Ms K Pro Infra Works Pvt Ltd vs Lda and 3 Ors

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Manipur High Court
Date
16 October 2019
Case No.
Arb.P.(J2) 2/2014
Result
Allowed
Bench
Mv Muralidaran
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

18. The Arbitrator is requested to complete the proceeding within 6 (six) months from the date of entering upon the reference. Arbitration Petn. (J2) No. 2 of 2014 is accordingly disposed of. FR/NFR Sushil WAIKH Digitally TONEN Date: 2019.11.07 MEITEI -08'00' Arbitration Petn. (J2) No. 2 of 2014

Filed under

Arbitration and Conciliation Act, 1996 Section 11, Arbitration and Conciliation Act, 1996 Arbitration and Conciliation Act

Guides on this topic, in plain language:

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

Page |1 IN THE HIGH COURT OF MANIPUR AT IMPHAL Arbitration Petn.(J2) No. 2 of 2014 M/s K. Pro Infra Works Pvt. Ltd. registered under the Companies Act, 1956 having its registered office at 704 Nilgiri Apartments, 9, Barakhamba Road New Delhi-110001 through its authorized signatory at Babupara, Imphal-795001, Manipur. ……. Petitioner -Versus1. The Loktak Development Authority represented by Member Secretary/Project Director, Loktak Development Authority, Second Floor, Susu Home, Opposite to First Manipur Rifles, Babupara, Imphal-795001, Manipur. 2. The Surveyor of works, Loktak Development Authority, 2nd Floor, Susu Home, Opp. 1st Manipur Rifles Babupara, Imphal-795001, Manipur. 3. Superintending Engineer, Loktak Development Authority, Second Floor, Susu Home, Opposite to First Manipur Rifles, Babupara, Imphal795001, Manipur. 4. Executive Engineers, Loktak Development Authority, Second Floor, Susu Home, Opposite to First Manipur Rifles, Babupara, Imphal795001, Manipur. … Respondents BEFORE HON’BLE MR. JUSTICE M.V. MURALIDARAN For the Petitioner :: Arbitration Petn. (J2) No. 2 of 2014 Mr. H.S. Paonam, Sr. Advocate, Mr. S. Dijeshwor, Advocate, Page |2 Mr. L. Ashinikumar, Advocate, Mr. N. Bipin, Advocate, Ms. Ksh. Harichhaya, Advocate, Mr. S. Gunabanta, Advocate, Mr. A. Arunkumar, Advocate, For the Respondents :: Mr. A. Bimol, Sr. Advocate, Mr. N. Ibotombi, Sr. Advocate, Mr. A. Rommel, Advocate. Date Hearing & Judgment & Order :: 16.10.2019 JUDGMENT AND ORDER (ORAL) This petition has been filed by the petitioner under Section 11 of the Arbitration and Conciliation Act, 1996 (in short “the said Act”), with the following prayers: “(i)AII disputes as raised by the petitioner be referred to arbitration. (ii) Confirm the appointment of one eligible/qualified personality including consideration of the personality suggested by the petitioner at Para 10 as independent arbitrator to adjudicate on the dispute that has arisen between the parties. (iii) Costs incidental to this application be included as costs to the arbitration proceedings.” 2. The petitioner M/s.Pro Infra Works Private Limited is engaged in the business of civil construction and execution of the Arbitration Petn. (J2) No. 2 of 2014 Page |3 contract work of National/State importance. On 02.11.2009, the petitioner Company and the first respondent herein had entered into an agreement for execution of Phumdi Management Work. However, the first respondent terminated the agreement on 31.3.2013 and had issued notice on 03.5.2013 under Clause 3 of the agreement for taking up final action for forfeiture of security deposit of the petitioner Company. According to the petitioner, the final biII/payment under the contract has not been paid or settled by the first respondent in terms of the work agreement. 3. Earlier the petitioner has filed a writ petition in W.P.(C) No.364 of 2013 before this Court seeking to set aside the notice dated 3.5.2013. The said writ petition came to be dismissed by this Court on 7.3.2014 holding that the disputed question of facts could be adjudicated upon by the Arbitrator as provided by the work agreement. Aggrieved by the same, the petitioner has preferred S.L.P.(C) No.10793 of 2014 before the Hon'ble Supreme Court and by an order dated 28.4.2014, the said S.L.P. came to be dismissed. Thereafter, the petitioner Company sent a demand notice/application on 12.5.2014 setting out 14 claims and notified that in case the dues are not settled within fifteen days from the receipt of the notice, the matter may be treated as a dispute and will be referred to arbitration in terms of Clause 22 of the agreement. Arbitration Petn. (J2) No. 2 of 2014 Page |4 4. According to the petitioner, the said notice dated 12.5.2014 is in addition to the application and notices sent earlier for invoking arbitration proceedings dated 9.5.2013 for resolving the issues and disputes which was further reminded and responded by several correspondences between the petitioner and the First respondent. However, the appointment of Arbitrator by mutual agreement could not be materialized for want of satisfaction from both ends. Thereafter, the petitioner addressed letters dated 24.5.2014 and 26.5.2014 to the Competent Authority of Loktak Development (First respondent herein). By a letter dated 7.6.2014, the Loktak Development admitted that the dispute has to be settled by arbitration, however, has not accepted the claim of the petitioner. 5. Again on 27.6.2014, the petitioner submitted another letter requesting for appointment of Sole Arbitrator in accordance with the Contract Agreement dated 2.11.2009 for settlement of disputes as per the provision of Clause 22 of the Agreement by mentioning two names of experts. By a letter dated 31.07.2014, the First respondent has not agreed to the proposed name for appointment of the SoIe Arbitrator for resolving the dispute. Hence, the petitioner is left with no other alternative, but to approach this Court for appointment of Sole Arbitrator. On 18.8.2014, the petitioner sent letter to the first respondent for appointment of Sole Arbitration Petn. (J2) No. 2 of 2014 Page |5 Arbitrator by mutual consent and since the respondents have failed to appoint an Arbitrator in terms of the arbitration clause, the petitioner has filed the present petition. 6. Resisting the petition, the Project Director of Loktak Development Authority has filed affidavit-in-opposition stating that when they proposed three named Arbitrators for resolving the disputes, the petitioner has not agreed. It is stated that since the main issue involved in the present case is interpretation of the agreement dated 2.11.2009, an Arbitrator who is well acquainted in the field of law is required to be appointed and as such they approached Hon’ble Justice Asok Potsangbam and the Hon'ble Justice B.D. Agarwal, retired Judges of Gauhati High Court for their consent for appointment as an Arbitrator. It is stated that both the Hon'ble Judges have agreed to spare their valuable time in case one of them is appointed as an Arbitrator by this Court. 7. The learned Senior Counsel for the petitioner argued that there exists arbitration clause and also disputes arose between the parties. He would submit that despite efforts made by the petitioner to resolve the disputes through arbitration, the respondents are in the habit of evading appointment of an Arbitrator to settle the disputes between the parties, which necessitated the petitioner in approaching this Court by fling the present petition. Arbitration Petn. (J2) No. 2 of 2014 Page |6 8. Per contra, the learned counsel for the respondents submitted that when the respondents agreed for arbitration and nominated Arbitrators, the petitioner has not given consent and, therefore, the petitioner cannot blame the respondents. 9. Heard the learned counsel appearing on either side and also perused the materials available on record. 10. There is beyond any dispute that dispute arose between the petitioner and the respondents and before filing the present petition, there were exchange of notices between the parties. There is also no dispute qua existence of arbitration Clause in the agreement. Clause 22 of the agreement provides for arbitration, which reads thus: “CLAUSE 22. Except where otherwise provided in the contract all questions and disputes relating to the meaning of the specifications, design, drawings and instructions hereinbefore mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or to the contract, designs, drawings, orders or relating specifications, estimates, instructions, these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the Arbitration Petn. (J2) No. 2 of 2014 Page |7 cancellation, termination, abandonment thereof completion shall be or dealt with as mentioned hereinafter: (i) If the Contractor considers any work demanded of him to be outside the requirements of the contract, or disputes any drawings, record or decision given in writing by the Engineer-incharge on any matter in connection with or arising out of the contract or carrying out of the work, to be unacceptable, he shall promptly within 15 days request the Superintending Engineer in writing for written instruction or decision. Thereupon, the Superintending Engineer shall give his written instructions or decision within a period of one month from the receipt of the Contractor’s letter. If the Superintending Engineer fails to give his instructions or decision in writing within the aforesaid period or if the Contractor is dissatisfied with the instructions or decision of the Superintending Engineer, the Contractor may, within 15 days of the receipt of Superintending Engineer's decision, appeal to the Project Director, LDA who shall afford an opportunity to the Contractor to be heard, if the latter so desires, and to offer evidence in support of his appeal. The Project Director, LDA shall give his decision within 30 days of receipt of Contractor’s appeal. If the Contractor is dissatisfied with this decision the Contractor shall within a period of 30 days from Arbitration Petn. (J2) No. 2 of 2014 Page |8 receipt of the decision, give notice to the Project Director, LDA for appointment of arbitrator failing which the said decision shall be final binding and conclusive and not referable to adjudication by the arbitrator. (ii) Except where the decision has become final, binding and conclusive in terms of sub-para (i) above disputes or difference shall be referred for adjudication through arbitration by a sole arbitrator mutually agreed upon by both parties and duly appointed by the Project Director, LDA. If the arbitrator so appointed is unable or unwilling to act or resigns his appointment or vacates his office due to any reason whatsoever another sole arbitrator shall be appointed in, the manner aforesaid. Such person shall be entitled to proceed with the reference from the stage at which it was left by his predecessor. It is a term of this contract that the party invoking arbitration shall give a list of disputes with amounts claimed in respect of each such dispute along with the notice for appointment of arbitrator and giving reference to the rejection by the Project Director, LDA of the appeal. It is also a term of this contract that no person other than a person appointed by such Project Director, LDA as aforesaid should at as arbitrator and if for any reason that is not possible, the matter shall not be referred to arbitration at all. Arbitration Petn. (J2) No. 2 of 2014 Page |9 It is also a term of this contract that if the Contractor does not make any demand for appointment of arbitrator in respect of any claims in writing as aforesaid within 120 days of receiving the intimation from the Engineer-in-charge that the final bill is ready for payment, the claim of the Contractor shall be deemed to have been waived and absolutely barred and the Government shall be discharged and released of all liabilities under the contract in respect of these claims. The arbitration shall be conducted in accordance with the provisions of the Arbitration and Conciliation Act, 1996 (6 of 1996) or any statutory modifications or re-enactment thereof and the rules made thereunder and for the time being in force shall apply to the arbitration proceeding under this clause. It is also a term of this contract that the arbitrator shall adjudicate on only such disputes as are referred to him by the appointing authority and give separate award against each dispute and claims referred to him and in all cases where the total amount of the claims by any party exceeds Rs.1,00,000/- the arbitrator shall give reasons for the award. It is also a term of this contract that if any fees are payable to the arbitrator these shall be paid equally by both the parties. Arbitration Petn. (J2) No. 2 of 2014 P a g e | 10 It is also a term of this contract that the arbitrator shall be deemed to have entered on the reference on the date he issues notice to both the parties calling them to submit their statement of claims and counter-statement of claims. The venue of arbitration shall be such place as may be fixed by the arbitrator in his sole discretion. The fees, if any, of the arbitrator, shall, if required to be paid before the award is made and published, be paid half and half by each of the parties. The cost of the reference and cost of the award (including the fees, if any, of the arbitrator) shall be in the discretion of the arbitrator who may direct to any by whom and in what manner, such costs or any part thereof shall be paid and fix or settle the amount of cost to be so paid. The place of arbitration and legal jurisdiction for any dispute arisen from this Agreement shall be at Imphal.” 11. From the pleadings, it appears that both the parties are agreeable for arbitration. Though the respondents contended that main issue to be decided in the present case is interpretation of the agreement dated 02.11.2009, the same cannot be adjudicated by this Court in the present proceedings and it is for the learned Arbitrator to decide the same. Anyhow, the respondents requested this Court to appoint Arbitrator who is well acquainted in Arbitration Petn. (J2) No. 2 of 2014 P a g e | 11 the field of law, particularly, a retired High Court Judge of Gauhati High Court and has given two names of the Hon'ble Judges. 12. In the affidavit-in-opposition, the respondents stated that they are agreeable to appoint either Hon’ble Mr. Justice Asok Potsangbam or Hon’ble Mr. Justice B.D.Agarwal, retired Judges of Gauhati High Court. 13. Today, when the matter is taken up, the learned Senior Counsel appearing for the petitioner informed this Court that Hon'ble Mr. Justice B.D.Agarwal was appointed as Member of Lok Ayukta and Hon'ble Mr. Justice Asok Potsangbam is willing to spare his valuable time in case he has been appointed as Sole Arbitrator. The said fact has not been disputed and/or denied by the learned counsel for the respondents. 14. In view of the fact that undisputedly an agreement inter se the parties contained an arbitration Clause and disputes have arisen inter se the parties within the jurisdiction of this Court, the Arbitrator has to be appointed in pursuance to the petition filed by the petitioner under Section 11 of the said Act. 15. In view of the fact that there is no disagreement between the parties as to the existence of the arbitration agreement, this application is disposed of by appointing Hon’ble Mr. Arbitration Petn. (J2) No. 2 of 2014 P a g e | 12 Justice Asok Postangbam a retired Judge of Gauhati High Court as sole Arbitrator to adjudicate the disputes between the parties. 16. The parties have agreed that they shall not challenge the composition and impartiality of the Arbitrator. 17. The commensurate remuneration preferably on consolidated basis shall be fixed by the Arbitrator at the first sitting of the arbitration. All costs, charges and expenses including the remuneration of the Arbitrator shall be borne by the parties in equal measures. 18. The Arbitrator is requested to complete the proceeding within 6 (six) months from the date of entering upon the reference. Arbitration Petn. (J2) No. 2 of 2014 is accordingly disposed of. JUDGE FR/NFR Sushil WAIKH Digitally signed by WAIKHOM OM TONEN MEITEI TONEN Date: 2019.11.07 11:16:31 MEITEI -08'00' Arbitration Petn. (J2) No. 2 of 2014

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Manipur HC judgments →

Arbitration & Mediation advocates near the Manipur High Court

Dealing with a similar matter? Send a free enquiry to advocates who handle it. Fees are agreed with the advocate directly.

All Arbitration & Mediation advocates in India