APHC010417762026
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3458]
THURSDAY, THE 17th DAY OF SEPTEMBER 2026
PRESENT
THE HONOURABLE SMT JUSTICE KIRANMAYEE MANDAVA
WRIT PETITION NO: 22550 OF 2026
Between:
1. N.V. GANESH KUMAR, S/O N.S.R. PANTHULU, AGED 66 YEARS,
R/O 12-25-46, SRI SADHAN, KOTHAPET MAIN ROAD, GUNTUR 522001
2. N.V. GURU DATH, S/O N.S.R. PANTHULU, AGED 64 YEARS, R/O
12-25-46, SRI SADHAN, KOTHAPET MAIN ROAD, GUNTUR - 522001
3. N. SATYA SAI, S/O N.S.R. PANTHULU, AGED 56 YEARS, R/O 12-2546, SRI SADHAN, KOTHAPET MAIN ROAD, GUNTUR - 522001
...PETITIONER(S)
AND
1. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL
SECRETARY
MUNICIPAL ADMINISTRATION AND URBAN
DEVELOPMENT
SECRETARIAT BUILDINGS, VELGAPUDI,
GUNTUR - 522238
2. THE GUNTUR MUNICIPAL CORPORATION,
COMMISSIONER, GUNTUR - 522003
REP.
BY
ITS
3. THE DISTRICT COLLECTOR, GUNTUR DISTRICT, GUNTUR 522004
4. THE REVENUE DIVISIONAL
GUNTUR - 522004
OFFICER,
GUNTUR
DIVISION,
5. THE TOWN SURVEYOR, GUNTUR MUNICIPAL CORPORATION
GUNTUR - 522004
6. THE CITY PLANNER,
GUNTUR - 522004.
GUNTUR
MUNICIPAL
CORPORATION
...RESPONDENT(S):
Counsel for the Petitioner(S):
1. K S MURTHY ASSOCIATES
Counsel for the Respondent(S):
1. VANKAYALAPATI N PRAVEEN SC For GNT,ONG,NLR Municipal
Corporations
2. GP FOR REVENUE
3. GP MUNCIPAL ADMN AND URBAN DEV AP
The Court made the following order:
Heard Sri K.S.Murthy, learned Senior Counsel appearing for the
petitioners,
learned
Assistant
Government
Pleader
for
Municipal
Administration and Urban Development appearing for respondent No.1 and
Sri V.Naga Praveen, learned Standing Counsel for Municipal Corporation
appearing for respondent No.2, 5 & 6.
2.
The instant writ petition is filed seeking for the following relief:
“……to issue Writ direction order or orders WRIT OF MANDAMUS
declaring the action of respondent corporation in not sending the correct
report regarding lands in T.S.No.481 Guntur Municipal Corporation Guntur
West Mandal Guntur District especially the land of petitioners to the extent
170 sq yards 142 Sq.Mts taking into consideration the memorandum of
compromise filed in W.P.No.15552 of 1998 to facilitate the R3 and R4 to
take corrective action regarding the lands notified for road widening as
illegal
arbitrary
and
unconstitutional
and
consequently
direct
the
respondents particularly respondent No 2 to address a reply to letter
addressed by the R3 by making it clear that the petitioners are owners of
the land of extent 170 Sq yards 142 Sq.Mts in part of T.S.No.481 Guntur
West Mandal, Guntur District consequentially direct R3 and R4 to act upon
such clarification…”
3.
The case of the petitioners, in brief, is that they are the absolute owners
and possessors of an extent of 1,361 square yards in T.S. No. 451 and 200
square yards in T.S. No. 481, situated at Guntur West Mandal, Guntur District.
In the said property, the petitioners’ grandfather, after obtaining the requisite
permission for construction, constructed a shopping complex. The petitioners
contend that, out of the aforesaid extent, an area admeasuring 200 square
yards in T.S. No. 481 was assigned in favour of their grandfather. In the year
1997, the petitioners’ grandfather passed away and, subsequently, their father
also passed away. After his demise, the petitioners, who are four brothers,
partitioned the property amongst themselves.
4.
Thereafter, Respondent No.2 allegedly attempted to encroach upon the
subject property. Aggrieved by the said action, the petitioners approached the
erstwhile High Court of Andhra Pradesh at Hyderabad, by filing a writ petition
in the year 1998. During the pendency of the said writ petition, the petitioner
and the respondent-Corporation entered into a compromise. Pursuant to the
said compromise, Petitioner No.1 agreed to forego a portion of the assigned
land in T.S.No.481, admeasuring 30 square yards, for the purpose of
providing a free left, subject to the condition that the remaining portion of the
open space would continue to remain in the possession of the petitioner and
his family and would be utilized for parking purposes.
5.
The petitioners contend that, on the basis of the said memorandum of
compromise, the writ petition was disposed of by the erstwhile High Court of
A.P., at Hyderabad, by recording the terms of the compromise. Thereafter,
Respondent No. 2 did not disturb the possession of the petitioners over the
remaining portion of the property. According to the petitioners, after
relinquishing/donating 30 square yards out of the total extent of 200 square
yards in T.S. No. 481 for the purpose of providing a free left, the remaining
extent of 170 square yards continues to remain in their possession and is
being utilized for parking purposes.
6.
In the year 2024, a proposal was made for an ROB at the existing ROB
in the locality. Subsequently, a preliminary notification dated 27.04.2026 was
issued under the provisions of the RFCTLARR Act, 2013. In the said
notification, the names of the petitioners’ grandfather and the petitioners were
notified in respect of an extent of 4.98 square yards and 18.78 square yards in
Survey Nos. 451-B1 and 451-B2, respectively, proposed to be acquired.
However, T.S.No.481 was not included in the said preliminary notification,
notwithstanding the petitioners’ claim over and possession of the remaining
extent of 170 square yards therein.
7.
Thereafter, a notice dated 18.05.2026 was issued to the petitioners in
connection with the proposed acquisition. The petitioners appeared before the
concerned authorities and requested that a survey be conducted in respect of
the subject property. They specifically contended that, without acquiring the
land comprised in T.S. No. 481, the lands in T.S.No.451 proposed to be
acquired could not be effectively utilized for the proposed project.
8.
Pursuant to the said request, the authorities issued a notice for
conducting the survey. During the course of the survey, the petitioners brought
to the notice of the respondents the compromise entered into between the
parties in the earlier round of litigation. The petitioners specifically requested
the authorities to conduct the survey in accordance with and keeping in view
the terms and conditions of the said compromise, which was entered into on
14-09-1998 and was duly recorded by this Court in the earlier writ
proceedings.
9.
However, the said request of the petitioners was not considered by the
respondents. Without taking into consideration the petitioners’ claim in respect
of T.S. No. 481, and without including the said survey number in the
acquisition proceedings, the respondents proceeded further with the
acquisition proceedings in respect of T.S. No. 451 under Section 11(1) of the
Act.
10.
The petitioners contend that the action of the respondents in proceeding
with the acquisition of the land in T.S.No.451 while excluding T.S. No. 481,
and in disregarding the terms of the compromise recorded in the earlier round
of litigation, is contrary to law. According to the petitioners, the respondents
ought to have considered the effect of the earlier compromise and conducted
the survey in accordance therewith before proceeding with the acquisition
proceedings. The petitioners therefore challenge the action of the respondents
in proceeding with the acquisition without considering their claim in respect of
T.S.No.481 and without taking into account the rights and possession claimed
by them pursuant to the earlier compromise.
11.
The respondents filed a counter-affidavit disputing the claim of the
petitioners. It is contended that, for the purpose of establishing the precise
boundaries and extent of the subject property, surveys of the structures
bearing Nos. 56 and 57 were conducted on two different occasions. The first
survey was conducted in the year 2024, prior to the initiation of the alignment
evaluation process. A subsequent survey was conducted in the year 2026 by
the specialized Survey Department attached to the Land Acquisition Officer.
According to the respondents, both structural surveys were technically
conducted with strict reference to the baseline Town Survey records. The
verification carried out on both occasions confirmed that the physical
boundaries and extent of the private property belonging to the petitioners
correspond with their registered title documents. However, it is specifically
contended that the title documents relied upon by the petitioners do not
include or confer any proprietary rights over the disputed extent of 170 Sq.yds
in T.S.No.481.
12.
The respondents further contended that, under the terms of the
compromise entered into in the earlier round of litigation, the petitioners had
accepted and conceded that the open site situated between the existing
permanent building line and the municipal masonry drain constituted
Government land/public road margin. According to the respondents, in
consideration of the petitioners acknowledging the State’s paramount title over
the said land, the Guntur Municipal Corporation agreed not to initiate penal
proceedings or issue demolition notices in respect of the violations relating to
the setbacks in the petitioners’ building complex.
13.
It is further contended that the Corporation has duly honoured and
complied with the terms of the said compromise from the year 1998 till date.
Having availed themselves of the legal protection and benefit of preservation
of their building pursuant to the compromise for nearly three decades, the
petitioners, according to the respondents, cannot now claim ownership over
the said land or seek compensation under the provisions of the Land
Acquisition Act.
14.
The
respondents
further
contend
that
the
State
Government
subsequently revised the Master Plan road width from 100 feet to 120 feet,
vide G.O.Ms.No.688 dated 30.12.2006, to facilitate the proposed alignment of
the four-lane Shankar Vilas Railway Over bridge (ROB) and its service road. It
is therefore contended that the disputed extent continues to form part of the
public road land/road margin, over which the petitioners have no proprietary
rights or locus to claim compensation.
15.
It is further stated that, pursuant to the preliminary notification issued in
Form 6-A dated 25.04.2026, the Government proposed to acquire the lands
belonging to the petitioners in T.S.Nos.451-B1 and 451-B2, admeasuring 4.98
square yards and 18.76 square yards, respectively. The respondents concede
that, insofar as the said notified extents are concerned, the petitioners would
be entitled to receive compensation in accordance with law.
16.
However, in so far as the 170 square yards in T.S.No.481 is concerned,
the respondents categorically contend that the petitioners are not entitled to
any compensation, as the said extent is situated between the existing building
line and the municipal masonry drain and forms part of the Government/public
road margin. According to the respondents, the petitioners’ claim of ownership
over the said 170 square yards is therefore untenable.
17.
The respondents accordingly contend that the petitioners have no
enforceable claim in respect of the disputed 170 square yards in T.S. No. 481
and accordingly pray that the writ petition be dismissed.
18.
Considered the submissions. In the earlier round of litigation, the
petitioners have challenged the action of the respondents in encroaching into
open space upto Masonary Municipal Drain (claimed to be) belonging to the
petitioners in the premises bearing D.No.6-4-68 to 6-5-50 in T.S.No.481. In
the said regard, the petitioners and respondent-Corporation have entered into
compromise. The said Writ Petition was disposed of in terms of the
memorandum of compromise. The relevant portion of the compromise clauses
for better appreciation are reproduced here under:
“1.
The petitioner claims the open space was to have been assigned by
the Government long back duly following the procedure:
In fact, the Petitioner’s family was in possession of the same and have
been paying the Municipal taxes since then as assessed. As the Respondent
Corporation explained the plans for development of the city and the need for
free left, the Petitioner is satisfied with the good intention of the Corporation
and agrees to forego h is claim on the part of the open space as shown in
the plan, for the purpose of free left on the condition that the remaining part
of the open space shall continue in the possession of the petitioner’s family
for parking purpose only as shown in the plan, without any let or hindrance.
2.
The respondent corporation will not insist on set-back violations if any,
in the building and willing to regularize the deviations as per the rules in
force.
3.
The Respondent Corporation also agrees not to take any further action
on the building belonging to the Petitioner in the overall interest of the City.
4.
A sketch plan signed by the both parties relating to the compromise is
filled herewith.
5.
Both parties agree for disposal of W.P.15532/98, before this Hon’ble
Court in terms of the above compromise.
6.
19.
Both parties agree to bear their own costs.”
In the light of the above, this Court is of the view that as the
respondents have not denied the claim of the petitioners’ possession for a
long time and in the light of the compromise memo, while conducting the
survey for the purpose of determining the rights of the parties for
compensation, the respondents shall take the same into consideration.
20.
Accordingly, this Court deems it appropriate to dispose of the writ
petition with a direction to the respondent-Corporation to conduct a survey in
respect of the land to an extent of 170 Sq. Yards (142.142 Sq.mts) belonging
to the petitioners in terms of the memorandum of compromise dated 14-091998 and the order passed in W.P.No.15552 of 1998 dated 21.04.1999. The
respondent-Corporation shall after conducting the survey send the survey
report to the 3rd respondent to enable him to conduct Award enquiry under
Section 19(1) of the Act, within a period of four (04) weeks from the date of
receipt of a copy of this order, after issuing notice and affording an opportunity
of hearing to the petitioners.
21.
With the above observation, the Writ Petition is disposed of. There shall
be no order as to costs.
As a sequel, miscellaneous petitions pending, if any, shall stand closed.
______________________________
JUSTICE KIRANMAYEE MANDAVA
Dated: 17.09.2026
BSK
THE HONOURABLE SMT JUSTICE KIRANMAYEE MANDAVA
WRIT PETITION NO: 22550 OF 2026
Dated: 17.09.2026
BSK
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review