IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 08TH DAY OF JANUARY, 2026
BEFORE
THE HON'BLE MR. JUSTICE M. NAGAPRASANNA
WRIT PETITION No.6708 OF 2025 (LA - KIADB)
C/W
WRIT PETITION No.33550 OF 2024 (LA - KIADB)
WRIT PETITION No.255 OF 2025 (LA - KIADB)
WRIT PETITION No.293 OF 2025 (LA - KIADB)
WRIT PETITION No.515 OF 2025 (LA - KIADB)
WRIT PETITION No.671 OF 2025 (LA - KIADB)
WRIT PETITION No.672 OF 2025 (LA - KIADB)
WRIT PETITION No.1173 OF 2025 (LA - KIADB)
WRIT PETITION No.1280 OF 2025 (LA - KIADB)
WRIT PETITION No.1399 OF 2025 (LA - KIADB)
WRIT PETITION No.1405 OF 2025 (LA - KIADB)
WRIT PETITION No.3447 OF 2025 (LA - KIADB)
WRIT PETITION No.4055 OF 2025 (LA - KIADB)
WRIT PETITION No.4061 OF 2025 (LA - KIADB)
WRIT PETITION No.4737 OF 2025 (LA - KIADB)
WRIT PETITION No.5030 OF 2025 (LA - KIADB)
WRIT PETITION No.5148 OF 2025 (LA - KIADB)
WRIT PETITION No.5949 OF 2025 (LA - KIADB)
WRIT PETITION No.20573 OF 2025 (LA - KIADB)
IN WRIT PETITION No.6708 OF 2025
BETWEEN:
1 . SRI NARASIMHAN N.,
AGED ABOUT 40 YEARS
S/O MANIKYA
NO.63, LAKSHMI SAGAR LAYOUT
MAHESHWAR TEMPLE ROAD
MAHADEVAPURA POST
BENGALURU – 560 048.
2 . SRI SHEKAR M.,
AGED ABOUT 41 YEARS
S/O MUNISWAMY
NO.14, GANGAMMA TEMPLE ROAD
2ND CROSS, MAHADEVAPURA
BENGALURU – 560 048.
... PETITIONERS
(BY SRI MURALI N., ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
REPRESENTED BY ITS PRINCIPAL SECRETARY
DEPARTMENT OF COMMERCE AND
INDUSTRIES DEVELOPMENT
VIKASA SOUDHA, DR. B.R.AMBEDKAR VEEDHI
BENGALURU – 560 001.
2.
THE KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD
REPRESENTED BY ITS CHAIRMAN
NO.14/3, RASTROTHANA BUILDING
NEAR RESERVE BANK NRUPATHUNGA ROAD
BENGALURU – 560 001
REPRESENTED BY ITS CHAIRMAN.
3.
THE SPECIAL LAND ACQUISITION OFFICER
KIADB, NO.14/3, RASTROTHANA BUILDING
NEAR RESERVE BANK, NRUPATHUNGA ROAD
BENGALURU – 560 001
REPRESENTED BY ITS CHIEF EXECUTIVE OFFICER.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI H.L.PRADEEP KUMAR, ADVOCATE FOR R2 AND R3)
THIS WRIT PETITION IS FILED UNDER ARTICLE 226 OF THE
CONSTITUTION
OF
INDIA
PRAYING
TO
PRELIMINARY
NOTIFICATION BEARING NO. CI 58 S PQ 2024 DATED 15/03/2024
VIDE ANNEXURE-A IN SO FAR IT RELATES TO THE PETITIONERS
PROPERTY MEASURING 01 ACRE 09 GUNTAS SY NO. 205/2 OF S
MEDAHALLI
VILLAGE, SARJAPUR
HOBLI,
ANEKAL TALUK,
BANGALORE.
IN WRIT PETITION No.33550 OF 2024
BETWEEN:
1.
PURAVANKARA LIMITED
A COMPANY REGISTERED UNDER
THE PROVISIONS OF THE COMPANIES ACT, 1956
HAVING ITS REGISTERED OFFICE AT
130/1, ULSOOR ROAD
BENGALURU – 560 042
REPRESENTED BY ITS PRESIDENT-LEGAL
JOHN S.VIJAYKUMAR.
2.
KALPAK REALTY PRIVATE LIMITED
A COMPANY REGISTERED UNDER
THE PROVISIONS OF THE COMPANIES ACT, 1956
HAVING ITS REGISTERED OFFICE AT
NO.10, VITTAL MALLYA ROAD
BENGALURU – 560 001
REPRESENTED BY ITS POA HOLDER
PURAVANKARA LIMITED
JATIN UJJINI C.S.
... PETITIONERS
(BY SRI PRABHULING K.NAVADGI, SENIOR ADVOCATE A/W.,
SRI JOSEPH ANTHONY, ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
REPRESENTED BY ITS PRINCIPAL SECRETARY
INDUSTRIES AND COMMERCE
VIKASA SOUDHA
BENGALURU – 560 001.
2.
THE KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD
NO.14/3, RASTROTHANA BUILDING
NEAR RESERVE BANK
NRUPATHUNGA ROAD
BENGALURU – 560 001
REPRESENTED BY ITS CHAIRMAN.
3.
THE SPECIAL LAND ACQUISITON OFFICER
KIADB, NO.14/3
RASTROTHANA BUILDING
NEAR RESERVE BANK
NRUPATHUNGA ROAD
BENGALURU – 560 001
REPRESENTED BY ITS
CHIEF EXECUTIVE OFFICER
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 AND R3)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE
PRELIMINARY NOTIFICATION DTD. 15.03.2024 BEARING NO. CI 58
S PQ 2024 INSOFAR AS IT PERTAINS TO THE SCHEDULE PROPERTY
OF THE PETITIONER (ANNX-B).
IN WRIT PETITION No.255 OF 2025
BETWEEN:
1.
TRIGUNA MAYURI REALTY PRIVATE LIMITED
A COMPANY INCORPORATED UNDER
THE PROVISIONS OF THE COMPANIES ACT, 2013
HAVING REGISTERED OFFICE AT
NO. 102, 1ST FLOOR, TRIGUNA ICON
NO.27, AREKAMPANAHALLI
HOSUR ROAD, BENGALURU - 550 027
REPRESENTED BY ITS
AUTHORIZED SIGNATORY
SRI BHATTAGIRI RAGHUNATH REDDY
S/O SRI BHATTAGIRI VENKATA REDDY
AGED ABOUT 50 YEARS.
2.
SRI VENU B. M.,
S/O MR. MUNIREDDY
AGED ABOUT 35 YEARS
RESIDING OF BILLAPURA VILLAGE
SARJAPURA HOBLI, ANEKAL TALUK
BENGALURU - 562 125
REPRESENTED BY GPA HOLDER
TRIGUNA MAYURI REALTY
PRIVATE LIMITED
REPRESENTED BY ITS AUTHORIZED SIGNATORY
SRI BHATTAGIRI RAGHUNATH REDDY
S/O SRI BHATTAGIRI VENKATA REDDY
AGED ABOUT 50 YEARS.
3.
SRI SHIVASHANKAR
S/O LATE SRI HUCHEERAIAH
AGED ABOUT 52 YEARS
RESIDING AT HORALAGALLU
KANAKAPUA TALUK
BENGALURU
REPRESENTED BY GPA HOLDER
TRIGUNA MAYURI REALTY
PRIATE LIMITED
REPRESENTED BY ITS AUTHORIZED SIGNATORY
SRI BHATTAGIRI RAGHUNATH REDDY
S/O SRI BHATTAGIRI VENKATA REDDY
AGED ABOUT 50 YEARS
... PETITIONERS
(BY SRI RAJESWARA P. N., ADVOCATE)
AND:
1.
STATE OF KARNATAKA
DEPARTMENT OF INDUSTRIES
AND COMMERCE
DR. B.R.AMBEDKAR BEEDI
VIKAS SOUDHA
BENGLAURU - 560 001
REPRESENTED BY
ADDITIONAL CHIEF SECRETARY.
2.
THE KARNATKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
IV AND V FLOORS, EAST WING
KHANIJA BHAVAN
RACE COURSE ROAD
BENGALURU - 560 001
REPRESENTED BY ITS
CHIEF EXECUIVE OFFICER AND
EXECUTIVE MEMBER.
3.
SPECIAL DEPUTY COMMISSIONER
KARNATAKA INDUSTRIAL AREAS
DEVELOPMENT BOARD
IV AND V FLOORS, EAST WING
KHANIJA BHAVAN
RACE COURSE ROAD
BENGALURU - 560 001.
4.
THE SPECIAL LAND ACQUISITION OFFICER-2
KARNATAKA INDUSTRIAL AREAS
DEVELOPMENT BOARD
MAHARSHI ARVIND BHAVAN
1ST FLOOR, NRUPATHUNGA ROAD
BENGALURU - 560 001.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 TO R4)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE
NOTIFICATIONS BEARING NO. CI 58 SPQ 2024 DTD. 15.03.2024
ISSUED BY R-1 UNDER SECTION 3(1) AND 1(3) OF THE KIAD ACT,
1966 AT ANNX-N AND P IN SO FAR AS THE PETITIONERS LANDS
MEASURING 5 ACRES 29 GUNTAS IN SY.NO. 121 OF
ADIGARAKALAHALLI VILLAGE, SARJAPURA HOBLI, ANEKAL TALUK,
BENGALURU URBAN DISTRICT IS CONCERNED.
IN WRIT PETITION No.293 OF 2025
BETWEEN:
1.
SRI B.Y.NAGARAJU
S/O LATE YELLA REDDY
AGED ABOUT 59 YEARS
RESIDENT OF BILLAPURA VILLAGE
SARJAPURA HOBLI, ANEKAL TALUK
BENGALURU - 562 125.
2.
SRI B.Y.NARAYANASWAMY
S/O LATE YELLA REDDY
AGED ABOUT 55 YEARS
3.
SMT. K.GEETHA KUMARI
S/O B.Y.NARAYANASWAMY
AGED ABOUT 53 YEARS
PETITIONERS NO. 2 AND 3 ARE
RESIDING AT NO.76, SRI NILAYA
NEAR EXIDE GATE, BILLAPURA
SARJAPURA, BENGALURU – 562 125.
4.
SRI M.KRISHNA REDDY
S/O LATE MUNISWAMY REDDY
AGED ABOUT 60 YEARS
5.
SMT. K.SUVARNA
W/O SRI M.KRISHNA REDDY
AGED ABOUT 57 YEARS
PETITIONERS NO. 4 AND 5 ARE
RESIDING AT NO.969/G, 3RD CROSS
‘A’ BLOCK, BENGALURU
AECS LAYOUT, KUDLU GATE, SINGASANDRA
BOMMANAHALLI, BENGALURU SOUTH
BENGALURU - 560 068.
6.
SRI B.D.VENKATESH
S/O LATE DASAPPA
AGED ABOUT 51 YEARS
RESIDENT OF BILLAPURA VILLAGE
SARJAPURA HOBLI, ANEKAL TALUK
BENGALURU - 562 125.
7.
SRI P.SRINIVASA REDDY
S/O LATE PEDDA REDDY
AGED ABOUT 49 YEARS
8.
SRI P.MURALESH
S/O LATE PEDDA REDDY
AGED ABOUT 47 YEARS
PETITIONERS NO.7 AND 8 ARE
RESIDENTS OF BILLAPURA VILLAGE
SARJAPURA HOBLI, ANEKAL TALUK
BENGALURU – 562 125.
... PETITIONERS
(BY SRI RAJESWARA P. N., ADVOCATE)
AND:
1.
STATE OF KARNATAKA
DEPARTMENT OF INDUSTRIES AND COMMERCE
DR. B.R.AMBEDKAR BEEDI
VIKAS SOUDHA, BENGALURU - 560 001
REP. BY ADDITIONAL CHIEF SECRETARY.
2.
THE KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
IV AND V FLOORS, EAST WING
KHANIJA BHAVAN
RACE COURSE ROAD
BENGALURU - 560 001
REPRESENTED BY ITS
CHIEF EXECUTIVE OFFICER AND
EXECUTIVE MEMBER.
3.
SPECIAL DEPUTY COMMISSIONER
KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
IV AND V FLOORS, EAST WING
KHANIJA BHAVAN, RACE COURSE ROAD
BENGALURU - 560 001.
4.
THE SPECIAL LAND ACQUISITION OFFICER - 2
KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
MAHARSHI ARVIND BHAVAN
1ST FLOOR, NRUPATHUNGA ROAD
BENGALURU - 560 001.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 TO R4)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 OF THE
CONSTITUTION
OF
INDIA
PRAYING
TO
QUASH
THE
NOTIFICATIONS BEARING NO. CI 58 SPQ 2024 DTD. 15.03.2024
ISSUED UNDER SECTIONS 3(1), 1(3), AND 28(1) OF THE KIAD
ACT, 1966 AT ANNX-A TO C ISSUED BY R-1 AND THE FINAL
NOTIFICATION BEARING NO. CI 58 SPQ 2024 DTD. 02.12.2024 AT
ANNX-D ISSUED BY R-1 IN SO FAR AS THE PETITIONERS LANDS
MENTIONED AT PARAGRAPH NO. 4 ARE CONCERNED.
IN WRIT PETITION No.515 OF 2025
BETWEEN:
1.
MOHAN H.C.,
S/O CHINNASWAMY REDDY
AGED ABOUT 56 YEARS
NO.259, SVS NILAYA
BEHIND PANCHAYATH OFFICE
HANDENAHALLI, BENGALURU - 562 125.
2.
RAMACHANDRA REDDY
S/O R.NARAYANA REDDY
AGED ABOUT 65 YEARS
HANDENAHALLI
BENGALURU - 562 125.
3.
N.KRISHNA REDDY
S/O NARAPPA
AGED ABOUT 75 YEARS
NO.77, HANDENAHALLI
BENGALURU - 562 125.
4.
H.K.SRINIVASA
S/O KRISHNA REDDY
AGED ABOUT 50 YEARS
NO.77, HANDENAHALLI
BENGALURU - 562 125.
5.
H.R.CHANDRASHEKAR
S/O RAMA REDDY
AGED ABOUT 54 YEARS
NO.141/B, MADI MANE
MADDURAMMA TEMPLE ROAD
HANDENAHALLI, BENGALURU - 562 125.
6.
SMT. PREMA
W/O. NANJUNDA REDDY
AGED ABOUT 51 YEARS
HANDENAHALLI
BENGALURU - 562 125.
7.
SRI. H.V.DHASHARATHA REDDY
S/O VENKATASWAMY REDDY
AGED ABOUT 47 YEARS
NO.243, HANDENAHALLI
BENGALURU - 562 125.
8.
SRI H.K.RAGHUNATH REDDY
S/O LATE KRISHNA REDDY
AGED ABOUT 55 YEARS
HANDENAHALLI
BENGALURU - 562 125.
9.
SRI VEERAPPA H. C.,
S/O CHINAPPA
AGED ABOUT 89 YEARS
HANDENAHALLI, ANEKAL TALUK
BENGALURU - 562 125.
10 .
SRI PRABHAKAR REDDY
S/O NARAYANNA REDDY
AGED ABOUT 59 YEARS
HANDENAHALLI, ANEKAL TALUK
BENGALURU - 562 125.
11 .
SRI MANJUNATH REDDY
S/O NARAYANA REDDY
AGED ABOUT 55 YEARS
NO.38, HANDENAHALLI
ANEKAL TALULK, BENGALURU - 562 125.
12 .
SRI MALLA REDDY H. V.,
S/O VENKATA REDDY
AGED ABOUT 80 YEARS
HANDENAHALLI
ANEKAL TALUK, BENGALURU - 562 125.
13 .
SRI PILLA REDDY B.,
S/O BHADRAREDDY
AGED ABOUT 71 YEARS
HANDENAHALLI
ANEKAL TALUK, BENGALURU - 562 125.
14 .
SRI H.P MURALI
S/O B.PILLA REDDY
AGED ABOUT 44 YEARS
NO.89, HANDENAHALLI
ANEKAL TALUK, BENGALURU - 562 125.
15 .
SRI VENUGOPAL H. K.,
S/O KRISHNAREDDY H. V.,
AGED ABOUT 56 YEARS
NO. 183, NAGAVISHNU KRUPA NILAYA
NEAR BUS STOP, HANDENAHALLI
ANEKAL TALUK, BENGALURU - 562 125.
16 .
SRI H.R.NANJUNDA REDDY
S/O RAMASWAMI REDDY
AGED ABOUT 61 YEARS
R/AT NO.1, HANDENAHALLI
ANEKAL TALUK, BENGALURU - 562 125.
17 .
SRI M.VENKATASWAMI REDDY
S/O MUNISWAMI REDDY
AGED ABOUT 60 YEARS
R/O HANDENAHALLI
ANEKAL TALUK
BENGALURU - 562 125.
18 .
SRI NAGESH H. G.,
S/O GOPALA REDDY
AGED ABOUT 45 YEARS
R/O NO.292, HANDENAHALLI
ANEKAL TALUK, BENGALURU - 562 125.
19 .
SMT. PARVATHAMMA
D/O NARAYANA REDDY
AGED ABOUT 66 YEARS
R/O HANDENAHALLI
ANEKAL TALUK, BENGALURU - 562 125.
20 .
SRI V.GOPALA REDDY
S/O VIRAPPA
AGED ABOUT 74 YEARS
R/O NO.270, HANDENAHALLI
ANEKAL TALUK, BENGALURU - 562 125.
21 .
SRI H.V.RAMESH REDDY
S/O VEERAPPA
AGED ABOUT 56 YEARS
R/O NO.V419, NAMBIAR BELLAZIA
NARAYANAGHATTA, BENGALURU - 560 099.
22 .
SRI H.S.MANJUNATH
S/O K.SRINIVASA REDDY
AGED ABOUT 42 YEARS
R/O NO.36, SARJAPURA ROAD
HANDENAHALLI, ANEKAL TALUK
BENGALURU - 562 125.
23 .
SRI NAGARAJA H. S.,
S/O SRINIVASA REDDY
AGED ABOUT 39 YEARS
R/O NO.36, HANDENAHALLI
KOTAGANAHALLI, ANEKAL TALUK
BENGALURU - 562 125.
24 .
SRI MUNIREDDY
S/O KONDAREDDY
AGED ABOUT 68 YEARS
R/O HANDENAHALLI
ANEKAL TALUK, BENGALURU - 562 125.
25 .
VEERAPPA REDDY
S/O THIMMARAYA REDDY
AGED ABOUT 68 YEARS
R/O NO.105/2, HANDENAHALLI
ANEKAL TALUK, BENGALURU - 562 125.
... PETITIONERS
(BY SRI M.SHIVAPRAKASH, ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001
REPRESENTED BY ITS CHIEF SECRETARY.
2.
THE PRINCIPAL SECRETARY
DEPARTMENT OF INDUSTRIES
AND COMMERCE
STATE OF KARNATAKA
1ST FLOOR, VIKASA SOUDHA
BENGALURU - 560 001.
3.
THE PRINCIPAL SECRETARY
DEPARTMENT OF REVENUE
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001.
4.
THE PRINCIPAL SECRETARY
DEPARTMENT OF AGRICULTURE
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001.
5.
THE DIRECTOR
DEPARTMENT OF HORTICULTURE
LALBAGH, BENGALURU - 560 004.
6.
THE EXECUTIVE MEMBER
KARNATAKA INDUSTRIAL AREA
DEVELOPMENT BOARD, (KIADB)
KHANIJA BHAVAN, BENGALURU - 560 001.
7.
THE CHAIRMAN/MEMBER SECRETARY
KARNATAKA STATE POLLUTION
CONTROL BOARD, CHURCH STREET
BENGALURU - 560 001.
8.
THE SECRETARY
DEPARTMENT OF MINOR IRRIGATION
AND TANKS/LAKES
STATE OF KARNATAKA
VIDHANA SOUDHA, BENGALURU - 560 001.
9.
THE DEPUTY COMMISSIONER
BANGALORE URBAN DISTRICT
BENGALURU – 560 001.
10 .
THE SPECIAL LAND ACQUISITION OFFICER-2
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD, (KIADB)
PALACE ROAD, BENGALURU - 560 001.
11 .
THE TAHASILDAR
ANEKAL TALUK
ANEKAL – 562 125
BENGALURU DISTRICT.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1 TO R5, R8, R9 AND
R11;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R6 AND R10)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 R/W 48A AND 51A(G) OF THE CONSTITUTION OF INDIA
PRAYING TO CALL FOR THE ENTIRE RECORDS PERTAINING TO
NOTIFICATION TO ACQUIRE LANDS WITH KIAD ACT IN THE
VILLAGE HANDENAHALLI, SOLLEPURA, MUTHANALLUR AMANIKERE
OF SARJAPURA HOBLI, ANEKAL TALUK, BANGALORE URBAN
DISTRICT IN CI 59-SPQ 2024 DATED 15/3/2024; QUASH THE
PRELIMINARY NOTIFICATION NO.CI59SPQ2024 DATED 15/03/2024
UNDER 28(1), T ANNEXURE-E1 AND FINAL NOTIFICATION NO.
CI59SPQ2024 DATED 03/10/2024 UNDER 28(4) AT ANNEXURE-G
AND NOTIFICATION DATED 13/12/2024 UNDER SEC.28(6) OF
KIADB ACT, ISSUED BY THE RESPONDENT-2, AND RESPONDENT10, CONSEQUENTLY TO DECLARE THAT THE NOTIFICATIONS
ISSUED IS ARBITRARY, AGAINST THE POLICIES OF THE
GOVERNMENTS AND DECISIONS RENDERED BEFORE THIS HON’BLE
COURT, IN THE MATTER OF ACQUIRING FERTILE AGRICULTURE
LANDS FOR INDUSTRIAL PURPOSES.
IN WRIT PETITION No.671 OF 2025
BETWEEN:
1.
ABHIGNA CONSTRUCTIONS
A PARTNERSHIP FIRM
HAVING OFFICE AT SY.NO.19/27
7TH CROSS, GREEN DOMAIN LAYOUT
KUNDANAHALLI, MAHADEVAPURA
BENGALURU - 560 037
REPRESENTED BY ITS PARTNER
SRI MUCHALA BHASKAR REDDY
S/O SRI KRISHNA REDDY M.,
AGED ABOUT 55 YEARS.
2.
SMT. C.INDIRAMMA
W/O LATE CHANDRASHEKAR
AGED ABOUT 62 YEARS
RESIDING AT S MEDAHALLI VILLAGE
SARJAPURA HOBLI, ANEKAL TALUK
BENGALURU - 562 107.
3.
SRI C.ARUNA KUMAR
S/O LATE CHANDRASHEKAR
AGED ABOUT 42 YEARS
RESIDING AT S MEDAHALLI VILLAGE
SARJAPURA HOBLI, ANEKAL TALUK
BENGALURU - 562 125.
4.
SRI ANIL KUMAR A.,
S/O LATE ANJANAPPA
AGED ABOUT 40 YEARS
RESIDING AT BIDARAGUPPE VILLAGE
ATTIBELE HOBLI, ANEKAL TALUK
BENGALURU - 562 107
REPRESENTED BY ITS G.P.A HOLDER
SRI MUCHALA BHASKAR REDDY.
... PETITIONERS
(BY SRI RAJESWARA P. N., ADVOCATE)
AND:
1.
STATE OF KARNATAKA
DEPARTMENT OF INDUSTRIES AND COMMERCE
DR. B.R.AMBEDKAR BEEDI
VIKAS SOUDHA, BENGALURU - 560 001
REPRESENTED BY ADDITIONAL CHIEF SECRETARY.
2.
THE KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
IV AND V FLOORS, EAST WING
KHANIJA BHAVAN, RACE COURSE ROAD
BENGALURU - 560 001
REPRESENTED BY ITS CHIEF EXECUTIVE OFFICER
AND EXECUTIVE MEMBER.
3.
SPECIAL DEPUTY COMMISSIONER
KARNATAKA INDUSTRIAL AREAS
DEVELOPMENT BOARD, IV AND V FLOORS
EAST WING, KHANIJA BHAVAN
RACE COURSE ROAD, BENGALURU - 560 001.
4.
THE SPECIAL LAND ACQUISITION OFFICER - 2
KARNATAKA INDUSTRIAL AREAS
DEVELOPMENT BOARD, MAHARSHI ARVIND BHAVAN
1ST FLOOR, NRUPATHUNGA ROAD
BENGALURU - 560 001.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 TO R4)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 OF THE
CONSTITUTION
OF
INDIA
PRAYING
TO
QUASH
THE
NOTIFICATIONS BEARING NO. CI 58 SPQ 2024 DATED 15.03.2024
ISSUED UNDER SECTIONS 3(1), 1(3) AND 28(1) OF THE KIAD ACT,
1966 AT ANNEXURES-A TO C ISSUED BY RESPONDENT NO.1 AND
THE FINAL NOTIFICATION BEARING NO. CI 58 SPQ 2024 DATED
02.12.2024 AT ANNEXURE-D ISSUED BY RESPONDENT NO.1 IN SO
FAR AS THE PETITIONERS LAND MEASURING 2 ACRES 03 GUNTAS
IN SY.NO.43/1 OF S. MEDAHALLI VILLAGE, SARJAPURA HOBLI,
ANEKAL TALUK, BENGALURU URBAN DISTRICT ARE CONCERNED.
IN WRIT PETITION No.672 OF 2025
BETWEEN:
ABHIGNA CONSTRUCTIONS
A PARTNERSHIP FIRM
HAVING OFFICE AT SY. NO. 19/27
7TH CROSS, GREEN DOMAIN LAYOUT
KUNDANAHALLI, MAHADEVAPURA
BENGALURU – 560 037.
REPRESENTED BY ITS PARTNER
SRI MUCHALA BHASKAR REDDY
S/O SRI KRISHNA REDDY M.,
AGED ABOUT 55 YEARS
... PETITIONER
(BY SRI RAJESWARA P. N., ADVOCATE)
AND:
1.
STATE OF KARNATAKA
DEPARTMENT OF INDUSTRIES
AND COMMERCE, DR. B.R.AMBEDKAR BEEDI
VIKAS SOUDHA, BENGALURU - 560 001
REPRESENTED BY
ADDITIONAL CHIEF SECRETARY.
2.
THE KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
IV AND V FLOORS, EAST WING
KHANIJA BHAVAN, RACE COURSE ROAD
BENGALURU - 560 001
REPRESENTED BY ITS
CHIEF EXECUTIVE OFFICER AND
EXECUTIVE MEMBER.
3.
SPECIAL DEPUTY COMMISSIONER
KARNATAKA INDUSTRIAL AREAS
DEVELOPMENT BOARD, IV AND V FLOORS
EAST WING, KHANIJA BHAVAN
RACE COURSE ROAD, BENGALURU - 560 001.
4.
THE SPECIAL LAND ACQUISITION OFFICER - 2
KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
MAHARSHI ARVIND BHAVAN
1ST FLOOR, NRUPATHUNGA ROAD
BENGALURU - 560 001.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 TO R4)
THIS WRIT PETITION IS FILED UNDER ARTICLE 226 OF THE
CONSTITUTION
OF
INDIA
PRAYING
TO
QUASH
THE
NOTIFICATIONS BEARING NO. CI 58 SPQ 2024 DATED 15.03.2024
ISSUED UNDER SECTIONS 3(1), 1(3) AND 28(1) OF THE KIAD ACT,
1966 AT ANNEXURES-A TO C ISSUED BY RESPONDENT NO.1 AND
THE FINAL NOTIFICATION BEARING NO. CI 58 SPQ 2024 DATED
02.12.2024 AT ANNEXURE-D ISSUED BY RESPONDENT NO.1 IN SO
FAR AS THE PETITIONERS LANDS MEASURING 1 ACRES 19
GUNTAS IN SY.NO.17 AND LAND MEASURING 00.08.08 GUNTAS IN
SY.NO.202 OF S. MEDAHALLI VILLAGE, SARJAPURA HOBLI, ANEKAL
TALUK, BENGALURU URBAN DISTRICT ARE CONCERNED.
INN WRIT PETITION No.1173 OF 2025
BETWEEN:
H.N.RAVINDRA REDDY
S/O LATE NUNJA REDDY
AGED ABOUT 66 YEARS
R/AT HANDENAHALLI VILLAGE
SARJAPURA HOBLI
ANEKAL TALUK – 562 125.
... PETITIONER
(BY SRI VARADARAJAN M. S., ADVOCATE)
AND:
1.
STATE OF KARNATAKA
BY ITS SECRETARY OF
DEPARTMENT OF COMMERCE AND INDUSTRY
M.S.BUILDING, BENGALURU – 560 001.
2.
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD
KIADB HEAD OFFICE
NO.4, 4TH FLOOR
KHANIJA BHAVAN
EAST WING, RACE COURSE ROAD
BENGALURU – 560 001
BY ITS SECRETARY.
3.
THE SPECIAL LAND ACQUISITION OFFICER
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD
SHANTHI GRUHA, BHARATH SCOUT
AND GUIDES BUILDING
NO.39, 4TH FLOOR
PALACE ROAD, BENGALURU – 560 001.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 AND R3)
THIS WRIT PETITION IS FILED UNDER ARTICLE 226 OF THE
CONSTITUTION OF INDIA PRAYING TO QUASH THE IMPUGNED
NOTIFICATION DTD. 03.10.2024 BEARING NO. CI 59 SPQ 2024
ISSUED BY THE RESPONDENT NO.1 UNDER SECTION 28(4) OF THE
KIADB ACT 1996 (ANNX-A) AND ETC.,
IN WRIT PETITION No.1280 OF 2025
BETWEEN:
1.
SRI MOHAN
S/O PAPA REDDY
AGED ABOUT 63 YEARS
RESIDENT OF NO.9
BIDARAGUPPE POST
TYAVAKANAHALLI VILLAGE
BENGALURU – 562 107.
2.
SRI M.N.BABU
S/O NARAYANAREDDY
AGED ABOUT 46 YEARS
RESIDENT OF S.MEDAHALLI VILLAGE
BIDARAGUPPE POST, ANEKAL TALUK
SARJAPURA HOBLI, BENGALURU – 562 107.
3.
SRI B.JAGADEESHA
S/O T.N.BASAVARAJU
AGED ABOUT 55 YEARS
4.
SRI VISHWANATH B.,
S/O T.N.BASAVARAJU
AGED ABOUT 54 YEARS
5.
SRI MAHADESH B.,
S/O T.N.BASAVARAJU
AGED ABOUT 46 YEARS
PETITIONERS NO.3 TO 5 ARE
RESIDING AT NO.24
ATTIBELE SARJAPURA ROAD
TYAVAKANAHALLI VILLAGE
BENGALURU – 562 107.
6.
SRI VENKATA REDDY
S/O V.JAYARAMA REDDY
AGED ABOUT 44 YEARS
7.
SMT. GEETHA C.,
W/O VENKATA REDDY
AGED ABOUT 30 YEARS
PETITIONERS NO. 6 AND 7 ARE
RESIDENTS OF S. MEDAHALLI VILLAGE
BIDARAGUPPE POST
ATTIBELE-SARJAPURA MAIN ROAD
BENGALURU – 562 107.
... PETITIONERS
(BY SRI RAJESWARA P. N., ADVOCATE)
AND:
1.
STATE OF KARNATAKA
DEPARTMENT OF INDUSTRIES
AND COMMERCE, DR.B.R.AMBEDKAR BEEDI
VIKASA SOUDHA, BENGALURU - 560 001
REPRESENTED BY
ADDITIONAL CHIEF SECRETARY.
2.
THE KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
IV AND V FLOORS, EAST WING
KHANIJA BHAVAN, RACE COURSE ROAD
BENGALURU - 560 001
REPRESENTED BY ITS
CHIEF EXECUTIVE OFFICER AND
EXECUTIVE MEMBER.
3.
SPECIAL DEPUTY COMMISSIONER
KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
IV AND V FLOORS, EAST WING
KHANIJA BHAVAN, RACE COURSE ROAD
BENGALURU - 560 001.
4.
THE SPECIAL LAND ACQUISITION OFFICER - 2
KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
MAHARSHI ARVIND BHAVAN
1ST FLOOR, NRUPATHUNGA ROAD
BENGALURU - 560 001.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 AND R4)
THIS WRIT PETITION IS FILED UNDER ARTICLE 226 OF THE
CONSTITUTION
OF
INDIA
PRAYING
TO
QUASH
THE
NOTIFICATIONS BEARING NO. CI 58 SPQ 2024 DTD. 15.03.2024
ISSUED UNDER SECTIONS 3(1), 1(3) AND 28(1) OF THE KIAD ACT,
1966 AT ANNX-A TO C ISSUED BY R-1 AND THE FINAL
NOTIFICATION BEARING NO. CI 58 SPQ 2024 DTD. 02.12.2024 AT
ANNX-D ISSUED BY R-1 IN SO FAR AS THE PETITIONERS LANDS
MENTIONED AT PARAGRAPH NO.4 ARE CONCERNED.
IN WRIT PETITION No.1399 OF 2025
BETWEEN:
MR. B.C.AMARNATH
S/O LATE MR. CHIKKAMUNISWAMY REDDY
AGED ABOUT 56 YEARS
R/AT NO. 177, OPPOSITE TO SBI BANK
14TH CROSS, 6TH SECTOR, HSR LAYOUT
BENGALURU – 560 102.
... PETITIONER
(BY SRI AJIT P. B., ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
BY THE UNDER SECRETARY
DEPARTMENT OF COMMERCE AND
INDUSTRIES, OFFICE AT 2ND FLOOR
49 KHANIJA BHAVAN, RACE COURSE ROAD
BENGALURU – 560 001.
2.
THE SPECIAL LAND ACQUISITION OFFICER -2
KIADB, 1ST FLOOR, MAHARSHI ARVIND BHAVAN
NRUPATUNGA ROAD, BENGALURU – 560 010.
3.
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD
A GOVERNMENT OF KARNATAKA
UNDERTAKING, NO. 14/3, 2ND FLOOR
RP BUILDING, NRUPATHUNGA ROAD
BENGALURU – 560 001
REPRESENTED BY ITS JOINT AND
CHIEF EXECUTIVE OFFICER.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 AND R3)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE
NOTIFICATION DTD. 15.03.2024 VIDE ANNX-F BEARING NO. (¹L 59
J¸ï ¦ PÀÆå 2024) AND NOTIFICATION DTD. 03.10.2024 VIDE ANNX-A
BEARING NO. ¹L 59 J¸ï ¦ PÀÆå 2024 ISSUED BY THE R-1 IN SO FAR
AS IT RELATES TO THE LAND BELONGING TO THE PETITIONER
BEARING SY.NO. 83/1, MEASURING 1 ACRE 10 GUNTAS, SY.NO.
84/1, MEASURING 2 ACRE 3 GUNTAS, SY.NO. 85, MEASURING 1
ACRE 35 GUNTAS, SY.NO. 86/1 MEASURING 26 GUNTAS SY.NO.
86/2 MEASURING 1 ACRE 21 GUNTAS AND SY.NO. 87/4,
MEASURING 19 GUNTAS, SITUATED AT SOLLEPURA VILLAGE,
SARJAPURA HOBLI, ANEKAL TALUK, BANGALORE URBAN DISTRICT
IS CONCERNED.
IN WRIT PETITION No.1405 OF 2025
BETWEEN:
1.
SRI YALLAREDDY
S/O NARAYANA REDDY
AGED ABOUT 89 YEARS
2.
SMT. PUTTAMMA
W/O LATE NANJAREDDY
AGED ABOUT 76 YEARS
3.
SRI SURESH H. K.,
S/O KRISHNA REDDY
AGED ABOUT 53 YEARS
4.
SRI MADHUSUDHAN
S/O N.PILLAREDDY
AGED ABOUT 46 YEARS
5.
SRI RAJENDRA REDDY
S/O CHANNA REDDY
AGED ABOUT 70 YEARS
6.
SMT. SAVITHRAMMA
D/O MUNISWAMY REDDY
AGED ABOUT 65 YEARS
PETITIONERS NO.1 TO 6 ARE
R/AT HANDENAHALLI, SARJAPURA HOBLI
ANEKAL TALUK, BENGALURU – 562 125.
7.
SRI RAM BABU SRINIVAS
S/O R.SRINIVAS
AGED ABOUT 54 YEARS
R/AT NO.205, CHETANA MAPLE
HADO SIDDAPURA
SARJAPURA MAIN ROAD
BENGALURU – 560 035.
8.
SMT. H.R.SHWETHA
W/O GURUMURTHY K.,
AGED ABOUT 40 YEARS
R/AT NEAR GOVERNMENT SCHOOL
KOMMASANDRA, DOMMASANDRA POST
ANEKAL, BENGALURU – 562 125.
9.
SRI KIRAN DASAPPA
S/O K.L.DASAPPA
AGED ABOUT 37 YEARS
R/AT NO.313, ‘HANUMAN NILAYA’
SARJAPURA MAIN ROAD
DODDAKANNALLI, CARMELRAM POST
BENGALURU – 560 035.
10 . SMT. CHAITRA H. V.,
D/O VENKATESH REDDY G. V.,
AGED ABOUT 35 YEARS
R/AT NO.237, 2ND CROSS
TEACHERS COLONY
CHANDAPURA ANEKAL TALUK
BENGALURU – 560 099.
... PETITIONERS
(BY SRI M.SHIVAPRAKASH, ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU – 560 001
REPRESENTED BY ITS CHIEF SECRETARY.
2.
THE PRINCIPAL SECRETARY
DEPARTMENT OF INDUSTRIES
AND COMMERCE, STATE OF KARNATAKA
1ST FLOOR, VIKASA SOUDHA
BENGALURU – 560 001.
3.
THE PRINCIPAL SECRETARY
DEPARTMENT OF REVENUE
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU – 560 001.
4.
THE PRINCIPAL SECRETARY
DEPARTMENT OF AGRICULTURE
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU – 560 001.
5.
THE DIRECTOR
DEPARTMENT OF HORTICULTURE
LALBAGH, BENGALURU – 560 004.
6.
THE EXECUTIVE MEMBER
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD, (KIADB)
KHANIJA BHAVANA, BENGALURU – 560 001.
7.
THE CHAIRMAN/ MEMBER SECRETARY
KARNATAKA STATE POLLUTION
CONTROL BOARD, CHURCH STREET
BENGALURU – 560 001.
8.
THE SECRETARY
DEPARTMENT OF MINOR IRRIGATION
AND TANKS/LAKES
STATE OF KARNATAKA, VIDHANA SOUDHA
BENGALURU – 560 001.
9.
THE DEPUTY COMMISSIONER
BANGALORE URBAN DISTRICT
BENGALURU – 560 001.
10 . THE SPECIAL LAND ACQUISITION OFFICER-1
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD, (KIADB)
PALACE ROAD, BENGALURU – 560 001.
11 . THE TAHASILDAR
ANEKAL TALUK
ANEKAL BENGALURU DISTRICT
PIN – 562 106.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1 TO R5, R8, R9 AND
R11;
SRI LOKESHA K., ADVOCATE FOR R7;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R6 AND R10)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO CALL FOR THE
ENTIRE RECORDS PERTAINING TO NOTIFICATION TO ACQUIRE
LANDS WITH KIADB ACT IN THE VILLAGE, HANDENAHALLI
SOLLEPURA, MUTHANALLUR AMANIKERE OF SARJAPURA HOBLI,
ANEKAL TALUK, BANGALORE URBAN DISTRICT IN CI 59-SPQ 2024
DTD. 15.03.2024; QUASH THE NOTIFICATION NO. CI-59-SPQ-2024
DTD. 15.03.2024 AT ANNX-E NOTIFICATION NO. CI 59-SPQ 21024
DTD.
03.10.2024
AT
ANNX-H
AND
NOTICE
NO.
KIADB/BNG/NAGARA/BHUSWA/2024-25
DTD.
13.02.2024
AT
ANNX-M1 AND M2 IN SO FAR AS PETITIONER CONCERNED ONLY,
CONSEQUENTLY TO DECLARE THAT THE NOTIFICATION ISSUED IS
ARBITRARY AND AGAINST THE PRINCIPLES/ POLICIES OF THE
GOVERNMENTS.
IN WRIT PETITION No.3447 OF 2025
BETWEEN:
1.
SRI T.SAMPANGI
S/O THIMMAIAH
AGED ABOUT 62 YEARS
R/AT NO.27/1, S.MEDIHALLI
BIDARAGUPPE POST
BENGALURU - 562 107.
2.
SMT. R.RATHNAMMA
W/O ASHOK REDDY
AGED ABOUT 53 YEARS
R/AT NO.30, S.MEDIHALLI
BIDARAGUPPE POST
BENGALURU - 562 107.
3.
SRI Y.KRISHNA REDDY
S/O LATE YALLAREDDY
AGED ABOUT 59 YEARS
R/AT NO.73, S.MEDIHALLI
BIDARAGUPPE POST
4.
BENGALURU - 562 107.
SRI Y.NARAYANA REDDY
S/O LATE YALLAREDDY
AGED ABOUT 74 YEARS
R/AT NO.35, S.MEDIHALLI
BIDARAGUPPE POST
BENGALURU - 562 107.
5.
SRI M.S.SRINIVAS
S/O LATE SHANKARAPPA
AGED ABOUT 55 YEARS
R/AT S.MEDIHALLI, BIDARAGUPPE POST
SARJAPURA HOBLI, ANEKAL TALUK
BENGALURU DISTRICT - 562 107.
6.
SRI P.ERA REDDY
S/O PILLA REDDY
AGED ABOUT 58 YEARS
R/AT NO.54, S.MEDAHALLI
SARJAPURA ROAD, ANEKAL
BENGALURU - 562 107.
7.
SMT. T.RATHNAMMA
W/O KRISHNA REDDY
AGED ABOUT 74 YEARS
R/AT S.MEDIHALLI
BIDARAGUPPE POST, ANEKAL TALUK
BENGALURU DISTRICT - 562 107.
8.
SRI KRISHNA REDDY
S/O GULLA REDDY
AGED ABOUT 78 YEARS
R/AT S.MEDIHALLI
BIDARAGUPPE POST
ANEKAL TALU
BENGALURU DISTRICT - 562 107.
9.
SRI S.RAMASWAMY REDDY
S/O LATE SIDDA REDDY
AGED ABOUT 64 YEARS
R/AT NO.56/1, S.MEDIHALLI
BIDARAGUPPE POST, ANEKAL TALUK
BENGALURU DISTRICT - 562 107.
10 .
SRI KRISHNA REDDY
S/O CHWDA REDDY
AGED ABOUT 83 YEARS
R/AT S.MEDIHALLI, BIDARAGUPPE POST
ANEKAL TALUK, BENGALURU DISTRICT - 562 107.
11 .
SRI KRISHNA REDDY
S/O LATE RAMAIAH
AGED ABOUT 83 YEARS
R/AT VTC-S-MEDIHALLI PO
BIDARAGUPPE, SUB DISTRICT
ANEKAL, BENGALURU DISTRICT - 562 107.
12 .
SMT. PARVATHAMMA
W/O LATE RAMASWAMY REDDY
AGED ABOUT 66 YEARS
R/AT 1ST STREET, S.MEDIHALLI
BENGALURU - 562 107.
... PETITIONERS
(BY SRI M.SHIVAPRAKASH, ADVOCATE)
AND:
1.
THE UNION OF INDIA
DEPARTMENT OF TEXTILE AND COMMERCE
UDYOG BHAWAN, NEW DELHI - 110 011
REPRESENTED BY ITS SECRETARY.
2.
THE STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001
REPRESENTED BY ITS
CHIEF SECRETARY.
3.
THE PRINCIPAL SECRETARY
DEPARTMENT OF INDUSTRIES
AND COMMERCE, STATE OF KARNATAKA
1ST FLOOR, VIKASA SOUDHA
BENGALURU - 560 001.
4.
THE PRINCIPAL SECRETARY
DEPARTMENT OF REVENUE
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001.
5.
THE PRINCIPAL SECRETARY
DEPARTMENT OF AGRICULTURE
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001.
6.
THE DIRECTOR
DEPARTMENT OF HORTICULTURE
AND SERICULTURE
STATE OF KARNATAKA
LALBAGH, BENGALURU - 560 004.
7.
THE PRINCIPAL SECRETARY
DEPARTMENT OF MINOR IRRIGATION
AND TANKS/LAKES, STATE OF KARNATAKA
VIDHANA SOUDHA, BENGALURU - 560 001.
8.
THE CHAIRMAN/MEMBER SECRETARY
KARNATAKA STATE POLLUTION
CONTROL BOARD, CHURCH STREET
BENGALURU - 560 001.
9.
THE EXECUTIVE MEMBER
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD, (KIADB)
KHANIJA BHAVAN, BENGALURU - 560 001.
10 .
THE CHAIRMAN/SECRETARY
CENTRAL SILK BOARD
BTM LAYOUT, BENGALURU - 560 076.
11 .
THE DEPUTY COMMISSIONER
BANGALORE URBAN DISTRICT
KANDAYA BHAVAN
BENGALURU - 560 009.
12 .
THE ASSISTANT COMMISSIONER
BENGALURU SOUTH, BENGALURU.
13 .
THE TAHASILDAR
ANEKAL TALUK
ANEKAL, BENGALURU DISTRICT
PIN - 562 106.
14 .
M.SHIVAKUMAR
THE SPECIAL LAND ACQUISITION OFFICER-II
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD, (KIADB)
PALACE ROAD, BHARATH SCOUTS AND
GUIDE BUILDING, BENGALURU - 560 001.
MR. TEJAS KUMAR
SPECIAL LAND ACQUISITION OFFICER-II
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD, (KIADB)
PALACE ROAD, BHARATH SCOUTS AND
GUIDE BUILDING, BENGALURU - 560 001.
... RESPONDENTS
(BY SRI H.SHANTHI BHUSHAN, DSGI FOR R1;
SRI SPOORTHY HEGDE N., HCGP FOR R2, TO R7, R11 TO R13;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R9 AND R15;
SRI AJAY J.NANDALIKE, ADVOCATE FOR R14;
NOTICE TO R10 IS DISPENSED WITH VIDE ORDER DATED
05/02/2025)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO CALL FOR THE
ENTIRE RECORDS PERTAINING TO NOTIFICATION TO ACQUIRE
LANDS WITH KIADB ACT IN THE VILLAGE S.MEDAHALLI OF
SARJAPURA HOBLI, ANEKAL TALUK, BANGALORE URBAN DISTRICT
IN CI 58-SPQ 2024 DATED 15/3/2024; QUASH THE NOTIFICATION
ISSUED UNDER SEC. 28(1) VIDE NO. CI-58-SPQ-2024 DATED
15/3/2024 AT ANNEXURE-F, AND NOTIFICATION UNDER SEC.
28(4) VIDE NO.CI 58-SPQ 2024 DATED 2/12/2024 AT ANNEXURE-G
AND NOTICE NO. BENGALURU/VIBHUSWAHA/2/243/2023-24 AND
NOTICE NO. BENGALURU/VIBHUSWAHA/2/270/2023-24 DATED
6/5/2024 AT ANNEXURE-K1 TO K14, CONSEQUENTLY TO DECLARE
THAT THE NOTIFICATION ISSUED IS NOT SUSTAINABLE IN THE
EYE OF LAW.
IN WRIT PETITION No.4055 OF 2025
BETWEEN:
1.
SRI G.RAJANNA
S/O GULLAPPA
AGED ABOUT 54 YEARS
R/AT NO.106, NEAR EXIDE GATE
THYVAKANAHALLI VILLAGE
TYAVAKANAHALLI, BIDARAGUPPE
ANEKAL, BENGALURU - 562 107.
2.
SRI JAYARAMA REDDY
S/O BEERA REDDY
AGED ABOUT 72 YEARS
3.
R/AT NO.46/4, NEW JANATA COLONY
S.MEDIHALLI, BIDARAGUPPE POST
BENGALURU - 562 107.
GOVINDA REDDY
S/O CHINNA REDDY
AGED ABOUT 62 YEARS
R/AT NO.42/3, NEAR FLOUR MILL
S.MEDIHALLI, BIDARAGUPPE POST
BENGALURU - 562 107.
4.
SRI GOPALACHARY
S/O RAMACHARI
AGED ABOUT 53 YEARS
R/O S.MEDIHALLI
BIDARAGUPPE POST
BENGALURU - 562 107.
5.
SRI MUNIKRISHNA
S/O KAKAPPA
AGED ABOUT 51 YEARS
R/AT NO.54, S.MEDIHALLI
BIDARAGUPPE POST
BENGALURU DISTRICT - 562 107.
6.
SRI CHINNAPPA
S/O MUNIYAPPA
AGED ABOUT 64 YEARS
R/O S.MEDAHALLI
BIDARAGUPPE POST, ANEKAL
BENGALURU - 562 107.
7.
SMT. SUSHEELAMMA
W/O LATE MUNITHIMMAIAH
AGED ABOUT 64 YEARS
R/AT NO.51, S.MEDIHALLI
BIDARAGUPPE POST
BENGALURU DISTRICT - 562 107.
... PETITIONERS
(BY SRI M.SHIVAPRAKASH, ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001
REPRESENTED BY ITS CHIEF SECRETARY.
2.
THE PRINCIPAL SECRETARY
DEPARTMENT OF INDUSTRIES AND COMMERCE
STATE OF KARNATAKA
1ST FLOOR, VIKHASA SOUDHA
BENGALURU - 560 001.
3.
THE PRINCIPAL SECRETARY
DEPARTMENT OF REVENUE
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001.
4.
THE PRINCIPAL SECRETARY
DEPARTMENT OF AGRICULTURE
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001.
5.
THE DIRECTOR
DEPARTMENT OF HORTICULTURE
AND SERICULTURE
STATE OF KARNATAKA
LALBAGH, BENGALURU - 560 004.
6.
THE EXECUTIVE MEMBER
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD, (KIADB),
KHANIJA BHAVAN, BENGALURU - 560 001.
7.
THE CHAIRMAN/SECRETARY
CENTRAL SILK BOARD, BTM LAYOUT
BENGALURU - 560 076.
8.
THE DEPUTY COMMISSIONER
BENGALURU URBAN DISTRICT
KANDAYA BHAVAN, BENGALURU - 560 009.
9.
THE ASSISTANT COMMISSIONER
BENGALURU SOUTH
BENGALURU – 560 001.
10 .
THE TAHASILDAR
ANEKAL TALUK, ANEKAL
BENGALURU DISTRICT
PIN: 562 106.
11 .
THE SPECIAL LAND ACQUISITION OFFICER-II
KARNATAKA INDUSTRIAL AREA DEVELOPMENT
BOARD, (KIADB), PALACE ROAD
BHARATH SCOUTS AND GUIDE BUILDING
BENGALURU - 560 001.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1 TO R5, AND R8,TO R10;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R6 AND R11)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO CALL FOR THE
ENTIRE RECORDS PERTAINING TO NOTIFICATION TO ACQUIRE
LANDS WITH KIADB ACT IN THE VILLAGE S-MEDAHALLI OF
SARJAPURA HOBLI, ANEKAL TALUK, BANGALORE URBAN DISTRICT
IN CI 58-SPQ 2024 DTD. 15.03.2024 (ANNX-E1); QUASH THE
NOTIFICATION ISSUED UNDER SEC. 28(1) VIDE NO.CI-58-SPQ2024 DATED 15/3/2024 AT ANNEXURE-E1, AND NOTIFICATION
UNDER SEC. 28(4) VIDE NO.CI 58-SPQ 2024 DATED 02/12/2024
AT
ANNEXURE-E2
AND
NOTICE
NO.BENGALURU/
VIBHUSWAHA/2/270/2023-24 DATED 6/5/2024 AT ANNEXURE-E3,
CONSEQUENTLY TO DECLARE THAT THE NOTIFICATION ISSUED IS
NOT SUSTAINABLE IN THE EYE OF LAW.
IN WRIT PETITION No.4061 OF 2025
BETWEEN:
SRI PULLANKAVUMKAL CHACKO CHACKO
SON OF MR. PULLANKAVUMKAL CHACKO
AGED ABOUT 73 YEARS
RESIDING AT PULICKALLU P.O.
KARICKATTOOR, KOTTAYAM DISTRICT
KERALA, REPRESENTED BY HIS GPA HOLDER
MR. JOSEPH VARGHESE.
... PETITIONER
(BY SRI TAJI GEORGE, ADVOCATE)
AND:
1.
STATE OF KARNATAKA
DEPARTMENT OF INDUSTRIES AND COMMERCE
DR. B.R.AMBEDKAR BEEDI
VIKASA SOUDHA
BENGALURU - 560 001
REPRESENTED BY ADDITIONAL CHIEF SECRETARY.
2.
THE KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
IV AND V FLOORS, EAST WING
KHANIJA BHAVAN
RACE COURSE ROAD
BENGALURU - 560 001
REPRESENTED BY ITS
CHIEF EXECUTIVE OFFICER
AND EXECUTIVE MEMBER.
3.
SPECIAL DEPUTY COMMISSIONER
KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
IV AND V FLOORS, EAST WING
KHANIJA BHAVAN, RACE COURSE ROAD
BENGALURU - 560 001.
4.
THE SPECIAL LAND ACQUISITION OFFICER-2
KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
MAHARSHI ARVIND BHAVAN
1ST FLOOR, NRUPATHUNGA ROAD
BENGALURU - 560 001.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 TO R4)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 OF THE
CONSTITUTION
OF
INDIA
PRAYING
TO
QUASH
THE
NOTIFICATIONS BEARING NO. CI 58 SPQ 2024 DTD. 15.03.2024
ISSUED UNDER SECTIONS 3(1), 1(3) AND 28(1) OF THE KIAD ACT,
1966 AT ANNX-A TO C ISSUED BY R-1 AND THE FINAL
NOTIFICATION BEARING NO. CI 58 SPQ 2024 DTD. 02.12.2024 AT
ANNX-D ISSUED BY R-1 IN SO FAR AS THE PETITIONERS LANDS
MENTIONED AT PARAGRAPH NO.3 AND 4 ARE CONCERNED.
IN WRIT PETITION No.4737 OF 2025
BETWEEN:
1.
SRI PILLAPPA
S/O DODDAMUNIYAPPA
AGED ABOUT 58 YEARS
2.
SMT. MUNIKAVERAMMA
W/O LATE YELLAPPA
AGED ABOUT 80 YEARS
3.
SRI Y.GANESH
S/O LATE YELLAPPA
AGED ABOUT 45 YEARS
4.
SRI SRINIVASA REDDY M.,
S/O LATE MUNISWAMAPPA
AGED ABOUT 54 YEARS
ALL ARE RESIDENTS OF
S.MEDAHALLI VILLAGE
SARJAPURA HOBLI
ANEKAL TALUK - 562 107
BENGALURU RURAL DISTRICT.
... PETITIONERS
(BY SRI M.SHIVAPRAKASH, ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001
REPRESENTED BY ITS CHIEF SECRETARY.
2.
THE PRINCIPAL SECRETARY
DEPARTMENT OF INDUSTRIES
AND COMMERCE, STATE OF KARNATAKA
1ST FLOOR, VIKASA SOUDHA
BENGALURU - 560 001
3.
THE PRINCIPAL SECRETARY
DEPARTMENT OF REVENUE
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001.
4.
THE PRINCIPAL SECRETARY
DEPARTMENT OF AGRICULTURE
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001.
5.
THE DIRECTOR
DEPARTMENT OF HORTICULTURE
LALBAGH, BENGALURU - 560 004.
6.
THE EXECUTIVE MEMBER
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD, (KIADB)
KHANIJA BHAVAN, BENGALURU - 560 001.
7.
THE SECRETARY
DEPARTMENT OF MINOR IRRIGATION
AND TANKS/LAKES
STATE OF KARNATAKA
VIDHANA SOUDHA
BENGALURU - 560 001.
8.
THE DEPUTY COMMISSIONER
BENGALURU URBAN DISTRICT
BENGALURU - 560 001.
9.
THE SPECIAL LAND ACQUISITION OFFICER-II
KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD, (KIADB),
PALACE ROAD, BENGALURU - 560 001.
10 .
THE TAHASILDAR
ANEKAL TALUK
ANEKAL, BENGALURU DISTRICT
PIN: 562 106.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1 TO R5, R8, R9 AND
R11;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R6 AND R10)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 R/W 48A AND 51A(G) OF THE CONSTITUTION OF INDIA
PRAYING TO ACQUIRE LANDS WITH KIADB ACT IN THE VILLAGE
HANDENAHALLI SOLLEPURA, MUTHANALLUR AMANIKERE OF
SARJAPURA HOBLI, ANEKAL TALUK, BANGALORE URBAN DISTRICT
IN
CI
58-SPQ
DTD.
15.03.2024
AT
ANNX-D1;
QUASH THE NOTIFICATION NO. CI-58-SPQ-2024 DTD. 15.03.2024
AT ANNX-D1 NOTIFICATION NO. CI 58-SPQ 2024 DTD. 02.12.2024
AT ANNX-D2 AND NOTICE NO. BENGALURU/VI-BHUSWA2/270/2023-24
DTD.
06.05.2024
AT
ANNX-E1
TO
E3
RESPECTIVELY, IN RESPECT OF PETITIONER LANDS OF
S.MEDAHALLI
CONSEQUENTLY
TO
DECLARE
THAT
THE
NOTIFICATION ISSUED IS ARBITRARY AND AGAINST THE
PRINCIPLES / POLICIES OF THE GOVERNMENTS.
IN WRIT PETITION No.5030 OF 2025
BETWEEN:
CONFIDENT PROJECTS INDIA PRIVATE LIMITED
COMPANY REGISTERED UNDER
THE COMPANIES ACT, 1956
NO. 6, LANGFORD TOWN
HOSUR MAIN ROAD, SHANTI NAGAR
BENGALURU - 560 025
REPRESENTED BY ITS
AUTHORIZED SIGNATORY
SRI T.K.SUNDARAM
... PETITIONER
(BY SRI VIVEK HOLLA, ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
REPRESENTED BY ITS SECRETARY
DEPARTMENT OF COMMERCE AND INDUSTRIES
VIKAS SOUDHA, BENGALURU - 560 001.
2.
KARNATAKA INDUSTRIAL
AREAS DEVELOPMENT BOARD
NRUPATHUNGA ROAD
BENGALURU - 560 002
REPRESENTED BY ITS
CHIEF EXECUTIVE OFFICER.
3.
THE SPECIAL LAND ACQUISITION OFFICER
KARNATAKA INDUSTRIAL AREAS
DEVELOPMENT BOARD
NRUPATHUNGA ROAD
KHENI BUILDINGS
BENGALURU - 560 009.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 AND R3)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE
NOTIFICATION DTD. 02.12.2024 ISSUED BY THE R-1 IN NO. CI 58
SPQ 2024 (ANNX-AC) IN SO FAR AS THE SAME RELATES TO THE
PETITIONERS LAND; QUASH THE NOTIFICATION DTD. 15.03.2024
ISSUED BY THE R-1 IN NO. CI 58 SPQ 2024 (ANNX-Q) IN SO FAR
AS THE SAME RELATES TO THE PETITIONERS LAND.
IN WRIT PETITION No.5148 OF 2025
BETWEEN:
1.
CENTURIONS HOUSING AND
CONSTRUCTIONS PVT. LTD.,
A COMPANY REGISTERED UNDER
THE PROVISIONS OF THE COMPANIES ACT, 1956
HAVING ITS REGISTERED OFFICE AT
33 AND 35 (PLOT NO. 23 AND 24)
SOUTH BEACH AVENUE, MRC NAGAR
RAJA ANNAMALAIPURUAM
CHENNAI, TAMIL NADU - 600 028
REPRESENTED BY ITS DIRECTOR
D.S. PATIL.
2.
SRI SAI SHELTERS
A PARTNERSHIP FIRM REGISTERED UNDER
THE PROVISIONS OF THE PARTNERSHIP ACT, 1932
HAVING ITS REGISTERED OFFICE AT
NO. 46, 7TH MAIN, YESHWANTHPUR
BENGALURU - 560 022
REPRESENTED BY ITS PARTNER
MADHUSUDHAN REDDY.
... PETITIONERS
(BY SRI PRABHULING K.NAVADGI, SENIOR ADVOCATE A/W.,
SRI JOSEPH ANTHONY, ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
REP. BY ITS PRINCIPAL SECRETARY
INDUSTRIES AND COMMERCE
VIKASA SOUDHA, BENGALURU - 560 001.
2.
THE KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD
NO.14/3, RASTROTHANA BUILDING
NEAR RESERVE BANK
NRUPATHUNGA ROAD
BENGALURU - 560 001
REP. BY ITS CHAIRMAN.
3.
THE SPECIAL LAND ACQUISITION OFFICER
KIADB, NO.14/3, RASTROTHANA BUILDING
NEAR RESERVE BANK
NRUPATHUNGA ROAD
BENGALURU - 560 001
REP. BY ITS CHIEF EXECUTIVE OFFICER.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 AND R3)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE
PRELIMINARY NOTIFICATION DATED MARCH 15, 2024 BEARING
NO. CI 59 S PQ 2024 INSOFAR AS IT PERTAINS TO THE SCHEDULE
PROPERTY OF THE PETITIONER (ANNX-B).
IN WRIT PETITION No.5949 OF 2025
BETWEEN:
PURAVANKARA LIMITED
A COMPANY REGISTERED UNDER
THE PROVISIONS OF THE COMPANIES ACT, 1956
HAVING ITS REGISTERED OFFICE AT
130/1, ULSOOR ROAD
BENGALURU - 560 042
REPRESENTED BY ITS EXECUTIVE LEGAL
SHREYA V.K.JAIN.
... PETITIONER
(BY SRI PRABHULING K.NAVADGI, SENIOR ADVOCATE A/W.,
SRI JOSEPH ANTHONY, ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
REPRESENTED BY ITS
PRINCIPAL SECRETARY
INDUSTRIES AND COMMERCE
VIKASA SOUDHA
BENGALURU - 560 001.
2.
THE KARNATAKA INDUSTRIAL
AREA DEVELOPMNET BOARD
NO. 14/3, RASTROTHANA BUILDING
NEAR RESERVE BANK
NRUPATHUNGA ROAD
BENGALURU - 560 001
REP. BY ITS CHAIRMAN.
3.
THE SPECIAL LAND ACQUISITION OFFICER
KIADB, NO. 14/3, RASTROTHANA BUILDING
NEAR RESERVE BANK
NRUPATHUNGA ROAD
BENGALURU - 560 001
REPRESENTED BY ITS
CHIEF EXECUTIVE OFFICER.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI B.B.PATIL, ADVOCATE FOR R2 AND R3)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE
PRELIMINARY NOTIFICATION DATED MARCH 15, 2024 BEARING
NO.CI 58 SPQ 2024 ISSUING BY R1 INSOFAR AS IT PERTAINS TO
THE SCHEDULE PROPERTY OF THE PETITIONER (ANNEXURE B).
IN WRIT PETITION No.20573 OF 2025
BETWEEN:
FERNS ESTATES AND DEVELOPERS
A PARTNERSHIP FIRM REGISTERED BEFORE
THE REGISTRAR OF FIRMS, SHIVAJINAGAR
BENGALURU, REPRESENTED BY ITS
MANAGING PARTNER
MR. ERROL FERNANDES
REPRESENTED BY HIS POWER OF ATTORNEY HOLDER
MR. JASON JOSEPH FERNANDES
S/O MR. ERROL FERNANDES
AGED ABOUT 29 YEARS
NO.95, AMAR JYOTHI LAYOUT
INTERMEDIATE RING ROAD
DOMLUR, BENGALURU - 560 071.
... PETITIONER
(BY SRI VIVEK ANAND ANTHONY BRITTO, ADVOCATE)
AND:
1.
THE STATE OF KARNATAKA
REPRESENTED BY ITS
PRINCIPAL SECRETARY TO GOVERNMENT
DEPARTMENT OF INDUSTRIES
AND COMMERCE, VIKASA SOUDHA
DR. B. R. AMBEDKAR VEEDHI
BENGALURU - 560 001.
2.
THE KARNATAKA INDUSTRIAL
AREA DEVELOPMENT BOARD
NO.14/3, RASTROTHANA BUILDING
NEAR RESERVE BANK OF INDIA
NRUPATHUNGA ROAD
BENGALURU - 560 001
REPRESENTED BY ITS
CHIEF EXECUTIVE OFFICER CUM CHAIRMAN.
3.
THE SPECIAL LAND ACQUISITION OFFICER
KIADB, NO.14/3, RASTROTHANA BUILDING
NEAR RESERVE BANK OF INDIA
NRUPATHUNGA ROAD, BENGALURU - 560 001.
... RESPONDENTS
(BY SRI SPOORTHY HEGDE N., HCGP FOR R1;
SRI K.SHASHI KIRAN SHETTY, ADVOCATE GENERAL A/W.,
SRI H.L.PRADEEP KUMAR, ADVOCATE FOR R2 AND R3)
****
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE
PRELIMINARY NOTIFICATION DATED MARCH 15, 2024 BEARING
NO. CI 58 SPQ 2024 ISSUED BY R1 INSOFAR AS IT PERTAINS TO
THE SCHEDULE PROPERTY OF THE PETITIONER (ANNEXURE-F);
QUASH THE FINAL NOTIFICATION DATED DECEMBER 02, 2024
BEARING NO. CI 58 SPQ 2024 ISSUED BY R1 INSOFAR AS IT
PERTAINS TO THE SCHEDULE PROPERTY OF THE PETITIONER
(ANNEXURE-J).
THESE
WRIT
PETITIONS
HAVING
BEEN
HEARD
AND
RESERVED FOR ORDERS, COMING ON FOR PRONOUNCEMENT THIS
DAY, THE COURT MADE THE FOLLOWING:-
CORAM:
THE HON'BLE MR JUSTICE M.NAGAPRASANNA
CAV ORDER
The conglomeration of these cases, call in question a
preliminary notification dated 15-03-2024, issued by respondent
No.2 - Karnataka Industrial Area Development Board (hereinafter
referred to as ‘the Board’ for short) and a final notification issued
thereon, on 02-12-2024.
The extent of land; ownership and the
details of the owners are all averred in the respective petitions.
2. Facts in brief, germane, are as follows:
2.1. The petitioners in the cases at hand claim to be absolute
owners and in complete possession of lands described in the
schedules to the respective petitions. For the sake of convenience, I
have felt it appropriate to notice the facts obtaining in Writ Petition
No.33550 of 2024 which are similar in other petitions.
The 1st
petitioner is Puravankara Limited (hereinafter referred to as ‘the
Company’ for short). It claims to be in possession of lands totally
measuring 32 acres 04 guntas in Sy.Nos. 110/2 to 4; 120/1 to 3;
207/1 to 4 and several other parcels of land at Medahalli and
Adigarakallahalli Villages, SarjapuraHobli, Anekal Taluk, Bangalore
Urban District. The Company is said to have secured conversion of
lands from agriculture to non-agricultural purposes/for residential
use under Section 95 of the Karnataka Land Revenue Act on various
dates ranging from 04-01-2014 to 27-10-2023. The aforesaid
various parcels of lands were purchased for the purpose of
development to form a residential lay-out. Thus, the purchase and
conversion were over in 10 years. In the interregnum between
24-11-2021 and 12-12-2023 it appears the Company enters into a
Joint Development Agreement with petitioner No.2 covering certain
area of lands. The details of lands that are subject matter of Joint
Development Agreement are appended to the petitions. Therefore,
the lands that the petitioners claim to be in their possession are
lands converted from agriculture to non-agricultural purposes/
residential. It appears that when the petitioner had reason to
believe
that
the
Board
would
acquire
the
said
properties,
communicated to the Board seeking information as to whether the
lands that the petitioners own were part of any acquisition
proceedings.
Communications
galore
between
the
two
culminated that it was not part of acquisition proceedings.
which
The
Company is said to have submitted a development plan to the
Satellite Town Ring Road Authority (‘STRRA’ for short) to develop a
residential lay-out on 22-11-2023. No objection certificates were
also sought from the Grama Panchayath for water supply and
BESCOM for supply of electricity. This was the position of the land
belonging to the Company as on 14-02-2024.
2.2.
On
16-02-2024
the
Board
commences
acquisition
proceedings. The Development Officer of the Board and the Special
Land Acquisition Officer together conduct a spot inspection in
connection with acquisition of 600 acres of land for formation of an
industrial area. According to the spot inspection, the entire extent
of land was not developed and mainly consisted of dry lands. There
was no development activity in the said lands and the same were
suitable for formation of industrial area in terms of connectivity and
their character. The said report is said to have been placed before
the Board and the Board resolves in its meeting held on 20.02.2024
that there is immense demand for industrial lands and various
industries and entrepreneurs in the said area were ready to accept
the proposal for acquisition of 600 acres of lands in various villages.
Thus, emerges a preliminary notification on 15-03-2024 under
Section 28(1) of the Karnataka Industrial Areas Development Board
Act, 1966 (hereinafter referred to as ‘the Act’ for short) for
acquisition of various lands including the schedule properties in all
these petitions. Individual notices were then issued under Section
28(2) of the Act on 06-05-2024. Pending replies/objections to the
individual notices, spot inspection takes place for acquiring another
800 acres of land for the purpose of setting up an integrated
industrial area. Public notifications were issued with regard to the
said additional acquisition. The petitioners in all these cases file
their objections between 16-07-2024 and 26-09-2024 to the
preliminary notification so issued and individual notices so sent as
obtaining under Section 28(1) and 28(2) of the Act. On 09-10-2024
the Board passes orders under Section 28(3) of the Act rejecting all
the objections of the petitioners by holding that the lands were
essential for industrial purposes and appropriate compensation
would be awarded under the Land Acquisition Act, 2013. Thereafter
on 02-12-2024 comes the final notification under Section 28(4) of
the Act. Challenging the said final notification, these petitions are
preferred on 07-12-2024 and on subsequent dates.
3. Heard Sri Prabhuling K. Navadgi, learned senior counsel
along with Sri Joseph Anthony, learned counsel for the petitioners
in W.P.Nos.33550/2024, 5148/2025, 5949/2025, Sri Murali N.,
learned counsel for the petitioner in W.P.No.6708/2025, Sri M.
Shivaprakash,
learned
W.P.Nos.515/2025,
counsel
for
1405/2025,
the
petitioners
3447/2025,
in
4055/2025,
4737/2025, , Sri Taji George, learned counsel for the petitioner in
W.P.No.4061/2025, Sri Varadarajan M.S., learned counsel for the
petitioner
counsel
in
for
W.P.No.1173/2025,
Sri
the
W.P.Nos.255/2025,
petitioners
in
Rajeswara
P.N.,
learned
293/2025,
671/2025, 672/2025, 1280/2025, Sri Ajith P.B., learned counsel for
the petitioner in W.P.No.1399/2025, Sri Vivek Holla, learned
counsel for the petitioner in W.P.No.5030/2025, Sri Vivek Anand
Anthony
Britto,
learned
counsel
for
the
petitioner
in
W.P.No.20573/2025, Sri H. Shanthi Bhushan, learned Deputy
Solicitor
General
of
India
for
respondent
No.1
in
W.P.No.3447/2025, Sri Spoorthy Hegde N., learned High Court
Government Pleader for respondent No.1 in all the petitions except
in W.P.No.3447/2025, wherein, he appears for respondent Nos.2 to
7, 11 to 13; in W.P.No.1405/2025, he appears for respondent Nos.1
to 5, 8, 9 and 11 and Sri K. Shashi Kiran Shetty, learned Advocate
General along with Sri H.L.Pradeep Kumar, learned counsel for
respondent
Nos.2
and
in
all
the
petitions
except
in
W.P.No.3447/2025, wherein appears for respondent Nos.9 and 15;
in W.P.No.1405/2025, appears for respondent Nos.6 and 10, Sri
Lokesha K., learned counsel for respondent No.7 and Sri Ajay J.
Nandalike,
learned
counsel
for
respondent
No.14
in
W.P.No.3447/2025.
4.1. Sri Prabhuling K. Navadgi, learned senior counsel
spearheading the submissions in all these cases for the petitioners,
would seek to contend that respondent No.2 – Karnataka Industrial
Area Development Board (hereinafter referred to as ‘the Board’)
has indulged in brazen exercise of power in several aspects of
acquisition and has behaved as acquisition in the colonial era.
Learned senior counsel further submits that two circulars are issued
by the State Government one on 03-03-2007 and another on
18-03-2013. The first circular mandates that the lands converted
from agricultural to non-agricultural ought to be excluded when the
lands are acquired for industrial purposes and the other circular
mandates that the residential land should also be excluded from
such acquisition.
4.2. He would submit that the Revised Master Plan 2031 of
the Anekal Local Planning Area, where the properties of the
petitioners are situated, is a residential area, which is shown as
yellow zone in the said plan.
The petitioners are said to have
purchased several parcels of land for development of residential
layout and purchases have been made for the last six years. Lands
have
been
converted
for
non-agricultural
purpose
and
the
conversion order expressly records that the said conversion is for
residential purpose. The STRRA has by an order dated 16-03-2024
granted an approval for residential layout under Section 17(2-A) of
the Town and Country Planning Act, 1961 on an application made
by the petitioner and provisional plan is also in place.
He would
submit that the preliminary notification issued by the Board suffers
from blatant non-application of mind as the petitioners have already
formed 510 residential plots, out of which 422 plots have
agreements of sale being entered into between the parties and 70%
of the homebuyers have availed loans from various banks.
He
would submit that petitioners have made huge investments for the
formation of the layout and are ready to execute the project.
4.3.
Learned
senior
counsel
further
submits
that
the
purported notice under Section 28(3) of the Act is said to have been
issued by Special Land Acquisition Officer, KIADB on 06-05-2024.
The notice indicates 30 days time to file objections and hearing the
stakeholders was scheduled on 22-05-2024 even before the
completion of expiry of 30 days from the date of notice. He would
submit that the petitioners were never aware of the preliminary
notification and become aware only on 25-06-2024. The SLAO has
by a perfunctory enquiry conducted on 22-05-2024, has rejected all
the objections filed by the stakeholders. He would submit that this
would be a classic case where the entire acquisition proceedings is
in vitiation on the score of non-consideration of the objections and
non-application of mind as the orders passed by the SLAO are
cyclostyled orders.
4.4. On the aforesaid facts, the learned senior counsel
projects that the acquisition proceedings lack procedural fairness
and on the said issue seeks to place reliance upon plethora of
judgments to buttress his submission, all of which would bear
consideration in the course of the order. He would contend that the
acquisition proceedings are bad in procedure as it is contravention
of the circulars issued by the State. The acquisition is contrary to
the provisions of the Karnataka Town and Country Planning Act.
The acquisition proceedings must be obliterated on account of
vagueness.
5. Sri M. Shivaprakash, learned counsel for the petitioners
particularly, the landowners who are agriculturists would toe the
lines of the learned senior counsel as observed hereinabove and
would amplify the alleged illegality of the Board in not following the
circulars issued by the State. According to the learned counsel, the
action of the SLAO is in complete violation of law and would
reiterate the submissions of the learned senior counsel that the
objections of the petitioners are not considered by the SLAO and
the final notification would undoubtedly be contrary to law. Perusal
of the record would clearly indicate that the orders passed are all
cyclostyled orders rejecting the objections of the petitioners.
He
would seek quashment of the acquisition proceedings on the sole
score that the petitioners are eking out their livelihood in the farms
that they have constructed and are growing grapes or pomegranate
as the case would be.
He would in all other aspects, adopt the
submissions of the learned senior counsel.
6. Sri Vivek Anand Anthony Britto, learned counsel for the
petitioner in W.P.No.27573/2025 would submit that the petitioner
had purchased several packets of land totalling 6 acres and 34
guntas and the lands belonging to the petitioner are all contiguous
and adjacent to each other.
The acquisition notification issued
under Section 28(4) of the Act seeking to acquire only a part of the
lands owned by the petitioner, are not contiguous and they are at
various places. This leaves the petitioner with few parcels of land
here and there loosing complete contiguity. He would submit that
either all the lands should be acquired or all the lands should be left
over or acquisition should be in uniformity.
He therefore submits
that the entire acquisition is non-application of mind. With regard
to the other submissions, he would toe the lines of Sri Prabhuling K.
Navadgi, learned senior counsel for the petitioners in respective
petitions.
7. Sri M.S.Varadarajan, learned counsel appearing for the
petitioner in W.P.No.1173/2025 would submit that no specific
purpose is stated in the impugned notification justifying the
acquisition.
Adequate opportunity to submit on the objections so
filed is not afforded to the petitioner.
The petitioner in his
objections to the preliminary notification has clearly mentioned that
the construction he has raised on the land is to an area of 50 ft. x
80 ft., which is in final stage, like paint job or otherwise. He would
submit that the land is for the purpose of residential and come
under yellow zone as declared by the Planning Authority.
For
remaining submissions, he would toe the lines of Sri Prabhuling K.
Navadgi, learned senior counsel for the petitioners in respective
petitions.
8. Sri Murali N., learned counsel for the petitioners in
W.P.No.6708/2025 would submit that the lands of the petitioner
have been converted from agricultural to non-agricultural in terms
of the official memorandum and the petitioner have purchased the
said land in terms of the registered sale deed. The petitioners have
filed their objections to drop the land from acquisition, the same is
not considered by issuing the final notification is the submission of
the learned counsel for the petitioner. The learned counsel submits
that the petitioner’s land is abutting the road.
On all these
grounds, the learned counsel would seek quashment of the
proceedings. Insofar as the common grounds urged, would toe the
lines of Sri Prabhuling K. Navadgi, learned senior counsel for the
petitioners in respective petitions.
9. Per contra, learned Advocate General representing the
respondents – Board would refute every one of the submissions,
contending that it is no law that in acquisition of lands for huge
magnitude, every land owners should be heard and every objection
of the petitioners / stakeholders should be considered. The SLAO
by his proceedings on 28-03-2025 has considered each of the
aspects and the objections of each of the land owners and has
tabulated them and rejected or accepted, as the case would be.
The rejection would naturally lead to issuance of final notification.
He would defend the action of the second respondent in contending
that the acquisition is for the purpose of setting up an industry and
what industry would come up would not bear in the acquisition
proceedings.
It is his submission that the consideration of the
objections done by the SLAO is in tune with law.
Insofar as the
circulars are concerned, the Advocate General would submit that it
is circulars for the purpose of functioning of the department, it
cannot override the provision of the Act. The Act clothes the State
with all such power statutorily and therefore, the circulars in the
teeth of the statute would be of no avail.
9.1. Learned Advocate General has placed original records for
a perusal at the hands of this Court with regard to the proceedings
of acquisition.
10. I have given my anxious consideration on the submissions
made by the learned counsel for the respective parties and have
perused the material on record.
11. It is the case of the petitioner in one of the batch of
petitions – M/s Puravankara Limited that the 2nd respondent/Board
on 06-04-2022 had confirmed that lands owned by the petitioners
would not be subject matter of acquisition. This is said to have been
confirmed
again
on
11-04-2022.
On
06-06-2022,
the
3rd
confirmation comes from the Board that lands were not involved in
any proposed industrial acquisition. Owing to the fact that it was
not the subject matter of acquisition, the 1st petitioner applies to
the STRRA for approval of a development plan for the proposed
project
of
the
scheduled
property,
which
residential and commercial development.
was
intended
for
In December, 2023 the
1st and 2nd petitioners entered into a joint development agreement
facilitating joint development of lands between two parties.
In
February, 2024, the 1st petitioner is said to have obtained No
Objection Certificate from Handenahalli Gram Panchayath.
The
petitioner is said to have paid ₹1,51,49,000/- to STRRA for plan
sanction. This happens on 1st March, 2024.
12. When things stood thus, on 15-03-2024, a preliminary
notification comes to be issued notifying the lands which are subject
matter of all these petitions for the purpose of acquisition. The
reason being the industrial development. After issuance of the
preliminary notification, on the next day of notification, it appears a
provisional development plan is proposed for the project in favour
of M/s Puravankara Limited. The petitioner then files its objections
to the proposed acquisition on 10-04-2024. Upon the objections, on
6th May, 2024, the 2nd respondent issued individual notices to the
petitioners under Section 28(2) of the Act informing the proposed
acquisition of lands and a public notification also comes to be issued
on 14-06-2024 and 27-06-2024. Against individual notices that
were issued to the petitioners, the petitioners filed their detailed
objections on two dates – one on 16-07-2024 and the other on
25-07-2024. Claiming to have considered the objections, a final
notification comes to be issued by the Board for acquisition of lands
so notified vide preliminary notification. This is broadly the
challenge
in
all
these
cases.
The
companion
petitions
i.e.,
W.P.No.515 of 2025 and W.P.No.6708 of 2025 are preferred by
agricultural land owners, who are said to be growing grapes or
other fruit bearing crops even as on today in those areas and would
toe the lines of the submissions of the learned senior counsel for
the petitioner in contending that none of the objections filed by the
petitioners have been considered and agricultural lands must be
kept away from the purview of acquisition.
13. The learned senior counsel Sri Prabhuling K. Navadgi and
the
learned
counsel
Sri
M.
Shivaprakash,
Sri
N.Murali
and
Sri Varadarajan appearing for the respective petitioners have relied
on several judgments of the Apex Court and that of this Court, all of
which would bear consideration qua their relevance in the course of
the order.
14. On all the aforesaid facts and submissions, the issues
deducible are four fold.
The first fold being, whether agricultural
lands could become subject matter of acquisition; the second fold,
the notification does not indicate what king of industry is to come
up, as public interest requires disclosure of reasons for acquisition;
the third fold, the acquisition runs counter to two circulars issued by
the State Government and the State Government has given a
gobye to the circulars and the fourth fold, there is no enquiry
conducted by the Special Land Acquisition Officer in terms of
Section 28(3) of the Act, therefore, the final notification under
Section 28(4) is unsustainable.
CONSIDERATION:
FIRST FOLD:
15. The contention is, that agricultural lands cannot become
subject of acquisition at all or right of hearing must be an effective
process and not a mere formality. The petitioners contend that the
executive orders or the Government orders on the issue cannot be
given a go-bye, by the State itself.
15.1. The issue whether agricultural lands can be the subject
matter of acquisition or not, is considered by this Court in the case
of M.HOOLEPPA v. STATE OF KARNATAKA1, wherein it is held as
follows:
“….
….
….
65. As rightly contended by Mr.Sabarad, learned counsel
appearing for the respondents 1 and 2 and Sri.Uday Holla,
learned Senior counsel appearing on behalf of 3rd respondent,
when vast tracts of lands are acquired for a specific purpose like
in the instant case, setting up of an integrated steel plant, a
portion of the land which even if it were to be garden land or
fertile land cannot be left out or it cannot be excluded from the
purview of acquisition has to be accepted and in this
background, the circular dated 03.03.2007 has to be read.
Infact
Co-ordinate
Bench
of
this
Court,
in Basappa v. State of Mysore, reported in (1974) 1 Kant
LJ (SN) 273 while examining the vires of provision of
2014 SCC OnLine Kar.13559
KIADB Act has held that lands which are garden lands
equipped with well and pump or the lands which are
situated near the gramatana and likely to be needed for
the village extension would not be a relevant ground for
exclusion from acquisition.Division Bench of this Court in
the case of Smt. Venkatamma v. Deputy Commissioner,
Bangalore District, reported in AIR 1995 Kar 351 while
examining the legality of the acquisition of lands under
the Karnataka acquisition of lands for grant of house sites
Act, 1972 has held that even the agricultural lands
located in the green belt area can also be acquired for a
public purpose. It has been held as under:
“9. We do not think that there is any substance
in this contention also. The Act does not limit the
power of the State Government to acquire any land for
a public purpose. No other provision of law has been
pointed out to us in support of the contention that
agricultural lands situated in green-belt cannot be
acquired by the State Government. In our opinion,
what the State Government is required to do in
such cases is to consider whether the said land
can still be regarded as suitable for the purpose
for which it is sought to be acquired.Section 95
of the Karnataka Land Revenue Act, restricts the
power of an occupant of agricultural land to put
it to any other use without permission. It does
not put any restriction on the power of the State
Government to utilise such land for any other
purpose. Moreover, the Deputy Commissioner
has the power under that provision to permit
change of user of agricultural land. We can safely
assume that the State Government was aware of
this provision and keeping in mind this provision
it thought it fit to acquire the appellants’ land.
Even though it is now included in the green-belt
it cannot be said that the satisfaction of the
State Government in that behalf is not
genuine”.”
(Emphasis supplied)
15.2. In the case of SMT. C.N.SHARADA v. THE STATE OF
KARNATAKA2, a learned single Judge of this Court has held as
follows:
“….
….
….
14. The petitioners have sought to challenge the
acquisition proceedings on two grounds. In fact, the two
grounds are interconnected. It was contended that no
notices were issued to the petitioners, nevertheless, they
filed objections before the SLAO contending that the
lands in question are fertile agricultural lands and
therefore, they should not be acquired.The foundation for
such objections is the Circular dated 18.03.2013. The
learned Advocate General is right in his submissions, that
the said Circular had in fact clarified the earlier Circular
dated 03.03.2007. The earlier circular dated 03.03.2007
found undesirable effect, not supported by the statutory
provisions. Therefore, in the case of M.Hooleppa& Others
Vs. State of Karnataka & Others, 2014 SCC OnLine Kar.
13559, it was held that such pockets of lands, though
fertile lands, cannot be left out of the acquisition
proceedings, since it would form islands within the
industrial area. A Division Bench of this Court in the case of
Sri C.Somashekar (supra) held that the Circular can only be
treated as a guideline to the acquiring body and reliance sought
to be placed by the petitioners on the strength of such Circular
would be misplaced and would defeat the purposes of
acquisition. Realising the mischief, the State Government
thought it fit to clarify the Circular dated 03.03.2007 and
consequently, issued another Circular on 18.03.2013.”
(Emphasis supplied)
Writ Petition No.12128 of 2015 decided on 22-09-2023
15.3. Further, another Division Bench of this Court in the case
of KARNATAKA INDUSTRIAL AREA DEVELOPMENT BOARD v.
THE STATE OF KARNATAKA3, has held as follows:
“….
….
….
11. Similarly, there is no material to show that in about
37 acres of land, thick forest growth is found and that
destruction of the same would affect the ecological balance and
the environment. As rightly contended by the learned Counsel
for the appellants, the record of rights produced collectively at
Annexure-M series do not show such tree growth in an extent of
37 acres of land. Even assuming that in some of these
survey numbers some tree growth and greenery has
come up, the same cannot be characterized as forest for
the purpose of Section 2 of the Forest Conservation Act,
1980. Therefore, it is not possible to accept the
contention that private lands where trees have been
grown cannot be acquired for public purpose and that
such acquisition violates the fundamental duties of the
citizens under Article 51A of the Constitution. It cannot
also be said that such acquisition will be against the ratio
laid
down
in Godavarman's case.
The
systematic
development of industrial area as provided under the Act
cannot be prevented on such considerations. The
fundamental duty cast on the citizen to protect the environment
and the forests cannot be stretched to such an extent to set
aside acquisition made of private lands for public purpose.”
(Emphasis supplied)
All the afore-quoted judgments rendered by this Court would
clearly indicate that there is no bar in proposing to acquire
2010 SCC OnLine Kar. 4387
agricultural lands or the lands in the green belt area for the
purpose of establishment of industrial areas. The coordinate
Bench in the judgments quoted supra, following the judgment of
the Apex Court, observes that systematic development of
industrial areas as provided under the Act cannot be prevented
on consideration that there is growth or greenery has come up
or otherwise. Therefore, the first fold that agricultural lands
cannot become subject matter of acquisition as contended by the
respective learned counsel does not hold water.
SECOND FOLD:
16. The submission is, that there is no indication in the
Notification as to why the acquisition has become necessary, as
public
interest
would
require
disclosure
of
reasons
for
acquisition. What kind of industry would come up should be
indicated in the Notification.
The said submission is again
unacceptable. The acquisition of lands in the case at hand is for
industrial purpose. If it is for industrial purpose, it is rather
difficult to project as to what kind of industry that the Board is
wanting to set up. The law does not make it obligatory on the
part of acquiring authority to disclose complete details as to
what it is going to do with the acquired land. It is for this reason
that
the
preliminary
notifications
generally
would
contain
whether the lands are being acquired for residential purpose or
to set up an industrial area.
If it is setting up an industrial area,
every notification need not project as to what kind of industry or
infrastructural facility would come up in the proposed lands for
acquisition. Therefore, the submissions that agricultural lands
cannot become the subject matter of acquisition have been
considered and negatived by different Benches of this Court.
16.1. The Apex Court in the case of P. NARAYANAPPA v.
STATE OF KARNATAKA4, has held as follows:
“….
….
….
13. The provision for acquisition of land under the Act is
contained in Section 28 which is somewhat different from the
provisions contained in Sections 4, 5-A and 6 of the Land
Acquisition Act. The legislature in its wisdom thought it proper
to make a specific provision for acquisition of the land in the Act
itself rather than to take recourse to Sections 4 and 6 of the
Land Acquisition Act. A plain reading of sub-section (1) of
Section 28 would show that land can be acquired for the
purpose of (i) development by the Board, or (ii) for any other
purpose in furtherance of the objects of the Act. Sub-section (3)
(2006) 7 SCC 578
of Section 28 is similar to Section 5-A of the Land Acquisition
Act and the final notification is issued under sub-section (4) of
Section 28. The necessary precondition for a valid notification
under sub-section (4) of Section 28 is that the State
Government should be satisfied that the land is required for the
purpose specified in the notification issued under sub-section (1)
viz. for the purpose of (i) development by the Board, or (ii) for
any other purpose in furtherance of the objects of the Act.
Therefore, in order to judge the validity of the notification
what is to be seen is whether the acquisition of land is
being made for securing the establishment of industrial
areas or to promote the establishment or orderly
development of industries in such areas. In view of the
wide definition of the words “industrial infrastructural
facilities” as contained in Section 2(7-a) of the Act,
making of a technology park, research and development
centre, townships, trade and tourism centres or making
provisions for marketing and banking which would
contribute to the development of industries will meet the
objectives of the Act and acquisition of land for such a
purpose would be perfectly valid.
14. Shri Shanti Bhushan, learned Senior Counsel for the
appellants, has strongly urged that as the impugned notification
under Section 28(1) of the Act did not mention that the land
was sought to be acquired for a technology park, research and
development centre, shopping mall, engineering college,
residential apartments, etc. the landowners could not make a
proper and effective representation under Section 28(2) of the
Act which deprived them of a valuable right given to them under
the Act of showing cause against the proposed acquisition and
consequently the notification is bad. Learned counsel has also
submitted that the notification is very vague and cryptic. We
are unable to accept the contention raised. Sub-section
(1) of Section 28 clearly shows that the land can be
acquired for (i) development by the Board; or (ii) for any
other purpose in furtherance of the objects of the Act.
Under sub-section (8) of Section 28, the State
Government is empowered, after it has taken possession
of land, to transfer the same to the Board for the purpose
for which the land has been acquired. Section 32
empowers the State Government to place at the disposal
of the Board any land vested in it and the Board is
enjoined to deal with the land in accordance with the
regulations made and directions given by the State
Government in this behalf. This stage when the Board
gets the authority to deal with the land comes at a later
stage which is after the land has been developed by it. An
entrepreneur or a company may give a proposal to the
State Government for setting up an industry or
infrastructural
facility and
the Government may
thereafter acquire the land and give it to the Board. It is
also possible that after the land has already been
acquired and developed by the Board, it may be allotted
to an entrepreneur or a company for setting up an
industry or infrastructural facility. Therefore, the scheme
of the Act does not show that at the time of acquisition of
the land and issuing a preliminary notification under
Section 28(1) of the Act, the complete details of the
nature of the industry or infrastructural facility proposed
to be set up should also be mentioned. At that stage what
is to be seen is whether the land is acquired for
development by the Board or for any other purpose in
furtherance of the objects of the Act, as mentioned in
sub-section (1) of Section 28 of the Act. In fact, if the
contention raised by the learned Senior Counsel for the
appellants is accepted, it would mean that even at the
stage of preliminary notification under Section 28(1) of
the Act, the nature of the activity which may be done by
some entrepreneur or a company which may give a
proposal for setting up an industry or infrastructural
facility much after land has been acquired should also be
taken note of and specifically mentioned in the
notification, which is well-nigh impossible. While
interpreting the provisions of the Act, the court should
not only take into consideration the facts of the present
case but should also have in mind all possible
contingencies. Therefore, on a plain reading of the
language used in the Act, it is not possible to accept the
contention of the learned Senior Counsel for the
appellants that the impugned notification is vague or
cryptic as the complete details of the project which was
proposed to be established by Vikas Telecom (P) Ltd.
(Respondent 9) were not mentioned and on account of
the aforesaid lacuna, the landowners were deprived of
their right to make a proper representation or to show
cause against the proposed acquisition.”
(Emphasis supplied)
The Apex Court holds in a case concerning acquisition by the Board
that it is not obligatory for the Board to project what kind of
industry it is going to set up at the time of issuance of preliminary
notification. At the stage of acquisition what is to be seen is
whether the land is acquired for development by the Board or for
any other purpose in furtherance of the objects of the Act as
mentioned under sub-section (1) of Section 28 of the Act. The
Apex Court further holds if the contention that the Board should
disclose everything in the preliminary notification is accepted it
would mean that even at the stage of preliminary notification the
nature of activity which may be done by some entrepreneur or
Company should also be taken note of in the notification which is
impossible. While interpreting the provisions of the Act, the Court
should not only take into consideration the facts of the said case,
but should bear in mind all possible contingencies. In that light, the
submission of the learned counsel appearing for the petitioners that
the Board in the preliminary notification has not indicated what
kind of industry it wants to set up is a submission that is sans
countenanced.
THIRD FOLD:
17. The contention is, that the acquisition runs counter to two
circulars issued by the State Government. Heavy reliance is placed
by all the petitioners upon those circulars issued by the State
Government. The circulars dated 03-03-2007 and 18-03-2013 read
as follows:
“ಕ ಾ ಟಕ ಸ ಾ ರ
ಸಂ ೆ :
ಐ 151 ಎ
ಕೂ 2007
ಕ ಾ ಟಕ ಸ ಾ ರದ ಸ
ಾಲಯ,
ಾಸ !ೌಧ
$ೆಂಗಳ'ರು, ) ಾಂಕ :03.03.2007.
ಸು*ೊ+ೕ-ೆ
ಷಯ: ೆ.ಐ.ಎ./.0.ವ23ಂದ ೈ5ಾ6 ಾ ಉ8ೆ9ೕಶ ೆ; ಜ=ೕನುಗಳನು?
ಭೂ!ಾA)ೕನಪ/ಸಲು ಅನುಸ6ಸ$ೇ ಾದ Dಾನಗಳ ಬ5ೆF.
*****
ೆ.ಐ.ಎ./.0.ವ23ಂದ ೈ5ಾ6 ಾ ಉ8ೆ9ೕಶ ೆ;/ ಏಕಘಟಕ ಸಂKೕಣ ಗM5ೆ ಜ=ೕನು ಗಳನು?
ಭೂ!ಾANೕನಪ/
ೊಳOP2+ದು9,
ಈ
ೆಳಕಂಡ
ೆ.ಐ.ಎ./.0.ಯು . ಜ=ೕನುಗಳನು? ಭೂ!ಾANೕನಪ/
1)
ೆ.ಐ
ಎ./
/.0
0.
ೆ ಐ.ಎ
ಪSಕರಣಗಳTU
ಸ6VಾW
ಪ6XೕTಸ8ೆYೕ
ೊಳOP2+ರುವZದು ಸ ಾ ರದ ಗಮನ ೆ; ಬಂ)8ೆ.
ಾY9 ಕಲಂ-28(1)
ರ ಅ/ \ಾSಥ=ಕ ಅNಸೂಚ ೆಯTU 8ೇವ!ಾ_ನ,
ಕಲಂ
`ಾ-ೆಗಳO,
`ಾ-ೆಗಳO ಸa`ಾನಗಳO ಮತು+ ಾಸದ ಮ ೆಗಳO !ೇ6ರುತ+ ೆ.ೆ
2)
cಾT ನdೆಯು2+ರುವ
ಧ ೈ5ಾ6 ೆಗಳO/eೋಗಗSಸ_
ೆಗಳO eೋಗಗSಸ_ ೈ5ಾ6 ಾ ಘಟಕಗಳO cೊಂ)ರುವ
ಜ=ೕನುಗಳO !ೇ6ರುತ+ ೆ.ೆ
3)
ಸ_Mೕಯ
fೕಜ ಾ
\ಾSN ಾರಗಳO
ವಸ2
ಉ8ೆ9ೕಶ ೆ;
ಅನುgೕ)ಸಲhijರುವ
ಜ=ೕನುಗಳO/ಸ
ಜ=ೕನುಗಳO ಸ ಾ ರದ ಭೂ ಬದ-ಾವkೆ5ೊಂ/ರುವ ಜ=ೕನುಗಳO/l-ಾU
ಜ=ೕನುಗಳO l-ಾUN ಾ6 ಗಳO
ಭೂಪ6ವತ
4)
ೆ mೕ/ರುವ ಪSಕರಣಗM5ೆ ಸಂಬಂN ದ ಜ=ೕನುಗಳO !ೇ6ರುತ+ ೆ.ೆ
ೈ5ಾ6 ೆಗM5ೆ ಪnರಕ ಾWರುವ ಆಸh*ೆS,
ಆಸh*ೆS \ೆpೊSೕq ಬಂr ಇತeೆ,
ಇತeೆ ಮೂಲಭೂತ !ೌಲಭ ಗಳ
ಪS8ೇಶಗಳ ಜ=ೕನುಗಳO !ೇ6ರುತ+ ೆ.ೆ
5)
*ೋಟಗಳO,
*ೋಟಗಳO ಫಲವ*ಾ+ದ ಜ=ೕನು cಾಗೂ ವಷ ೆ; 2 $ೆuೆ $ೆuೆಯುವ ಜ=ೕನುಗಳO,
ಜ=ೕನುಗಳO ತ6
ಜ=ೕನುಗಳO !ೇ6ರುತ+ ೆ.ೆ
ೆ.ಐ.ಎ./. ಾY9 ಕಲಂ28(4)ರ/ ಅಂ2ಮ ಅNಸೂಚ ೆಯನು? ತVಾ6ಸು ಾಗ vೕ-ೆ cೇMದ
ಜ=ೕನುಗಳನು? cೊರತುಪ/
ೆ.ಐ.ಎ./. ಾY9 ಕಲಂ-4ರ/ ಅNಸೂಚ ೆಯನು? cೊರ/ಸ-ಾಗು2+8ೆ.
ಇದ6ಂ8ಾW \ಾSಥ=ಕ ಅNಸೂಚ ೆ
+ೕಣ ಕೂ; ಅಂ2ಮ ಅNಸೂಚ ೆ
+ೕಣ ದTU ವ *ಾ ಸ
ಉಂpಾಗು2+ರುವZದು ಸ ಾ ರದ ಗಮನ ೆ; ಬಂ)ರುತ+8ೆ.
vೕ-ೆ cೇMದ -ೋಪ8ೋಷಗಳನು? ಸ6ಪ/ಸಲು
ಉ8ೆ9ೕಶ ೆ;/ಏಕಘಟಕ
ಸಂKೕಣ ಗM5ೆ
ಜ=ೕನುಗಳನು?
ಅNಸೂಚ ೆಯನು? ತVಾ6ಸುವ ಸಂದಭ ದTU ಈ ೆಳಕಂಡ
ೆ.ಐ.ಎ./.0.ವ23ಂದ
ೈ5ಾ6 ಾ
ಭೂ!ಾANೕನಪ/ಸಲು
\ಾSಥ=ಕ
Dಾನವನು? ಇನು? ಮುಂ8ೆ \ಾTಸಲು ಈ
ಮೂಲಕ ಸೂ ಸ-ಾW8ೆ.
1)
\ಾSಥ=ಕ
ಅNಸೂಚ ೆಯನು?
ತVಾ6ಸುವ
ನಂಬರು ಾರು ಅಳ*ೆ wಾ/ , ಜಂi ಅಳ*ೆ
gದಲು
ಭೂ
wಾಪಕ6ಂದ
ಸ ೆ
ಾಯ ವನು? mವ y ದ ನಂತರ ೇ
\ಾSಥ=ಕ ಅNಸೂಚ ೆಯನು? cೊರ/ಸುವZದು.
cೊರ/ಸುವZದು
2)
8ೇವ!ಾ_ನ, ಸa`ಾನ,
ಸa`ಾನ `ಾ-ೆ ಮತು+ ಆಟದ vೖ8ಾನ,
vೖ8ಾನ ಾಸದ ಮ ೆ ಇರುವ ಪS8ೇಶಗಳನು?
\ಾSಥ=ಕ ಅNಸೂಚ ೆಯTU !ೇ6ಸ$ಾರದು.
!ೇ6ಸ$ಾರದು
3)
cಾT ನdೆಯು2+ರುವ
ಧ ೈ5ಾ6 ೆಗಳO,
ೆಗಳO eೋಗಗSಸ_ ೈ5ಾ6 ಾ ಘಟಕಗಳ ಪS8ೇಶಗಳನು?
cೊರತುಪ/ಸುವZದು.
cೊರತುಪ/ಸುವZದು
4)
ಆಯಕಕij5ೆ ದ ೆ; ಉಂpಾಗದಂ*ೆ ಸ_Mೕಯ fೕಜ ಾ \ಾSN ಾರಗಳO/ಸzಮ\ಾSN
ಾರಗಳO ಸzಮ\ಾSN ಾರ
ಗಳO ಭೂ ಬದ-ಾವkೆ5ೆ ಅನುಮ2 mೕ/ರುವ ಜ=ೕನುಗಳನು? cೊರತುಪ/ಸ$ೇಕು.
cೊರತುಪ/ಸ$ೇಕು
5)
ೈ5ಾ6 ೆಗM5ೆ ಪnರಕ ಾWರುವ ಆಸh*ೆS,
ಆಸh*ೆS \ೆpೊSೕq ಬಂr ಇತeೆ ಮೂಲಭೂತ !ೌಲಭ ಗಳ
ಪS8ೇಶಗಳನು? cೊರತುಪ/ಸುವZದು.
cೊರತುಪ/ಸುವZದು
6)
ಆಯಕij5ೆ ಧ ೆ; ಉಂpಾಗದಂ*ೆ *ೋಟಗಳO,
*ೋಟಗಳO ಫಲವ*ಾ+ದ ಜ=ೕನು cಾಗೂ ವಷ ೆ; 2 $ೆuೆ
$ೆuೆಯುವ
$ೆuೆಯುವ ತ6 ಜ=ೕನುಗಳನು? cೊರತುಪ/ಸುವZದು.
cೊರತುಪ/ಸುವZದು
7)
5ಾSಮ {ಾಣದ ಸರಹ)9mಂದ 5ಾSಮದ ಸುತ+ಲೂ
ಸ+ರkೆ5ಾW 100 =ೕಟ}
ಾ ಯ
+
ಜ=ೕನುಗಳನು? cೊರತುಪ/ಸುವZದು.
cೊರತುಪ/ಸುವZದು
ಸy/(ಎ .-ೋಕ ಾಥeಾ~)
ಸ ಾ ರದ ಅNೕನ ಾಯ ದX ( ೈ.ಅ)
ಾ•ಜ ಮತು+ ೈ5ಾ6 ಾ ಇ-ಾ ೆ”
(Emphasis added)
****
****
****
“ಕ ಾ ಟಕ ಸ ಾ ರ
ಸಂ ೆ : ಐ 590 ಎ
ಕೂ 2012
ಕ ಾ ಟಕ ಸ ಾ ರದ ಸ
ಾಲಯ,
ಾಸ !ೌಧ
$ೆಂಗಳ'ರು, ) ಾಂಕ : 18.03.2013
ಸು*ೊ+ೕ-ೆ
ಷಯ:
ಕ ಾ ಟಕ ೈ5ಾ6 ಾ ಪS8ೇ`ಾ•ವೃ)ƒ ಮಂಡM3ಂದ ೈ5ಾ6 ಾ
ಉ8ೆ9ೕಶ ಾ;W ಜ=ೕನುಗಳನು? ಭೂ!ಾANೕನಪ/ಸಲು ಅನುಸ6ಸ$ೇ ಾದ
Dಾನಗಳ ಬ5ೆF.
****
ಕ ಾ ಟಕ ೈ5ಾ6 ಾ ಪS8ೇ`ಾ•ವೃ)ƒ ಮಂಡM ವ23ಂದ ೈ5ಾ6 ಾ ಉ8ೆ9ೕಶ ಾ;W / ಏಕ
ಘಟಕ ಸಂKೕಣ
fೕಜ ೆಗM5ಾW ಜ=ೕನುಗಳನು? ಭೂ!ಾANೕನಪ/
ಪSಕರಣಗಳTU
ಸ6VಾW
ಭೂ!ಾANೕನಪ/
ೊಳOP2+ರುವZದು ಸ ಾ ರದ ಗಮನ ೆ; ಬಂ)8ೆ.
ಪ6XೕTಸ8ೆYೕ
ೊಳOP2+ದು9, ಈ
ೆ.ಐ.ಎ./.0.ಯು
ೆಳಕಂಡ
ಜ=ೕನುಗಳನು?
ೆ.ಐ
ಎ./
/.
ೆ ಐ.ಎ
1.
ಾY9 ಕಲಂ 28(1)ರ
ರ \ಾSಥ=ಕ ಅNಸೂಚ ೆಯTU 8ೇವ!ಾ_ನ, `ಾ-ೆಗಳO,
`ಾ-ೆಗಳO,
ಸa`ಾನಗಳO ಮತು+ ಾಸದ ಮ ೆಗಳO !ೇ6ರುತ+ ೆ.ೆ
cಾT ನdೆಯು2+ರುವ
2.
ಧ ೈ5ಾ6 ೆಗಳO / eೋಗಗSಸ_ ೈ5ಾ6 ಾ ಘಟಕಗಳO cೊಂ)ರುವ
ಜ=ೕನುಗಳO !ೇ6ರುತ+ ೆ.ೆ
ಸ_Mೕಯ fೕಜ ಾ \ಾSN ಾರಗಳO ವಸ2 ಉ8ೆ9ೕಶ ೆ; ಅನುgೕ)ಸಲhijರುವ ಜ=ೕನುಗಳO
3.
ಸ ಾ ರದ ಭೂ ಬದ-ಾವkೆ5ೊಂ/ರುವ ಜ=ೕನುಗಳO / l-ಾUN ಾ6ಗಳO ಭೂ ಪ6ವತ
ೆ
mೕ/ರುವ ಪSಕರಣಗM5ೆ ಸಂಬಂN ದ ಜ=ೕನುಗಳO !ೇ6ರುತ+ ೆ.ೆ
*ೋಟಗಳO,
*ೋಟಗಳO ಫಲವ*ಾ+ದ ಜ=ೕನು cಾಗೂ ವಷ ೆ; 2 $ೆuೆ $ೆuೆಯುವ ಜ=ೕನುಗಳO,
ಜ=ೕನುಗಳO ತ6
4.
ಜ=ೕನುಗಳO !ೇ6ರುತ+ ೆ.ೆ
ೆ.ಐ.ಎ./. ಾY9 ಕಲಂ 28(4)ರ/ ಅಂ2ಮ ಅNಸೂಚ ೆಯನು? ತVಾ6ಸು ಾಗ vೕ-ೆ
cೇMದ
ಜ=ೕನುಗಳನು?
cೊರತುಪ/ ,
ೆ.ಐ.ಎ./.
cೊರ/ಸ-ಾಗು2+8ೆ. ಇದ6ಂ8ಾW \ಾSಥ=ಕ ಅNಸೂಚ ೆ
ಾY9
ಕಲಂ 4ರ/ ಅNಸೂಚ ೆಯನು?
+ೕಣ ಕೂ;, ಅಂ2ಮ ಅNಸೂಚ ೆಯTUನ
+ೕಣ ಕೂ; ವ *ಾ ಸ ಉಂpಾಗು2+ರುವZದು ಸ ಾ ರದ ಗಮನ ೆ; ಬಂ)ರುತ+8ೆ.
ಈ ನೂ ನ*ೆಗಳನು? ಸ6ಪ/ಸಲು ಈ yಂ8ೆ ) ಾಂಕ: 03.03.2007ರಂದು cೊರ/ಸ-ಾದ
ಸು*ೊ+ೕ-ೆ
ಐ 151 ಎ
ಕೂ
2007 ಈ
ೆಳಕಂಡ ಅಂಶಗM5ೆ ಸಂಬಂN ದಂ*ೆ „ಾಗಶಃ
wಾಪ /ಸ-ಾW8ೆ.
ೆ.ಐ.ಎ./.0. ವ23ಂದ ೈ5ಾ6 ಾ ಉ8ೆ9ೕಶ ೆ; / ಏಕ ಘಟಕ ಸಂKೕಣ
fೕಜ ೆಗM5ೆ
ಜ=ೕನುಗಳನು? ಭೂ!ಾANೕನಪ/ಸಲು \ಾSಥ=ಕ ಅNಸೂಚ ೆಯನು? ತVಾ6ಸುವ ಸಂದಭ ದTU ಇನು?
ಮುಂ8ೆ ಈ ೆಳಕಂಡ Dಾನವನು? \ಾTಸಲು ಈ ಮೂಲಕ ಸೂ ಸ-ಾW8ೆ:
1.
\ಾSಥ=ಕ
ಅNಸೂಚ ೆ
ಪS!ಾ+ವ ೆಯನು?
ದƒಪ/ಸುವ
gದಲು
`ೇಷ
ಭೂ!ಾANೕ ಾN ಾ6ಯವರು
ಾ6ಯವರು ಪS!ಾ+ ತ ಜ=ೕmನ vೕ-ೆ† ಲzಣಗಳ ಬ5ೆF ಸ_ಳ ಪ6Xೕಲ ೆ ನdೆ ದ
ನಂತರ ಸ_ಳ ತm ಾ iಪh• ಸyತ \ಾSಥ=ಕ ಅNಸೂಚ ೆ ಪS!ಾ+ವ ೆಯನು?,
ೆಯನು? ಸTUಸುವZದು cಾಗೂ
ಅಂ2ಮ ಅNಸೂಚ ೆ cೊರ/ಸುವ gದಲು ಜಂi ಅಳ*ೆ
ಾಯ ವನು? ಪneೈ , ನಂತರ
ಅಂ2ಮ ಅNಸೂಚ ೆ ಪS!ಾ+ವ ೆ ದƒಪ/ಸುವZದು
2.
8ೇವ!ಾ_ನ, ಸa`ಾನ,
ಸa`ಾನ `ಾ-ೆ ಮತು+ ಆಟದ vೖ8ಾನ,
vೖ8ಾನ ಾಸದ ಮ ೆಗಳO / ವಸ2 ಪS8ೇಶಗಳನು?
ಆಯಕij5ೆ
ಧ ೆ;
cೊರತುಪ/ಸುವZದು.
cೊರತುಪ/ಸುವZದು
ಉಂpಾಗದಂ*ೆ
!ಾಧ ಾದಷುj
ಭೂ!ಾANೕನ
ಪSKSY3ಂದ
3.
cಾT ನdೆಯು2+ರುವ
ಆಯಕij5ೆ
ಧ ೆ;
ಧ ೈ5ಾ6 ೆಗಳO,
ೆಗಳO eೋಗಗSಸ_ ೈ5ಾ6 ಾ ಘಟಕಗಳ ಪS8ೇಶಗಳನು?
ಉಂpಾಗದಂ*ೆ
ಉಂpಾಗದಂ*ೆ
!ಾಧ ಾದಷುj
ಭೂ!ಾANೕನ
ಪSKSY3ಂದ
cೊರತುಪ/ಸುವZದು.
cೊರತುಪ/ಸುವZದು
4.
ಆಯಕij5ೆ ಧ ೆ; ಉಂpಾಗದಂ*ೆ *ೋಟಗಳO,
*ೋಟಗಳO ಫಲವ*ಾ+ದ ಜ=ೕನು cಾಗೂ ವಷ ೆ; 2 $ೆuೆ
$ೆuೆಯುವ ಜ=ೕನುಗಳO,
ಜ=ೕನುಗಳO ತ6 ಜ=ೕನುಗಳನು? ಭೂ!ಾANೕನ ಪSKSY3ಂದ cೊರತುಪ/ಸುವZದು.
cೊರತುಪ/ಸುವZದು
5. 5ಾSಮ{ಾkಾದ ಸರಹ)9mಂದ 5ಾSಮದ ಸುತ+ಲೂ
ಸ+ರkೆ5ಾW
kೆ5ಾW 100 =ೕಟ}
ಾ ಯ
+
ಜ=ೕನುಗಳನು? cೊರತುಪ/ಸುವZದು.
cೊರತುಪ/ಸುವZದು
ಸy/(ಎ. .eಾಮಕೃಷˆ)
ಸ ಾ ರದ ಅNೕನ ಾಯ ದX ( ೈ.ಆ)
wಾ•ಜ ಮತು+ ೈ5ಾ6 ೆ ಇ-ಾ ೆ.”
(Emphasis added)
The Circular dated 03-03-2007 is issued concerning the lands that
they should not be acquired.
There are six kinds of lands that
should be dropped from acquisition i.e., lands of temples, schools,
graveyards and residential houses; lands of running/sick industries;
lands that come within the purview of Master Plan; lands of certain
enterprises which are running essential services for public purpose;
lands approved by the concerned authorities for conversion and
horticulture lands which grow two produces in a year. This is again
amplified by the circular dated 18-03-2013, which is for the same
purpose. The addition is that, the lands can be dropped only if it
does not violate the contiguity in the project proposed. However,
lands which are converted are not exempted from acquisition under
this circular.
The agricultural land holders who had filed several
petitions contend that even today they are continuing with
agricultural/horticultural activities.
Therefore, the circulars would
become applicable to the kinds of lands that can be exempted
subject to the condition that it would not take away the contiguity
of the industrial set up, the purpose for which the acquisition is now
made. A plantation or an agricultural land where horticulture crops
are grown, cannot be seen to be subsisting in a thick industrial
surrounding. Therefore, it is for the respondent/SLAO or the Board
or the State even, to consider the applicability of the circulars, only
if it does not take away the contiguity.
FOURTH FOLD:
18. The submission is, that there is no enquiry conducted by
the Special Land Acquisition Officer as necessary under Section
28(3) of the Act. It is the submission of all the learned counsel
appearing for the petitioners in the cases at hand that there is no
enquiry as contemplated under Section 28(3) of the Act conducted
by the Special Land Acquisition Officer, as even before the last date
of filing of objections, the objections had been rejected and final
notification is issued. Therefore, all other submissions with regard
to the process of acquisition are not tenable or the Circulars not
being followed would take a back seat or brushed into oblivion for
the sole reason of one stream of submission meriting acceptance
that is the petitioners were not heard in the matter.
The Apex
Court holds that in land acquisition cases where property is being
taken away, right to hear must be an effective process and not
mere formality.
18.1. The Apex Court in the case of KOLKATA MUNICIPAL
CORPORATION v. BIMAL KUMAR SHAH5, has held as follows:
“….
….
….
33.2.The Right to be heard
33.2.1. Following the right to a meaningful and
effective prior notice of acquisition, is the right of the
property-bearer to communicate his objections and
concerns to the authority acquiring the property. This
right to be heard against the proposed acquisition must
be meaningful and not a sham.
2024 SCC OnLine SC 968
33.2.2. Section 5-A of the Land Acquisition Act, 1894,
Section 3(1) of the Requisitioning and Acquisition of Immovable
Property Act, 1952, Section 15 of the Right to Fair
Compensation
and
Transparency
in
Land
Acquisition,
Rehabilitation and Resettlement Act, 2013, and Section 3-C of
the National Highways Act, 1956, are some statutory
embodiments of this right.
33.2.3. Judicial opinions recognising the importance
of this right are far too many to reproduce. Suffice it to
say that that the enquiry in which a landholder would
raise his objection is not a mere formality.
33.3. The Right to a reasoned decision
33.3.1. That the authorities have heard and
considered the objections is evidenced only through a
reasoned order. It is incumbent upon the authority to
take an informed decision and communicate the same to
the objector.
33.3.2. Section 6 of the Land Acquisition Act, 1894,
Section 3(2) of the Requisitioning and Acquisition of Immovable
Property Act, 1952, Section 19 of the Right to Fair
Compensation
and
Transparency
in
Land
Acquisition,
Rehabilitation and Resettlement Act, 2013 and Section 3-D of
the National Highways Act, 1956, are the statutory
incorporations of this principle.
33.3.3. Highlighting
the
importance
of
the
declaration of the decision to acquire, the Courts have
held that the declaration is mandatory, failing which, the
acquisition proceedings will cease to have effect.”
(Emphasis supplied)
18.2. The Apex Court was following the judgment rendered in
the case of HINDUSTAN PETROLEUM CORPORATION LIMITED
v. DARIUS SHAPUR CHENAI6, wherein it is held as follows:
“….
….
….
9. It is trite that hearing given to a person must be
an effective one and not a mere formality. Formation of
opinion as regards the public purpose as also suitability thereof
must be preceded by application of mind as regards
consideration of relevant factors and rejection of irrelevant
ones. The State in its decision-making process must not commit
any misdirection in law. It is also not in dispute that Section
5-A of the Act confers a valuable important right and
having regard to the provisions contained in Article 300-A
of the Constitution it has been held to be akin to a
fundamental right.”
(Emphasis supplied)
18.3. In the case of KAMAL TRADING PRIVATE LIMITED
v. STATE OF WEST BENGAL7, the Apex Court has held as follows:
“….
….
….
14. It must be borne in mind that the proceedings
under the LA Act are based on the principle of eminent
domain and Section 5-A is the only protection available to
a person whose lands are sought to be acquired. It is a
minimal safeguard afforded to him by law to protect
himself from arbitrary acquisition by pointing out to the
authority concerned, inter alia, that the important
ingredient, namely, “public purpose” is absent in the
proposed acquisition or the acquisition is mala fide. The
LA Act being an expropriatory legislation, its provisions will have
to be strictly construed.
(2005) 7 SCC 627
(2012) 2 SCC 25
15. Hearing contemplated under Section 5-A(2) is
necessary to enable the Collector to deal effectively with
the objections raised against the proposed acquisition
and make a report. The report of the Collector referred to
in this provision is not an empty formality because it is
required to be placed before the appropriate Government
together with the Collector's recommendations and the
record of the case. It is only upon receipt of the said
report that the Government can take a final decision on
the objections. It is pertinent to note that declaration under
Section 6 has to be made only after the appropriate
Government is satisfied on the consideration of the report, if
any, made by the Collector under Section 5-A(2). As said by this
Court in Hindustan Petroleum Corpn. Ltd. [(2005) 7 SCC 627] ,
the appropriate Government while issuing declaration under
Section 6 of the LA Act is required to apply its mind not only to
the objections filed by the owner of the land in question, but
also to the report which is submitted by the Collector upon
making such further inquiry thereon as he thinks necessary and
also the recommendations made by him in that behalf.
…
…
…
18. In Munshi Singh v. Union of India [(1973) 2 SCC 337]
this Court while dealing with Section 5-A of the LA Act observed
as under: (SCC p. 342, para 7)
“7. Section 5-A embodies a very just and
wholesome principle that a person whose property is
being or is intended to be acquired should have a proper
and reasonable opportunity of persuading the authorities
concerned that acquisition of the property belonging to
that person should not be made. … The legislature has,
therefore, made complete provisions for the persons
interested to file objections against the proposed
acquisition and for the disposal of their objections. It is
only in cases of urgency that special powers have been
conferred on the appropriate Government to dispense
with the provisions of Section 5-A.”
…
…
20. In Mukesh Hans [(2004) 8
reiterated that: (SCC p. 28, para 36)
…
SCC
14]
this
Court
“36. … right of representation and hearing
contemplated under Section 5-A of the Act is a
very valuable right of a person whose property is
sought to be acquired and he should have
appropriate
and
reasonable
opportunity
of
persuading the authorities concerned that the
acquisition of the property belonging to that
person should not be made.”
(Emphasis supplied)
18.4. In the case of GOJER BROTHERS PRIVATE LIMITED
v. STATE OF WEST BENGAL8, the Apex Court has held as follows:
“….
….
….
15. The ambit and scope of Section 5-A had been
considered in several judgments, but we do not consider it
necessary to burden this judgment by noticing various judicial
precedents and feel that it would be sufficient to take
cognizance of four recent judgments in Raghbir Singh
Sehrawat v. State of Haryana [Raghbir Singh Sehrawat v. State
of Haryana, (2012) 1 SCC 792 : (2012) 1 SCC (Civ) 402]
, Kamal Trading (P) Ltd. v. State of W.B. [Kamal Trading (P)
Ltd. v. State of W.B., (2012) 2 SCC 25 : (2012) 1 SCC (Civ)
506] , Surinder Singh Brar v. Union of India [(2013) 1 SCC 403
: (2013) 1 SCC (Civ) 620] and Usha Stud and Agricultural Farms
(P) Ltd. v. State of Haryana [(2013) 4 SCC 210 : (2013) 2 SCC
(Civ) 556] .
16. In Raghbir
Singh
Sehrawat v. State
of
Haryana [Raghbir Singh Sehrawat v. State of Haryana, (2012) 1
SCC 792 : (2012) 1 SCC (Civ) 402], the Court referred to the
earlier precedents on the subject and culled out the following
propositions: (SCC p. 805, paras 39-40)
“39. In this context, it is necessary to
remember that the rules of natural justice have
been ingrained in the scheme of Section 5-A with a
(2013) 16 SCC 660
view to ensure that before any person is deprived
of his land by way of compulsory acquisition, he
must get an opportunity to oppose the decision of
the
State
Government
and/or
its
agencies/instrumentalities
to
acquire
the
particular parcel of land. At the hearing, the
objector can make an effort to convince the Land
Acquisition Collector to make recommendation
against the acquisition of his land. He can also
point out that the land proposed to be acquired is
not suitable for the purpose specified in the
notification issued under Section 4(1). Not only
this, he can produce evidence to show that
another piece of land is available and the same
can be utilised for execution of the particular
project or scheme.
40. Though it is neither possible nor desirable to
make a list of the grounds on which the landowner can
persuade the Collector to make recommendations
against the proposed acquisition of land, but what is
important is that the Collector should give a fair
opportunity of hearing to the objector and
objectively
consider
his
plea
against
the
acquisition of land. Only thereafter, he should make
recommendations supported by brief reasons as to why
the particular piece of land should or should not be
acquired and whether or not the plea put forward by the
objector merits acceptance. In other words, the
recommendations made by the Collector must reflect
objective application of mind to the objections filed by
the landowners and other interested persons.”
…
…
…
21. In our view, non-consideration of the objections filed
under Section 5-A(1) has resulted in denial of effective
opportunity of hearing to the appellant. The manner in which
the Joint Secretary to the Government approved the
recommendation made by the Land Acquisition Collector
favouring acquisition of the property is reflective of total nonapplication of mind by the competent authority to the
recommendation made by the Land Acquisition Collector and the
report prepared by him.”
(Emphasis supplied)
The afore-quoted judgments of the Apex Court would indicate that
opportunity of hearing to those persons, whose lands would become
subject matter of acquisition or consideration of their objections
would become imperative. Section 5A of the Land Acquisition Act,
1894 provides an opportunity to the citizens to file objections and
thus confers a valuable right contained under Article 300A of
Constitution.
18.5. Even under the statutory landscape of the Act, a
coordinate Bench
of this
Court
AMENCHERLA v.
THE STATE
in
the
case
of SRI ANIL
OF KARNATAKA9, interprets
Section 28(3) of the Act and holds as follows:
“….
….
….
27. In Re. Question No. 2: The well-reasoned order
under Section 28(3) of the KIAD Act would constitute the
raw-material for the Government to take a final call on
the issuance of the final notification under Section 28(4)
of the KIAD Act. When Section 28(3) order itself is
deficient, Section 28(4) notification also becomes
unsustainable. This is all the more so when nothing is placed
on record to show that the Government has applied its mind
afresh to the objections of the petitioners and the report of the
SLAO.
2013 SCC OnLine Kar.6457
28. As held in the case of Kamal Trading (supra), the final
notification has to be issued only after the Government is
satisfied on considering of Section 5-A report (Section 28(3)
order in these cases). It is reiterated in the said decision
that the Government, while issuing the final notification,
is required to apply its mind not only to the objections
filed by the owner of the land in question, but also to the
report which is submitted by the Collector (SLAO in the
instant case) and also the recommendations made by him
in that behalf. Mere rote acceptance or endorsement of the
SLAO's order by the Government does not meet the
requirements of law.”
(Emphasis supplied)
The coordinate Bench holds that when the order passed under
Section 28(3) of the Act itself is deficient, the final notification
issued under Section 28(4) of the Act becomes unsustainable.
19. On a coalesce of the judgments rendered by the Apex
Court and the co-ordinate Bench of this Court what would
unmistakably emerge is, once a preliminary notification is issued
under Section 28(1) of the Act and objections are called under
Section 28(2), the proceedings to be held or complied with under
Section 28(3) of the Act is imperative.
Whether there has been
compliance or not is necessary to be noticed in the case at hand.
For illustration, the date on which the notice is served upon the
petitioners under Section 28(2) of the Act and the dates of filing of
objections and rejection of objections are noted petition-wise. They
are as follows:
(a) In W.P.No.293/2025, notice dated 06-05-2024 under
Section 28(2) of the Act is served on the petitioner on 24-05-2024;
the petitioner filed his objections to the preliminary notification on
24-05-2024;
the
petitioner
submits
a
detailed
objection
on
09-06-2024; respondent No.3 rejected the objections of the
petitioner in terms of his order dated 09-10-2024;
(b) In W.P.No.255/2025, notice dated 06-05-2024 under
Section 28(2) of the Act returned unserved on the petitioner on
07-05-2024; the petitioner filed his objections to the preliminary
notification
on
07-06-2024;
respondent
No.3
rejected
the
objections of the petitioner in terms of his order dated 01-10-2024;
(c) In W.P.No.515/2025, petitioners file their objections
before issuance of the notice under Section 28(2) of the Act to the
preliminary notification on 03-04-2024, notice dated 06-05-2024
under Section 28(2) of the Act is served on the petitioners on
25-05-2024; the petitioners filed their objections to the preliminary
notification after issuance of notice under Section 28(2) of the Act
on 03-03-2024; respondent No.3 rejected the objections of the
petitioner.
(d) In W.P.No.671/2025, the petitioner filed his objections to
the preliminary notification on 02-05-2024; the petitioner submits
his objections on 20-05-2024; notice dated 06-05-2024 under
Section 28(2) of the Act is served on the petitioner on 27-05-2024;
respondent No.3 rejected the objections of the petitioner in terms
of his order dated 09-10-2024;
(e) In W.P.No.672/2025, the petitioner filed his objections to
the preliminary notification on 02-05-2024; petitioner submits his
objections on 20-05-2024; notice dated 06-05-2024 under Section
28(2) of the Act is served on the petitioner on 27-05-2024;
respondent No.3 rejected the objections of the petitioner in terms
of his order dated 09-10-2024;
(f) In W.P.No.1173/2025, notice dated 07-05-2024 under
Section 28(2) of the Act is served on the petitioner on 07-05-2024;
the petitioner filed his objections to the preliminary notification on
07-06-2024; respondent No.3 under Section 28(3) of the Act
rejects the objections of the petitioner in terms of his order dated
21-09-2024;
(g) In W.P.No.1399/2025, petitioner files his objections even
before issuance of the notice under Section 28(2) of the Act to the
preliminary notification on 23-04-2024; notice dated 07-05-2024
under Section 28(2) of the Act is served on the petitioner on
07-05-2024; the petitioner filed his objections to the preliminary
notification on 26-06-2024; respondent No.3 under Section 28(3) of
the Act rejects the objections of the petitioner in terms of his order
dated 21-09-2024;
(h) In W.P.No.1405/2025, notice dated 08-05-2024 under
Section 28(2) of the Act is served on the petitioner; the petitioner
filed his objections to the preliminary notification on 06-06-2024;
respondent No.3 under Section 28(3) of the Act rejects the
objections of the petitioner in terms of his order dated 21-09-2024;
(i) In W.P.No.4055/2025, notice dated 06-05-2024 under
Section 28(2) of the Act is served on the petitioner on 23-05-2024;
petitioners filed his objections to the preliminary notification on
29-05-2024; respondent No.3 rejected the objections of the
petitioner in terms of his order dated 07-10-2024;
(j) In W.P.No.5030/2025, the Board issued notice seeking
objections on the preliminary notification on 06-05-2024; the
petitioner filed his objections to the preliminary notification on
16-04-2024; respondent No.3 rejected the objections of the
petitioner in terms of his order dated 07-10-2024;
(k) In W.P.No.1280/2025, notice dated 06-05-2024 under
Section 28(2) of the Act is served on the petitioner on 24-05-2024;
the petitioner filed his objections to the preliminary notification on
29-05-2024; respondent No.3 rejected the objections of the
petitioner in terms of his order dated 23-03-2016;
(l) In W.P.No.33550/2024, petitioner files his objections even
before issuance of the notice under Section 28(2) of the Act to the
preliminary notification on 10-04-2024; notice dated 06-05-2024
under Section 28(2) of the Act is served on the petitioner; the
petitioner filed his objections to the preliminary notification on
16-07-2024; respondent No.3 under Section 28(3) of the Act
rejects the objections of the petitioner in terms of his order dated
09-10-2024;
20. In all the aforementioned cases, notices are served upon
the respective petitioners as obtaining under Section 28(2) of the
Act on different dates as noted supra.
The petitioners have filed
their respective objections to the preliminary notification on
different dates as noted hereinabove.
The 3rd respondent rejects
the objections by drawing up proceedings under Section 28(3) of
the Act in terms of the respective orders as indicated supra.
Although
objections
are
rejected
prior
to
issuance
of
final
notification, which comes about on 02-12-2024, on a perusal of
original records, the objections are tabulated and no contention
advanced by the petitioners qua the Circulars or otherwise, is
considered by the Special Land Acquisition Officer. If regard is had
to the findings of the Apex Court in the judgment in KOLKATA
MUNICIPAL
CORPORATION’S
case
supra
what
would
unmistakably emerge is that, there has been violation of principles
of natural justice.
21. It is a settled principle of law that what is not considered
by way of objections cannot be supplanted by way of objections in
the
writ
petition
when
the
matter
is
brought
before
the
Constitutional Court.
21.1. It becomes apposite to refer to the judgment of the
Apex Court in the case of MOHINDER SINGH GILL v. CHIEF
ELECTION COMMISSIONER10. It reads as follows:
“….
….
….
8. The second equally relevant matter is that when
a statutory functionary makes an order based on certain
grounds, its validity must be judged by the reasons so
mentioned and cannot be supplemented by fresh reasons
in the shape of affidavit or otherwise.Otherwise, an order
bad in the beginning may, by the time it comes to court
on account of a challenge, get validated by additional
grounds later brought out. We may here draw attention to
the observations of Bose, J. in GordhandasBhanji [Commr. of
Police, Bombay v. GordhandasBhanji, 1951 SCC 1088: AIR 1952
SC 16]:
“Public orders, publicly made, in exercise of
a statutory authority cannot be construed in the
light of explanations subsequently given by the
officer making the order of what he meant, or of
what was in his mind, or what he intended to do.
Public orders made by public authorities are meant
to have public effect and are intended to affect the
actings and conduct of those to whom they are
addressed and must be construed objectively with
reference to the language used in the order itself.”
(1978) 1 SCC 405
Orders are not like old wine becoming better as they
grow older.”
(Emphasis supplied)
21.2. This judgment is subsequently followed by the Apex
Court in the case of STATE OF PUNJAB v. BANDEEP SINGH11,
wherein it holds as follows:
“….
….
….
4. There can be no gainsaying that every decision of
an administrative or executive nature must be a
composite and self-sustaining one, in that it should
contain all the reasons which prevailed on the official
taking the decision to arrive at his conclusion. It is
beyond cavil that any authority cannot be permitted to
travel beyond the stand adopted and expressed by it in
the impugned action. If precedent is required for this
proposition it can be found in the celebrated decision
titled Mohinder Singh Gill v. Chief Election Commr. [(1978) 1
SCC 405: (1978) 2 SCR 272] of which the following paragraph
deserves extraction: (SCC p. 417, para 8)
“8. The second equally relevant matter is
that when a statutory functionary makes an order
based on certain grounds, its validity must be
judged by the reasons so mentioned and cannot be
supplemented by fresh reasons in the shape of
affidavit or otherwise. Otherwise, an order bad in
the beginning may, by the time it comes to court
on account of a challenge, get validated by
additional grounds later brought out. We may here
draw attention to the observations of Bose, J.
in Gordhandas Bhanji [Commr. of Police v. Gordhandas
Bhanji, 1951 SCC 1088: AIR 1952 SC 16: 1952 SCR
135]: (AIR p. 18, para 9)
(2016) 1 SCC 724
‘9. … public orders, publicly made, in
exercise of a statutory authority cannot be
construed
in
the
light
of
explanations
subsequently given by the officer making the
order of what he meant, or of what was in his
mind, or what he intended to do. Public orders
made by public authorities are meant to have
public effect and are intended to affect the
actings and conduct of those to whom they are
addressed and must be construed objectively
with reference to the language used in the order
itself.’
Orders are not like old wine becoming better as
they grow older.””
(Emphasis supplied)
21.3. Later, in the case of 63 MOONS TECHNOLOGIES
LIMITED v. UNION OF INDIA12, the Apex Court holds as follows:
“….
….
….
100. Valiant attempts have been made by counsel in the
High Court as well as counsel in this Court to support the order
on grounds which are outside the order, stating that such
grounds make it clear that in any case, the government order
has been made in public interest. The celebrated passage
in Mohinder Singh Gill [Mohinder Singh Gill v. Chief Election
Commr., (1978) 1 SCC 405] states that: (SCC p. 417, para 8)
“8. The second equally relevant matter is
that when a statutory functionary makes an order
based on certain grounds, its validity must be
judged by the reasons so mentioned and cannot be
supplemented by fresh reasons in the shape of
affidavit or otherwise. Otherwise, an order bad in
the beginning may, by the time it comes to court
on account of a challenge, get validated by
additional grounds later brought out. We may here
(2019) 18 SCC 401
draw attention to the observations of Bose, J.
in Gordhandas
Bhanji [Commr.
of
Police v. Gordhandas Bhanji, 1951 SCC 1088: AIR
1952 SC 16: 1952 SCR 135]: (SCR p. 140: AIR p.
18, para 9)
‘9. … public orders, publicly made, in
exercise of a statutory authority cannot be
construed
in
the
light
of
explanations
subsequently given by the officer making the
order of what he meant, or of what was in his
mind, or what he intended to do. Public orders
made by public authorities are meant to have
public effect and are intended to affect the
actings and conduct of those to whom they are
addressed and must be construed objectively
with reference to the language used in the order
itself.’
Orders are not like old wine becoming better as
they grow older.”
We are of the view that it is the Central Government that
has to be “satisfied” that its order is in public interest
and such “satisfaction” must, therefore, be of the Central
Government itself and must, therefore, appear from the
order itself. All these valiant attempts made to sustain such
order must be rejected.”
(Emphasis supplied)
22. In the light of the records being sketchy with regard to
the objections filed by these petitioners, the matters would require
remittance to the Special Land Acquisition Officer to consider the
objections, afford opportunity of hearing and pass necessary orders
in accordance with law. In the light of the acquisition being in
violation of sub-section (3) of Section 28 of the Act, as a natural
consequence, the final notification under Section 28(4) would be
rendered unsustainable. The only submission that has merited
consideration at this juncture is that there is violation of Section
28(3) of the Act. Though it is not the law that every objections of
every land owner which are identical should bear consideration but
there should be semblance of application of mind while considering
the objections filed by the land owners. Therefore, this Court has
found fault with the procedure adopted under Section 28(3) of the
Act while the preceding procedure under Section 28(1) and (2) is
not found fault with. For the reason that there is violation of Section
28(3) of the Act, the final notification so issued would also tumble
down along with the order under Section 28(3) of the Act. The
preliminary notification thus stands undisturbed.
23. For the aforesaid reasons, the following:–
ORDER
(i)
Writ Petitions are allowed in part.
(ii)
Orders passed considering the objections under Section
28(3) of the Act stand quashed in all these cases. As a
consequence, Final Notifications dated 03.10.2024 and
02.12.2024, issued by the 2nd respondent / Karnataka
Industrial Areas Development Board under Section
28(4) of the Karnataka Industrial Areas Development
Act, 1966 also stands quashed.
(iii)
The matters are remitted back to the Special Land
Acquisition
Officer/respondent
No.3
to
redo
the
proceedings from the stage of Section 28(3) of the Act
and take the issue to its logical conclusion.
(iv)
The proceedings as directed now to be done afresh from
the stage of Section 28(3) of the Act shall conclude
within an outer limit of 8 weeks from the date of receipt
of the copy of the order, if not earlier, bearing in mind
the observations made in the course of the order.
All pending I.As’ in these petitions stand disposed, as a
consequence.
Sd/(M.NAGAPRASANNA)
JUDGE
Nvj/CT:SS
Page No. 99 is retyped and replaced vide chamber order dated 20.02.2026
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.