HIGH COURT OF CHHATTISGARH AT BILASPUR
WPC No. 4173 of 2024
1 - Prabhat Kumar Ranjan S/o Shri Girijanandan Sinha, Aged About 56 Years
R/o Sanjay Nagar, Baikunthpur, District- Korea ( C.G.).
... Petitioner(s)
versus
1 - State Of Chhattisgarh Through- Secretary, Public Works Department,
Mantralaya, Mahanadi Bhawan, Nava Raipur, Raipur (C.G.).
2 - The Chief Engineer Public Works Department, Sarguja Division,
Ambikapur (C.G.).
3 - The Surperintendant Engineer Public Works Department, Ambikapur
Division, Ambikapur (C.G.).
4 - The Executive Engineer, Public Works Department, Korea Division,
Manendragarh ( C.G.).
... Respondent(s)
(cause title taken from CIS)
For Petitioner(s)
:
Mr. Shishir Dixit, Advocate
For Respondent(s)
:
Mr. Sangharsh Pandey, Govt. Advocate
Hon'ble Shri Ramesh Sinha, Chief Justice
Hon'ble Shri Ravindra Kumar Agrawal, Judge
Order on Board
Per Ramesh Sinha, Chief Justice
19/08/2026
1.
Heard Mr. Shishir Dixit, learned counsel for the petitioner as well as Mr.
Sangharsh Pandey, Govt. Advocate for the Respondent/ State.
2.
The present petition has been filed by the petitioner seeking the
following reliefs:“(i) That, this Hon'ble Court may kindly be
pleased to set aside the order dated 15.2.2024
passed by the Respondent No. 3 and order
dated 26.4.2024 passed by Respondent No. 2,
in the interest of justice.
(ii) direct the That, this Hon'ble court be pleased
to Respondents to release the amount of Rs.
8,90,887/- which has been deducted in
pursuance of clause 2 of the condition of
contract, in the interest of justice.
(iii) That, this Hon'ble Court be pleased to direct
the Respondents to release the amount of
escalation of Rs. 9,28,696/ withheld in
pursuance of clause 2 of the conditions of
contract, in the interest of justice.
(iv) Any other relief which this Hon'ble Court may
deem fit be granted.”
3.
The brief facts of the case are that the petitioner, a B-Class contractor,
was awarded a work order dated 10.06.2020 for construction of
residential quarters for judicial officers and staff at Baikunthpur, District
Korea, for a contract value of Rs.153.23 lakhs, with the stipulated
period of completion being eight months.
The petitioner was initially granted two extensions under Clause
5 of the Conditions of Contract, without penalty, as the delay was
attributable to the respondent department due to reasons such as nonprovision of layout, non-availability of sand, Covid-19 lockdown and
non-release of funds. Thereafter, the petitioner sought a third extension
from 30.03.2022 to 30.03.2023, specifically pointing out that payments
for the work already executed had not been released due to paucity of
funds. The concerned authority also recommended the extension and
subsequently permitted completion of the work. The work was
completed and a completion certificate was issued.
However, despite the department itself having acknowledged
that the delay was caused due to non-availability of funds, Respondent
No.3, by order dated 15.02.2024, granted the third extension under
Clause 2 and imposed a penalty of 6% on the petitioner. Consequently,
an amount of Rs.8,90,887/- was deducted towards penalty and
escalation amount of Rs.9,28,696/- was also withheld. The petitioner
challenged the action before Respondent No.2, but his representation
was rejected vide order dated 26.04.2024. Aggrieved by the imposition
of penalty and withholding of the aforesaid amounts, the petitioner has
preferred the present petition.
4.
Learned counsel for the petitioner would submit that the delay in
completion of the work was not attributable to the petitioner, but was
occasioned solely due to lack of funds and delay in release of payment
by the respondent department. It is submitted that the said fact was
specifically recorded and recommended by Respondent No.4, which
was not properly considered by Respondent Nos.2 and 3 while
imposing penalty under Clause 2 of the Conditions of Contract.
Learned counsel further submits that the petitioner cannot be penalized
for a default which was not committed by him and for circumstances
beyond his control. The impugned order imposing penalty of 6% is,
therefore, arbitrary, unjust and contrary to the material available on
record, particularly the recommendation of Respondent No.4, and
consequently, the deduction of Rs.8,90,887/- towards penalty and
withholding of the escalation amount of Rs.9,28,696/- are also
unsustainable in law. It is accordingly prayed that the impugned order
and consequential deductions/withholding may kindly be set aside and
the petitioner be granted consequential relief.
5.
Learned State counsel, opposing the petition, submits that the
impugned order dated 15.02.2024 granting the final extension under
Clause 2 of the Conditions of Contract and imposing compensation at
the rate prescribed therein is in accordance with the terms of the
contract. It is submitted that the petitioner was required to complete the
work by 09.03.2021, whereas the work was actually completed only on
26.03.2023, resulting in a delay of 747 days. Though two extensions
were earlier granted under Clause 5 without penalty, the petitioner
failed to complete the work within the extended period up to
29.03.2022. Learned State counsel further submits that the allegation
that the delay was solely attributable to non-availability of funds is not
borne out from the record, as the bills raised by the petitioner were
substantially paid within a reasonable period and the delay in payment
of the escalation bill was attributable to the process of examination and
allotment of funds. It is therefore contended that the respondents were
justified in invoking Clause 2 and levying compensation of 6%,
amounting to Rs.8,90,886.72/-, in terms of the contractual conditions. It
is further submitted that the petitioner has already availed the remedy
under Clause 28 by approaching Respondent No.2, who upheld the
decision of Respondent No.3, and thereafter the petitioner has an
efficacious alternative remedy of approaching the Arbitration Tribunal.
Accordingly, learned State counsel submits that no arbitrariness or
illegality is made out in the impugned action and the writ petition, being
devoid of merit and involving disputed contractual issues, deserves to
be dismissed.
6.
We have heard learned counsel for the parties and perused the
material available on record.
7.
Having heard learned counsel for the parties and upon perusal of the
pleadings, documents and material placed on record, this Court finds
that the dispute in the present case essentially arises out of the
contractual relationship between the petitioner and the respondentDepartment and pertains to the delay in completion of the work, grant
of extension of time and levy of compensation/penalty under Clause 2
of the Conditions of Contract. It is not in dispute that the agreement
executed between the parties contains a specific mechanism for
resolution of disputes under Clause 28 of the Conditions of Contract.
The petitioner, having already availed the remedy of approaching the
Chief Engineer under the said clause, and the decision rendered
thereon having been upheld, the contract itself provides for further
resolution of the dispute through the Arbitration Tribunal. Thus, the
grievance raised by the petitioner involves interpretation and
enforcement of the contractual terms, particularly with regard to
attribution of delay and levy of compensation, which can appropriately
be examined by the forum prescribed under the agreement.
8.
The agreement executed between the parties admittedly contains a
detailed dispute resolution mechanism under Clause 28 of the
General Conditions of Contract, which reads as under:
“Clause 28- Except as otherwise provided in this
contract all question and dispute relating to the
whatsoever in any way arising out of or relas and
the contract designs, drawings, specification,
meaning of the specification, designs, drawings
and instruction herein before mentioned as to
thing estimate, concerning the works, or the
execution of failure to execute the same, whether
arising during the progress of the work, or a after
the abandonment there of shall be referred to the
Superintending Engineer for his decision, within a
period of 30 (thirty) days of such an occurrence
(s). There upon the Superintending Engineer
shall give his written instructions and/or
decisions, after hearing the contractor and
Executive Engineer within a period of 15 (fifteen)
days of such request. This period can be
extended by mutual consent of parties.
Upon receipt of written instructions or decisions,
of Superintending Engineer the parties shall
promptly proceed without delay to comply such
instructions or decisions. if the Superintending
Engineer fails to give his instruction or decisions
in writing within a period of 15 (fifteen) days or
mutually agreed time after being requested
and/or, if the party (es) is/are aggrieved against
the decision of the Superintending Engineer, the
aggrieved party may within 30 days prefer an
appeal to the Chief Engineer, who shall afford an
opportunity to the parties of being heard and te
offer evidence in support of his appeal. The,
Chief Engineer will give his decision within 30
(thirty) days, or such, mutually agreed period.
If any party is not satisfied with the decision of
the Chief Engineer he can file the petition for
resolving the dispute through arbitration in the
arbitration tribunal.
A reference to Arbitration Tribunal shall be no
ground for not continuing the work on the part of
the Contractor. Payment as per original terms
and condition of the agreement shall be
continued by the Executive Engineer in
accordance with clause 8 above."
9.
A bare perusal of Clause 28 of the Conditions of Contract
demonstrates that a complete and efficacious mechanism for resolution
of disputes has been contractually agreed between the parties,
providing for reference of the dispute initially to the Superintending
Engineer, followed by an appeal to the Chief Engineer and, thereafter,
reference to the Arbitration Tribunal in case either party remains
dissatisfied with the decision of the Chief Engineer. The clause further
prescribes specific timelines and an opportunity of hearing to the
parties at each stage of the adjudicatory process. In the present case,
the petitioner has already availed the remedy before the Chief
Engineer, who has upheld the decision of the Superintending Engineer,
and the petitioner has thereafter approached this Court without availing
the further remedy of arbitration specifically provided under the
contract. In such circumstances, particularly when the dispute involves
attribution of delay, interpretation of contractual conditions and
entitlement to compensation, which raise disputed questions of fact
and contractual obligations, this Court is of the considered view that
exercise of writ jurisdiction under Article 226 of the Constitution of India
is not warranted, the petitioner having an efficacious alternative remedy
under the agreed contractual mechanism.
10.
The Hon’ble Supreme Court in Kerala State Electricity Board v. Kurien
E. Kalathil, (2000) 6 SCC 293 has categorically held:
“10. We find that there is a merit in the first
contention of Mr. Raval. Learned Counsel has
rightly questioned the maintainability of the writ
petition. The interpretation and implementation of
a clause in a contract cannot be the subject
matter of a writ petition. Whether the contract
envisages actual payment or not is a question of
construction of contract. If a term of a contract is
violated, ordinarily the remedy is not the writ
petition under Article 226. We are also unable to
agree with the observations of the High Court
that the contractor was seeking enforcement of a
statutory contract. A contract would not become
statutory simply because it is for construction of a
public utility and it has been awarded by a
statutory body. We are also unable to agree with
the observation of the High Court that since the
obligations imposed by the contract on the
contracting parties come within the purview of the
Contract Act, that would not make the contract
statutory. Clearly, the High Court fell into an error
in coming to the conclusion that the contract in
question was statutory in nature.
11. A statute may expressly or impliedly confer
power on a statutory body to enter into contracts
in order to enable it to discharge its functions.
Dispute arising out of the terms of such contracts
or alleged breaches have to be settled by the
ordinary principles of law of contract. The fact
that one of the parties to the agreement is a
statutory or public body will not of itself affect the
principles to be applied. The disputes about the
meaning of a covenant in a contract or its
enforceability have to be determined according to
the usual principles of the Contract Act. Every act
of a statutory body need not necessarily involve
an exercise of statutory power. Statutory bodies,
like private parties, have power to contract or
deal with property. Such activities may not raise
any issue of public law. In the present case, it
has not been shown how the contract is statutory.
The contract between the parties is in the realm
of private law. It is not a statutory contract. The
disputes relating to interpretation of the terms
and conditions of such a contract could not have
been agitated in a petition under Article 226 of
the Constitution of India. That is a matter for
adjudication by a civil court or in arbitration if
provided for in the contract. Whether any amount
is due and if so, how much and refusal of the
appellant to pay it is justified or not, are not the
matters which could have been agitated and
decided in a writ petition. The contractor should
have been relegated to other remedies.”
11.
In the present case, the issues raised by the petitioner, including
attribution of delay in completion of the work, alleged non-availability of
funds, effect of the recommendations made by Respondent No.4,
applicability of Clause 2 for levy of compensation, and entitlement to
the withheld escalation amount, are all matters arising out of the
contractual obligations of the parties and require detailed examination
of the relevant documents, payment records, correspondence and
other evidence, as well as interpretation of the terms and conditions of
the contract. Such disputed questions of fact and contractual
interpretation cannot appropriately be adjudicated in summary
proceedings under Article 226 of the Constitution of India, particularly
when the parties have agreed upon a specific dispute resolution
mechanism culminating in reference to the Arbitration Tribunal.
12.
In view of the aforesaid legal position and considering that (i) the
dispute is purely contractual in nature and relates to delay in
completion of the work and levy of compensation under Clause 2 of the
Conditions of Contract, (ii) the determination of attribution of delay,
effect of non-availability of funds, payment of bills and entitlement to
escalation involves disputed questions of fact requiring examination of
evidence and contractual terms, and (iii) an efficacious and
comprehensive alternative remedy of dispute resolution culminating in
arbitration is specifically available under Clause 28 of the Conditions of
Contract, this Court is not inclined to entertain the present writ petition.
The petitioner has already availed the remedy before the Chief
Engineer and, being aggrieved by the decision rendered thereon, may
pursue the further remedy of reference to the Arbitration Tribunal as
contemplated under Clause 28. The law is well settled that writ
jurisdiction under Article 226 of the Constitution of India is not intended
to supplant an agreed contractual remedy, particularly where the
contract itself provides an efficacious mechanism for adjudication of
disputes.
13.
Accordingly, the writ petition being devoid of merits is hereby
dismissed. No order as to costs.
Sd/(Ravindra Kumar Agrawal)
Judge
sagrika
Sd/(Ramesh Sinha)
Chief Justice
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review