Serial No.01
Regular List
HIGH COURT OF MEGHALAYA
AT SHILLONG
Arb.A.No.2/2022
Date of Order: 26.04.2023
North Eastern Electric
Power Corporation Ltd.
Coram:
Vs.
M/s Hindustan Construction
Company Limited
Hon’ble Mr. Justice Sanjib Banerjee, Chief Justice
Hon’ble Mr. Justice W. Diengdoh, Judge
Appearance:
For the Appellant
: Mr. V.K. Jindal, Sr.Adv with
Mr. V. Kumar, Adv
For the Respondent
: Mr. J. Chowdhury, Adv with
Mr. V. Jhunjhunwala, Adv
Ms. D.R. Chowdhury, Adv
Mr. K. Verma, Adv
Mr. J. Shylla, Adv
i) Whether approved for reporting in
Law journals etc.:
ii) Whether approved for publication
in press:
Yes
No
JUDGMENT: (per the Hon’ble, the Chief Justice) (Oral)
The appellant herein engaged the respondent for the
construction of a power project that goes by the name of Papumpare in
Arunachal Pradesh. There is no dispute that the hydroelectric project is
now fully functional, though the work was completed some two years
beyond the original estimated period of three years.
2.
The letter of intent in this case was issued to the respondent
contractor on August 31, 2009 indicating that the tenure of the contract
would be 36 months from such date. The claim in the arbitral reference
was for the period of August 31, 2009 to June 30, 2011, primarily on
account of the estimated work projected to be completed during such
period not having been undertaken. The various head of claims were on
account of idle labour, idle overhead expenditure, idle cost of employees
and machinery and the like. The tenure of the contract was extended, first,
by a letter of July 28, 2012, till the end of August, 2013; and, next, by a
letter of August 27, 2013, till the end of July, 2014.
3.
The appellant employer contends that in view of the extension
of time given to the contractor to complete the work, additional payments
were made on account of cost overruns and other heads and, as such, the
contractor could have had no claim on account of the failure to adhere to
the extent of the work projected to be completed by the contractor during
the original tenure of the contract.
4.
On the appellant being pressed as to the specific grounds under
Section 34 of the Arbitration and Conciliation Act, 1996 that it invokes to
assail the arbitral award of September 15, 2015, it is submitted that in
terms of Section 34(2)(b)(ii) of the said statute, the arbitral award is in
conflict with the public policy of India. To boot, it is asserted on behalf of
the appellant that the Explanation that governed the provision at the
relevant point of time, prior to the Act being amended in 2016, referred to
certain specific aspects being covered by the expression “in conflict with
the public policy of India” but the opening words of the Explanation did
not interfere with the general sense that the relevant sub-clause conveyed.
In other words, the appellant submits that whatever may be contained in
the rest of the Explanation, the opening words of the Explanation to the
relevant sub-clause indicates that the Explanation did not detract from the
generality of what the relevant sub-clause implies.
5.
The appellant amplifies the argument by referring to Section 28
of the Act and relying on the principle recognised in one of the earlier
decisions under Section 34 of the Act rendered in the judgment reported
at (2003) 5 SCC 705 (Oil & Natural Gas Corporation Ltd v. Saw Pipes
Ltd). According to the appellant, an award will regarded to be opposed to
the public policy of India if such award is in conflict with the laws of
India. The appellant goes on to suggest that when a contract between the
parties prohibits certain claims from being made or entertained, an award
in derogation of such contractual prohibition would amount to an act
which was opposed to the public policy of India.
6.
For such purpose, the appellant refers to its pleadings before the
arbitrator, including its written notes of submission submitted in course of
the reference. It appears from a sur-rejoinder filed by the appellant before
the arbitrator that it referred to clause 24(vii) of the contract being a bar to
the several heads of claim fashioned by the contractor. Such reference is
clearly found in paragraph 4 of the relevant document where clause
24(vii) is expressly invoked in conjunction with clause 20 of the matrix
contract between the parties. The same objection is repeated in paragraphs
8 and 30 of the relevant document. The appellant also refers to one of its
written submissions filed which appears at page 435 of the appeal papers.
At paragraph 18 of the relevant document, clauses 24 and 74 of the
contract are specifically referred to. The appellant accepts that apart from
the aforesaid references, there is nothing else in the pleadings or other
documents filed on behalf of the appellant to question the claim of the
contractor on any other ground of prohibition incorporated in the contract.
7.
In this context, it is necessary to look into the three clauses
expressly referred to by the appellant in course of the reference as
prohibiting the claimant from making the claim that was carried to the
reference and from the arbitrator even taking up such matter for
consideration, far less awarding any part of such claim.
8.
Clause 20 of the contract pertained to suspension of work. Such
clause recorded that if there was any suspension of work at the behest of
the engineer-in-charge, certain consequences would follow. These
consequences included extension of the time to complete work and
additional payments to be made to the contractor for the suspension of the
work. However, it is the admitted position that there was no suspension of
work under the contract in the present case. As such, clause 20 of the
contract would have no manner of application in the context of the claim
that was carried by the contractor to the reference or the award that was
rendered thereon.
9.
Clause 24 of the contract pertained to completion time and
extension. Thus, the scope of the clause was confined to the time by
which the tenure of the contract was extended. In such context, clause
24(vii) provided as follows:
“No compensation is admissible other than whatever provided
for in the Clause No.20 (Suspension of Work) for any extension
of time, if granted.”
10.
Quite plainly, the relevant sub-clause would apply only in case
of any extension of time, should such extension be granted. Further, the
extension of time contemplated in clause 24(vii) would have to be in
connection with the suspension of work as clause 20 was specifically
referred to in the provision. Thus, since there was no suspension of work
and no extension as a consequence of suspension, clause 24(vii) of the
contract was not attracted at all.
11.
Clause 74 of the contract between the parties pertained to price
adjustment and variation. Indeed, the opening limb of such provision
referred to fluctuation in the cost of labour, materials, high speed diesel
and the like except for materials supplied by the employer to the
contractor. The second sub-clause in the relevant clause spelt out a
formula for the price adjustment or variation that the contractor would be
entitled to consequent upon the fluctuation of the relevant rates. The last
limb of clause 74 provided as follows:
“No claim, whatsoever, for Price Adjustment/Variation, other
than those stipulated above, shall be entertained.”
12.
The above sub-clause (e) was a part of clause 74 of the contract
and its effect had necessarily to be confined to the clause rather than to
the entirety of the contract. It would have been a completely different
kettle of fish if clause 74(e) were to be a stand-alone, independent clause
that would have governed by the preceding clauses in the contract.
However, as noticed above, clause 74(e) merely clarified the foregoing
provisions in clause 74 of the contract.
13.
The claim in this case that was carried by the contractor had
three main heads: reimbursement for reduced functioning from the
inception of the contract till June 30, 2011; reimbursement of entry tax;
and, claim on account of reinforced steel used in precast RCC lagging. In
respect of the reimbursement of the additional costs incurred, inter alia,
on account of idle hired machinery, under-utilisation of officers and staff,
under-utilisation of labour and expenses at site and office or unachieved
work, the claim carried to the reference was in excess of Rs.40 crore. The
claim for entry tax was in excess of Rs.1.67 crore and that for reinforced
steel was in excess of Rs.5 crore. The second and third heads of claim –
on account of entry tax and reinforced steel – were rejected and the claim
in excess of Rs.40 crore on account of the projected level of work not
being done till June 30, 2011 was whittled down to slightly over Rs.23
crore for which an award was made.
14.
At this stage, it is necessary to refer to the other aspect, on
which there is no dispute. The arbitrator has awarded the principal sum
together with interest. The parties agree that the contract contained a
clause prohibiting the arbitrator from awarding any interest. As such, the
respondent contractor has submitted that it will not press for any interest
other than for the post-award period. The respondent will be bound by
such submission made in course of the present proceedings.
15.
As to the quantification of the claim, the appellant refers to its
comments on the quantification and submits that a rather inflated claim
was made on such count. The other, more substantial, part of the
appellant’s challenge to the award is that upon the contractor being paid
additional money for the extended period that it was granted to complete
the work, there could have been no claim on account of the original tenure
of the contract. In plain words, the assertion of the appellant on such
count is that the claim in the reference was nothing but a duplication and
the same should not have been allowed by the arbitrator.
16.
It is possible that a claimant carries a bad claim to an arbitral
reference. However, a claim that is bad on merits may not be a claim that
is prohibited by the contract. In the present case, the ground that is urged
under Section 34 of the Act is that the award is opposed to the public
policy of India on the ground that the arbitrator has exceeded his authority
and has entered into a no-go territory despite the arbitrator being a
creature of the same agreement which prohibits the very entertainment of
the relevant head of claim.
17.
It is elementary that in this jurisdiction, the court is more
excited with errors of jurisdiction rather than errors within jurisdiction.
Indeed, even faulty interpretations of law by an arbitrator are left
untouched in course of a challenge to an award, unless the court finds
that, as a consequence, there has been a serious miscarriage of justice.
Whether the court strikes down any award or a part thereof on the ground
that there is serious miscarriage of justice as a consequence of any error
committed by the arbitrator or whether any part of the award shocks the
conscience of the court, it matters little since the consequence is the same.
However, what the court cannot do in exercise of the limited authority
granted to it under Section 34 of the Act is to sit in judgment over the
arbitral award as in case of a regular appeal. The reason for this is that
since the parties had agreed to take their dispute resolution mechanism
outside the sovereign field of a court and to a private forum, the court, on
rebound, will not address the issues unless it finds manifest miscarriage of
justice or to the extent that it shocks the conscience of the court. Errors of
law, or of interpretation, or errors of other kinds are within the authority
of the arbitrator and are, more often than not, left uncorrected by the court
in exercise of its jurisdiction under Section 34 of the said Act.
18.
The appellant herein had, without prejudice to its contention
that the entire claim carried by the contractor was inadmissible, asserted
that the contractor had attempted to inflate its claim by using a reduction
factor of 68 which may not have been appropriate. It appears from the
records of the reference that on various aspects, the arbitrator wanted
comments or notes to be filed by the parties, including on the aspect of
quantification under the first head of claim on account of additional costs
incurred for commensurate work not being done. It also appears that upon
the employer objecting to the original quantification of the claim by the
contractor, the contractor scaled it down to closer to what has been
ultimately awarded. Again, the arbitrator gave the employer an
opportunity to deal with the modified quantification, but the employer
failed to avail of the opportunity and did not file its comments to the
modified quantification on the first head of claim filed by the contractor.
19.
In course of appraising the claim and the quantification thereof,
the arbitrator referred to a document that was called “the book of
hindrances” by the parties. The parties apparently maintained such book
to indicate to what extent the work had been impeded on a particular day
and the reasons therefor. It is from such book of hindrances that it was
discovered whether a day’s work or a part of the day’s work on any given
days was less because of any reason attributable to the contractor or to the
employer or otherwise. The contractor founded the claim on the basis that
it was entitled to due compensation for the extent of work not being
achieved as projected in the contract provided there was no wrongdoing
on the part of the contractor. On the other hand, the contention of the
employer before the reference was that only the delay attributable to the
employer should be considered for the purpose of compensating the
contractor. What the employer meant was that if there was any delay that
may not have been attributable to either the contractor or the employer,
the contractor could not be compensated on such account by penalising
the employer.
20.
Though not in so many words, the arbitrator reasoned that since
a projected level of work had been indicated and such level of work was
not met in a given month, on the basis of charts which are appended to the
award itself, calculations were made as to the extent of damages that the
contractor would be entitled to. It may do well, in this context, to
understand the basis of the claim and the award therefor. In simple terms,
the contractor claimed that for the purpose of achieving the extent of work
that it was required to do within a particular time, the contractor had to
engage men and machinery. Upon the work not being done to the
expected extent, a part of the labour and machinery that the contractor had
hired in anticipation of such resources being required, were left idle for
which the contractor had to bear the expenses; but since no commensurate
work was done, the contractor was not to be compensated in such regard.
It is such claim of the contractor which has been allowed by the arbitrator
to a limited extent and without paying heed to the appellant’s contention
that the delay not attributable to the appellant should not be counted
against the appellant.
21.
The decision to such extent fell squarely within the domain of
the arbitrator’s authority and the court, in exercise of power under Section
34 of the Act, does not look for small mistakes with an intention to
interfere with the award. In fact, the mantra under Section 34 of the Act –
indeed, as it has always been in this branch of law – is that the court will
not interfere unless there is grave injustice occasioned to the party
assailing the arbitral award.
22.
The court of the first instance noticed that several of the
grounds that were sought to be urged in course of the petition under
Section 34 of the Act may not have been presented before the arbitrator or
may not have been incorporated in the grounds filed along with the
petition to challenge the arbitral award. The appellant asserts that it
matters little whether a ground has been specifically taken in the petition
under Section 34 of the Act as long as it can be demonstrated that a clause
in the contract prohibited in a particular head of claim which has been
allowed by the arbitrator.
23.
In such context, the appellant relies on a recent judgment
reported at (2022) 2 SCC 275 (State of Chhattisgarh v. Sal Udyog (P)
Ltd.) Paragraph 24 of the judgment is pressed into service:
“24. We are afraid, the plea of waiver taken against the
appellant State on the ground that it did not raise such an
objection in the grounds spelt out in the Section 34 petition and
is, therefore, estopped from taking the same in the appeal
preferred under Section 37 or before this Court, would also not
be available to the respondent Company having regard to the
language used in Section 34(2-A) of the 1996 Act that
empowers the Court to set aside an award if it finds that the
same is vitiated by patent illegality appearing on the face of the
same. Once the appellant State had taken such a ground in the
Section 37 petition and it was duly noted in the impugned
judgment, the High Court ought to have interfered by resorting
to Section 34(2-A) of the 1996 Act, a provision which would be
equally available for application to an appealable order under
Section 37 as it is to a petition filed under Section 34 of the
1996 Act. In other words, the respondent Company cannot be
heard to state that the grounds available for setting aside an
award under sub-section (2-A) of Section 34 of the 1996 Act
could not have been invoked by the Court on its own, in
exercise of the jurisdiction vested in it under Section 37 of the
1996 Act. Notably, the expression used in the sub-section is
“the Court finds that”. Therefore, it does not stand to reason
that a provision that enables a Court acting on its own in
deciding a petition under Section 34 for setting aside an award,
would not be available in an appeal preferred under Section 37
of the 1996 Act.”
24.
What cannot be lost sight of is that paragraph 23 of the report in
Sal Udyog records that the objection on the ground of prohibition in
contract was raised before the arbitral tribunal, but a ground in such
regard was not specifically incorporated in the petition challenging the
award. It was in such context that the finding as rendered in paragraph 24
of the judgment came to be made. In the present case, it has already been
discussed that the only three clauses that were placed by way of
prohibitory provisions before the arbitrator were clauses 20, 24 and 74.
As already noticed, none of such clauses can be read to amount as a
prohibition on the arbitrator to entertain the claim on the first head as
carried by the contractor to the reference.
25.
In any event, the ratio decidendi in paragraph 24 of the
judgment in Sal Udyog would be inapplicable in the present case since the
award in this case was rendered on September 15. 2015 and this matter
would be governed by the provisions of the said Act of 1996 prior to its
2016 amendment. Sub-section (2-A) was inserted in Section 34 of the Act
by the 2016 amendment.
26.
As a result, the judgment and order dated October 25, 2022 are
left untouched except that the award on account of interest in the award of
September 15, 2015 is set aside for the pre-reference period and whatever
may have been awarded as pendente lite interest. This will not prevent the
respondent herein to claim interest at the indicated rate from the date of
the award in accordance with law.
27.
To clarify, the award of the principal sum is left undisturbed.
The grounds of challenge carried by the appellant are found to be without
merit.
28.
Arb.A.No.2 of 2022 is disposed of with costs assessed at
Rs.50,000/- to be paid by the appellant to the respondent within three
months from date, failing which it will carry interest at the same rate as
provided by the arbitrator for the post-award period.
(W. Diengdoh)
Judge
(Sanjib Banerjee)
Chief Justice
Meghalaya
26.04.2023
“Lam DR-PS
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.