for the parties and
perused the material on record.
14)
The dispute, which has given rise to the present
proceedings, owes its origin to contract agreement dated
08.02.2006 executed between the petitioner company and
respondent PWD(R&B) Department for construction of
Mughal Road from Bafliaz District Poonch to Shopian
(Pulwama). The original date of completion of the project
was
28.02.2009.
It
appears
that
a
supplementary
agreement was executed between the parties in March,
2009, whereby the date of completion was extended to
31.03.2011. Another extension was granted for completion
of the project upto 15.02.2012. However, the project was
completed only on 31.12.2012. Regarding extension of
time upto 15.02.2012, it appears that the petitioner
company had filed an arbitration claim for damages on
account of alleged delays caused by the employer for an
amount of Rs.103.92 crores.
15)
The record shows that at this stage, communication
dated
18.10.2014
was
addressed
by
the
petitioner
company to the Chief Engineer of the project. This
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
communication is the critical document, on the basis of
which the present proceedings have originated. The
contents of the said communication are reproduced as
under:
The Chief Engineer
Mughal Road Project
Lalmandi, Srinagar
Sub: Construction of Mughal Road from Bafliaz (Poonch) to
Shopian (Pulwama): Defect Liability Certificate - reg
Ref Your letter no. CEMRP/1228-32 dated 17.10.2014
Dear Sir,
At the outset we take this opportunity to thank you for the
issue of the Defect Liability Certificate and release of the bank
guarantees which marks a significant event with regard to the
satisfactory closure of the project.
However, we would like to clarify that the issue of Defect
Liability Certificate was consequent to the discussions mutually
agreed between the Contractor and Employer with the following
understanding:
1. The whole of the works shall be treated as completed
with effect from 31.12.2012
2. The escalation payment for the works executed beyond
15.02.2012 shall be regulated as per the indices
prevailing during 15.02.2012.
3. The employer shall not resort to invocation of liquidated
damages clause for the period between 15.02.2012 to
31. 12. 2012.
4. The Contractor will not pursue his claim for extension of
time (which is subject matter of Arbitration) in view of
point no. 3 above.
5. The Contractor shall also not pursue the claim for extra
cost for the period from 15.02.2012 to 31.12. 2012.
The aforesaid understanding and agreement between the
Contractor and Employer is placed on recordfor the sake of good
order and record to ensure that the Contractor and Employer are in
a position to give effect to the mutually agreed suggestions for
closure of the project
Thanking you and assuring you all our cooperation.
Yours faithfully.
For Hindustan Construction Co. Ltd
Sunil Bagga
Project In-charge
Copy
1. The Superintending Engineer, Mughal Road Project, Lalmandi,
Srinagar.
2 The Executive Engineer, Mughal Road Division. Shopian.
3 The Executive Engineer, Mughal Road Division, Bafliaz.
“The conditions S.No. 1 o 5 agreed by the Deptt”
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
(Endorsement in the handwriting of Chief Engineer)
Sd/
Chief Engineer Raman Puri
18.10.2014
16)
In terms of the aforesaid communication, petitioner
Raman Puri had agreed to conditions at serial Nos.1 to 5
on behalf of the department. As is clear from these
conditions, the department had treated the works to be
completed with effect from 31.12.2012, the contractor had
agreed to receive payment for the works executed even
beyond 15.02.2012 on the basis of indices prevailing
during 15.02.2012, meaning thereby that the petitioner
company had given up its claim in respect of price
escalation beyond 15.02.2012. As per condition No.3, the
department had given up its claim regarding liquidated
damages between 15.02.212 to 31.12.2012. As per
condition No.4, the petitioner company had agreed to
forego its claim which was subject matter of arbitration
and it had also agreed to give up its claim for extra cost for
the period between 15.02.2012 to 31.12.2012. From this it
is clear that the petitioner company and the Chief
Engineer had mutually agreed to certain conditions, some
of which were beneficial to the contractor and the others
of which were beneficial to the department.
17)
During the arbitration proceedings, the petitioner
company
while
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
projecting
its
claims
against
the
respondent department placed reliance upon the aforesaid
communication dated 18.10.2014. A perusal of the
arbitral award passed by the Arbitral Tribunal reveals that
while considering the claims of the petitioner company
and the statement of defence given by the department, the
learned Arbitral Tribunal framed the following issues:
Issue No.1: Whether it is factually correct that
discussions took place between the
claimant and the respondent’s Chief
Engineer and both had agreed to certain
conditions?
Issue No.2: Whether any of the mutually agreed
terms were bad in law?
Issue No.3: What was the agreement between the
parties with respect to the price
adjustment/price escalation?
Issue No.4: Whether the respondent has estopped
from acting otherwise from that what
was agreed to mutually? If yes, then
whether the doctrine of promissory
estoppel
will
act
against
the
respondent?
18)
While deciding issue No.1, the Arbitral Tribunal
concluded that discussions had taken place between the
claimant and the Chief Engineer and that both had agreed
to
the
terms
contained
in
communication
dated
18.10.2014. While deciding issue No.2 quoted above, the
Arbitral Tribunal concluded that the agreement reached
between the parties vide communication dated 18.10.2014
is not vague, unfeasible or against the law. The Arbitral
Tribunal while deciding issue No.3 concluded that there
was an agreement between the parties with respect to
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
price adjustment payment and that the price adjustment
payment was payable to the petitioner company till
31.12.2012. The award of the Arbitrator further reveals
that while deciding issue No.4, the Tribunal had opined
that a promise enforceable by law was made by the
respondent department to the claimant in terms of letter
dated 18.10.2014 and even if the said promise was made
without formal consideration, the claimant had relied
upon the said promise and the respondent department
backed out of the said promise in respect of price
adjustment/price escalation payments.
19)
It is pertinent to mention here that in the statement
of claims put up by the petitioner company before the
Arbitral Tribunal, a specific mention was made about
alleged
mutually
agreed
terms
contained
in
communication dated 18.10.2014 in paras (3.8) to (3.10)
of the claim petition, which are reproduced as under:
3.8) Later, the Claimant vide letter no. 2263
dated 18.10.2014 had placed on record the
mutually agreed conditions between the
Claimant and Respondent for closure of the
project. In doing so, the Respondent was
fully aware that the Claimant had given up
some of his claims/extended numbers of
concessions in respect of the financial
benefits
to
the
Respondent.
The
Respondent had also given its acceptance
to mutually agreed conditions in the said
letter dated 18.10.2014. The relevant
excerpt from the agreement is reproduced
below:
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
1.) The whole of the works shall be treated
as completed with effect from 31.12.2012.
2.) The escalation payment for the works
executed beyond 15.02.2012 shall be
regulated as per the indices prevailing
during 15.02.2012
3.) The Employer shall not resort to
invocation of liquidated damages clause for
the period between 15.02.2012 to
31.12.2012.
4.) The Claimant will not pursue his claim
for extension of time (which is subject
matter of Arbitration) in view of point no. 3
above.
5.) The Claimant shall also not pursue the
claim for extra cost for the period from
15.02.2012 to 31.12.2012.
…..The conditions Sl. No. 1 to
5 agreed by the Dept. (C.E.)"
A copy of the Claimant's letter no. 2263
dated 18.10.2014 is enclosed herewith as
Exhibit C-3/3.
3.9) Thus, the Claimant had given
up/agreed to forego his entitlements under
point no. 2, 4 & 5. The conditions agreed
upon were subject to the Respondent's
acceptance on point no. 1, 2 & 3, which
was agreed to by the Respondent on
18.10.2014.
3.10.) From the above agreement, it is
evident that the issue of price adjustment
was settled between the parties in following
manner:-
20)
i.
The escalation payment for the works
executed beyond 15.02.2015 shall be
regulated as per the indices
prevailing during 15.02.2012, and
ii.
In view of the agreement on point no.
1, 3, 4 & 5, it is settled that the issue
of extension of time till 31.12.2012 is
no longer a dispute. Accordingly, the
price adjustment is payable till
31.12.2012.
In answer to the aforesaid assertions of the petitioner
company, the respondent department, in its statement of
defence, responded in the following manner:
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
3.7 to 3.9) In reply to para 3.7 to 3.9 it is
submitted here that there has been no
mutual agreement alleged. There nothing
on record to suggest that there has been
any prior meeting of minds on the subject
which has been given a formal shape in
the shape of formal agreement. The
communication placed record by on the
claimant cannot be construed as that of
an agreement any legal having force.
The communication is not part of the
contract. In fact, the farce of respondent
having rescinded from the so called
mutually agreed terms as being projected
by the claimant, is only an anxious
attempt by the claimant to raise such
claims which are otherwise barred by
law, in addition to being in complete
derogation from the terms of contract
agreement.
3.10 to 3.21) In reply to the averments
made in it is submitted here the paras
3.10 to 3.21, that there being no
agreement which is legal and in
accordance with law, claimant cannot
claim that there is an issue of price
adjustment which is required to be settled
between the parties. The stand taken by
the claimant contrary to the terms and
conditions under of the contract All as per
the It is law is not permissible. admissible
price variations/escalation have been
paid to the claimant formula and indices
applicable. submitted here that revised
rates cannot be made applicable to the
works completed and paid before
publication of rates with base year of
2004-2005 became effective. It is
specifically denied that the respondent
had certified the price adjustments as per
the revised index. The objections raised
by the claimant cannot be taken note of
and were found without any merit as the
payments were made strictly in
accordance with the terms and
conditions. of contract as well as the
price adjustment due at the time of
payment.
21)
From the above, it is clear that the respondent
department had raised a specific plea before the learned
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
Arbitrator that there was no formal agreement between the
parties whereby the conditions contained in letter dated
18.10.2014
were
accepted
and
that
the
said
communication is not part of the contract. In fact, the
respondent department had disputed the legality of the
said communication. Therefore, the Arbitral Tribunal was
seized of the issue as to whether communication dated
18.10.2014 has been formulated by a competent person or
whether the terms and conditions contained therein are
binding
upon
the
respondent
department.
After
considering these issues, the learned Arbitral Tribunal
came to the conclusions as narrated hereinbefore.
22)
The respondent department, while challenging the
arbitral award dated 28.03.2019 by way of a petition
under Section 34 of the J&K Arbitration and Conciliation
Act, 1977 has specifically raised the contention that letter
dated 18.10.2014 has no legal value on which the
claimant could have relied upon. It has also been
contended by the respondent department in its petition
u/s 34 of the Act of 1997 that the Chief Engineer could
not have accepted/altered the conditions of contract of his
own and that the contents of the communication are
contrary to the terms and conditions of the contract. The
respondent department has gone one to contend that the
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
said letter is in-effective, in-operational and not binding
upon it.
23)
From the above narration of the facts, which are not
in dispute, it is clear that legality and validity of letter
dated 18.10.2014 was subject matter of adjudication
before the Arbitral Tribunal and it is presently subject
matter of adjudication before the Court in proceedings
under Section 34 of the Arbitration and Conciliation Act.
The question that arises for determination is as to whether
it would be open to the respondent Investigating Agency to
launch criminal prosecution against the petitioners on the
basis of the same very letter.
24)
The legal position on the aforesaid aspect has been
deliberated upon by the Supreme Court and various High
Courts of the Country in a number of precedents. The
Supreme Court in the case of Paramjeet Batra vs. State
of Uttarakhand, (2013) 11 SCC 673, has held that, while
a complaint disclosing civil transaction may also have a
criminal texture to it yet the High Court has to see
whether a dispute, which is essentially of a civil nature,
has been given a cloak of criminal offence. In this regard it
would be apt to refer to the observations made by the
Supreme Court in para (12) of the said judgment, which
read as under:
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
“12.While exercising its jurisdiction under Section
482 of the Code the High Court has to be
cautious. This power is to be used sparingly and
only for the purpose of preventing abuse of the
process of any court or otherwise to secure ends
of justice. Whether a complaint discloses a
criminal offence or not depends upon the nature
of facts alleged therein. Whether essential
ingredients of criminal offence are present or not
has to be judged by the High Court. A complaint
disclosing civil transactions may also have a
criminal texture. But the High Court must see
whether a dispute which is essentially of a civil
nature is given a cloak of criminal offence. In such
a situation, if a civil remedy is available and is, in
fact, adopted as has happened in this case, the
High Court should not hesitate to quash criminal
proceedings to prevent abuse of process of
court.”
25)
A similar view has been taken by the Supreme Court
in the case of Usha Chakraborty and Anr. vs. State of
West Bengal and Anr,2023 SCC OnLine SC 90.
26)
In Sarabjit Kaur vs. State of Punjab and Anr,
(2023) 5 SCC 360, the Supreme Court, while drawing a
distinction between an offence of cheating and a mere
breach of contractual obligation, held that every breach of
contract would not give rise to the offence of cheating and
it is required to be shown that the accused had fraudulent
or dishonest intention at the time of making the promise.
27)
From the foregoing analysis of law on the subject, it
is clear that a particular set of facts can give rise to both
civil consequences as well as a criminal offence. Therefore,
a duty is cast upon the High Court while exercising its
powers under Section 528 of BNSS to ascertain from the
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
allegations made in the FIR/complaint or the material
collected by the Investigating Agency as to whether
criminal proceedings have been initiated with an oblique
motive so as to give a criminal colour to a purely civil
dispute. If it is found that from the material on record a
particular fact situation would give rise to both remedies
under criminal law as well as in civil law, then both the
remedies can be pursued by the aggrieved person as the
object of the criminal law is to punish the offender who
commits an offence whereas the object of the civil law
remedy is to provide monetary compensation to the person
wronged.
28)
With the aforesaid legal position in mind, let us now
advert to the facts of the present case. As has been
already noted, the bone of contention between the parties
is the communication dated 18.10.2014. While the
respondent department claims that petitioner Raman Puri
was not competent to vary the terms of the contract
unless he had the approval of the competent authority,
the petitioner company claims that the Chief Engineer was
the authorized signatory and had, in fact, signed the
contract on behalf of the government, as such, he was
authorized to execute the aforesaid letter. It is also the
case of the petitioner company that the respondent
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
department has raised objection only with respect to one
of the agreed terms contained in letter dated 18.10.2014
and they have not disputed the authenticity of the said
communication as a whole.
29)
All the aforesaid rival contentions that have been
raised by the parties are also the subject matter of arbitral
award and are presently subject matter of adjudication in
a petition under Section 34 of the Arbitration and
Conciliation Act, which is pending before the learned
District Judge. The allegation made in the impugned FIR
that petitioner Raman Puri had no authority to vary the
terms and conditions of the contract as contained in letter
dated 18.10.2014, is a matter of adjudication in the
arbitration proceedings. Similarly, the question whether
the
respondent
department
was
entitled
to
claim
liquidated damages from the petitioner company was also
a subject matter of adjudication before the Arbitral
Tribunal and is now subject matter of arbitration before
the District Judge in Section 34 proceedings.
30)
If the respondent Investigating Agency is allowed to
investigate the aforesaid aspects of the matter, it would
amount to permitting the said agency to sit in appeal over
the
findings
impermissible
of
the
Arbitral
Tribunal,
which
is
in law. If the respondent Investigating
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
Agency is allowed to proceed with the investigation of the
case, there may be a situation where ultimately the
arbitral proceedings may end up in a judgment in favour
of the petitioner company but still it will have to face the
criminal prosecution despite its
stand having been
vindicated by the courts at various levels. If the result of
the arbitration proceedings goes against the petitioner
company, in that case there would be no loss to the State
exchequer on account of execution of letter dated
18.10.2014 by petitioner Raman Puri as the petitioner
company would not be entitled to any compensation from
the department and the department would be entitled to
recover liquidated damages from the petitioner company
provided the same is permissible under the terms of the
agreement. Thus, in both the eventualities, no offence can
be stated to have been made out against the petitioner
and, as such, the petitioners cannot be prosecuted for a
criminal offence in respect of a matter which appears to be
purely civil in nature.
31)
The Supreme Court in the case of Prakash Aggarwal
vs Ganesh Benzoplast Limited and another, (2023) 20
SCC 323, while being seized of an issue of somewhat
similar nature, dealt with the legal position on the said
issue in an elaborate manner. In the said case, the
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
Supreme Court while agreeing with the proposition that
where a complainant participates in the arbitration
proceedings and an arbitral award has been passed which
was under challenge under Section 34 of the Arbitration
and Conciliation Act at the instance of the complainant,
continuation of the criminal proceedings would amount to
abuse of process of law, observed as under:
35. It is thus clear that Respondent 1 complainant
was having knowledge of the sale of shares in the
year 2001 itself when the arbitration proceedings
were initiated. In the complaint, it is alleged that,
during the pendency of the arbitration
proceedings, Respondent 1 complainant became
suspicious of the illegalities committed by the
accused persons/appellants and sought for
certain information. However, since the accused
persons/appellants did not give the information,
Respondent 1 complainant applied to Bombay
Stock Exchange (for short “BSE”) and National
Stock Exchange (for short “NSE”) in the year
2006 for details of sale of its shares by the
accused persons/appellants on 24-8-2001, 31-82001, 3-9-2001 and 12-9-2001. It is stated in the
complaint that only thereafter, in the year 2006,
Respondent 1 complainant came to know of the
fact that most of the shares were sold at the
closing time of the share market and at the lowest
price of the day. It is averred that, only at that
point in time, Respondent 1 complainant came to
know that the shares were sold by the accused
persons/appellants to their own companies.
36. It could thus be seen that, though Respondent
1 complainant was aware about the sale of
shares as early in the year 2001, he did nothing
till the year 2006 when, according to it, it had
applied to BSE and NSE for details. Even after
the year 2006, Respondent 1 complainant waited
till the year 2011 to lodge the complaint. Though,
it is sought to be urged by Respondent 1
complainant before us that it came to know about
the
fraudulent
act
of
the
accused
persons/appellants in the year 2009, which gave
a cause of action to it to file the complaint, there
is no averment to that effect in the complaint.
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
37. Insofar as the other contention that the shares
were sold at a lesser price than the market price
is concerned, there is no averment in the
complaint in that regard. In any case, the
transactions have been made through the BSE
and NSE. As such, the contention in that regard is
without substance. In any case, a specific finding
has been given by the learned arbitrator in that
regard. As already informed to us, the said
arbitral award is under challenge in the
proceedings under Section 34 of the Arbitration
Act. We do not wish to observe anything about
the merits or demerits of the said award as the
competent court is seized of the same.
38. However, it would clearly reveal that
Respondent 1 complainant has attempted to turn
a purely contractual dispute between the parties
into a criminal case. Not only that, there is an
inordinate delay in lodging the complaint. Though
Respondent 1 complainant was aware about the
sale of the shares in the year 2001, it did not do
anything except filing an application before the
learned arbitrator. According to Respondent 1
complainant, it received the information from the
BSE and NSE in the year 2006, which fortified its
suspicion about the fraud being played. Even
thereafter, for a period of 5 years, it was silent
and filed the complaint only in the year 2011. As
already stated hereinabove, though an attempt
was made at the time of hearing to contend that it
has only filed the complaint after it came to know
about the fraud in the year 2009, there is no
averment to that effect in the complaint.
39. We find that the complaint, taken at its face
value, does not disclose that any of the
ingredients of the offence complained of have
been made out. In the totality of the
circumstances, we find that the present complaint
is nothing else but an abuse of process of law.
We, therefore, find that the appeals deserve to be
allowed.
32)
From the foregoing analysis of law on the subject, it
is
clear
that
once
the
allegations
made
in
the
complaint/FIR have been adjudicated upon by way of an
arbitral award, which is under challenge in proceedings
under Section 34 of the Arbitration and Conciliation Act,
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
the attempt of the respondent department to turn a purely
contractual dispute into a criminal case cannot be
sustained.
33)
There is yet another aspect of the matter which is
required to be noticed. The letter, which is subject matter
of
controversy,
has
been
issued
on
18.10.2014.
Admittedly, petitioner Raman Puri had sought clarification
from the department about the said letter on 19.05.2015
and thereafter, during arbitration proceedings, existence
of letter dated 18.10.2014 had come to the notice of the
respondent department and, in fact, they responded to the
same in their statement of defence which they filed before
the
learned
Arbitral
Tribunal
on
28.12.2017.
The
respondent department suffered the arbitral award after
the legality and validity of the said letter was deliberated
upon and determined by the Arbitral Tribunal vide its
award dated 28.03.2019. All along during this period, the
respondent department slept over the matter and did not
choose to file any complaint with regard to letter dated
18.10.2014 before any authority including the respondent
Investigating Agency. It seems that the respondent
department, with a view to avoid the arbitral award which
had been passed against it, has, on the basis of the letter
addressed by the learned Advocate Genera, proceeded to
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
lodge the impugned FIR, which, in the facts and
circumstances of the case, appears to be nothing but a
ploy to create a defence against the arbitral award.
34)
The Supreme Court has, in Prakash Agarwal’s case
(supra),
while
dealing
with
circumstances,
proceeded
to
somewhat
quash
the
similar
criminal
proceedings. The effect of delayed lodging of the complaint
has been dealt with by the Supreme Court paras (35) to
(37) of the said judgment, which have already been
reproduced hereinbefore.
35)
When we apply the aforesaid legal position to the
facts of the present case, it is clear that the respondent
department has slept over the matter and proceeded to
lodge the complaint after nine years of issuance of the
disputed letter dated 18.10.2014, when during all these
years the department was having knowledge about the
same. It is not a case where the respondent department all
of a sudden came to know about the existence of letter
dated 18.10.2014 when the learned Advocate General
addressed a communication to the department in the year
2023 but it is a case where the said communication was
subject matter of adjudication before the Arbitral Tribunal
and the respondent department all along knew about its
existence. No explanation has been tendered by the
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
respondent department for not lodging the FIR during all
these nine years. The explanation tendered by the
respondent Investigating Agency that the matter was
brought to its notice only in the year 2023, therefore,
there is no delay in lodging of the FIR, cannot come to the
rescue of the complainant who has slept over the matter
for about nine long years. The only inference that can be
drawn from the unexplained delay in lodging the FIR is
that the respondent department is trying to create a
defence against the claim of the petitioner company which
is under adjudication in the proceedings under Section 34
of the Arbitration and Conciliation Act.
36)
For what has been discussed hereinbefore, this
Court has no doubt in holding that the impugned criminal
proceedings have been lodged against the petitioners at
the instance of respondent department only with an
oblique motive of creating a defence to the arbitral award.
The dispute between the petitioner company and the
respondent department is purely of a civil nature having
no criminal texture to it and, as such, the continuation of
criminal proceedings against the petitioners, in these
circumstances, would be nothing but an abuse of process
of law.
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
37)
Accordingly, both the petitions are allowed and the
impugned FIR and the proceedings emanating therefrom
are quashed.
(Sanjay Dhar)
Judge
Srinagar,
14.08.2025
“Bhat Altaf-Secy”
Naresh Kumar
2025.08.14 17:56
I attest to the accuracy and
integrity of this document
Whether the judgment is speaking:
YES
Whether the judgment is reportable:
YES
CRM(M) No.729/2024 c/w
CRM(M) No.721/2024
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review