IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 13.07.2026
Pronounced on: 11.08.2026
Uploaded on: 11.08.2026
#
CNR No. DLHC010265822022
+
O.M.P. (COMM) 293/2022 & I.A. 10899/2022
NATIONAL HIGHWAYS AUTHORITY OF INDIA .....Petitioner
Through: Mr. Manish K. Bishnoi and Mr.
Khubaib Shakeel, Advocates.
versus
KNR CONSTRUCTIONS LTD.
.....Respondent
Through: Ms. Kiran Suri, Senior Advocate
with Mr. Hitendra Nath Rath and
Ms. Laxmi, Advocates.
CORAM:
HON’BLE MR. JUSTICE PRATEEK JALAN
JUDGMENT
1.
By way of this petition under Section 34 of the Arbitration and
Conciliation Act, 1996 [hereinafter, “the Act”], the petitioner – National
Highways Authority of India [hereinafter, “NHAI”], assails an arbitral
award dated 08.12.2021, by which a three-member arbitral tribunal has
adjudicated a dispute arising out of a contract dated 22.10.2009, wherein
the respondent – M/s. KNR Constructions Limited [hereinafter, “KNR”]
was awarded “Balance works of Widening to 4/6-Lanes and Strengthening
of Existing 2- Lane Carriageway of NH-5 in the State of Orissa from Km
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
284.000 to Km 338.000 (Ganjam-Sunakhala) (Project Chainage from Km
284.000 to 340.006)” [hereinafter, “the Agreement”].
A. BACKGROUND
2.
This is the second round of proceedings between the parties,
arising out of arbitral proceedings under the Agreement. Arbitral
proceedings were earlier commenced by KNR on 08.07.2013, and
resulted in an Award dated 29.04.2017, which was substantially in its
favour [hereinafter, “the 2017 Award”]. However, the Award was
challenged by both parties. NHAI’s challenge1 was dismissed by an order
of this Court dated 25.10.2018. The said order was unsuccessfully
assailed by NHAI before the Supreme Court2. The 2017 Award was also
challenged by KNR3, to the extent that the Arbitral Tribunal had denied
pre-reference interest on the awarded amount of price adjustment, and
also with regard to the rate of interest awarded for the pendente lite and
post-award period. KNR’s challenge was successful, and the Award, to
the aforesaid extent, was set aside by an order of this Court dated
03.05.2019. It was left open to the parties to re-agitate their claims or
counterclaims by way of appropriate proceedings. The impugned Award
dated 08.12.2021 has been rendered pursuant to that process.
3.
In the first round of arbitral proceedings, the Arbitral Tribunal was
constituted by nominees of each of the parties, who will be referred to in
this judgment as “Arbitrator A” [nominee of KNR] and “Arbitrator B”
[nominee of NHAI]. They nominated a Presiding Arbitrator, who will be
referred to as “Arbitrator C”. The dispute pertained to payment of price
O.M.P.(COMM) 396/2017.
SLP (C) Diary No. 12360/2019, decided on 03.07.2019.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
adjustment on all items of the Bill of Quantities [hereinafter, “BOQ”],
and interest thereon. A majority of the Tribunal, comprising Arbitrators A
and C, awarded a sum of Rs. 35,39,67,728/- in favour of KNR. Interest
was awarded on delayed payments from 03.08.2013, being the date of
filing of the Statement of Claim, at the rate of 10% per annum, till the
date of the Award, and further at the same rate from the date of the Award
till the date of payment. Arbitrator B delivered a dissenting opinion,
dismissing KNR’s claims.
4.
As noted above, challenges by both parties culminated in partial
setting aside of the 2017 Award, at the instance of KNR, only on the
question of denial of interest for the pre-reference period and the rate of
interest for the post-reference period.
5.
Pursuant to liberty granted by the order of this court dated
03.05.2019, KNR’s plea relating to interest was again adjudicated by a
Tribunal of three arbitrators. Arbitrators B and C were common to both
proceedings. Arbitrator A, however, recused himself by letter dated
06.02.2020 citing “personal problems and pre-occupation”, and KNR
nominated a new arbitrator, hereinafter referred to as “Arbitrator D”.
6.
By the Award dated 08.12.2021, impugned in this petition, the
Tribunal held in favour of KNR, relying upon Clause 60.8 of the
Conditions of Particular Application [hereinafter, “COPA”]. It was held
that KNR was entitled to interest at the rate of 10% per annum
compounded monthly, on the amount of price adjustment awarded, such
interest also being payable for the pre-reference period, i.e., from the date
on which the amount should actually have been paid, until the date of
O.M.P.(COMM) 295/2017.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
actual payment. The impugned Award was also rendered by majority, this
time consisting of Arbitrators C and D. Arbitrator B dissented.
B. SCOPE OF CHALLENGE
7.
I have heard Mr. Manish K. Bishnoi, learned counsel for NHAI,
and Ms. Kiran Suri, learned Senior Counsel for KNR.
8.
The challenge was argued on two broad grounds – the first relating
to the jurisdiction of the arbitral tribunal comprising arbitrators B, C, and
D, and the second relating to the merits of the award. Each of these
aspects is taken up in turn below, including reference to the arguments of
learned counsel, and the authorities cited by them.
C. RELEVANT CLAUSES OF THE AGREEMENT
9.
As the impugned Award is confined to the question of interest, it is
not necessary to enter into the factual position with regard to the
substantive dispute, in detail. Only two clauses of the contract are
relevant for the present purposes, being the clauses relating to interest and
to arbitration.
10.
Clause 60 of COPA deals with certificates and payment. Sub-clause
60.8 provides for time of payment and interest payable to the contractor.
Clause 67 of COPA deals with settlement of disputes. Sub-clause 67.1
provides for a Disputes Review Board [hereinafter, “DRB”] and, if the
recommendations of the DRB is unacceptable to either the employer or
the contractor, then it provides for commencement of arbitration by notice
to the other party. Sub-clause 67.3 contains detailed provisions with
regard to the resulting arbitration. The relevant clauses are extracted
hereinbelow:
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
“Sub-Clause 60.8
Clause 67:
Sub-Clause 67.1:
Time of Payment and Interest
“The amount due to the Contractor under any
Interim Payment Certificate issued by the Engineer
pursuant to this Clause, or to any other term of the
Contract, shall, subject to Clause 47, be paid by
the Employer to the Contractor upto fifty percent
(50%) of eligible payment within 7 (seven) days of
receipt of acceptable Monthly Statement from the
Contractor. The balance eligible payment shall be
released within 42 days after the Contractor’s
monthly statement has been submitted to the
Engineer for certification or, in the case of Final
Certificate pursuant to Sub-Clause 60.13, within
84 days after the agreed Final Statement and
written discharge have been submitted to the
Engineer for certification. ln the event of the
failure of the Employer to make payment within the
times stated, the Employer shall pay to the
Contractor interest compounded monthly at the
rate stated in the Appendix to Bid upon all sums
unpaid from the date upon which the same should
have been paid, in the currencies in which the
payments are due.
However, for calculation of interest, the specified
time limit of 42 (Forty two) days will be
applicable.
Settlement of Disputes
The procedure for settlement of disputes is
stipulated below.
Disputes Review Board
Sub-Clause 67.1 is substituted by the following:
“67.1 If any dispute arises between the Employer
and the Contractor in connection with, or arising
out of, the Contract or the execution of the Works,
whether during the execution of the Works or after
their completion and whether before or after the
repudiation or other termination of Contract,
including any disagreement by either party with
any action, inaction, opinion, instruction,
determination, certificate Or valuation of the
Engineer, the matter in dispute shall, in the first
place be referred to the Disputes Review Board
("the Board").
xxx
xxx
xxx
Either the Employer or the Contractor may refer a
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
dispute to the Board in accordance with the
provisions of Annex B to these Conditions of
Particular Application.
If either the Employer or the Contractor is
dissatisfied with any Recommendation of the
Board, or if the Board fails to issue its
Recommendation within 56 days after receipt by
the Chairman of the Board of the written Request
for Recommendation, then either the Employer or
the Contractor may, within 14 days after his
receipt of the Recommendation, or within 14 days
after the expiry of the said 56-day period, as the
case may be, give notice to the other party, with a
copy for information to the Engineer, of his
intention to commence arbitration, as hereinafter
provided, as to the matter in dispute. Such notice
shall establish the entitlement of the party giving
the same to commence arbitration, as hereinafter
provided, as to such dispute and, subject to SubClause 67.4, no arbitration in respect thereof may
be commenced unless such notice is given.
If the Board has issued a Recommendation to the
Employer and the Contractor within the said 56
days and no notice of intention to commence
arbitration as to such dispute has been given by
either the Employer or the Contractor within 14
days
after
the
parties
received
such
Recommendation
from
the
Board,
the
Recommendation shall become final and binding
upon the Employer and the Contractor.
Whether or not it has become final and binding
upon the Employer and the Contractor, a
Recommendation shall be admissible as evidence
in any subsequent dispute resolution procedure,
including any arbitration or litigation having any
relation to the dispute to which the
Recommendation relates.
All Recommendations which have become final
and binding shall be implemented by the parties
forthwith, such implementation to include any
relevant action of the Engineer.
xxx
xxx
xxx
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
Sub-Clause 67.3
Arbitration
Sub-Clause 67.3 is modified to read as follows:
"Any dispute in respect of which the
Recommendation(s), if any, of the Board has not
become final and binding pursuant to Sub-Clause
67.1 shall be finally settled by arbitration as set
forth below. The arbitral tribunal shall have full
power to open-up, review and revise any decision,
opinion, instruction, determination, certificate or
valuation
of
the
Engineer
and
any
Recommendation(s) of the Board related to the
dispute.
A dispute with an Indian Contractor shall be
finally settled by arbitration in accordance with
the Arbitration & Conciliation Act 1996, or any
statutory amendment thereof. The arbitral tribunal
shall consist of 3 arbitrators, one each to be
appointed by the Employer and the Contractor.
The third Arbitrator shall be chosen by the two
Arbitrators so appointed by the Parties and shall
act as Presiding arbitrator. In case of failure of the
two arbitrators, appointed by the parties to reach
upon a consensus within period of 30 days from
the appointment of the arbitrator appointed
subsequently, the Presiding arbitrator shall be
appointed by the President, Indian Roads
Congress. For the purposes of this Sub-Clause, the
term "Indian Contractor" means a contractor who
is registered in India and is a juridic person
created under Indian law as well as a joint venture
between such a contractor and a Foreign
Contractor.
xxx
xxx
xxx
(v) If one of the parties fail to appoint its arbitrator
in pursuance of sub- clause (i) and (ii) above,
within 30 days after receipt of the notice of the
appointment of its arbitrator by the other party,
then the President of Indian Road Congress both in
cases of foreign contractors as well as Indian
Contractors, shall appoint the arbitrator. A
certified copy of the order of the President of
Indian Road Congress making such an
appointment shall be furnished to each of the
parties.”
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
D. RE: JURISDICTION OF THE TRIBUNAL
11.
The first contention requires adjudication of a fundamental
argument, as to the validity of the second round of proceedings. Mr.
Bishnoi contended that the entire procedure adopted by the Tribunal, after
the order of this Court dated 03.05.2019, was fundamentally flawed in
law. Relying upon Section 31 of the Act, he argued that the mandate of
the first Arbitral Tribunal stood terminated as soon as the 2017 Award
was passed on 29.04.2017. The present case, he submitted, neither fell
within the scope of a rectification application under Section 33 of the Act,
nor was the matter remanded to the Tribunal under Section 34(4) thereof.
In these circumstances, Mr. Bishnoi submitted that, as a consequence of
the liberty granted by the Court to re-agitate the matter, KNR could only
have invoked arbitration anew under Clause 67 of COPA read with
Section 21 of the Act.
12.
In order to adjudicate this contention, the conduct of the arbitral
proceedings, after the order of this Court dated 03.05.2019 in O.M.P.
(COMM) 295/2017, must be noticed in some detail. Those facts are
undisputed, and are as follows:
a. After the order dated 03.05.2019, KNR did not issue any fresh
request for arbitration with regard to its claim for interest. Instead,
it addressed an application dated 05.06.2019 to the earlier Arbitral
Tribunal, comprising Arbitrators A, B, and C. The application
referred
to
the
aforesaid
order
of
this
Court
and
to
“Recommencement of Arbitration Proceeding for pronouncement
of award on account of interest pertaining the claim “payment
towards price adjustment on all the BOQ items of work””. It
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
requested the Tribunal to convene arbitral proceedings for oral
deliberation of the aforesaid issue and to take appropriate action.
b. Arbitrator C addressed a communication dated 18.06.2019 to both
parties and to the other Arbitrators, stating as follows:
“In this reference one of the party had prayed on 05/06/2019, and
since then two weeks have passed. Taking cognisance of above facts,
with consent of both parties, the Arbitral Tribunal hereby notify for
start of proceedings, and soon the date/place of meeting/ hearing
shall be intimated.”
c. On 22.06.2019, KNR once again requested that a date for
arbitration be fixed.
d. A hearing was held before the said three Arbitrators on 10.07.2019,
at which both parties were represented by counsel. The minutes
record that the meeting was convened and was held “with the
consent of all concerned”5. The parties undertook to submit a
“write-up” with regard to the claim under adjudication.
e. On 24.07.2019, KNR submitted a document to the Arbitral
Tribunal titled “Re-agitation of Interest Claim”. It referred to
various clauses of COPA – Clauses 60.1, 60.2, and 60.8 read with
the Appendix to Bid, and judgments of this Court with regard to
payment of interest under Clause 60.8 of COPA. It then formulated
the relief sought in the following terms:
“(i) Monthly compounding interest @10% p.a. is payable from the
date of reference till the date of actual payment of the amount
awarded qualifying clause 60.8 of COPA.
(ii) Monthly compounding interest @10% p.a. is payable as per
Clause 60.8 of COPA till the day preceding the date of reference i.e.
03.08.2013.
Emphasis supplied.
Emphasis supplied.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
(iii) Monthly compounding interest @10%PA is payable as per
clause 60.8 of COPA for monthly statement- IPC 35, 36, & 37 and
final certificate as per provision of the contract.
(iv) And to pass any other award as the Hon'ble Tribunal may find it
proper in the interest of justice.”
f. The said document was accompanied by a table computing the
interest payable on Interim Payment Certificates [hereinafter,
“IPCs”] Nos. 1 to 37 and the Final Payment Certificate dated
25.06.2015.
g. As NHAI failed to submit its response, by a communication dated
01.10.2019, Arbitrator C directed it to do so.
h. In view of NHAI’s continued failure, KNR, by a communication
dated 24.01.2020, requested the Tribunal to hold further hearings.
i. Arbitrator C, by a further letter dated 07.02.2020, once again
requested NHAI to respond.
j. NHAI, through its counsel, finally submitted a “Statement of
Defence for and on behalf of the respondent to the fresh Claim No.
6 [Interest]” on 11.02.2020. The claim was contested on merits, but
no dispute was raised with regard to the jurisdiction or the
procedure of the Arbitral Tribunal. In fact, NHAI’s only challenge
to maintainability was due to KNR’s failure to approach the
Tribunal within the period of 30 days as contemplated by Section
33 of the Act.
k. By a letter dated 13.02.2020, Arbitrator C informed the parties that
Arbitrator A had been replaced as KNR’s nominee by Arbitrator D,
and that the Arbitral Tribunal “stands reconstituted”. The
communication of KNR to this effect was also circulated, as was
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
Arbitrator D’s declaration in terms of the Sixth Schedule to the Act.
At this stage also, NHAI did not raise any objection.
l. KNR addressed a further letter dated 16.03.2020 to NHAI, in
which it referred to an email dated 13.03.2020 addressed by
Arbitrator B to the Chairman, NHAI. Arbitrator B expressed an
opinion that the erstwhile Arbitral Tribunal was without any
mandate to examine or re-examine any fresh claims, and sought a
response towards resolution of this issue, as to whether the
mandate of the erstwhile Tribunal stood revived. KNR specifically
consented to the mandate of the Tribunal comprising Arbitrators B,
C, and D in this regard.
m. KNR thereafter filed a rejoinder to the Statement of Defence on
01.06.2020.
n. A further meeting of the Arbitral Tribunal was held on 11.07.2020.
In the minutes of the hearing dated 11.07.2020, a communication
of Arbitrator B to Arbitrator C, dated 11.03.2020, has been
extracted in full. Arbitrator B expressed his reservation about the
mandate of the Arbitral Tribunal and opposed further hearings
before resolving this basic issue. He contended that the mandate
had been terminated in terms of Section 32 of the Act, after which
re-examination of any fresh claim was beyond the mandate of the
erstwhile Tribunal. The further observations of the Tribunal in the
said minutes are of great relevance, and are reproduced below6:
“2.7 Presiding arbitrator asked the parties whether they would like
to give their point of view/ make their submissions on above
KNR is described as the “claimant”, and NHAI as the “respondent” in the below extract.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
communication. The respondent's advocate suggested for video/
audio recordings of the proceedings from here. All the participants
agreed and Shri Rajeev Kapoor favoured the AT by doing audio
recording (later on he made it available to all).
2.8 Both the Claimant and Respondent made their detail
submissions. Shri Prabhat Krishna Co-Arbitrator cross questioned
many times to both the parties during their submissions.
2.9 Rather than making it an essay or award, both the parties in
unison opined and stated that this present matter of claim
pertaining to interest, in reference to Hon'ble Delhi High Court
order dated 03/05/2019 and Claimant's application dated
05/06/2019 is to be dealt in continuity to the previous claim of
price escalation, and there was no need for separate mandate. It
was also stated in clear terms that they cooperated in full, and
participated in first meeting of 10/07/2019 and submitted their
pleadings. None of the parties ever objected. Shri S L Jadhav CoArbitrator agreed with the views of both the parties and opined for
proceeding in the matter. The Presiding arbitrator also agreed with
the views/ submissions of both the parties, and Co-Arbitrator Shri S
L Jadhav.
2.10 The Presiding arbitrator explained that the minutes of
10/07/2019 meeting were drawn with final consent of AT. All the
members of AT, without any reservation, signed the order and
delivered to both the parties. There had been no comment over that
till Shri C K Das recused himself on 06/02/2020 on account of his
personal problems and preoccupation. So, nothing more can be
assumed except Shri C K Das co-arbitrator's own letter, as "It is to
intimate that I will not be able to continue/perform my obligation as
the Co- Arbitrator in the above case because of my personal
problems and pre-occupation. Hence I do hereby recuse from the
said Tribunal with immediate effect."
xxx
xxx
xxx
2.13 Thus, with consent of all, it was decided to hold the zoom
meetings at 2.30 pm on 22/07/2020 and 11.50 am on 23/07/2020.
After this, all the participants (except AT members) left the meeting
for enabling the AT for further discussions amongst them.
2.14 The AT deliberated the matter. Both the Presiding Arbitrator
and Shri S L Jadhav Co-arbitrator again opined the same, as
hearing this matter of interest, in continuity.”
o. These minutes, as available on the record, were signed only by
Arbitrator C. Arbitrator B objected to the aforesaid minutes by an
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
email dated 17.07.2020. He suggested the following amendments
to paragraphs 2.8 and 2.9 of the minutes dated 11.07.2020:
“Para 2.8 may be re-drafted to read: “The Council for the
Claimant (sic.) agreed that there was no provision for reviving the
Erstwhile Arbitral Tribunal in the Arbitration and Reconciliation
Act, 1996 (sic.). However, according to him, the Claimant had the
option to either refer the matter to a fresh Arbitral Tribunal or at
its discretion seek adjudication through the Erstwhile Arbitral
Tribunal itself. He further stated that matter now being brought up
has to be treated as a fresh claim. The Council for the Respondent
(sic.) concurred with the view of the Council for the Claimant
(sic.) that there was no provision in the Arbitration and
Reconciliation Act, 1996 (sic.) for reviving the erstwhile Arbitral
Tribunal and also agreed with him that if both the parties agreed,
the matter could be adjudicated upon by the Erstwhile Arbitral
Tribunal. He, however, was of the firm view that the matter now
brought up could not be considered as a fresh claim and had to be
dealt with as an extension to the earlier claim already adjudicated
upon by the Erstwhile Arbitral Tribunal. He also wanted a ruling on
the above issues from the Arbitral Tribunal before proceeding
further.”
Para 2.9 may be re-drafted to read “The Presiding Arbitrator and
Mr. Jadav, the substitute Arbitrator were of the view that in the
light of the submissions made by both the Councils (sic.), the
Erstwhile Arbitral Tribunal had the jurisdiction to adjudicate the
matter but the Claim would not be considered as a fresh claim and
would be dealt with as an extension to the earlier claim already
dealt with and adjudicated upon by the Erstwhile Arbitral
Tribunal. The Arbitral Tribunal therefore ruled accordingly.”
p. The next hearing was held on 22.07.2020, by which the aforesaid
paragraphs of the earlier minutes were replaced with the
paragraphs suggested by Arbitrator B. Parties were directed to
make copies of the contract and previous pleadings available to all
the Arbitrators, and further meetings were fixed with the consent of
all the parties.
Emphasis supplied.
Emphasis supplied.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
q. At this stage, on 01.08.2020, counsel for NHAI requested the
Tribunal to adjourn its proposed sitting on 05.08.2020 to enable it
to object to the recusal of Arbitrator A and to seek a direction that
Arbitrator A must continue
as
an arbitrator. KNR, by
communication dated 03.08.2020, objected to this request and
urged the Tribunal to “continue with the proceedings of the AT9 to
finalize the matter at the earliest”.
r. A meeting was, in fact, held on 05.08.2020, but was kept in
abeyance due to the aforesaid request of NHAI.
s. On 24.09.2020, however, NHAI informed the Tribunal that it had
decided not to pursue the above issue and requested the
reconstituted Tribunal to take necessary action for further
proceedings. On 22.02.2021, KNR submitted another document,
updating its interest claim on account of a further period having
lapsed.
t. Hearings were thereafter held, at which counsel for both parties
made their submissions. No further objection was recorded at any
stage with regard to the continuation of the proceedings.
u. The impugned Award was rendered on 08.12.2021.
13.
Mr. Bishnoi argued that the entire procedure adopted by the
Arbitral Tribunal was illegal and without jurisdiction. The decision of the
Tribunal, that it was continuing with the old arbitral proceedings, as
reflected in its minutes dated 11.07.2020 read with minutes dated
22.07.2020, was, according to him, without any basis in law. The
substratum of the adjudicatory process being thus vitiated, learned
Arbitral Tribunal.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
counsel submitted that the impugned Award could also not stand scrutiny
under Section 34 of the Act.
14.
Mr. Bishnoi further contended that the question of consent or
acquiescence did not arise, since the Tribunal had proceeded on the
understanding that it was a continuation of the earlier Arbitral Tribunal,
and not a newly constituted one. He also submitted that consent cannot
validate proceedings which are inherently without jurisdiction, as in the
present case. In support of this submission, Mr. Bishnoi cited judgments
of the Supreme Court in Inder Sain Mittal v. Housing Board, Haryana
and Others10, Srei Infrastructure Finance Ltd. v. Tuff Drilling Pvt. Ltd.11,
Lion Engineering Consultants v. State of Madhya Pradesh and Ors.12, and
Hindustan Zinc Ltd. v. Ajmer Vidyut Vitran Nigam Ltd.13. He also referred
to the judgment in Sweta Construction v. Chhattisgarh State Power
Generation Co. Ltd.14, which follows an earlier judgment in M.P. Rural
Road Development Authority v. L.G. Chaudhary Engineers &
Contractors15.
15.
Mr. Bishnoi submitted that, in any event, even on facts, the
proceedings before the reconstituted Tribunal could not be construed as
independent proceedings. There was no exchange of pleadings before the
new Tribunal, no filing of documents, no evidence – whether
documentary or oral – was taken, issues were not framed, and the entire
(2002) 3 SCC 175 [hereinafter, “Inder Sain Mittal”].
(2018) 11 SCC 470 [hereinafter, “Srei Infrastructure”].
(2018) 16 SCC 758 [hereinafter, “Lion Engineering”].
(2019) 17 SCC 82 [hereinafter, “Hindustan Zinc”].
(2024) 4 SCC 722 [hereinafter, “Sweta Construction”].
(2018) 10 SCC 826 [hereinafter, “L.G. Chaudhary”].
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
proceedings were, thereafter, irregular, and not in compliance with
statutory provisions, particularly Sections 23 and 24 of the Act.
16.
Ms. Suri, on the other hand, submitted that the facts detailed above
clearly demonstrate that NHAI had acquiesced in the determination of
this issue by the Arbitral Tribunal, as constituted with Arbitrators B and D
as its Members, and Arbitrator C as the Presiding Arbitrator. She
submitted that no objection on account of jurisdiction or procedure was
raised by NHAI at any stage. Even after the issue was flagged by
Arbitrator B, instead of raising an objection, NHAI expressly consented
to the continuation of proceedings. Ms. Suri submitted that arbitral
proceedings, being founded in the concept of consent to the submission of
disputes before a mutually constituted tribunal, cannot be reopened at the
instance of a party which did not file any objection under Section 16 of
the Act. She places reliance on judgments of the Supreme Court in L.G.
Chaudhary, Quippo Construction Equipment Ltd. v. Janardan Nirman
Pvt. Ltd.16, M.P. Housing and Infrastructure Development Board and Anr.
v. K.P. Dwivedi,17 Sweta Construction, and JMC Projects (India) Ltd. v.
Madhya Pradesh18, in support of these contentions.
17.
As evident from the above submissions, it is factually undisputed
that, after the order dated 03.05.2019, KNR sought to “re-agitate” its
interest claim before the Tribunal, which had rendered the 2017 Award.
Its submission of a “write-up” also expressly proceeded on this basis.
NHAI not only failed to object to this procedure, but expressly consented
to it. This is especially clear from paragraphs 2.8 and 2.9 of the minutes
(2020) 18 SCC 277 [hereinafter, “Quippo Construction”].
(2022) 3 SCC 783 [hereinafter, “K.P. Dwivedi”].
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
of the hearing dated 11.07.2020, as corrected on 22.07.2020, both of
which are extracted in paragraphs 6(n) and 6(o) hereinabove. It was also
clearly conscious of the course it was adopting. The very issue of the
Tribunal’s mandate had been raised by Arbitrator B, and recorded in the
Tribunal’s minutes dated 11.07.2020 and 22.07.2020. It was in response
to this, that both parties consented to the proceedings. In fact, the
question of objecting to the constitution of the Tribunal was considered
by NHAI, albeit in the context of the recusal of Arbitrator A, as reflected
in the letter of Arbitrator C dated 02.08.2020, and the minutes of the
meeting dated 05.08.2020. NHAI, however, decided not to pursue that
line of objection. It is difficult to believe that NHAI applied its mind to
the question of whether KNR’s nominee arbitrator should be permitted to
recuse himself for personal reasons, but did not apply its mind to the
much more obvious question which it now seeks to raise.
18.
In this context, the judgments cited by Ms. Suri preclude an
objection by NHAI at the Section 34 stage:
a. As far as the composition of the Tribunal is concerned, the
Supreme Court held, in Quippo Construction, that statutory
provisions relating to the composition of the arbitral tribunal are
derogable. It follows therefrom that such objections can be waived.
b. The question before the Court in L.G. Chaudhary, was with regard
to a special State Act of the State of Madhya Pradesh, namely,
Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983
[hereinafter, “M.P.MAA”]. The Court took the view that the State
Act would prevail over the Central Act – Arbitration and
(2024) 4 SCC 729 [hereinafter, “JMC Projects”].
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
Conciliation Act, 1996, in view of Section 2(4) of the Central Act.
It, therefore, held that pending proceedings before the arbitral
tribunal would be transferred to the tribunal constituted under the
M.P.MAA, but also observed as follows:
“17. We do not express any opinion on the applicability of the State
Act where award has already been made. In such cases if no
objection to the jurisdiction of the arbitration was taken at relevant
stage, the award may not be annulled only on that ground.
xxxx
xxxx
xxxx
CA No. 2616 arising out of SLP (C) No. 35641 of 2011
19. Leave granted. In view of the order [Set out in paras 15 to 18,
above.] passed in CA No. 2751 of 2018 arising out of SLP (C) No.
16615 of 2012, no objection having been raised by the respondents
in terms of Section 16(2) of the Arbitration and Conciliation Act,
1996 at appropriate stage within the time stipulated, the award
could not have been annulled.”
c. K.P. Dwivedi also considered the relationship between the Central
Act and the M.P.MAA. Relying upon L.G. Chaudhary, a
submission was raised that an award could not be annulled on the
ground of jurisdiction, if no objection had been raised before the
arbitrator. One of the parties sought to re-agitate the issue before
the State Tribunal after the arbitral award had been made. This
procedure was held to be impermissible, with the following
observations:
“33. Even otherwise it is required to be noted that no objection was
raised by the respondent contractor before the arbitrator —
Housing Commissioner on the jurisdiction of the Housing
Commissioner to act as an arbitrator. On the contrary as observed
hereinabove the order passed by the High Court referring the
dispute between the parties for adjudication to the arbitrator —
Housing Commissioner was a consent order and the respondent
contractor conceded to and accepted the said order and submitted
Emphasis supplied.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
his claim before the arbitrator — Housing Commissioner. The
arbitrator — Housing Commissioner also passed an award on the
said claim. Therefore, as no objections were raised by the
respondent contractor at the appropriate stage, the award cannot
be annulled subsequently. At the cost of repetition, it is observed
that at no point of time the respondent contractor had challenged
the award passed by the arbitrator — Housing Commissioner and
as observed and held hereinabove even no court has set aside the
award declared by the arbitrator — Housing Commissioner dated 711-2008 and the same has attained finality. Therefore, the same is
binding between the parties. Hence, the subsequent fresh reference
petition before the learned Arbitral Tribunal under the 1983 Act for
the very same claims which were raised before the arbitrator —
Housing Commissioner would not be maintainable at all. We agree
with the view taken by the Arbitral Tribunal.”
d. In Sweta Construction, the Court followed L.G. Chaudhary, and
further decided the case on its facts, as follows:
“18. We are also of the view that in particular facts of the present
case, the position is even more gross because when the appellant
claimed arbitration, the respondent accepted invocation of
arbitration, suggested a panel of arbitrators, the appellant chose
one of the arbitrators out of the two suggested and the arbitrator
was so appointed as the sole arbitrator. Thus, the arbitration
proceedings commenced in pursuance to the acts of the
respondent and it cannot be permitted to get away to say that the
whole process was gone through because of some misconception
or inappropriate legal advice. Arbitration by consent is always
possible. The mode and manner of conduct of arbitration is possible
and how those arbitration proceedings would be governed is also a
matter of consent. If at all there were any rights of the respondent to
have claimed arbitration under the 1983 Adhiniyam, that right was
never exercised or waived. The respondent cannot be permitted to
approbate and reprobate and that too in arbitration proceedings
and that too in dispute or resolution through the method of
arbitration defeating the very purpose of an alternative dispute
resolution to arbitration as an expeditious remedy.”
e. The aforesaid judgment in L.G. Chaudhary was also followed in
JMC Projects.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
19.
As against this line of judgments, Mr. Bishnoi relied upon Lion
Engineering, which also deals with the relationship between the
M.P.MAA and the 1996 Act. He submitted that the Court in Lion
Engineering, had specifically observed that a plea of jurisdiction could be
taken in Section 34 proceedings, even in the absence of an application
under Section 16 of the Act. It may be noted in this connection, that in
Sweta Construction, the Court considered the earlier authorities,
including L.G. Chaudhary and Lion Engineering, and observed as
follows:
“15. However, as pointed by the learned counsel for the respondent,
there appears to be some lack of clarity on the issue raised in the
present petition on account of the same three-Judge Bench having
opined in another order passed in Lion Engg. Consultants v. State of
M.P. [Lion Engg. Consultants v. State of M.P., (2018) 16 SCC 758 :
(2019) 1 SCC (Civ) 699] on 22-3-2018 i.e. about three weeks after
that. The issue however, raised was whether there was any bar to the
plea of jurisdiction being raised by way of an objection under
Section 34 of the 1996 Act even if no objection was raised under
Section 16 of that Act. It was opined that public policy of India
refers to law enforced in India i.e. both Central law as well as the
State law. The respondent State was given liberty to argue before the
trial court its objections that the 1996 Act stood excluded by the
State Adhiniyam even without formal pleadings being a pure legal
plea. This was in the context of an amendment sought being beyond
limitation. In that context there is an observation in one sentence,
“we do not see any bar to plea of jurisdiction being raised by way of
an objection under Section 34 of the Act even if no objection was
raised under Section 16 of that Act”.
16. If we appreciate the aforesaid observation in Lion Engg.
Consultants [Lion Engg. Consultants v. State of M.P., (2018) 16
SCC 758 : (2019) 1 SCC (Civ) 699] and that too emerging from
identical Bench in the two matters, we would have to construe as
what is meant by this sentence extracted aforesaid. We take note of
the fact that this is an order and not a judgment. The controversy
before the Court was something different as noticed by us aforesaid.
In that context, this sentence has been inserted, but that does not
Emphasis supplied.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
take away the law laid down in the substantive judgment (in M.P.
Rural Road Development Authority [M.P. Rural Road Development
Authority v. L.G. Chaudhary Engineers & Contractors, (2018) 10
SCC 826 : (2019) 1 SCC (Civ) 97]) dealing with the issue at hand in
respect of awards already made where petitions were pending before
the competent Court under Section 34 of the said Act.
17. This Court (in M.P. Rural Road Development Authority [M.P.
Rural Road Development Authority v. L.G. Chaudhary Engineers
& Contractors, (2018) 10 SCC 826 : (2019) 1 SCC (Civ) 97] ) in
the context of the 1996 Act and the 1983 Adhiniyam, keeping in
mind the cleavage of judicial view earlier and expounding on the
law in that judgment has in succinct terms set out that the
objections under Section 34 of the said Act, where no such plea of
jurisdiction was raised in proceedings before the arbitrator, should
not be dealt with “alone” on the plea of jurisdiction i.e. it should
be considered on merits. One can say that possibly this part of the
order can also be read as one made under Article 142 of the
Constitution of India to do substantive justice inter se the parties,
more so, when arbitration as an alternative dispute resolution
mechanism presupposes an expeditious disposal of commercial
disputes and that objective would stand nullified if a contrary view
was taken.”
20.
The matter has more recently been clarified, to an even greater
extent, in Gayatri Project Limited v. Madhya Pradesh Road Development
Corporation Limited22. The Court held therein, that L.G. Chaudhary and
Lion Engineering are not contradictory to each other. It was specifically
held that L.G. Chaudhary carves out an exception to the ratio of Lion
Engineering to the extent that, when a plea of lack of jurisdiction was not
taken before the arbitral tribunal, an award would not be annulled only on
that ground. It was further held that Lion Engineering was confined to the
question of whether an amendment of pleadings in a Section 34 petition
could be permitted, and not to the extent that an award may be annulled
solely on that ground. That issue has specifically been dealt with only in
Emphasis supplied.
2025 SCC OnLine SC 1136 [hereinafter, “Gayatri Project”].
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
L.G. Chaudhary. The Court clarified that a plea of jurisdiction raised at
the stage of Section 34 for the first time, cannot result in automatic
annulment of the award, even in terms of the ratio of Lion Engineering.
The Court in Gayatri Project, relied upon its earlier decisions in Union of
India v. Pam Development (P) Ltd.23, Gas Authority of India Ltd. v. Keti
Construction (I) Ltd.24, and AC Chokshi Share Broker (P) Ltd. v. Jatin
Pratap Desai25 to arrive at the following conclusion:
“35. Thus, what can be discerned from the aforesaid is that
although a plea of lack of jurisdiction, being a question of law,
can be raised even for the first time in the proceedings under
Section 34 as held in Lion Engineering (supra), yet such a plea
ought not to be allowed to be raised as it is deemed to have been
waived in view of Section 4 of the Act, 1996 as per Pam
Development (supra), unless the party makes out a strong and good
reason for its failure to take such a plea before the arbitral tribunal
as per Gas Authority of India (supra), and as per the dictum of L.G.
Chaudhary (II) (supra) any failure to raise the issue of applicability
of the MP Act, 1983 before the arbitral tribunal is not a strong and
good reason to permit raising such a plea in the proceedings under
Section 34 of the Act, 1996.
D. CONCLUSION
36. What emerges from the foregoing is that although Lion
Engineering (supra) affirms that a plea of lack of jurisdiction, being
a question of law, may be raised for the first time under Section 34
of the Act, 1996, yet such a plea is nevertheless subject to the waiver
as held in Pam Development (supra). Furthermore, as per Gas
Authority of India (supra), such a plea may only be entertained if
the party demonstrates a strong and sufficient reason for not
raising it before the arbitral tribunal. However, L.G. Chaudhary (II)
(supra) makes it clear that a failure to raise the issue of
applicability of the MP Act, 1983 at the appropriate stage cannot be
regarded as a sufficient reason, and therefore the plea cannot be
permitted at the stage of Section 34 proceedings.
(2014) 11 SCC 366.
(2007) 5 SCC 38.
2025 SCC OnLine SC 281.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
37. L.G. Chaudhary (II) (supra) carved out the aforesaid limited
exception to the general rule laid down in Lion Engineering (supra)
that a plea of lack of jurisdiction, being a pure question of law, may
be raised for the first time under Section 34 of the Act, 1996. The
failure of L.G. Chaudhary (II) (supra) to take into consideration the
decision of this Court in Lion Engineering (supra) does not render
the former per incuriam, as there exists no direct conflict between
the two. While Lion Engineering (supra) permits a jurisdictional
plea to be raised under Section 34 of the Act, 1996 even if not
urged under Section 16, L.G. Chaudhary (II) (supra) merely
clarifies that an arbitral award will not be annulled solely on that
ground, particularly where the issue was not raised before the
tribunal. On the contrary, the aforesaid observations of L.G.
Chaudhary (II) (supra) had been consciously made by this Court
keeping in mind the ratio of Lion Engineering (supra), even though
the latter was never explicitly referred to. L.G. Chaudhary (II)
(supra) cannot be termed to be per incuriam, as the very factum that
the aforesaid observations were made by L.G. Chaudhary (II)
(supra) in paras 16, 17 and 19 respectively shows that this Court
was well aware of the decision of this Court in Lion Engineering
(supra), and accordingly chose to carve out an exception to the ratio
of Lion Engineering (supra) keeping in mind the cleavage of judicial
view that was prevailing earlier.”
21.
On a consideration of the aforesaid authorities, in light of the facts
of this case and the conduct of NHAI in the subject arbitral proceedings, I
am of the view that its challenge to the jurisdiction of the Tribunal must
be rejected. Even if Lion Engineering permits such an objection at the
Section 34 stage, later judgments restrict its applicability to questions of
amendment of pleading, and require the Court to view the matter from the
perspective of Section 4 of the Act, which permits waiver of derogable
provisions. NHAI’s conduct in this case parallels the facts noticed by the
Supreme Court in Sweta Construction and Gayatri Project, where the
jurisdictional objections, raised for the first time, were considered and
Emphasis supplied.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
rejected. NHAI has also not sought to explain its failure to raise the
objection before the Tribunal.
22.
In the face of these direct authorities, I am unable to accept Mr.
Bishnoi’s submission relying upon Inder Sain Mittal, Srei Infrastructure,
and Hindustan Zinc, for the following reasons:
a. Inder Sain Mittal was a case under the Arbitration Act, 1940. Even
there, the Court upheld the principle of acquiescence by
participation in arbitral proceedings, but held that breach of a
mandatory provision of law could be raised even at the stage of
objections to an award. In the present case, however, no such
mandatory provisions of law have been cited, so as to permit such a
turnaround by NHAI.
b. In Hindustan Zinc, it was held that a question of inherent lack of
jurisdiction could be raised for the first time in proceedings under
Section 37 of the Act. The question arose in the context of Section
86(1)(f) of the Electricity Act, 2003, which provides for
adjudication by the State Electricity Regulatory Commission upon
disputes between licensees and generating companies, including
the power to refer any dispute for arbitration. The Court held that
the reference of a dispute between a licensee and a consumer did
not fall within the scope of Section 86(1)(f), and that such a plea
could have been raised in challenge proceedings. The question
remains as to whether this objection is one of “inherent lack of
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
jurisdiction”, as expressed in Hindustan Zinc27. On this point also,
I am of the view that NHAI’s contention cannot prevail.
c. Similarly, Srei Infrastructure did not concern this question of
jurisdictional objection at all, but rather the applicability of Section
32(2)(c). It is in this context that the Court observed that
termination of proceedings by making of an award under Section
33(1) contemplates termination of the mandate of the tribunal.
23.
Upon a holistic consideration of these authorities, I have come to
the conclusion that NHAI’s jurisdictional objection must fail for the
reasons outlined above. A question certainly arises as to the legal nature
of the proceedings taken before the Arbitral Tribunal, particularly in the
light of Section 33(1) of the Act, and the judgment in Srei Infrastructure.
The Tribunal was, in my view, quite wrong in arrogating to itself the
power to continue the earlier proceedings, which had already been
terminated by making of the 2017 Award. As a matter of law, Mr. Bishnoi
is right in saying that the proceedings had come to an end; neither Section
33 nor 34(4) had been invoked, and the matter could not have been
reopened as a continuation of the old proceedings. However,
notwithstanding the Tribunal’s own determination to the contrary, I am of
the view that the proceedings, as a matter of law, must be construed as a
fresh arbitration instituted with the consent of both parties, before a
tribunal also constituted by express consent. Such consent is manifest in
the orders of the Tribunal dated 10.07.2019, 11.07.2020, and 22.07.2020,
and the communications of NHAI recorded above.
Paragraph 17.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
24.
The alternative course, suggested by Mr. Bishnoi, would permit a
recalcitrant litigant to participate fully in an arbitration, express its
consent unequivocally, and then wriggle out of the consequences of an
award by raising jurisdictional objections belatedly. I hasten to add that,
in my view, the objections raised by NHAI, if raised at the appropriate
juncture and in the appropriate manner, may have been worthy of
acceptance, but its conduct estops it from raising this contention at this
stage.
25.
Mr. Bishnoi’s argument that the procedure of the fresh arbitration
had not been undertaken, inasmuch as no substantive pleadings were filed
and no evidence taken, is also unmerited. The pleadings and documents
filed before the erstwhile Arbitral Tribunal were available to the Tribunal
in the present case also, as evidenced by minutes dated 11.07.2020. The
particulars of the claim being adjudicated by the Tribunal, were clear
from the order of this Court dated 03.05.2019 and KNR’s submission
dated 24.07.2019. The proceedings concerned only a claim for interest,
which was to be decided in terms of contractual clauses and admitted
documents. NHAI’s “Statement of Defence” dated 11.02.2020 does not
indicate any confusion with regard to the scope of the proceedings. NHAI
could well have filed an objection raising these grounds or have filed
further documents and pleadings if it was so inclined, but it chose not to
do so.
26.
The Tribunal, as also the parties, would have done well to pay
greater attention to procedural provisions in the conduct of the
proceedings, but the present case does not reveal a fundamental
miscarriage, so as to vitiate the proceedings altogether. Reference, in this
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
connection, may be made to Sections 18 and 19 of the Act, which vest the
Tribunal with considerable latitude in procedural matters, subject to
adherence to the fundamental principles of equality and natural justice.
There is no suggestion that NHAI was subjected to any breach of such
principles, and, on balance, I am of the view that the Award is not
required to be set aside on this ground.
27.
Ancillary to the argument with regard to the Tribunal’s jurisdiction,
Mr. Bishnoi also submitted that, after the order of this Court dated
03.05.2019, no fresh declarations under Section 12 of the Act were given
by Arbitrators B and C. Arbitrator D, who was substituted for Arbitrator
A, did make a declaration, but Mr. Bishnoi submitted that, in order to
constitute a valid fresh arbitration, such declarations would also have
been required from Arbitrators B and C, particularly in view of the
amendment to the Act in 201528. In this connection, he relied upon a
judgment of the Division Bench in Ram Kumar and Another v. Shriram
Transport Finance Co. Limited29, to submit that the impugned Award is
required to be set aside, as a result of this lapse.
28.
I am not inclined to accept this submission, in the facts of the
present case. While the manner in which the Tribunal proceeded has
resulted in avoidable ambiguity as to the status of the proceedings, the
fact is that Arbitrators B and C had both given their declarations under
Section 12 of the Act in the first round of arbitral proceedings30.
Arbitrator D has admittedly made his disclosure, at the stage he entered
into the reference. NHAI participated in the entirety of the proceedings
Arbitration and Conciliation (Amendment) Act, 2015.
2022 SCC OnLine Del 4268.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
without demur. Whether non-disclosure may, in a given case, be fatal to
an award, is not relevant to the present proceedings, as the concerned
arbitrators had made declarations which were accepted by the parties,
without protest. The fact that Arbitrators B and C had made those
declarations in the earlier round of proceedings, and did not do so in the
present proceedings, is evidently due to their erroneous presumption that
the present proceedings were a continuation thereof. However, such a
lapse does not, in my view, vitiate the proceedings altogether. It may also
be noted that no such ground was raised by NHAI before the Tribunal,
giving rise to an argument of waiver under Section 4 of the Act31, and no
such ground has been taken even in the present petition.
29.
The jurisdictional objections to the impugned Award are, therefore,
rejected.
E. RE: MERITS OF THE IMPUGNED AWARD
30.
By the impugned majority Award, the Tribunal has held that KNR
was entitled to interest on the amounts awarded by the 2017 Award, at the
rate of 10% per annum compounded monthly, from the date when the
amount was payable until the date of actual payment. For this purpose, it
relied upon Sub-Clause 60.8 of COPA.
31.
Mr. Bishnoi’s first submission was that the award is vitiated by
lack of pleadings and documents, as no formal pleadings or documents
were invited, after the order of this Court dated 03.05.2019. I have dealt
with this aspect in Section D above.
Paragraph 1.05 of the 2017 Award.
Quippo Construction.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
32.
Mr. Bishnoi’s further submission was that NHAI had clearly argued
before the Tribunal that Clause 60.8 of COPA was inapplicable to the
claims agitated by KNR, as the price adjustments were not certified by
the independent engineer. Consequently, no rate of interest was
contractually provided, as far as these claims are concerned. According to
Mr. Bishnoi, by holding to the contrary, that Clause 60.8 is applicable to
all dues, the impugned Award is tantamount to rewriting of the contract.
He drew my attention to paragraph 10 of the “Statement of Defence”
dated 11.02.2020, filed by NHAI before the reconstituted Tribunal, which
according to him remained unaddressed in the impugned Award.
33.
Ms. Suri, in her response on this aspect, submitted that the Tribunal
has proceeded on the basis of a plausible interpretation of Clause 60.8,
with which the Court should decline interference under Section 34 of the
Act. Matters of contractual interpretation are within the domain of the
Arbitral Tribunal, and the Tribunal’s view cannot be substituted by the
Court’s interpretation, unless it is manifestly arbitrary or perverse. She
also relied upon the judgments of this Court in NHAI v. ITD Cementation
India Limited32 and NHAI v. ITD Cementation India Limited33 to submit
that the Tribunal’s interpretation in the present case, did not fall within
this narrow category. Ms. Suri further submitted that interest was, in any
event, payable under Section 31(7)(a) of the Act, as held by the Supreme
Court in Delhi Airport Metro Express Private Limited v. Delhi Metro Rail
Corporation34.
2009 SCC OnLine Del 2327 [hereinafter, “NHAI v. ITD – 2009”].
2012 SCC OnLine Del 6210.
2022 9 SCC 286.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
34.
The majority award deals with this aspect as follows:35
“5.14 Per Contra, the Claimant protested the isuse of certification by
the Engineer, and contended that, whether the Engineer certified the
payment or not, once the amount is held as payable pursuant to the
award passed by the AT and upheld by the Hon'ble Courts of the land,
the same would be construed as the amount which should have been
certified and paid at that material point of time. The same should have
been passed with interest upon determination by the agreed
mechanism as if the same is payable at the agreed rate i.e. from the
date when it should have been paid, had it been correctly certified /
determined as payable.
5.15 The amount of price adjustment as per clause 60.8 of COPA is
payable and as the award upheld to that by the Hon'ble Supreme
Court even in absence of certification, therefore, now, the issue of
certification by the Engineer has been settled and interest becomes
payable to the Claimant as per the mechanism provided is Clause
60.8 of COPA.
lt was also a submission of the Respondent that the Claimant did not
include the claim of interest in respective IPCs but such plea of interest
is being taken for the first time, which needs no consideration, as the
issue has already been adjudicated and awarded on it. ln this regard,
the Claimant made the argument that Respondent's contention is
incorrect for the reason that Clause 60.1 of COPA does not have any
such item/s to incorporate interest in IPCs. Rather it has one item for
price adjustment which the Claimant has fully complied with. At the
moment the Claimant incorporated the price adjustment in the
respective IPCs, it was the contractual obligation on the part of the
Engineer to certify the price adjustment for payment.
5.16 The AT perused the Clause 60.1. According to this clause, the
Contractor was required to submit a monthly statement to the Engineer
for certification for the work executed up to the end of previous month
in a tabulated form approved by the Engineer. According to Clause
60.8 the interest becomes payable on the amount certified by the
Engineer and if there is any delay beyond the period stipulated in
Clause 60.8. In this case the Contractor was continuing to include the
item of price adjustment in the monthly statements, however the
Engineer did not certify the amount of price adjustment in any of the
IPCs. Unless the amount of price adjustment was certified and the date
of payment was known, the amount of interest in the subsequent IPCs
could not be determined and claimed. Therefore the contention of the
Respondent that the interest should have been incorporated in the
monthly statements is not correct.
KNR is described as the “claimant”, and NHAI as the “respondent” in the below extract.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
5.17 The Respondent by referring Section 3 of Interest Act, stated that
the Court may, if it thinks fit, allow interest to the person entitled to the
debt or damages only after the same is adjudicated, in this case is
29.04.2017. Per contra, the Claimant argued that Section 3 of Interest
Act also provides that no restriction can be imposed if the interest is
payable as per conditions of the "Written Agreement".
5.18 There is 'written agreement' in terms of Clause 60.8 of COPA
for payment of interest, therefore, necessity of re-adjudication arose.
Thus, the interest is payable on the awarded sum of price adjustment
in all IPCs with effect from the date it became due till the date of
payment as per agreed terms of the Clause 60.8 of COPA.
5.19 The Claimant’s contentions are that from the plain reading of
Clause 60.8 of COPA,_it was agreed by the parties that, if the amount
due to the Claimant contractor is not paid within the time period
stipulated in the said clause, the interest @ 10% p.a. compounding
monthly as per the rate stipulated under the Appendix to Bid, would be
paid to the Claimant Contractor from the date the amount was payable
till the actual date of payment. Once it is agreed by the parties that
unpaid amount will attract the interest at stipulated rate, none of the
party can wriggle out from the agreed rate on any ground such as
being excessive or unreasonable, because following provisions of laws
does not support such wriggling out.
5.20 Section- 3 of the Interest Act provides that no such restriction can
be imposed if the interest is payable as per conditions of the " Written
agreement". As per Section 31 (7) of the Arbitration Act, the AT has
authority to have its discretion if and "unless otherwise agreed by the
parties Since the parties have "otherwise agreed" for payment of
interest under Clause 60.8 of COPA read with Appendix to Bid, the AT
cannot deviate from the conditions of the contract, for not allowing
lower percentage of interest rate than what has been agreed in the
Contract. As per Section 73 and 74 of Indian Contract Act, the
compensation or damages at a reasonable rate is permissible and both
the parties had agreed that the rate @ 10% p.a. compounding monthly
as reasonable rate on account of blocked up capital with other party.
The Clause 60.8 of COPA, never been supplemented by the parties for
reduction in the rate of interest. The Respondent argued that it too,
relying on Section 3 of the Interest Act which provides that, the Court
has power to allow interest in any proceeding for recovery of any debt
or damages, if it thinks fit, to the person entitled to the debt or
damages or to the person making such claim, as the case may be. As
per Section 3 of the Interest Act, the amount or debt becomes payable
only when it was adjudicated i.e. on 29.04.2017 and not before that.
5.21 The AT is bound by the following provisions of the Arbitration
Act. While deciding and making an award, the arbitral tribunal shall
in all cases, take into account the terms of the Cantract and Trade
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
usages applicable to the transaction., Section 31 (7/ (a) : "Unless
otherwise agreed by the parties ...... which award is made". Evidently,
AT is bound to take in the consideration the terms and conditions
prescribed in the Contract Agreement while passing the award. In the
present case the Clause 60.8 of COPA read with Appendix to Bid
provides the terms clearly.
5.22 The Contract is supreme and once both the parties agreed and
signed the Contract entered into, subsequently they cannot deviate
from their stand as such the agreed terms upon the parties. In the
present case, both the parties agreed that upon default of payment, the
interest @ 10% p.a. compounding monthly shall be payable by the
defaulting party.
5.23 The AT is of the considered view that the Tribunal is bound by the
provisions of Contract with respect to the rate of interest as agreed
upon the parties and specified in the Contract. Thus, the AT is of the
considered opinion that, the rate of interest can not be changed than
what has been specified in the Clause 60.8 of COPA read with
Appendix to Bid.
5.24 The AT has reached to the conclusion that it cannot travel beyond
the provisions under Section 28 (3) and 31 (7) (a) of the Arbitration
Act as well as the agreed terms provided under Clause 60.8 of COPA
read with Appendix to Bid and therefore is of the considered opinion
that the Claimant is entitled to receive the rate of interest @ 10% p.a.
compounding monthly from the date it became due till the date of
actual payment.”
35.
Having regard to the aforesaid observations in the impugned
Award, I am inclined to agree with Ms. Suri, that the view taken by the
Tribunal does not warrant judicial interference. The Tribunal has clearly
held that Clause 60.8 of COPA applies to awarded sums of price
adjustments in all IPCs37. The interpretation of contractual provisions is a
matter that falls within the province of the Arbitral Tribunal. The Courts,
exercising jurisdiction under Section 34 of the Act, are precluded from
interfering with the Tribunal’s interpretation or substituting their own
interpretation for that of the Tribunal, except in the very narrow class of
Emphasis supplied.
Impugned Award, paragraphs 5.15, 5.16 and 5.18.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
cases, in which they are compelled to return findings of perversity or
manifest arbitrariness. Reference in this connection may be made to the
recent judgment of the Supreme Court in Prakash Atlanta (JV) v.
National Highways Authority of India38, wherein the Court observed as
follows:
“27. As long back as in the year 2006, in McDermott International Inc. v.
Burn Standard Co. Ltd.39, this Court affirmed that construction of a
contract is within the jurisdiction of the arbitrator and interpretation
thereof is a matter for the arbitrator to determine, even if it gives rise to a
question of law. This was affirmed in National Highways Authority of
India v. ITD Cementation India Limited40, wherein this Court held that
construction of the terms of a contract is primarily for an arbitrator to
decide and he is entitled to take the view that he holds to be the correct
one, after considering the material and after interpreting the terms of the
contract. It was observed that the Court, while considering a challenge to
an arbitral award, does not sit in appeal over the findings and decision
therein, unless the arbitrator construed the contract in such a way that no
fair-minded or reasonable person would do. We may note that, in this
case, the issue was whether additional costs owing to a change in the
seigniorage fee had been taken into account in the indexing of inputs,
while providing for price adjustment in the contract. NHAI had contended
that the said levy was already factored into the indexing price formula
and, therefore, no further payments were to be made to the contractor.
xxx
xxx
xxx
29. In UHL Power Company Limited v. State of Himachal Pradesh41, a 3Judge Bench of this Court reiterated that if there are two plausible
interpretations of the terms and conditions of the contract, then no fault
can be found if the arbitrator proceeds to accept one interpretation as
against the other. Again, in Ssangyong Engineering and Construction
Company Limited v. National Highways Authority of India42, this Court
held that construction of the terms of a contract is primarily for an
arbitrator to decide unless the arbitrator construes the contract in a
manner that no fair-minded or reasonable person would; in short, that the
arbitrator’s view is not a plausible view to take.
2026 SCC OnLine SC 98.
(2006) 11 SCC 181.
(2015) 14 SCC 21.
(2022) 4 SCC 116.
(2019) 15 SCC 131.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
30. In Dyna Technologies Private Limited v. Crompton Greaves Limited43,
a 3-Judge Bench of this Court held that an arbitral award should not be
interfered with in a casual and cavalier manner, unless the perversity of
the award goes to the root of the matter, without there being a possibility
of an alternative interpretation that may sustain it. It was held that Section
34 is different in its approach and cannot be equated with normal
appellate jurisdiction and that its mandate is to respect the finality of the
award and the parties’ autonomy to get the dispute adjudicated by an
alternative forum as provided by law. This Court cautioned that if Courts
were to interfere with awards in the usual course on factual aspects, then
the commercial wisdom behind opting for alternative dispute resolution
would stand frustrated.
xxx
xxx
xxx
52. The issue, in effect, boils down to whether the failure of the
respondents to factor in their bid prices the cess payable under the BOCW
Act and the Cess Act can be said to be in keeping with Clause 14.3,
thereby attracting the ‘subsequent legislation’ procedure in Clause 70.8.
In essence, it would come down to interpretation of these terms of the
contract. The argument of NHAI that the ‘subsequent legislation’ clause
only pertains to changes in existing laws or introduction of new laws
overlooks the fact that there was a specific timeframe of twenty-eight days
mentioned therein which was linked to the last date for submission of the
bids and that is the basis on which the arbitral tribunals construed and
interpreted that provision. Having considered the arbitral awards passed
by the arbitral tribunals in the five appeals filed by NHAI, we find that the
interpretation and construction of those terms and clauses by the arbitral
tribunals cannot be said to be arbitrary, perverse or patently illegal.
Given the situation obtaining in relation to the two Acts at the relevant
time, the arbitral awards cannot be said to have violated the public policy
of India or be in breach of Section 28(1)(a) of the Arbitration Act. Once
the view taken by the arbitral tribunal is found to be a plausible and
possible one on facts and not an unreasonable one, it is not for the Courts,
under Sections 34 or 37 of the Arbitration Act, or for this Court to sit in
appeal or substitute its view for that of the arbitral tribunal.
xxx
xxx
xxx
59. We may now sum up our conclusions as under:
xxx
xxx
xxx
(vi) If an arbitral tribunal's view is found to be a possible and plausible
one, it cannot be substituted merely because an alternate view is possible.
Construction and interpretation of a contract and its terms is a matter for
the arbitral tribunal to determine. Unless the same is found to be one that
no fair-minded or reasonable person would arrive at, it cannot be
interfered with. If there are two plausible interpretations of the terms of a
(2019) 20 SCC 1.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
contract, then no fault can be found if the arbitrator accepts one such
interpretation as against the other. To be in conflict with the public policy
of India, the award must contravene the fundamental policy of Indian law,
which makes it narrower in its application.
(vii) We find that the arbitral awards in NHAI's five appeals turned upon
interpretation and construction of identical terms in the contract and as
the view taken by the arbitral tribunals was not only a plausible and
possible one but also a justified one, on facts, we find no reason to
interfere therewith. The awards are not perverse, patently illegal or
opposed to the public policy of India. Further, we do not find the awards
to be in breach of Section 28(1)(a) of the Arbitration Act.”
A similar view has also recently been expressed by a Division Bench of
this Court in JSW Ispat Steel Limited v. Gas Authority of India Limited44.
36.
I do not find the Tribunal’s interpretation in the present case to fall
within the narrow exception outlined in these judgments. The view taken
by the Tribunal is also consistent with the judgment of this Court in NHAI
v. ITD – 2009, cited by Ms. Suri, which concerns the very same clause.
37.
Mr. Bishnoi’s final argument, on merits, was that the award is
vague and uncertain, as it has failed to quantify the amount or to ascertain
the period for which the interest claim was being awarded. For this
purpose, he relied upon the operative portion of the majority award,
which reads as follows:
“The Claimant/ Contractor is entitled for getting interest @10% (Ten)
per annum compounding monthly on the amount of price adjustment
awarded, including IPC 35, 36 & 37 for the pre-reference period i.e.
from date upon which the same should have been paid till the date of
actual payment, as per Clause 60.8 of COPA, read with Appendix to
Bid.”
Learned counsel submitted that such a vague quantification was contrary
to the judgment of the Division Bench in NHAI v. ITD Cementation India
Limited45.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
38.
On this aspect, Ms. Suri submitted that the aforesaid finding of the
Tribunal was capable of quantification without any difficulty, as the
amounts of price adjustment, and dates upon which the payment was to
be made, had been clearly quantified in the 2017 Award. She also
submitted that in paragraphs 4.49, 4.50, 5.1, and 5.2 of the 2017 Award,
the Tribunal had already awarded interest on price adjustments upto the
34th running bill of March 2013, as well as other interim payments
pending to be released. This, thus, covers all interim payments including
IPCs No. 35, 36, and 37, which form part of the impugned Award. This
was specifically reiterated in the document dated 24.07.2019 filed by
KNR, after the order of this Court dated 03.05.2019, and was not disputed
in NHAI’s reply dated 11.02.2020. The claim was again included with
proper quantification in an application under Section 23 of the Act, filed
by KNR before the reconstituted Tribunal on 13.02.2020.
39.
While I am of the view that the Tribunal ought to have undertaken
the exercise of quantification, or atleast referenced the necessary
documents from which the quantification could be ascertained, I do not
consider it necessary to set aside the impugned award on this ground. The
material cited by Ms. Suri, including the 2017 Award, and the documents
and charts placed before the reconstituted tribunal, quantify the amounts
with sufficient certainty for the computation to take place, consequent to
the award. It may be noted that, pursuant to an order dated 18.07.2022 in
these proceedings, NHAI itself has filed an affidavit dated 07.09.2022,
computing the amounts payable under the Award. This suggests that, even
2026 SCC OnLine 3924, paragraph 21.
2007 SCC OnLine Del 1590.
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
according to NHAI, the amount was capable of computation on the basis
of the impugned Award.
40.
In view of the above, NHAI’s challenge to the impugned Award, on
merits, is also rejected.
F. CONCLUSION
41.
For the reasons aforesaid, I do not find any reason to interfere with
the impugned majority Award dated 08.12.2021, in exercise of the
jurisdiction under Section 34 of the Act.
42.
The petition is, therefore, dismissed, but with no orders as to costs.
43.
Pending application also stands disposed of.
PRATEEK JALAN, J
AUGUST 11, 2026
PV/tg/KA/
Signed By:PARUL
VASHIST
20:15
O.M.P. (COMM) 293/2022
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review