THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : Cont.Cas(C)/323/2024
MRINAL DAS
S/O- SRI DHONIRAM DAS, VILL.- NO. 1 MOHAIJAN, P.O. MOHAIJAN P.S.
NORTH LAKHIMPUR, DISTRICT- LAKHIMPUR, PIN- 787032.
VERSUS
JAY SHIVANI AND 2 ORS.
COMMISSIONER, PANCHAYAT AND RURAL DEVELOPMENT
DEPARTMENT, ASSAM, PANJABARI, JURIPAR, GUWAHATI- 781037.
2:GAYATRI HYALINGE
THE DISTRICT COMMISSIONER CUM DISTRICT PROGRAMME
COORDINATOR MGNREGA
DIST.- LAKHIMPUR
NORTH LAKHIMPUR
PIN- 787001.
3:SEUTY DOLEY
THE BLOCK DEVELOPMENT OFFICER
LAKHIMPUR DEVELOPMENT BLOCK
NORTH LAKHIMPUR
DIST.- LAKHIMPUR
PIN- 787001
Advocate for the Petitioner : MR. M K NEOG, MR. S K SINGHA
Page No.# 2/ 7
Advocate for the Respondent : MR S DUTTA (R-1,2 & 3), MR S DUTTA
(R1),MS. N BORAH (R1),MR. K KONWAR (R1)
BEFORE
HONOURABLE MR. JUSTICE MANISH CHOUDHURY
ORDER
Date : 10-02-2026
1.
Heard Mr. S.K. Singha, learned counsel for the Petitioner; Ms. N. Borah,
learned counsel for the respondent no. 1; and Ms. U. Das, learned counsel
for the respondent no. 3.
2.
This contempt petition under Section 12 of the Contempt of Courts Act,
1971 read with Article 215 of the Constitution of India is preferred alleging
that there is non-compliance of the direction given by this Court in an
Order dated 28.02.2024, passed in a writ petition, W.P.[C.] no.
1042/2024, which was preferred by the petitioner.
3.
In the writ petition, the petitioner had averred that the petitioner had
executed two contract-works awarded to the petitioner in respect of two
Schemes, namely, [i] Raised Platform at Lohan Gaon near Namghar under
MGNREGA 2021-2022 [8Contract-Work no. 19, for short]; and [ii] Earth
Filling and Land Development at proposed site of PMAY-G Colony at 0.2
Kalioni under MGNREGA 2021-2022 [8Contract-Work no. 29, for short]. The
State respondents did not release his outstanding liabilities amounting to
Rs. 28,26,895/- till the date of filing of the writ petition, despite execution
of the two contract-works fully by the petitioner.
4.
The writ petition came up for consideration on 28.02.2024. The Court took
into consideration the decision of the Full Bench of this Court in the case
of Tamsher Ali and others vs. State of Assam and others, 2008 [4] GLT
1, to observe that any contract amount payable would have to be
approved/ admitted by the concerned Head of the Department. As the
Commissioner, Panchayat & Rural Development Department, Assam was
the Head of the Department in respect of the two Schemes/contract-works
against which the petitioner had claimed the amount, the Court directed
Page No.# 3/ 7
the Commissioner, Panchayat & Rural Development Department, Assam to
re-verify the list of pending material bills under the MGNREGA, which was
annexed to a Letter dated 09.10.2023 by the concerned Block
Development Officer, found annexed to the writ petition, in relation to the
petitioner's claim. The Court further directed that if upon verification, it
was found that the petitioner was entitled to some outstanding amount,
then the admitted liability should be paid by the respondents. The Court
directed to complete the entire exercise within a period of two months
from the date of receipt of a certified copy of the order.
5.
The petitioner stated that the copy of the Order dated 28.02.2024 was
duly submitted to the respondents impleaded herein on 03.05.2024. As
the exercise directed by the Order dated 28.02.2024 was not completed
within the time period mentioned therein, the petitioner had approached
this Court by the present contempt petition.
6.
The respondent no. 1 and the respondent no. 3 have brought their stands
by way of affidavits-in-opposition. The respondent no. 1 in the affidavit-inopposition, filed on 16.05.2025, has inter-alia stated that the Scheme,
8Earth Filling and Land Development at proposed site of PMAY-G Colony at
0.2 Kalioni under MGNREGA for FY 2021-20229 [Contract-Work no. 2] had
been marked as ongoing in MIS without entering material bills. From the
affidavit-in-opposition of the respondent no. 3, it is discernible that by an
Office Order dated 05.08.2025, the respondent no. 1 constituted a team of
three officials of State Headquarter to physically verify and ascertain the
volume of earth filling done in respect to the Scheme, 8Earth Filling and
Land Development at proposed site of PMAY-G Colony at 0.2 Kalioni under
MGNREGA for FY 2021-20229 [Contract-Work no. 2]. The team so
constituted went for physical verification at the site on 21.08.2025 and
submitted an Enquiry Report, which is found annexed as Annexure-2 to
the affidavit-in-opposition of the respondent no. 3. As per the Enquiry
Report, the team after field verification found that the volume of actual
earthwork done was 8605.44 cum [cubic meter] which was 86.99% of the
compacted volume after considering shrinkage as per the working
Page No.# 4/ 7
estimate. It was further observed that a proper site survey and crosssection method of earthwork calculation were not undertaken prior to the
preparation of the estimate and the same had led to an overestimation of
the project volume in the official documents. Subsequent to submission of
the Enquiry Report, the Chief Executive Officer, Lakhimpur Zilla Parishad
wrote to the Commissioner, Panchayat & Rural Development Department,
Assam vide Office Letter dated 02.09.2025 stating inter-alia that after
carrying out technical verification and submission of report, the admissible
amount had been assessed at Rs. 9,54,850/-. A statement of payment
details made to the petitioner issued under the hand of the respondent no.
3 [Block Development Officer, Lakhimpur Development Block] has been
annexed to the said affidavit-in-opposition giving break-up of five bills with
their respective bill amount. As per the said statement, out of the five bills,
four bills had already been cleared and in so far as the payment with
regard to the 5th bill is concerned, the payment was in queue due to
technical problem and the same would be solved within a week.
7.
The petitioner has, however, disputed the stance taken by the
respondents by filing an affidavit-in-reply. According to him, the total bill
amount recorded in the MIS on 10.04.2022 in respect to the Scheme
under reference was Rs. 25,74,490/-, and the said amount had to be
treated as an admitted liability. It has been further averred that out of Rs.
25,74,490/-, an amount of Rs. 7,93,169/- had only been paid by the
respondent no. 3.
8.
As regards the Scheme named 8Raised Platform at Lohan Gaon near
Namghar under MGNREGA 2021-20229 [Contract Work no. 1], the
respondents have taken a clear stand that the said Scheme is not a
permissible work under the MGNREGA as per para 7.2 of the Annual
Master Circular 2021-2022 and as such, no material payment can be made
against such non-permissible Scheme. In view of such categorical stand, it
is not necessary to delve further into the issue.
Page No.# 5/ 7
9.
It needs to iterate that the full Bench of this Court in Tamsher Ali [supra]
has observed that a writ petition involving contractual liability can be
considered only in the event there is admission of liability certified by the
respective Chief Engineer in the Works Department and in respect of other
departments by the head of the department.
10.
In the case in hand, as there was no admission of liability by the Head of
the Department, i.e., the Commissioner, Panchayat & Rural Development
Department, Assam, in respect of the two contract-works against which
the petitioner had claimed the amount against execution, the writ petition
was disposed of with a direction to the Commissioner, Panchayat & Rural
Development Department, Assam to make a verification and upon
verification, if it is found that the petitioner is entitled to any outstanding
amount then the liability to the extent admitted should be paid.
11.
The stand as regards liability taken by the respondent no. 1 is found to the
extent of Rs. 9,54,850/-. Ms. Das has placed on record the status of
payment details against the Scheme, 8Earth filling land development at
Propose site of PMAY-G Colony of No. 2 Kolioni9 [Contract-Work no. 2]
under MGNREGA 2021-2022 as under :-
Financial
year
Work Code
Name of the Work
Bill No. Vendor Name Bill Amount
FTO No.
2021-22
0410003005/
LD/
9010306153
PAYMENT DETAILS OF EARTH
FILLING & DEVELOPMENT AT
PROPOSED SITE OF PMAY-G
COLONY AT NO. 2 KOLIONI
MRINAL DAS
199391
041000300SSPAY
REQ2811202515
2021-22
0410003005/
LD/
9010306153
PAYMENT DETAILS OF EARTH
FILLING & DEVELOPMENT AT
PROPOSED SITE OF PMAY-G
COLONY AT NO. 2 KOLIONI
MRINAL DAS
197925
041000300SSPAY
REQ2811202516
2021-22
0410003005/
LD/
9010306153
PAYMENT DETAILS OF EARTH
FILLING & DEVELOPMENT AT
PROPOSED SITE OF PMAY-G
COLONY AT NO. 2 KOLIONI
MRINAL DAS
197925
041000300SSPAY
REQ2811202517
2021-22
0410003005/
LD/
9010306153
PAYMENT DETAILS OF EARTH
FILLING & DEVELOPMENT AT
PROPOSED SITE OF PMAY-G
COLONY AT NO. 2 KOLIONI
MRINAL DAS
197925
041000300SSPAY
REQ2811202518
2021-22
0410003005/
LD/
9010306153
PAYMENT DETAILS OF EARTH
FILLING & DEVELOPMENT AT
PROPOSED SITE OF PMAY-G
MRINAL DAS
161521
041000300SSPAY
REQ210120266
Page No.# 6/ 7
COLONY AT NO. 2 KOLIONI
Total
12.
954687
Relying upon the above statement, Ms. Das has submitted that the entire
amount of Rs. 9,54,687/- has already been paid to the petitioner.
13.
Mr. Singha has, on the other hand, disputed to the extent that the 5 th bill
amount shown as Rs. 1,61,521/- has not been received by the petitioner
till date.
14.
Having regard to the direction made in the Order dated 28.02.2024, this
Court after consideration has found that the respondent no. 1 had carried
out a verification process to ascertain the extent of work completed
against the Scheme, 8Earth filling land development at Propose site of
PMAY-G Colony of No. 2 Kolioni9 [Contract-Work no. 2] under MGNREGA
2021-2022 by constituting a team of technical experts and it was on the
basis of the Enquiry Report submitted by the team, the liability to the
extent of Rs. 9,54,850/- has been found entitled by the petitioner.
15.
Taking into consideration the scope and ambit of contempt jurisdiction,
which is only limited to the direction made in the Order dated 28.02.2024,
this Court is of the considered view that it is not necessary to proceed
further in this contempt petition as the respondent no. 1 had carried out
the necessary exercise, as directed, albeit with some delay.
16.
Taking into consideration the objection made by the learned counsel for
the petitioner with regard to non-receipt of the amount of Rs. 1,61,521/as the final bill, this Court directs that if the amount of Rs. 1,61,521/- has
not been released to the petitioner till date, then the respondent no. 1
shall ensure that the said amount is disbursed to the petitioner, within a
period of 2 [two] months from today.
17.
It is further clarified that if the petitioner has any further claim with regard
to the Schemes concerned, the petitioner is at liberty to avail appropriate
remedy as permissible under the law before the appropriate forum.
Page No.# 7/ 7
18.
This order disposes of the contempt petition.
19.
The document placed by Ms. Das is kept with the case record by marking
it as Document – 8X9.
JUDGE
Comparing Assistant
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review