IN THE HIGH COURT OF DELHI AT NEW DELHI
%
+
Judgment Reserved on: 22.07.2026
Judgment delivered on: 14.08.2026
Judgment uploaded on: 14.08.2026
FAO(OS) (COMM) 236/2023 CM APPL. 55402/2023
OMAXE LTD.
.....Appellant
versus
MR. JOGINDER SINGH NIJJAR & ANR.
.....Respondents
Advocates who appeared in this case
For the Appellant
:
Sh. Ramesh Singh, Senior Advocate
with Mr. Mukti Bodh, Ms. Mala
Diwadi and Ms. Nanya Hage,
Advocates with Ms. Neha Chaturvedi,
AR
For the Respondents
:
Ms. Shobhana Takiar with Mr.
Shivam Takiar, Mr. Prateek Dhir and
Mr. Kuljeet Singh, Advocates
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA
JUDGMENT
MANMEET PRITAM SINGH ARORA, J.
1.
The present appeal has been preferred under Section 37 of the
Arbitration and Conciliation Act, 1996 [‘Act of 1996’], assailing the
judgment dated 19.07.2023 [‘impugned judgment’] passed by the learned
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
Single Judge in OMP (COMM.) No. 203/2021 titled Omaxe Ltd. v.
Joginder Singh Nijjar & Anr., dismissing Appellant’s challenge under
Section 34 of the Act of 1996 to the Arbitral Award dated 20.03.2020
[‘Arbitral Award’].
1.1.
The dispute arises out of an Allotment Agreement dated 02.05.2008
[‘Allotment Agreement’] and Addendum dated 02.05.2008 [‘Addendum’]
executed between the parties in relation to allotment of proposed
Commercial Unit No. 26 in the under-construction ‘Omaxe Novelty Mall’,
in Amritsar. The Respondent Nos. 1 and 2 terminated the said agreements
vide legal notice dated 18.04.2013 and lodged a claim for refund of entire
principal amount along with interest. The parties were referred to arbitration.
1.2.
The Arbitral Tribunal was presided over by a retired Supreme Court
Judge, Justice B.S. Chauhan (Retd.) as the Sole Arbitrator [‘Arbitral
Tribunal’], appointed by the Supreme Court.
1.3.
The Arbitral Tribunal vide Award dated 20.03.2020 passed an order
for refund, in favour of the Respondents, for the principal amount of Rs.
3,35,04,650/- plus pendente lite interest computed at Rs. 4,16,94,674/-.
Thus, the total sum awarded is Rs. 7,51,99,324/-. The Arbitral Tribunal
awarded future interest at 12% on this total sum awarded, from the date of
the Arbitral Award till the date of realization, plus costs of Rs. 25 lakhs, in
favour of the Respondents. The Arbitral Tribunal rejected remaining claims
of the Respondents, and the said rejection has attained finality. The Arbitral
Tribunal also rejected the counter-claims of the Appellant.
1.4.
The Appellant challenged the Arbitral Award dated 20.03.2020 in the
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
Section 34 petition, which has been dismissed by the learned Single Judge
by the impugned judgment. Aggrieved by the said refusal to set aside the
Arbitral Award, the Appellant has preferred the present appeal.
FACTS
2.
Facts stated in the appeal are as under: -
2.1
The Appellant, a real estate development company, undertook the
development of a commercial project, namely ‘Omaxe Novelty Mall’ at
Lawrence Road, in Amritsar, pursuant to a Collaboration Agreement dated
23.05.2005 executed with one M/s Novelty Associates Pvt. Ltd. The project
was sanctioned by the Municipal Corporation, Amritsar (‘Municipal
Corporation’) on 25.05.2006 for construction up to a height of 30 meters,
following which construction for the commercial project commenced.
2.2
The Respondents applied for allotment of a Commercial Unit in the
commercial project on 10.02.2007. Between 10.02.2007 and 26.11.2007 a
sum of Rs. 10,05,13,952/- (i.e., 95% of basic sale price of Rs. 10,58,04,160)
of the Commercial Unit No. 26 stood paid to the Appellant. The entire
payment was made from the account of Respondent No. 1.
2.3
Vide Allotment Agreement dated 02.05.2008, Commercial Unit No.
26 located on 04th and 05th floor having an approximate super area of
2601.263 sq. mts./28,000 sq. ft. was signed between the parties. The
Allotment Agreement was issued in favour of the Respondent No. 1 and 2 at
16.665% each, and also in the names of Mr. Jatinder Singh Chatta at
16.665%, Mr. Mohinder Singh Sanghera at 16.665% and Mr. Ashwani
Kumar Uppal at 33.34% [‘five co-allottees’]
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
Thus, Respondent No. 1 and 2 together held 33.33% allotment rights
in the Commercial Unit No. 26.
2.4
Simultaneously, an Addendum dated 02.05.2008 to the Allotment
Agreement was executed between the five co-allottees and the Appellant,
under which the Appellant agreed to pay monthly assured return of
Rs.9,84,199/- till the offer of possession of the Commercial Unit No. 26.
The said amount was calculated as return of 9% on the aforesaid payment of
Rs.10,05,13,952/- (i.e., 95% of the basic sale consideration).
It is stated that the said assured monthly payment was made by the
Appellant with effect from 29.11.2007 and continued till 30.04.2010. No
payment was made thereafter.
2.5
It is stated that the Allotment Agreement at Clause 26(a) expressly
stipulated a construction period of 36 months from the date of signing of the
Allotment Agreement, subject to force majeure and other contractual
conditions.
The said 36 months of the construction period, as per the Allotment
Agreement dated 02.05.2008, expired on 01.05.2011.
2.6
It is a matter of record that Appellant was unable to complete the
construction by 01.05.2011 [i.e., the stipulated date] and in these facts the
Respondents issued a legal notice dated 18.04.2013 cancelling the Allotment
Agreement and seeking refund of its principal amount along with interest. It
also sought reference to arbitration.
2.7
It is stated that during the course of construction, the Archaeological
Survey of India [‘ASI’] objected to the project on the ground that it fell
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
within the regulated area of the Maharaja Ranjit Singh Summer Palace, a
protected monument, and directed that construction beyond height of 15
meters be stopped. According to the Appellant, these objections were raised
by ASI only after the Municipal Corporation had sanctioned the building
plans and construction had substantially progressed. The Appellant contends
that it had obtained all requisite approvals from the Municipal Corporation
and was unaware of any requirement to obtain prior clearance from the ASI.
Consequently, the project remained stalled from April 2007 until February
2012 while the Appellant pursued approvals before the ASI, which
ultimately permitted construction up to height of 24 meters, along with an
additional 2 meters for ancillary structures, vide permission 22.02.2012.
Thereafter, revised building plans were sanctioned, construction resumed,
and a Completion Certificate for the Commercial Unit No. 26 was issued on
08.07.2015.
As per the Appellant, the stoppage of the construction between 2007
to 2012 on account of the objections of ASI should be construed as force
majeure and this period should be excluded for computing the period of 36
months stipulated under Clause 26(a) of the Allotment Agreement.
2.8
Appellant contends that following the due completion of the project,
the Appellant offered possession of the Commercial Unit No. 26 to the
Respondents vide letters dated 16.07.2015, 21.11.2015 and 18.02.2017 and
called upon them to clear outstanding dues and take possession. The
Appellant asserts that despite repeated reminders, the Respondents wilfully
failed to take possession, allegedly due to the downturn in the real estate
market. The Appellant further claims that although the project remained
delayed due to circumstances beyond its control, it nevertheless paid
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
approximately Rs. 2.85 crores towards assured monthly returns as per the
Addendum during the period of ASI restrictions, despite there being no
contractual obligation to do so in view of the force majeure conditions.
2.9
It is a matter of record that the Completion Certificate dated
08.07.2015 was cancelled on 29.01.2016. The said cancellation was assailed
before High Court of Punjab and Haryana at Chandigarh, which stayed the
cancellation vide order dated 17.02.2016. The Completion Certificate was
ultimately restored on 31.07.2019.
2.10 The Appellant vide letters dated 21.11.2015 and 18.02.2017 insisted
that Respondents must perform the Allotment Agreement and accept
possession of Commercial Unit No. 26. However, Respondents did not
accept the said offers and sought reference of the disputes to arbitration
seeking refund of the sale consideration, interest, unpaid assured returns,
delay compensation, damages and costs.
2.11 The Supreme Court vide order dated 17.09.2018 appointed Justice
B.S. Chauhan (Retd.) as the Sole Arbitrator. The Appellant contested the
claims and filed counter-claims seeking, inter alia, refund of assured returns
paid during the force majeure period, holding charges, specific performance
directing the Respondents to take possession, forfeiture of earnest money,
damages and costs.
2.12 After recording evidence, the Arbitral Tribunal passed the Arbitral
Award dated 20.03.2020 awarding refund of the claim of principal amount
and interest plus costs as set out at paragraph 1.1 of this judgment in favour
of the Respondents. The other claims of the Respondents were dismissed.
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
The counter-claims of the Appellant were rejected.
SUBMISSIONS OF THE PARTIES
3.
Sh. Ramesh Singh, learned senior counsel for the Appellant assails the
impugned judgment and the Arbitral Award on the ground that they are
patently illegal, contrary to the terms of the contract and the substantive law
of India, engrafted in the Indian Contract Act, 1872 [‘Act of 1872’].
3.1
It is contended that the Arbitral Tribunal erred in upholding the
Respondents’ termination of the Allotment Agreement dated 02.05.2008 and
directing refund of the sale consideration with interest, solely on the premise
of delay in completion of the project from 2011 to 2015, despite the
undisputed position that the project had ultimately been completed and
possession had been offered to the Respondents in 2015.
3.2
It is contended that the Arbitral Tribunal failed to appreciate that time
was never the essence of the Allotment Agreement, a finding which the
Arbitral Tribunal itself recorded while deciding Issue No. 3 of the Arbitral
Award. The Respondents had never issued any notice making time the
essence of the contract; further, the Addendum executed contemporaneously
with the Allotment Agreement expressly provided for payment of
Rs.9,84,199/- per month as assured monthly returns until the offer of
possession, thereby demonstrating that the parties had consciously
contemplated the possibility of delay and contractually provided the
consequences thereof.
It is stated that Clause 26(e) of the Allotment Agreement also
stipulated compensation of Rs. 10 per sq. ft. of super area, per month, for
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
delay attributable to the Appellant, thereby excluding any right of unilateral
termination to the Respondent. Reliance is placed upon Section 55 of the
Act of 1872 and relies on the decisions of the Supreme Court in Bangalore
Development Authority v. Syndicate Bank1 and IREO Grace Realtech
Pvt. Ltd. v. Abhishek Khanna2, to submit that once possession had been
offered after completion of the project, the Respondents were bound to
accept possession and could only claim contractual compensation for delay.
3.3
The Appellant further submitted that, in any event, the delay
attributable to the Appellant stood substantially reduced after excluding the
period during which construction of the project remained stalled due to
restrictions imposed by the ASI. It is argued that the cancellation of the
ASI’s No Objection Certificate [‘NOC’] between 03.07.2008 and
22.02.2012 constituted a force majeure event squarely covered under Clause
26(b) of the Allotment Agreement, as the stoppage of construction was
beyond the Appellant's reasonable control. It is submitted that the Arbitral
Tribunal, however, erroneously declined to extend the benefit of this force
majeure period (i.e., 2008 to 2012) on the ground that the ASI intervention,
in the project, predated the Allotment Agreement, while ignoring that the
operative cancellation of the NOC occurred only after execution of the
Allotment Agreement with the Respondents. It is stated that the Arbitral
Tribunal also overlooked evidence showing that the Respondents were
aware of the ASI proceedings and that the ASI itself subsequently vide NOC
dated 22.02.2012 permitted construction up to a greater height, thereby
demonstrating that the earlier restrictions on construction were temporary in
nature.
2007 (6) SCC 711
2021 (3) SCC 241
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
3.4
It is also submitted that the Arbitral Award is legally unsustainable as
the notice of termination dated 18.04.2013 was issued only by two of the
five co-allottees, despite the allotment of the Commercial Unit No. 26 being
joint and indivisible. The remaining co-allottees were neither parties to the
termination nor impleaded in the arbitral proceedings. It is contended that
the Arbitral Tribunal erred in holding that the non-joinder of the remaining
co-allottees was not fatal, resulting in an Award which neither effectively
terminated the joint Allotment Agreement nor completely discharged the
Appellant from its obligations under the Allotment Agreement.
3.5
The Appellant also challenges the award of interest on the refund of
the principal amount, contending that both the rate and the period for which
interest has been granted are contrary to the contract and settled law. It is
argued that the force majeure period (i.e., 2008 to 2012) and the period after
the offer of possession (i.e., 16.07.2015 onwards) ought to have been
excluded while computing interest; further, the contractual stipulation
contemplated interest only at the rate of 6%, whereas the Arbitral Tribunal
awarded interest at 14% for pre-reference period and pendente lite without
assigning adequate reasons.
It is submitted that the substantial amount of Rs. 2,85,71,431/- was
already paid by the Appellant (i.e., between 2007-2010) towards assured
monthly returns under the Addendum, the same ought to have been adjusted
against interest amount awarded for the pre-reference period, particularly
since the termination of the Allotment Agreement would necessarily result
in rescission of the Addendum as well.
3.6
It is submitted that the Arbitral Tribunal wrongly rejected the
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
Appellant’s counter-claims seeking specific performance, recovery of
holding charges, taxes and other dues payable after the offer of possession
on the ground of limitation. It is argued that the cause of action arose only
upon the Respondents’ failure to take possession after the renewed offer
dated 29.06.2016, rendering the counter-claims well within limitation.
4.
Ms. Shobhana Takiar, learned counsel for the Respondents states that
the Appellant herein has made a statement on 11.03.2024 before the
Executing Court in execution petition OMP (ENF.) (COMM) 65/2021 titled
Joginder Singh Nijjar and Anr. v. M/s Omaxe Ltd. that it shall pay the
awarded amount in seven (7) instalments. She states that there is no stay of
execution granted in these proceedings and yet the Appellant has failed to
pay the awarded amount.
4.1.
She states that Appellant is mischievously relying upon order dated
13.05.2025 passed in Crl. Appl. No. 2567-2568/2025. She submits that the
said order only pertains to Respondent No.1 and has no concern with
Respondent No. 2. She states that Respondent No. 1 has already availed its
legal remedies against the order declaring it to be a proclaimed offender. She
states that the said proceedings do not entitle the Appellant to withhold the
payments due and payable under the Arbitral Award.
4.2.
She states that the remaining three (3) allottees have also initiated
arbitration proceedings against the Appellant for refund of the principal
amount. She states that similar awards on identical findings have been
passed against the Appellant directing refund in favour of the allottees.
However, Appellant has elected only to challenge the subject Arbitral
Award.
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
5.
In response, learned senior counsel for the Appellant states that no
communication has been received by the Appellant from investigating
agency for attachment of the sums payable under the Arbitral Award in
pursuance of the order dated 13.05.2025. He states that Appellant has not
made payments due under the Arbitral Award on account of its personal
knowledge of the order dated 13.05.2025 passed by the Supreme Court in
Crl. Appl. No. 2567-2568/2025. He states that Appellant is ready and
willing to deposit the amounts due and payable under the Arbitral Award
with the Executing Court.
FINDINGS AND ANALYSIS
6.
This Court has heard the learned counsel for the parties and perused
the record.
7.
The core legal challenges raised by the Appellant against the
impugned judgment are:a. That the impugned judgment fails to appreciate that the Allotment
Agreement and the Addendum expressly contemplated delay in
completion and provided for payment of assured returns at 9% as
compensation for delayed possession. Consequently, once the
project stood completed and possession had been offered, the
Respondents were not entitled to terminate the Allotment
Agreement and seek refund of the sale consideration. It is stated that
time was not the essence of the contract. The Appellant submits that
the impugned judgment is thus contrary to the principles embodied
in Section 55 of the Act of 1872.
b. The delay in completion of the project (from 2008 to 2012) was a
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
force majeure event (Section 56 of the Act of 1872) arising from
restrictions imposed by the ASI, after construction began, which
were beyond the Appellant’s reasonable control.
c. The rejection of the Appellant’s counter-claims was wrongly held to
be barred by limitation. It is submitted that the cause of action arose
only upon the Respondents’ failure to take possession after the
renewed offer of possession dated 29.06.2016 and, therefore, the
counter-claims were well within the prescribed period of three (3)
years.
d. That the learned Single Judge further erred in sustaining the award
of interest at the rate of 14%, contrary to the contractual stipulation
providing for interest at 6% or the Addendum providing for 9%.
8.
The Arbitral Tribunal dealt with the disputes issue-wise and recorded
the following findings; the Tribunal held that the Appellant had commenced
the project without obtaining the mandatory NOC from ASI despite being
aware of the statutory requirement. The Appellant knew about ASI’s
objections even before execution of the Allotment Agreement and inspite of
the same continued accepting bookings from customers without disclosure
of its disputes with ASI. It consequently rejected the plea of force majeure,
holding that the alleged impediment was pre-existing and attributable to the
Appellant's own default. The Tribunal further held that the Appellant had
breached the Allotment Agreement by failing to comply with statutory
requirements, delaying completion of the project, and suppressing material
facts relating to the ASI proceedings and cancellation of the Completion
Certificate.
The Tribunal held that time was not the essence of the contract in
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
view of the contractual provisions permitting extension of time and the
parties’ conduct and found that the Addendum dated 02.05.2008 formed an
integral part of the original Allotment Agreement.
The Tribunal further held that the claims of the Respondents were
within limitation, as arbitration commenced upon receipt of the notice
invoking arbitration, and that the other co-allottees were not necessary
parties, though the Respondents’ were entitled only to their proportionate
share corresponding to their 33.33% interest in the allotted Commercial Unit
No. 26. On merits, the Tribunal directed refund of the Respondents’
proportionate investment of Rs. 3,35,04,650/- along with pre-award and
post-award interest and costs, while rejecting the remaining monetary
claims. The Tribunal also dismissed the Appellant's counter-claims to be
barred by limitation as no dispute had been validly raised or arbitration was
invoked prior to filing them.
9.
The learned Single Judge, has upheld the findings of the Tribunal,
consequently upholding the Arbitral Award.
10.
During oral arguments, the emphasis of the learned Senior Counsel
for the Appellant was on Section 55 of the Act of 1872. He contended that
since the Addendum contemplated assured return of 9% on the principal
amount, the Respondents were duly compensated and could not have
terminated the Allotment Agreement due to the delay. He stated that since
the Arbitral Tribunal had agreed that time was not of the essence of the
Allotment Agreement, the termination of the Allotment Agreement by
Respondents could not have been upheld and therefore, the Arbitral Award
is contrary to Section 55 of the Act of 1872.
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
11.
In this regard, we note that the Appellant’s challenge to the Arbitral
Award on the ground that it is contrary to Section 55 of the Act of 1872 is
not, by itself, a ground available for setting aside an Arbitral Award under
Section 34 of the Act of 1996, after the amendments introduced by the
Arbitration and Conciliation (Amendment) Act, 2015. As explained by the
Supreme Court in Ssangyong Engineering and Construction Company
Limited v. National Highways Authority of India (NHAI)3, the postamendment scope of judicial interference with a domestic Arbitral Award is
significantly circumscribed. A mere allegation of erroneous application or
contravention of substantive law does not furnish a valid ground for
interference unless such illegality goes to the root of the matter and falls
within the limited ambit of ‘patent illegality’ under Section 34(2A), or
attracts the narrow confines of the ‘public policy of India’ ground under
Section 34(2)(b)(ii).
12.
In the facts of the present case, the factual premise underlying the
Appellant's reliance on Section 55 of the Act of 1872 is itself absent. The
Appellant contends that since the Respondents were entitled to assured
returns at the rate of 9% under the Addendum dated 02.05.2008, they were
adequately compensated for the delay and were therefore not entitled to
terminate the Allotment Agreement. However, it is an admitted position that
the Appellant unilaterally discontinued payment of the assured returns with
effect from 01.05.2010, whereas the Respondents terminated the Allotment
Agreement only on 18.04.2013. By its own conduct, the Appellant rendered
the assured return Clause in the Addendum inoperative and cannot now rely
(2019) 15 SCC 131, at Paragraph 36 to 39
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
upon the same as a defence to the Respondents' termination. Indeed, Section
54 of the Act of 1872 embodies the principle that, a party who fails to
perform its reciprocal promise cannot insist upon performance by the other
party. Having itself discontinued payment of the assured returns, the
Appellant forfeited any right to compel the Respondents to continue with the
allotment and accept possession. Therefore, even on the Appellant's own
construction of Section 55 of the Act of 1872, the contention is devoid of
factual and legal merit. We, therefore, find no infirmity in the Arbitral
Award upholding the Respondents’ termination of the Allotment Agreement
or in the judgment of the learned Single Judge.
The hollowness of this submission of the Appellant can also be
gauged from the fact that the Appellant has failed to pay the awarded
amounts despite their being no stay on the award. The conduct of the
Appellant in not depositing the awarded amount with the Executing Court
and discontinuing payment of the assured returns under the Addendum after
2010 all evidence its lack of readiness and willingness to pay compensation
to the Respondents. The Appellant by its own conduct is disentitled from
relying upon Section 55 of the Act of 1872.
13.
With respect to the Appellant’s challenge to the findings of the
Arbitral Tribunal opining that the suspension of the project between 2008 to
2012 cannot be construed as a force majeure period, we find no merit in the
said submission. The Arbitral Tribunal has considered this issue in detail
while deciding issue nos. (1) and (6) at paragraphs 29 to 49 of the Arbitral
Award. The Arbitral Tribunal after perusing the correspondence exchanged
between the Appellant and ASI concluded that the Appellant was fully
aware of its statutory obligation to obtain NOC from ASI before
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
commencing construction. The Arbitral Tribunal concluded that the
commencement of construction by the Appellant without the NOC was
impermissible in law. The Arbitral Tribunal held that the Appellant’s action
of entering into Allotment Agreement with the Respondents on 02.05.2008,
with full notice that it does not have the requisite NOC from ASI, disentitles
the Appellant from claiming the period of 2008-2012, when construction
could not be carried out due to disputes with the ASI, as a force majeure
event. It is a matter of record that ASI has granted NOC on 27.07.2007 for
15 meters height, thus, the Appellant’s attempt to thereafter construct a
building which 30 meters height was obviously illegal and contrary to the
said NOC. In our considered opinion, the said finding of fact returned by the
Arbitral Tribunal rejecting the Appellant’s submission that the period of
suspension of construction from 2008 to 2012 was a force majeure event, is
unexceptional and is in conformity with the evidence on record.
14.
In view of our finding that the Arbitral Tribunal rightly upheld the
termination of the Allotment Agreement by the Respondents and rightly
ordered the refund, the reliefs sought by the Respondents for specific
performance and payment of holding charges, damages etc. cannot be
granted even on merits. On the issue of limitation, the Arbitral Tribunal has
discussed the facts in detail at paragraph 101 and 102 of the Arbitral Award
and we find no ground to interfere in the said finding that the counter-claim
is barred by limitation.
15.
This brings us to the issue of award of interest on the principal
amount by the Arbitral Tribunal at 14%. Learned Senior Counsel for the
Respondent has contended that the contractual stipulation at Clause 26(f) of
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
the Allotment Agreement contemplates refund of the principal amount with
6% interest. He states that even if, the terms of the Addendum are taken into
consideration, where assured return were to be paid at 9% interest, this could
have been the highest rate at which the interest should have been awarded.
The Arbitral Tribunal has returned its finding on award of interest at
paragraph nos. 80 to 83 of the Arbitral Award. The Arbitral Tribunal
considered various clauses of the Allotment Agreement which reserve a
right to the Appellant to recover outstanding dues from the allottees at
interest rate varying from 18% to 24%. The Arbitral Tribunal noted in the
facts of this case, the transaction between the parties has been tainted by
suppression of material information by the Appellant from the Respondents.
The Arbitral Tribunal was of the opinion that the Respondents had been
made to run from pillar to post from 2008 to 2020 by the Appellant. In this
conspectus, the Arbitral Tribunal after detailed deliberation held that w.e.f.
01.05.2011 till the date of Award i.e., 20.03.2020, the Respondents will be
entitled to 14% simple interest per annum on the principal sum of Rs.
3,35,04,650/-. The interest for this period was computed and quantified as
Rs. 4,16,94,674/-. The Arbitral Tribunal further directed that Respondents
will be entitled to interest at 12% on the total sum of Rs. 7,51,99,324/- (Rs.
3,35,04,650 + Rs. 4,16,94,674) from the date of realization.
We find no grounds for interfering in the aforesaid determination by
the Arbitral Tribunal. Clause 26(f) of the Allotment Agreement on which,
the Appellant places reliance can have no application as the said Clause
contemplates delay in completion due to force majeure. However, in the
facts of this case, the plea of force majeure has been decided against the
Appellant. The Arbitral Tribunal has taken into consideration the different
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
clauses of the Allotment Agreement which provide levy of interest rates
between 18% to 24% and has thereafter, consciously with due deliberation
awarded 14% interest. We may note that despite the disapproval of the
Appellant’s conduct vis-à-vis the Respondents recorded by the Arbitral
Tribunal at paragraph 82 of the Award, the Appellant has failed to pay the
awarded amount to the Respondents like a law-abiding citizen. The
Respondents have been compelled to file an execution petition OMP(ENF.)
(COMM) 65/2021 titled Joginder Singh Nijjar and anr v. M/S Omaxe
Ltd. and despite there being no stay granted by this Court, the Appellant has
not paid the decretal amount. The Appellant’s disregard for legal process is
writ large.
16.
The Appellant during arguments had sought to rely upon the order
dated 13.05.2025 passed by the Supreme Court in Criminal Appeal No.
2567-2568 of 2025 vis-à-vis Respondent No. 1 to not pay the awarded
amount. The Appellant has admitted that it has not received any notice from
the police authorities attaching the awarded amount. We accordingly direct
the Appellant to forthwith deposit the awarded amount along with up-to-date
interest with the Executing Court within one (1) week. The amount payable
to Respondent No. 2 shall be released by the Executing Court forthwith and
the amount receivable by Respondent No. 1 shall be released only after
Respondent No. 1 produces before the Executing Court the necessary
permission from the Court concerned dealing with the proceedings pursuant
to the order dated 13.05.2025 passed by the Supreme Court in Criminal
Appeal Nos. 2567-2568 of 2025.
17.
The reliance of the Appellant in Bangalore Development Authority
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
v. Syndicate Bank (supra) is clearly distinguishable on facts and in law.
Firstly, it arose under the Consumer Protection Act, 1986 and concerned the
nature of relief to be granted by a Consumer Forum in cases of delay in
delivery of possession by a statutory development authority, whereas the
present case concerns the limited scope of judicial interference with an
Arbitral award under Section 37 of the Act of 1996. Secondly, in Bangalore
Development Authority (supra), the allottee accepted possession during the
pendency of the consumer proceedings and sought interest/compensation for
delayed delivery. The Supreme Court therefore held that once possession at
the agreed price had been accepted, the allottee would ordinarily not be
entitled to interest on the sale consideration.
In the present case, however, the Respondents had terminated the
Allotment Agreement much prior to the offer of possession and sought
refund of the sale consideration; they never accepted the belated offer of
possession. Accordingly, the said judgment has no application to the facts of
the present case.
18.
The reliance placed by the Appellant on Ireo Grace Realtech Pvt.
Ltd. v. Abhishek Khanna (supra) is misplaced, as the said judgment was
rendered in the context of consumer disputes under the Consumer Protection
Act and RERA concerning delayed possession, interpretation of a specific
apartment buyer’s agreement, and the effect of mandatory statutory
approvals such as Fire NOC under the Haryana Fire Safety Act. The
Supreme Court’s findings were based on the peculiar contractual terms and
statutory framework applicable in that case, including the issue of one-sided
contractual clauses and consumer remedies, none of which arise in the
present arbitration proceedings.
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
Accordingly, the ratio of the said judgment has no application to the
facts or issues involved in the present case.
19.
The reliance placed by the Appellant on Shanmughasundaram v.
Diravia Nadar4 is misplaced. The Supreme Court in this judgment held that
the Arbitral Award was unenforceable because the subject property was
jointly owned by two brothers and three sisters, whereas only the brothers
had entered into the arbitration agreement. Since the absent co-owners
possessed independent proprietary rights in the very property forming the
subject matter of arbitration, the award could not bind them and was
therefore held to be invalid. The Court emphasized that an Arbitral Award
cannot affect the rights of persons who are not parties to the arbitration
agreement, particularly where they are indispensable co-owners of the
disputed property.
The present case stands on an entirely different footing. Here, the
dispute arises out of an Allotment Agreement dated 18.04.2013, to which
both co-allottees were parties, and the arbitration was conducted between the
contracting parties themselves. The Award neither determines nor
prejudicially affects the rights of any independent third-party co-owner or
non-signatory. The Appellant's contention that the Award would not
‘completely discharge’ its obligations under the Allotment Agreement does
not render the Award invalid, as the Award only adjudicates the contractual
rights and liabilities of the parties before the Tribunal. Unlike
Shanmughasundaram (supra), there is no question of the Tribunal deciding
rights of absent persons having an independent interest in the subject matter
2005(10) SCC 278
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
of arbitration.
20.
Similarly, Geo Miller & Co. Pvt. Ltd. v. Bihar Urban
Infrastructure Development Corporation Ltd.,5 is also inapplicable. This
case concerned the maintainability of arbitration proceedings at the instance
of a party which was not itself a signatory to the arbitration agreement,
namely Geo Miller, whereas the arbitration agreement existed between the
Special Purpose Vehicle (SPV) and BUIDCO. The High Court considered
whether a non-signatory could invoke the arbitration Clause despite not
being a contracting party.
In the present case, there is no dispute regarding the identity of the
parties to the arbitration agreement; both parties before the Arbitral Tribunal
are signatories to the arbitration Clause, and the Award binds only those
parties.
21.
The appeal is however bereft of any merits and is hereby dismissed
with costs of Rs. 2,00,000/- payable by the Appellant to the Respondents
equally within two weeks. The proof of payment of cost shall be filed within
two weeks.
22.
Pending applications, if any, stands dismissed.
MANMEET PRITAM SINGH ARORA, J
V. KAMESWAR RAO, J
AUGUST 14, 2026/rhc/hp/AM/IB
2017:DHC:1019-DB
Signed By:MOHIT
Signing
Date:14.08.2026 18:40
FAO(OS) (COMM) 236/2023
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review