HIGH COURT OF CHHATTISGARH AT BILASPUR
ARBA No. 48 of 2025
{Arising out of order dated 2-5-2025 passed by the Commercial Court
(District Judge Level), Nava Raipur, Atal Nagar, District Raipur in
Arbitration MJC No.11/2025}
Rajesh Kumar Hablani, S/o Shri Puranlal Hablani, aged about 51
years, R/o C-279, Opposite Fun Fiesta Ground, Shailendra Nagar,
Raipur, District Raipur (C.G.)
... Appellant
versus
1. State of Chhattisgarh, through Secretary, Housing and Environment
Department, Mahanadi Bhawan, Mantralaya, Capital Complex, Atal
Nagar, Nawa Raipur, District Raipur (C.G.)
2. Raipur Development Authority, through its Chief Executive Officer,
2nd Floor, Bhakta Mata Karma Vyavsayik Parisar, New Rajendra
Nagar, Raipur, District Raipur (C.G.)
3. Chief Executive Officer, Raipur Development Authority, 2 nd Floor,
Bhakta Mata Karma Vyavsayik Parisar, New Rajendra Nagar, Raipur
District Raipur (C.G.)
4. Revenue Officer (Tehsildar), Raipur Development Authority, Raipur,
District Raipur (C.G.)
... Respondents
For Appellant
: Mr. Manoj Paranjpe, Senior Advocate with Mr.
Kabeer Kalwani, Advocate.
For Respondent No.1
: Mr. Rahul Tamaskar, Government Advocate.
For Respondents No.2 to 4 : Mr. Ashish Shrivastava, Senior Advocate with Mr.
Pankaj Agrawal, Advocate.
Division Bench: Hon'ble Shri Sanjay K. Agrawal and
Hon'ble Shri Sachin Singh Rajput, JJ.
(ARBA No.48/2025)
Judgment On Board
(05/05/2026)
Sanjay K. Agrawal, J
For sake of exposition, this Judgment is divided in following parts:S.No.
Particulars
Page Nos.
1.
The Appeal
2.
Quintessential Facts
3.
Finding of the Commercial Court
4.
Submissions on behalf of the Appellant
5.
Submissions on behalf of the Respondent RDA
6.
Provision relating to Condonation of Delay
7.
Finding and Analysis
8.
Conclusion
The Appeal
1. Invoking the jurisdiction of this Court under Section 37 of the
Arbitration and Conciliation Act, 1996 (for short, ‘the Act of 1996’), the
appellant herein has preferred this appeal calling in question legality,
validity and correctness of order dated 2-5-2025 passed by the
Commercial Court (District Judge Level), Nava Raipur, Atal Nagar,
District Raipur in Arbitration MJC No.11/2025, by which the appellant’s
objection application under Section 34 of the Act of 1996 has been
rejected finding no merit.
2. The aforesaid challenge has been made on the following factual
backdrop: -
(ARBA No.48/2025)
Quintessential Facts
3. The respondent Raipur Development Authority (RDA) issued Notice
Inviting Tender for allotment of commercial plots on lease for 30 years
at Devendra Nagar, Raipur in which the appellant has made his offer for
the said allotment and was declared as the highest bidder and in terms
of the bid conditions, he deposited ₹ 24,38,000/- as the amount of
earnest money/security deposit and the order of allotment of
commercial plot was issued in his favour, and the appellant was further
directed to deposit the remaining amount in two installments which he
could not deposit leading to order of cancellation of allotment dated 2011-2023 and forfeiture of earnest money by the competent authority of
the RDA, which the appellant questioned in writ petition before this
Court, however, this Court did not entertain the writ petition and
reserved liberty in favour of the appellant to invoke the arbitration
clause with an interim order for a limited period of 15 days.
4. The appellant approached the named Arbitrator i.e. the Chairman of the
RDA invoking the arbitration clause and common award was passed
and claim made by the appellant herein was dismissed holding that it
has no substance.
5. The award was passed on 5-9-2024 and it was received by the appellant
under Section 31(5) of the Act of 1996 on 18-9-2024 and the objection
application under Section 34(1) of the Act of 1996 has to be filed within
three months therefrom and thus, the application ought to have been
filed up to 18-12-2024, however, the said application was filed on 6-1-
(ARBA No.48/2025)
2025 with a delay of 18 days, but within the period of 30 days which is
admissible under the proviso to Section 34(3) of the Act of 1996
assigning reason that the filing of arbitration application took time in
consulting Advocates from this Court and thereafter Mr. Rakesh Puri,
Advocate, took his own time in perusing the documents and preparing
the application and as such, the delay of 18 days in filing the objection
application under Section 34(1) deserves to be condoned.
Finding of the Commercial Court
6. The Commercial Court by its impugned order, rejected the application
holding that though the objection application was filed with a delay of
18 days, but sufficient cause has not been shown for filing the same with
delay of 18 days leading to filing of the instant appeal under Section 37
of the Act of 1996.
Submissions on behalf of the Appellant
7. Mr. Manoj Paranjpe, learned Senior Counsel appearing on behalf of the
appellant herein, would submit that the Commercial Court is absolutely
unjustified in construing the sufficient cause leading to rejection of
application, as the appellant has shown sufficient cause for the delay of
18 days in filing the objection application which ought to have been
entertained, as rules of limitation are not meant to destroy the rights of
the parties and they are meant to see that parties do not resort to
dilatory tactics but seek their remedy promptly. As such, the delay of 18
days in filing the objection application be condoned and the matter be
(ARBA No.48/2025)
remitted to the Commercial Court for deciding the objection afresh and
for setting aside the arbitral award on merits.
Submissions on behalf of the Respondent RDA
8. Mr. Ashish Shrivastava, learned Senior Counsel appearing on behalf of
respondents No.2 to 4 herein/RDA, would submit that the delay of 18
days has not been properly explained. He would further submit that the
delay has to be condoned, if the same is explained properly, however, in
the present case, three months had already elapsed after passing and
communicating the arbitral award, therefore, there was no reason for
taking further 18 days in filing the objection i.e. for consulting
Advocates and as such, the appeal deserves to be dismissed.
9. We have heard learned counsel for the parties and considered their rival
submissions made herein-above and also gone through the record with
utmost circumspection.
Provision relating to Condonation of Delay
10. In order to consider the dispute raised at the Bar, it would be
appropriate to notice Section 34(3) of the Act of 1996, which states as
under: “34. Application for setting aside arbitral award.—(1)
and (2) xxx xxx xxx
(3) An application for setting aside may not be made
after three months have elapsed from the date on which the
party making that application had received the arbitral award
or, if a request had been made under section 33, from the date
on which that request had been disposed of by the arbitral
tribunal:
(ARBA No.48/2025)
Provided that if the Court is satisfied that the applicant
was prevented by sufficient cause from making the
application within the said period of three months it may
entertain the application within a further period of thirty
days, but not thereafter.”
11. A careful reading of Section 34(3) of the Act of 1996 would show that
application for setting the award has to be made within three months
from the date on which the party making that application had received
the arbitral award, however, the proviso to Section 34(3) carves out an
exception and makes it abundantly clear that while the Court may, upon
being satisfied that the applicant was prevented by sufficient cause,
entertain an application filed beyond the prescribed period of three
months, however, such indulgence is strictly confined to a further
period of thirty days. The legislative mandate is unequivocal in that and
the delay cannot be condoned beyond the additional period of 30 days
(120 days + 30 days), thereby prescribing an absolute outer limit for the
exercise of the Court’s discretion in condoning the delay.
12. As such, a party aggrieved by an award may raise objections for setting
aside the award within a period 3 months from the date of receipt of a
singed copy of the award from the arbitral tribunal subject to a further
period of 30 days which may be condoned by the court if sufficient
cause is shown, but not thereafter. The words “but not thereafter” in
Section 34(3) of the Act of 1996 amount to an express exclusion within
the meaning of Section 29(2) of the Limitation Act. Express exclusion
can also be inferred from history, scheme and objectives of the Act of
(ARBA No.48/2025)
1996, one of whose main objective is to restrict judicial intervention in
arbitral matters as much as possible.
13. Their Lordships of the Supreme Court in the matter of Consolidated
Engineering Enterprises v. Principal Secretary, Irrigation
Department and others1, while dealing with Section 34(3) of the Act
of 1996, have clearly held that the proviso to Section 34(3) being a
specific
legislation
excludes
applicability
of
general
provisions
contained in Section 5 of the Limitation Act and, therefore, the Court
has no discretion to extend limitation beyond 30 days prescribed in
proviso to Section 34(3) even if sufficient cause is shown for it, and
observed as under:“20. Section 29(2) of the Limitation Act inter alia provides
that where any special or local law prescribes for any suit,
appeal or application a period of limitation different from the
period of limitation prescribed by the Schedule, the
provisions of Section 3 shall apply as if such period was the
period prescribed by the Schedule and for the purpose of
determining any period of limitation prescribed for any suit,
appeal or application by any special or local law, the
provisions contained in Sections 4 to 24 shall apply only
insofar as, and to the extent, they are not expressly excluded
by such special or local law. When any special statute
prescribes certain period of limitation as well as provision for
extension up to specified time-limit, on sufficient cause being
shown, then the period of limitation prescribed under the
special law shall prevail and to that extent the provisions of
the Limitation Act shall stand excluded. As the intention of
the legislature in enacting sub-section (3) of Section 34 of the
Act is that the application for setting aside the award should
be made within three months and the period can be further
extended on sufficient cause being shown by another period
of 30 days but not thereafter, this Court is of the opinion that
the provisions of Section 5 of the Limitation Act would not be
applicable because the applicability of Section 5 of the
Limitation Act stands excluded because of the provisions of
1 (2008) 7 SCC 169
(ARBA No.48/2025)
Section 29(2) of the Limitation Act. However, merely because
it is held that Section 5 of the Limitation Act is not applicable
to an application filed under Section 34 of the Act for setting
aside an award, one need not conclude that provisions of
Section 14 of the Limitation Act would also not be applicable
to an application submitted under Section 34 of the Act of
1996.”
R.V. Raveendran, J. in his concurring judgment held as under: “53. Sub-section (3) of Section 34 of the AC Act prescribes
the period of limitation for filing an application for setting
aside an award as three months from the date on which the
applicant has received the arbitral award. The proviso thereto
vests in the court discretion to extend the period of limitation
by a further period not exceeding thirty days if the court is
satisfied that the applicant was prevented by sufficient cause
for not making the application within three months. The use
of the words “but not thereafter” in the proviso makes it clear
that even if a sufficient cause is made out for a longer
extension, the extension cannot be beyond thirty days. The
purpose of proviso to Section 34(3) of the AC Act is similar to
that of Section 5 of the Limitation Act which also relates to
extension of the period of limitation prescribed for any
application or appeal. It vests a discretion in a court to extend
the prescribed period of limitation if the applicant satisfies
the court that he had sufficient cause for not making the
application within the prescribed period. Section 5 of the
Limitation Act does not place any outer limit in regard to the
period of extension, whereas the proviso to sub-section (3) of
Section 34 of the AC Act places a limit on the period of
extension of the period of limitation. Thus the proviso to
Section 34(3) of the AC Act is also a provision relating to
extension of period of limitation, but differs from Section 5 of
the Limitation Act, in regard to period of extension, and has
the effect of excluding Section 5 alone of the Limitation Act.”
14. Thereafter, the Supreme Court in the matter of State of Himachal
Pradesh and another v. Himachal Techno Engineers and
another2 has held that if a petition is filed beyond the prescribed
period of three months, the court has the discretion to condone the
2 (2010) 12 SCC 210
(ARBA No.48/2025)
delay only to an extent of thirty days, provided sufficient cause is shown
and where a petition is filed beyond three months plus thirty days, even
if sufficient cause is made out, the delay cannot be condoned by the
court. Their Lordships of the Supreme Court posed three questions for
consideration and answered the same which are as under: “(i) What is the date of commencement of limitation?
(ii) Whether the period of three months can be counted as 90
days?
(iii) Whether only three months plus twenty-eight days had
expired when the petition was filed as contended by the
appellant, or whether petition was filed beyond three months
plus thirty days, as contended by the respondent?
Re : Question (i)
11. In this case, it is not disputed that though the cover
containing the award was delivered to the beldar in the Office
of the Executive Engineer on 10-11-2007 which was a holiday,
the Executive Engineer received the award on 12-11-2007
(Monday), which was the next working day. Therefore we
hold that the date of delivery of the award on a holiday (10-112007) could not be construed as “receipt” of the award by the
appellant. The date of receipt therefore should be taken as 1211-2007 and not 10-11-2007.
12. Section 12 of the Limitation Act, 1963 provides for
exclusion of time in legal proceedings. Sub-section (1) thereof
provides that in computing the period of limitation for any
application, the day from which such period is to be reckoned,
shall be excluded. The applicability of Section 12 of the
Limitation Act, 1963 to petitions under Section 34 of the Act
is not excluded by the provisions of the Act.
13. Section 9 of the General Clauses Act, 1897 provides that
in any Central Act, when the word “from” is used to refer to
commencement of time, the first of the days in the period of
time shall be excluded. Therefore the period of “three months
from the date on which the party making that application had
received the arbitral award” shall be computed from 13-112007.
(ARBA No.48/2025)
Re : Question (ii)
15. Sub-section (3) of Section 34 of the Act and the proviso
thereto significantly, do not express the periods of time
mentioned therein in the same units. Sub-section (3) uses the
words “three months” while prescribing the period of
limitation and the proviso uses the words “thirty days” while
referring to the outside limit of condonable delay. The
legislature had the choice of describing the periods of time in
the same units, that is, to describe the periods as “three
months” and “one month” respectively or by describing the
periods as “ninety days” and “thirty days” respectively. It did
not do so. Therefore, the legislature did not intend that the
period of three months used in sub-section (3) to be equated
to 90 days, nor intended that the period of thirty days to be
taken as one month.
18. Therefore when the period prescribed is three months
(as contrasted from 90 days) from a specified date, the said
period would expire in the third month on the date
corresponding to the date upon which the period starts. As a
result, depending upon the months, it may mean 90 days or
91 days or 92 days or 89 days.
Re : Question (iii)
19. As the award was received by the Executive Engineer on
12-11-2007, for the purpose of calculating the three months
period, the said date shall have to be excluded having regard
to Section 12(1) of the Limitation Act, 1963 and Section 9 of
the General Clauses Act, 1897. Consequently, the three
months should be calculated from 13-11-2007 and would
expire on 12-2-2008. Thirty days from 12-2-2008 under the
proviso should be calculated from 13-2-2008 and, having
regard to the number of days in February, would expire on 133-2008. Therefore the petition filed on 11-3-2008 was well in
time and was not barred by limitation.”
15. Thereafter, in the matter of Haryana Urban Development
Authority, Karnal v. Mehta Construction Company and
another3, their Lordships of the Supreme Court while dealing with
Section 34(3) of the Act of 1996 in an application seeking condonation
3 (2022) 5 SCC 432
(ARBA No.48/2025)
of delay held that the Court had the power to condone the delay beyond
the period thirty days, in terms of the proviso to sub-section (3) to
Section 34 of the Act and proceeded to condone the delay of eight days
in filing the objection application under Section 34(1) of the Act of 1996.
16. Similarly, in the matter of Chintels India Limited v. Bhayana
Builders Private Limited4, their Lordships of the Supreme Court
have held that the application under Section 34(1) of the Act of 1996
itself must be within time, and if not within a period of three months,
must be accompanied with an application for condonation of delay,
provided it is within a further period of 30 days, this Court having made
it clear that Section 5 of the Limitation Act, 1963 does not apply.
17. As such, from the aforesaid principles of law laid down by their
Lordships of the Supreme Court, it is abundantly clear that the
objection application for setting aside the award under Section 34(1) of
the Act of 1996 has to be filed within a period of three months from the
date of receiving the award under Section 31(5) of the Act of 1996 and
the Court may entertain the application if sufficient cause is shown for
further delay of 30 days. The legislative mandate is clear and writ large
as the court dealing in Section 34(1) application cannot condone the
delay beyond the period of 30 days as the word “thereafter” has been
used restricting the power of court to condone the delay beyond the
period of 30 days.
4 (2021) 4 SCC 602
(ARBA No.48/2025)
Finding and Analysis
18. Admittedly, in this case, the arbitral award was passed on 5-9-2024 and
copy of the award was received by the appellant on 18-9-2024 and three
months therefrom, the objection application could not have been filed
on or before 18-12-2024, but it was filed with a delay of 18 days on 6-12025, which the appellant sought to explain that he kept consulting with
the Advocates from this Court and thereafter, it was handed-over to Mr.
Rakesh Puri, Advocate, who took his own time in perusing the
documents and in filing the objection application under Section 34(1) of
the Act of 1996, which the Commercial Court did not accept as sufficient
cause holding that it would not constitute sufficient cause within the
meaning of the proviso to Section 34(3) of the Act of 1996.
19. In this regard, the decision of the Supreme Court rendered in the matter
of N. Balakrishnan v. M. Krishnamurthy 5 may be noticed herein
in which their Lordships have held that rules of limitation are not meant
to destroy the right of parties and the object of providing a legal remedy
is to repair the damage caused by reason of legal injury, and observed as
under: “11. Rules of limitation are not meant to destroy the rights
of parties. They are meant to see that parties do not resort to
dilatory tactics, but seek their remedy promptly. The object of
providing a legal remedy is to repair the damage caused by
reason of legal injury. The law of limitation fixes a lifespan
for such legal remedy for the redress of the legal injury so
suffered. Time is precious and wasted time would never
revisit. During the efflux of time, newer causes would sprout
up necessitating newer persons to seek legal remedy by
approaching the courts. So a lifespan must be fixed for each
5 (1998) 7 SCC 123
(ARBA No.48/2025)
remedy. Unending period for launching the remedy may lead
to unending uncertainty and consequential anarchy. The law
of limitation is thus founded on public policy. It is enshrined
in the maxim interest reipublicae up sit finis litium (it is for
the general welfare that a period be put to litigation). Rules of
limitation are not meant to destroy the rights of the parties.
They are meant to see that parties do not resort to dilatory
tactics but seek their remedy promptly. The idea is that every
legal remedy must be kept alive for a legislatively fixed period
of time.”
Their Lordships of the Supreme Court further held that there is no
presumption that delay in approaching the court is always deliberate.
Their Lordships also held that the words “sufficient cause” under
Section 5 of the Limitation Act should receive a liberal construction so
as to advance substantial justice, and observed as under: “12. A court knows that refusal to condone delay would
result in foreclosing a suitor from putting forth his cause.
There is no presumption that delay in approaching the court
is always deliberate. This Court has held that the words
“sufficient cause” under Section 5 of the Limitation Act should
receive a liberal construction so as to advance substantial
justice vide Shakuntala Devi Jain v. Kuntal Kumari6 and
State of W.B. v. Administrator, Howrah Municipality7.”
20. Coming to the facts of the case in light of the principles of law laid down
by their Lordships of the Supreme Court in N. Balakrishnan (supra),
it is admittedly clear that there is delay of 18 days in filing the objection
application which the appellant sought to explain that it took time in
consulting the Advocate at High Court, Bilaspur and thereafter, Mr.
Rakesh Puri, Advocate, was handed-over the file to peruse the
documents and prepare the objection application which took time
resulting in delay of 18 days in filing the application, which in our
6 AIR 1969 SC 575 : (1969) 1 SCR 1006
7 (1972) 1 SCC 366 : AIR 1972 SC 749
(ARBA No.48/2025)
considered opinion would constitute sufficient cause within the
meaning of Section 34(3) of the Act of 1996, as if the delay is not
condoned, the appellant would suffer injustice as he had deposited huge
amount for allotment of plots, in this case, ₹ 24,38,000/- and that has
been forfeited, and the writ court dismissed the writ petition on the
ground to invoke the arbitration clause, and the Arbitrator has also
dismissed the claim of the appellant, and further, the objection
application preferred under Section 34 of the Act of 1996 has also been
dismissed on the ground of limitation. Thus, if delay is not condoned, it
would result in substantial injustice to the appellant, as it would further
foreclose his remedy. It is not the case of the respondents that the
objection application has been filed for setting aside the arbitral award
after the period of 120 days + 30 days, rather it has been filed within the
period of 30 days and thus, the delay is condonable under the proviso to
Section 34(3) of the Act of 1996. The Commercial Court dealing with
such matter ought to have taken a pragmatic view of the matter, rather
than too technical in rejecting the objection application for short delay
of 18 days which is not inordinate and sufficient cause has been shown
for the delay of 18 days in filing the objection application. As such, the
Commercial Court is absolutely unjustified in rejecting the application
for condonation of delay by recording a finding which is totally
unacceptable and liable to be set aside.
(ARBA No.48/2025)
Conclusion
21. Consequently, the delay of 18 days in filing the objection application is
hereby condoned being condonable and within the period of 120 days +
30 days as provided in the proviso to Section 34(3) of the Act of 1996.
The impugned order dated 2-5-2025 passed by the Commercial Court
(District Judge Level), Nava Raipur, Atal Nagar, District Raipur in
Arbitration MJC No.11/2025, is set aside and the matter is remitted to
the file of the Commercial Court which shall consider and decide the
objection application under Section 34(1) of the Act of 1996 afresh on
merits expeditiously keeping in view that the dispute dates back to 223-2018.
22. The appeal is allowed to the extent indicated herein-above. There shall
be no order as to costs.
Sd/(Sanjay K. Agrawal)
Judge
Soma
Sd/(Sachin Singh Rajput)
Judge
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review