Page |1
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
Arbitration Petn.(J2) No. 2 of 2014
M/s K. Pro Infra Works Pvt. Ltd. registered under
the Companies Act, 1956 having its registered
office at 704 Nilgiri Apartments, 9, Barakhamba
Road New Delhi-110001 through its authorized
signatory at Babupara, Imphal-795001, Manipur.
……. Petitioner
-Versus1. The Loktak Development Authority represented
by Member Secretary/Project Director, Loktak
Development Authority, Second Floor, Susu
Home, Opposite to First Manipur Rifles,
Babupara, Imphal-795001, Manipur.
2. The Surveyor of works, Loktak Development
Authority, 2nd Floor, Susu Home, Opp. 1st
Manipur Rifles Babupara, Imphal-795001,
Manipur.
3. Superintending Engineer, Loktak Development
Authority, Second Floor, Susu Home, Opposite
to First Manipur Rifles, Babupara, Imphal795001, Manipur.
4. Executive Engineers, Loktak Development
Authority, Second Floor, Susu Home, Opposite
to First Manipur Rifles, Babupara, Imphal795001, Manipur.
… Respondents
BEFORE
HON’BLE MR. JUSTICE M.V. MURALIDARAN
For the Petitioner
::
Arbitration Petn. (J2) No. 2 of 2014
Mr. H.S. Paonam, Sr. Advocate,
Mr. S. Dijeshwor, Advocate,
Page |2
Mr. L. Ashinikumar, Advocate,
Mr. N. Bipin, Advocate,
Ms. Ksh. Harichhaya, Advocate,
Mr. S. Gunabanta, Advocate,
Mr. A. Arunkumar, Advocate,
For the Respondents
::
Mr. A. Bimol, Sr. Advocate,
Mr. N. Ibotombi, Sr. Advocate,
Mr. A. Rommel, Advocate.
Date Hearing &
Judgment & Order
::
16.10.2019
JUDGMENT AND ORDER
(ORAL)
This petition has been filed by the petitioner under
Section 11 of the Arbitration and Conciliation Act, 1996 (in short “the
said Act”), with the following prayers:
“(i)AII disputes as raised by the petitioner be referred
to arbitration.
(ii) Confirm the appointment of one eligible/qualified
personality including consideration of the personality
suggested by the petitioner at Para 10 as independent
arbitrator to adjudicate on the dispute that has arisen
between the parties.
(iii) Costs incidental to this application be included as
costs to the arbitration proceedings.”
2.
The petitioner M/s.Pro Infra Works Private Limited is
engaged in the business of civil construction and execution of the
Arbitration Petn. (J2) No. 2 of 2014
Page |3
contract work of National/State importance. On 02.11.2009, the
petitioner Company and the first respondent herein had entered into
an agreement for execution of Phumdi Management Work.
However, the first respondent terminated the agreement on
31.3.2013 and had issued notice on 03.5.2013 under Clause 3 of
the agreement for taking up final action for forfeiture of security
deposit of the petitioner Company. According to the petitioner, the
final biII/payment under the contract has not been paid or settled by
the first respondent in terms of the work agreement.
3.
Earlier the petitioner has filed a writ petition in W.P.(C)
No.364 of 2013 before this Court seeking to set aside the notice
dated 3.5.2013. The said writ petition came to be dismissed by this
Court on 7.3.2014 holding that the disputed question of facts could
be adjudicated upon by the Arbitrator as provided by the work
agreement. Aggrieved by the same, the petitioner has preferred
S.L.P.(C) No.10793 of 2014 before the Hon'ble Supreme Court and
by an order dated 28.4.2014, the said S.L.P. came to be dismissed.
Thereafter,
the
petitioner
Company
sent
a
demand
notice/application on 12.5.2014 setting out 14 claims and notified
that in case the dues are not settled within fifteen days from the
receipt of the notice, the matter may be treated as a dispute and will
be referred to arbitration in terms of Clause 22 of the agreement.
Arbitration Petn. (J2) No. 2 of 2014
Page |4
4.
According to the petitioner, the said notice dated
12.5.2014 is in addition to the application and notices sent earlier
for invoking arbitration proceedings dated 9.5.2013 for resolving the
issues and disputes which was further reminded and responded by
several correspondences between the petitioner and the First
respondent. However, the appointment of Arbitrator by mutual
agreement could not be materialized for want of satisfaction from
both ends. Thereafter, the petitioner addressed letters dated
24.5.2014 and 26.5.2014 to the Competent Authority of Loktak
Development (First respondent herein). By a letter dated 7.6.2014,
the Loktak Development admitted that the dispute has to be settled
by arbitration, however, has not accepted the claim of the petitioner.
5.
Again on 27.6.2014, the petitioner submitted another
letter requesting for appointment of Sole Arbitrator in accordance
with the Contract Agreement dated 2.11.2009 for settlement of
disputes as per the provision of Clause 22 of the Agreement by
mentioning two names of experts. By a letter dated 31.07.2014, the
First respondent has not agreed to the proposed name for
appointment of the SoIe Arbitrator for resolving the dispute. Hence,
the petitioner is left with no other alternative, but to approach this
Court for appointment of Sole Arbitrator. On 18.8.2014, the
petitioner sent letter to the first respondent for appointment of Sole
Arbitration Petn. (J2) No. 2 of 2014
Page |5
Arbitrator by mutual consent and since the respondents have failed
to appoint an Arbitrator in terms of the arbitration clause, the
petitioner has filed the present petition.
6.
Resisting the petition, the Project Director of Loktak
Development Authority has filed affidavit-in-opposition stating that
when they proposed three named Arbitrators for resolving the
disputes, the petitioner has not agreed. It is stated that since the
main issue involved in the present case is interpretation of the
agreement dated 2.11.2009, an Arbitrator who is well acquainted in
the field of law is required to be appointed and as such they
approached Hon’ble Justice Asok Potsangbam and the Hon'ble
Justice B.D. Agarwal, retired Judges of Gauhati High Court for their
consent for appointment as an Arbitrator. It is stated that both the
Hon'ble Judges have agreed to spare their valuable time in case
one of them is appointed as an Arbitrator by this Court.
7.
The learned Senior Counsel for the petitioner argued
that there exists arbitration clause and also disputes arose between
the parties. He would submit that despite efforts made by the
petitioner to resolve the disputes through arbitration, the
respondents are in the habit of evading appointment of an Arbitrator
to settle the disputes between the parties, which necessitated the
petitioner in approaching this Court by fling the present petition.
Arbitration Petn. (J2) No. 2 of 2014
Page |6
8.
Per contra, the learned counsel for the respondents
submitted that when the respondents agreed for arbitration and
nominated Arbitrators, the petitioner has not given consent and,
therefore, the petitioner cannot blame the respondents.
9.
Heard the learned counsel appearing on either side
and also perused the materials available on record.
10.
There is beyond any dispute that dispute arose
between the petitioner and the respondents and before filing the
present petition, there were exchange of notices between the
parties. There is also no dispute qua existence of arbitration Clause
in the agreement. Clause 22 of the agreement provides for
arbitration, which reads thus:
“CLAUSE 22. Except where otherwise provided in the
contract all questions and disputes relating to the
meaning of the specifications, design, drawings and
instructions hereinbefore mentioned and as to the
quality of workmanship or materials used on the work
or as to any other question, claim, right, matter or
thing whatsoever in any way arising out of or to the
contract, designs, drawings, orders or relating
specifications,
estimates,
instructions,
these
conditions or otherwise concerning the works or the
execution or failure to execute the same whether
arising during the progress of the work or after the
Arbitration Petn. (J2) No. 2 of 2014
Page |7
cancellation,
termination,
abandonment thereof
completion
shall be
or
dealt with as
mentioned hereinafter:
(i) If the Contractor considers any work demanded
of him to be outside the requirements of the
contract, or disputes any drawings, record or
decision given in writing by the Engineer-incharge on any matter in connection with or arising
out of the contract or carrying out of the work, to
be unacceptable, he shall promptly within 15 days
request the Superintending Engineer in writing for
written instruction or decision. Thereupon, the
Superintending Engineer shall give his written
instructions or decision within a period of one
month from the receipt of the Contractor’s letter.
If the Superintending Engineer fails to give his
instructions or decision in writing within the
aforesaid period or if the Contractor is dissatisfied
with
the
instructions
or
decision
of
the
Superintending Engineer, the Contractor may,
within 15 days of the receipt of Superintending
Engineer's decision, appeal to the Project
Director, LDA who shall afford an opportunity to
the Contractor to be heard, if the latter so desires,
and to offer evidence in support of his appeal. The
Project Director, LDA shall give his decision
within 30 days of receipt of Contractor’s appeal. If
the Contractor is dissatisfied with this decision the
Contractor shall within a period of 30 days from
Arbitration Petn. (J2) No. 2 of 2014
Page |8
receipt of the decision, give notice to the Project
Director, LDA for appointment of arbitrator failing
which the said decision shall be final binding and
conclusive and not referable to adjudication by
the arbitrator.
(ii) Except where the decision has become final,
binding and conclusive in terms of sub-para (i)
above disputes or difference shall be referred for
adjudication
through
arbitration
by
a
sole
arbitrator mutually agreed upon by both parties
and duly appointed by the Project Director, LDA.
If the arbitrator so appointed is unable or unwilling
to act or resigns his appointment or vacates his
office due to any reason whatsoever another sole
arbitrator shall be appointed in, the manner
aforesaid. Such person shall be entitled to
proceed with the reference from the stage at
which it was left by his predecessor.
It is a term of this contract that the party invoking
arbitration shall give a list of disputes with
amounts claimed in respect of each such dispute
along with the notice for appointment of arbitrator
and giving reference to the rejection by the
Project Director, LDA of the appeal.
It is also a term of this contract that no person
other than a person appointed by such Project
Director, LDA as aforesaid should at as arbitrator
and if for any reason that is not possible, the
matter shall not be referred to arbitration at all.
Arbitration Petn. (J2) No. 2 of 2014
Page |9
It is also a term of this contract that if the
Contractor does not make any demand for
appointment of arbitrator in respect of any claims
in writing as aforesaid within 120 days of receiving
the intimation from the Engineer-in-charge that
the final bill is ready for payment, the claim of the
Contractor shall be deemed to have been waived
and absolutely barred and the Government shall
be discharged and released of all liabilities under
the contract in respect of these claims.
The arbitration shall be conducted in accordance
with the provisions of the Arbitration and
Conciliation Act, 1996 (6 of 1996) or any statutory
modifications or re-enactment thereof and the
rules made thereunder and for the time being in
force shall apply to the arbitration proceeding
under this clause.
It is also a term of this contract that the arbitrator
shall adjudicate on only such disputes as are
referred to him by the appointing authority and
give separate award against each dispute and
claims referred to him and in all cases where the
total amount of the claims by any party exceeds
Rs.1,00,000/- the arbitrator shall give reasons for
the award.
It is also a term of this contract that if any fees are
payable to the arbitrator these shall be paid
equally by both the parties.
Arbitration Petn. (J2) No. 2 of 2014
P a g e | 10
It is also a term of this contract that the arbitrator
shall be deemed to have entered on the reference
on the date he issues notice to both the parties
calling them to submit their statement of claims
and counter-statement of claims. The venue of
arbitration shall be such place as may be fixed by
the arbitrator in his sole discretion. The fees, if
any, of the arbitrator, shall, if required to be paid
before the award is made and published, be paid
half and half by each of the parties. The cost of
the reference and cost of the award (including the
fees, if any, of the arbitrator) shall be in the
discretion of the arbitrator who may direct to any
by whom and in what manner, such costs or any
part thereof shall be paid and fix or settle the
amount of cost to be so paid.
The place of arbitration and legal jurisdiction for
any dispute arisen from this Agreement shall be
at Imphal.”
11.
From the pleadings, it appears that both the parties
are agreeable for arbitration. Though the respondents contended
that main issue to be decided in the present case is interpretation
of the agreement dated 02.11.2009, the same cannot be
adjudicated by this Court in the present proceedings and it is for the
learned Arbitrator to decide the same. Anyhow, the respondents
requested this Court to appoint Arbitrator who is well acquainted in
Arbitration Petn. (J2) No. 2 of 2014
P a g e | 11
the field of law, particularly, a retired High Court Judge of Gauhati
High Court and has given two names of the Hon'ble Judges.
12.
In the affidavit-in-opposition, the respondents stated
that they are agreeable to appoint either Hon’ble Mr. Justice Asok
Potsangbam or Hon’ble Mr. Justice B.D.Agarwal, retired Judges of
Gauhati High Court.
13.
Today, when the matter is taken up, the learned Senior
Counsel appearing for the petitioner informed this Court that
Hon'ble Mr. Justice B.D.Agarwal was appointed as Member of Lok
Ayukta and Hon'ble Mr. Justice Asok Potsangbam is willing to spare
his valuable time in case he has been appointed as Sole Arbitrator.
The said fact has not been disputed and/or denied by the learned
counsel for the respondents.
14.
In view of the fact that undisputedly an agreement inter
se the parties contained an arbitration Clause and disputes have
arisen inter se the parties within the jurisdiction of this Court, the
Arbitrator has to be appointed in pursuance to the petition filed by
the petitioner under Section 11 of the said Act.
15.
In view of the fact that there is no disagreement
between the parties as to the existence of the arbitration
agreement, this application is disposed of by appointing Hon’ble Mr.
Arbitration Petn. (J2) No. 2 of 2014
P a g e | 12
Justice Asok Postangbam a retired Judge of Gauhati High Court as
sole Arbitrator to adjudicate the disputes between the parties.
16.
The parties have agreed that they shall not challenge
the composition and impartiality of the Arbitrator.
17.
The commensurate remuneration preferably on
consolidated basis shall be fixed by the Arbitrator at the first sitting
of the arbitration. All costs, charges and expenses including the
remuneration of the Arbitrator shall be borne by the parties in equal
measures.
18.
The Arbitrator is requested to complete the proceeding
within 6 (six) months from the date of entering upon the reference.
Arbitration Petn. (J2) No. 2 of 2014 is accordingly
disposed of.
JUDGE
FR/NFR
Sushil
WAIKH Digitally
signed by
WAIKHOM
OM
TONEN MEITEI
TONEN Date:
2019.11.07
11:16:31
MEITEI -08'00'
Arbitration Petn. (J2) No. 2 of 2014
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review