Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
APHC010559832009
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3573]
THURSDAY, THE 12th DAY OF NOVEMBER 2026
PRESENT
THE HONOURABLE SRI JUSTICE BALAJI MEDAMALLI
APPEAL SUIT NO: 619/2009
Between:
1. PORUBOINA YEDUKONDALA, S/O. BHAVANNARAYANA, HINDU
CONTRACTOR R/O. PONNUR POST AND MANDAL, GUNTUR
DISTRICT.
...APPELLANT
AND
1. THE
COMMISSIONER
MUNICIPALITY, PONNUR.
MUNICIPAL
COUNCIL,
PONNUR
2. THE STATE OF ANDHRA PRADESH, REP. BY TIS PRINCIPAL
SECRETARY TO MUNICIPAL ADMINISTRATION, SECRETARIAT,
SAIFABAD, HYDERABAD.
...RESPONDENT(S):
Appeal filed Under Section 96 of CPC before the High Court , to allow
the appeal by setting aside the decree and judgment dated 28-08-2008 in
O.S.No.7 of 2004 on the file of the Court of 1st Additional District Judge,
Guntur and decree the suit as prayed for with costs throughout and pass such
other relief or reliefs as may be deemed fit and proper in the circumstances of
this case.
IA NO: 1 OF 2009(ASMP 1822 OF 2009
Petition under Section 151 CPC praying that in the circumstances stated
in the affidavit filed in support of the petition, the High Court may be pleased
to condone the delay of 256 days in representing the appeal in
A.S.Sr.No.13556 of 2008 in the interest of justice and pass such other order or
Page |2
orders as this Hon'ble Court may deem fit and proper in the circumstances of
the case.
Counsel for the Appellant:
1. NIMMAGADDA SATYANARAYANA
Counsel for the Respondent(S):
1. SIREESHA RANI VALLABHANENI
The Court made the following:
Page |3
THE HONOURABLE SRI JUSTICE BALAJI MEDAMALLI
APPEAL SUIT NO: 619 of 2009
JUDGMENT:
1.
Aggrieved by the Decree and Judgment dated 28.08.2008 in
O.S.No.7 of 2004 passed by the learned I Additional District Judge,
Guntur, (for short "the trial Court"), the appellant/plaintiff preferred
this appeal questioning the correctness of the Decree and Judgment
passed by the Trial Court.
2.
For the sake of convenience, the parties will hereinafter be
referred to as arrayed in the Original Suit.
3.
The plaintiff, a Class-I civil contractor at Ponnur, participated in
the tender called by the 1st defendant for construction of a shopping
complex-cum-auditorium under the Integrated Development of Small
and Medium Towns Scheme. His tender was accepted, and a work
order was issued on 12.02.1999 for an estimated cost of Rs.37.72/lakhs, followed by an agreement. The plaintiff completed the work as
per the contract and deposited Rs.94,500/-, refundable with interest.
However, the defendants paid only Rs.1,73,776.74/- towards the
work without interest or compensation for the delay. Despite issuing
a legal notice under Section 80 CPC on 25.08.2003, demanding
Rs.10,00,000/- as damages, the defendants failed to respond or pay
the amount. Hence, the plaintiff filed the suit.
Page |4
4.
The 2nd defendant remained ex parte, while the 1st defendant
filed a written statement denying the plaintiff's claim. However, the
1st defendant admitted that the plaintiff's tender was accepted for
Rs.34,15,132.29/- at 9.26% below the estimated rates. It was
contended that the plaintiff delayed in entering into the agreement by
12 days and that, due to a change in Government policy, the release
of funds was delayed. Subsequently, pursuant to G.O.Rt.No.1485,
dated 10.12.2002, the defendants paid Rs.6,00,000/- in March 2003
and the balance of Rs.1,72,125/- in January 2004, which the
plaintiff
accepted
on
28.01.2004.
The
1st
defendant
further
contended that the earnest money deposit of Rs.94,500/- was
refundable only upon a written request, which the plaintiff had not
submitted. It was also contended that the excess amount of
Rs.1,72,125/- was paid under the revised administrative sanction
vide C.R.No.34, dated 21.05.2003. On these grounds, the 1st
defendant sought dismissal of the suit.
5.
Based on the above pleadings, the Trial Court framed the
following issues, which are as under:1) Whether the plaintiff is entitled for the suit amount or any part
thereof?
2) Whether the plaintiff is entitled for the interest as claimed?
3) To what relief?
Page |5
6.
On behalf of the plaintiff, two witnesses were examined and got
marked Exs.A1 to A6, during the evidence of these witnesses Exs.X-1
to X-6 were marked. On behalf of the defendants, The Commissioner,
Ponnur Municipality was examined, but, no documents were got
marked.
7.
After considering the evidence on record, the trial Court
dismissed the suit directing both the parties to pay their own costs.
8.
Against the same, the appellant preferred the present Appeal
Suit.
9.
Heard Sri P.Rishyendra Sai, learned counsel representing Sri
Nmmagadda
Satyanarayana,
appellant/plaintiff
representing
and
Sri
Smt.Sireesha
learned
Y.Rajesh
Rani,
counsel
Reddy,
learned
learned
counsel
for
the
counsel
for
the
respondent/defendant.
10. Learned counsel for the appellant contended that the trial Court
erred in dismissing the suit despite the appellant having completed
the contract work worth Rs.37.72/- lakhs within the stipulated time.
It was submitted that, due to the delay in payments by the 1st
respondent, the appellant was compelled to borrow substantial
amounts from Andhra Bank, Ponnur, through SOD Account
No.15102 and from private individuals by executing promissory
notes, thereby incurring heavy interest.
Page |6
11. Learned counsel further contended that the trial Court failed to
properly appreciate Exs.A1 to A6 and Exs.X1 to X6, particularly
Ex.A4, which disclosed that an amount of Rs.14,00,000/- remained
due as on 16.01.2001. It was also argued that the evidence of P.Ws.2
and 3, the promissory notes marked as Exs.X1 and X2, and the bank
statement marked as Ex.X3 established the borrowings made by the
appellant. The trial Court also failed to consider the admission of the
1st respondent regarding the delay in payment, the absence of a
reply to the legal notice dated 25.08.2003 and the failure of the 2 nd
respondent to contest the proceedings. The counsel therefore
submitted that the trial Court had erroneously appreciated the
evidence and sought to set aside the judgment and decree under
appeal and prays to allow the Appeal Suit.
12. Learned counsel for the respondents contended that the plaintiff
had submitted his tender at 9.26% below the estimated rates for
Rs.34,15,132.29/- and had entered into the agreement with a delay
of 12 days. It was submitted that, due to a change in Government
policy, the respondents were initially unable to release the funds.
However, pursuant to G.O.Rt.No.1485, dated 10.12.2002, an amount
of Rs.6,00,000/- was paid in March 2003 and the balance of
Rs.1,72,125/- was paid in January 2004, which was accepted by the
plaintiff on 28.01.2004. Learned counsel further contended that the
Page |7
earnest money deposit of Rs.94,500/- was refundable only upon
submission of a written request, which the plaintiff had failed to
make. It was also submitted that the excess amount of Rs.1,72,125/was paid pursuant to the revised administrative sanction vide
C.R.No.34,
dated
21.05.2003.
Accordingly,
the
respondents
contended that the plaintiff was not entitled to the relief claimed and
sought dismissal of the appeal and hence, he prays to dismiss this
Appeal Suit.
13. Upon hearing both sides and perusing the material on record,
the appellant failed to produce the work order or agreement to
establish the terms and conditions of the contract between the
parties. Further, the agreement did not contain any stipulation
regarding payment of interest or damages payable by the 1st
respondent. Though the plaintiff claimed to have submitted a claim
for damages along with calculations, no such claim was placed on
record. Nor he produced any evidence regarding payment receipts
subsequent to the filing of the suit. The plaintiff also admitted that he
had not issued any written requisition to the defendant seeking the
return of the E.M.D. Thus, the plaintiff failed to establish that he had
suffered damages, that the 1st defendant was liable to compensate
him, or that he had demanded such damages before filing the suit.
Accordingly, the trial Court dismissed the suit on the ground that the
Page |8
plaintiff had failed to establish his legitimate claim for damages.
However, learned counsel for the appellant sought to rely on the
evidence of D.W.1, contending that D.W.1 had admitted the delay in
making payments and further submitted that the delay in completion
and the penal provisions were also admitted by the plaintiff. But the
said admission regarding delay in making payment by itself will not
entitle the appellant to get damages unless the same is substantiated
by placing the relevant agreement which makes him entitled to claim
such damages.
14. It is settled law that a plaintiff must establish his claim through
his own evidence and cannot rely upon the weaknesses of the
defendant. In the present case, the appellant failed to produce the
work order or agreement, establish the contractual terms entitling
him to damages, produce evidence of the alleged damages, or prove
that such damages had been demanded from the defendant.
Therefore, the trial Court assigned sound reasons for dismissing the
suit.
15. In view of the above, this Court finds no grounds to interfere
with the findings of the trial Court, which has duly analysed the
entire evidence on record and recorded findings supported by cogent
reasons.
Page |9
16. Accordingly, this Court finds no merit in the Appeal Suit, and
the same is dismissed. There shall be no order as to costs.
Consequently, miscellaneous petitions pending, if any, shall also
stand closed.
_________________________________
JUSTICE BALAJI MEDAMALLI
Dt. 12.11.2026
MKK
P a g e | 10
THE HONOURABLE SRI JUSTICE BALAJI MEDAMALLI
APPEAL SUIT NO.619 of 2009
DATE: 12.11.2026
MKK
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review