IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
CARBC No.80 of 2025
Decided on 27.05.2026
Reserved on 07.05.2026
M/s Ganga Ram and sons
…Petitioner
Versus
The Engineer-in-Chief HPPWD and others
…Respondents
Coram
Hon’ble Mr. Justice Ajay Mohan Goel, Judge
Whether approved for reporting? No.
For the petitioner:
For the respondents
Ms. Sunita Sharma, Senior
Advocate, with Mr. Saurav
Upadhay, Advocate.
:
Mr. S.D. Vasudeva, Deputy Advocate
General.
Ajay Mohan Goel, Judge
These objections under Section 34 of the Arbitration
and Conciliation Act are directed against the award passed by
the learned Arbitrator, in terms whereof, the claim of the
petitioner/objector has been partly allowed by the learned
Arbitrator.
2.
Brief facts necessary for the adjudication of this
petition are that the work of the construction of Kyari-Gundah
road portion 15/1 to 19/200 kilometers was awarded to the
claimant
on
20.06.2006.
The
cost
of
the
work
was
Rs.34,82,019/-. The work was to be completed within one year,
which was to be reckoned from the 15th day of the issuance of
letter. During the execution of the work, a dispute arose and the
same was referred for arbitration to the Sole Arbitrator Sh.
Ravinder Thakur, Advocate. The claimant put forth the following
claim before the learned Arbitrator:“1. Balance work payment:
a). The contractor was awarded the work for
approximately 35 lacs and the payment received by the
contractor as per work done certificate and M.B.
concerned, is only approximately 9 lacs. So the balance
work payment i.e. 35 lacs-9 lacs + 26
lacs(approximately) may be paid to the contractor.
2. Ideal Machinery charges:
a). The machineries which were arranged and hired
strictly for the construction of this work stood ideal for a
period of 9 months i.e. from 1 April, 2008 to 31st Dec.
2008. So the ideal machinery charges of 9 months may
be paid to the contractor. The detail of the machineries,
which were hired for this work is as under:Sr.
No.
Machinery
Nos
JCB
2 Nos
2.
L&T
1 Nos
3.
Air
2Nos
Compressor
s
Tractor with 1 No
trolley
4.
Rate
Amount of
months
12000/- per dayx30 32,40,000
days=3,60,000
per
month
1000/- per day x30 27,00,000/days =3,00,000 pr
month
4000/- per month of 2 3,60,000/compressors
20000/- per month
1,80,000/-
5.
Labours
15 Nos 90,000/- per month
8,10,000/Total ideal machinery 72,90,000
claim
(Rupees
seventy two lacs
and
ninety
thousand only
3. Loss of Profit :a). Due to the complete negligence of the department,
the contractor was deprived of executing the balance
work of approximately 26 lacs, which contractor would
have successfully completed, in case the land dispute
problem at site had been solved by the department and
he court stay orders had been vacated. So loss of profit
of 25% is claimed by the contractor on the balance of
work of 26 lacs i.e. 25% of 26 lacs approximately 7 lacs
is also claimed.
4. Security amount deducted from the running bills.
Any amount which has been deduced from the
running bills in the form of securities and entered in the
MB's may kindly be released to the contractor at the
earliest.
5.
Interest
of Total
amount
claimed
Rs.
1,06,90,000/-. Interest @ 18% on total amount of claim
for 9 months approximately Rs. 13,50,000/- Total
amount Rs. 1,20,40,000/- (one crore twenty lacs and
forty thousand only).”
3.
Opposing the same, it was the stand of the
Department before the learned Arbitrator that the site was free
from all encumbrances and was handed over to the claimant.
The contractor executed the work from Kilometer 15/0 onwards
upto 16/825 and thereafter stopped the work and removed his
machinery and manpower from site and that too without any
intimation to the Department. According to the Department,
the amount which was payable to the contractor for the work
executed by him was duly paid.
4.
It is recorded in the impugned award that during the
pendency of the proceedings on the request of the claimant,
the spot was visited with the consent of the parties on
26.07.2014 and spot inspection revealed that road from 15/0
kilometer to 16/825 kilometer stood constructed by the
claimant. However, no machinery was found at the spot.
The claimant/contractor himself stated that after construction of
the road upto 16/825 somewhere in the year 2008, he had
removed the machinery and labour deployed for the work on
account of an ex party stay order obtained by Sh. Salku Ram
qua the work in issue.
5.
The award also reveals that though it was the claim
of the claimant that he had also constructed the road from 12
kilometer to 15 kilometer, but on the spot when confronted by
local residents who claimed that road from 12 kilometer to 15
kilometer was constructed by some other contractor, the
claimant conceded to the same.
6.
The award also demonstrates that the claimant
admitted that as per the measurement of road constructed by
him from 15/0 to 16825 he had received the entire payment of
the amount of Rs.15,48,891/- in four running bills.
7.
Learned Arbitrator held with regard to claim No.1
i.e., balance of work payment that in the light of the fact that the
contractor had executed the work from kilometer 15/02 to
16/825 only and abandoned the work thereafter on the pretext
of stay order and as the contractor stood paid for the work
executed by him as total some of Rs.15,48,891/- was paid to
him in four running bills, nothing was payable to the claimant
under claim No.1.
8.
With regard to claim No.2 i.e., idle machinery
charges, learned Arbitrator held that the claimant had pointed
out that certain machineries i.e., two JCB, one L&T, Two Air
Compressors and one Tractor Trolley alongwith 15 labourers
were arranged and hired for construction of road which
remained idle from 01.04.2008 to 31.12.2008 and on this count,
the claimant had claimed an amount of Rs.72,90,000/-, but in
support of this contention, no evidence was placed on record
by the contractor and in the absence of any documentary proof
to demonstrate said facts, this claim was denied by the learned
Arbitrator to the claimant.
9.
With regard to issue No.3 that is loss of profit,
learned Arbitrator held that according to the claimant, because
of the negligence of the Department on account of land dispute
etc., as well as stay order, he was deprived from executing the
balance was worth Rs.26 lacs and on account thereof he has
suffered losses i.e., 25% of the value of the balance work which
comes to Rs.7 lacs, whereas, the stand of the Department was
to the contrary. As per the Department, the contractor had
himself stopped the work and had removed the machineries
and labourers from the site of work without intimating the
Department. It was further the stand of the Department that
there was no stay whatsoever regarding the execution of the
work beyond 16/825 kilometers. Learned Arbitrator further held
that perusal of the complaint demonstrated that in the Civil Suit
filed for injunction, only the claimant contractor and one private
individual were impleaded as parties and the contractor after
receiving the ex-parte order did not care to contest the Civil Suit
nor any written request was made to the Department for getting
the issue settled. Learned Arbitrator also observed that though
the ex parte stay order was passed somewhere in the year
2008 and execution of the work was stopped by the contractor,
however, neither the Department nor the contractor made any
attempt to get the stay vacated. On these basis, learned
Arbitrator held that the plea of the contractor that he was
deprived of the execution of the balance wok was not correct,
more so, when the work contract was kept alive and, therefore,
the contractor was not entitled for the said claim. Thereafter,
learned Arbitrator held that in case the work is rescinded for
any reason and contractor is not allowed to execute the work,
in that eventuality on account of loss of profit, the contractor
shall be entitled to an amount of Rs.1,94,000/- i.e., 10% of the
value of balance work.
10.
With regard to claim No.4 and 5, learned Arbitrator
held that as the contract was still alive and if the claimant is
allowed to execute the remaining work and he completes the
same within reasonable time, he will be entitled for the refund
of security, but if the work is rescinded, then, the contractor
shall be entitled for refund of security amount alongwith interest
@8% from the date mentioned therein.
11.
As far as interest is concerned, the prayer thereof
was rejected and limited relief of interest @8% on an amount of
Rs.1,94,000/- was awarded in favour of the claimant.
12.
Feeling aggrieved, the claimant has filed this
objection petition.
13.
Learned Senior Counsel for the petitioner has
vehemently argued that the award passed by the learned
Arbitrator is not sustainable in the eyes of law as the learned
Arbitrator has not at all appreciated the contention of the
claimant while deciding the claim. Learned Senior Counsel
submitted that as it was evident that the work could not be
executed by the claimant on account of the stay order that was
passed by the Court, learned Arbitrator erred in not
appreciating that the petitioner was entitled for damages on
account of the non-execution of the work as also for damages
on account of loss of profit. Learned Senior Counsel also
submitted that the award was against the public policy as
learned Arbitrator had not taken into consideration the evidence
led by the petitioner, in the correct perspective qua the
deployment of labour as well as machinery on the site.
Accordingly, learned Senior Counsel submitted that as the
award passed by the learned Arbitrator is not sustainable in the
eyes of law, the same be set aside. No other point was urged.
14.
On the other hand, learned Deputy Advocate
General submitted that as the Department had accepted the
award and had decided not to assail the same, therefore, the
same being a reasonable award, calls for no interference.
15.
Having heard learned Senior Counsel for the
petitioner as well as learned Deputy Advocate General and
having perused the award under challenge, this Court is of the
considered view that in the facts and circumstances involved
herein, the petitioner is not entitled for any relief.
16.
In terms of the judgment of the Hon’ble Supreme
Court on the scope of interference under Section 34 of the
Arbitration and Conciliation Act against an award in issue, it is
now well settled that the arbitral award should not be interfered
with in a casual and cavalier manner, unless the Court comes
to the conclusion that perversity of the award goes to the root of
the matter. Hon’ble Supreme Court has also held that the
provision of Section 34 is different and is not to be equated with
appellate jurisdiction. Hon’ble Supreme Court has held that the
mandate under Section 34 is to respect the finality of the award
and if the Courts were to interfere with the arbitral award in
usual courses on factual aspects, then the commercial wisdom
behind opting for alternative dispute resolution would stand
frustrated.
17.
Coming to the facts of the present case, learned
Arbitrator rejected claim No.1 and 2 by holding that the claimant
could not demonstrate that the payment for the work executed
was not released in his favour by the Department. In fact, an
observation has been made in the award by the learned
Arbitrator that when the site was visited at the time of spot
inspection, the claimant had admitted that for the work
executed by him, the entire payment of Rs.15,48,891/- was
released in his favour in four running bills.
18.
Similarly with regard to claim No.3, learned
Arbitrator by referring to the respective contention of the parties
and material on record observed that after the stay order was
passed by the learned Civil Court in the Suit filed for rejection,
the contract who was a party defendant in the Civil Suit did not
take any step for the vacation of the stay nor he appeared
before the learned Court. Learned Arbitrator also held that the
contractor did not even approach the Department for the
vacation of the stay etc.
19.
With regard to issue No.4 and 5, learned Arbitrator
returned the findings that as the contract was alive, therefore, if
the claimant was allowed to execute the remaining work and he
completed the same within some reasonable time, the
contractor shall be entitled for refund of security, but, if the work
is rescinded, then he shall be entitled for refund of security
alongwith interest.
20.
This Court is of the considered view that in the
peculiar facts of this fact, it cannot be said that the award
passed by the learned Arbitrator suffers from any perversity so
as to entail interference under Section 34 of the Arbitration and
Conciliation Act by this Court. In terms of the award, learned
Arbitrator took into consideration the respective contention of
the parties and thereafter has returned his findings. Obviously,
as this Court in exercise of its power under Section 34 of the
Arbitration and Conciliation Act is not to act as an Appellate
Court and substitute its view for that of the contractor if another
view was possible, in the absence of any grave perversity being
demonstrated by the learned Senior Counsel for the petitioner,
this Court sees no reason to interfere with the award.
21.
The arguments raised by the learned Senior
Counsel that the evidence led by the contractor was not
appreciated in the correct perspective could also not be proved
before the Court in the course of arguments as it could not be
pointed
out
as
to
which
evidence
was
misread
or
misappreciated by the learned Arbitrator.
22.
Therefore, in the light of the above observations as
the award passed in the present case does not call for any
interference under Section 34 of the Arbitration and Conciliation
Act, this petition is dismissed.
23.
Pending miscellaneous applications, if any, also
stand disposed of.
(Ajay Mohan Goel)
Judge
May 27, 2026
(Vinod)
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review