IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 8TH DAY OF JANUARY, 2026
PRESENT
THE HON'BLE MRS. JUSTICE ANU SIVARAMAN
AND
THE HON'BLE MR. JUSTICE VIJAYKUMAR A. PATIL
MISCELLANEOUS FIRST APPEAL NO.7153 OF 2024 (AA)
BETWEEN:
MR. H. L. NAGARAJA
AGED ABOUT 74 YEARS,
S/O MR. H.C.LAKSHMIPATHAIAH,
RESIDING AT NO.212, III STAGE,
II BLOCK, JUDGES COLONY,
BASAVESHWARANAGAR
BANGALORE - 560 079.
...APPELLANT
(BY SRI. MITHUN S.K., ADV.,)
AND:
1.
M/S. SIDDHSHEKHA DEVELOPERS LLP
(FORMERLY KNOWN AS
M/S. SIDDHSHEKHA DEVELOPERS PVT. LTD.,)
ALSO AT 1/1,
N.V. HOUSE,
1ST FLOOR, H. SIDDHAIAH ROAD,
BANGALORE - 560 002.
REPRESENTED BY ITS PARTNER
MR. SHAILESH KUMAR S.
HARAN
2.
MR. JUSTICE V. JAGANNATHAN,
RETIRED, SOLE ARBITRATOR,
AT ARBITRATION CENTRE,
KHANIJA BHAVAN NO.49,
3RD FLOOR, EAST WING,
RACE COURSE ROAD,
BENGALURU - 560 001.
...RESPONDENTS
(BY SRI. UDAYA HOLLA, SR. ADV. FOR
SRI. SANJAY H. SETHIYA, ADV. FOR C/R1)
THIS MFA IS FILED UNDER SECTION 37(1)(c) OF THE
ARBITRATION AND CONCILIATION ACT, 1996, AGAINST THE
ORDER DATED 21.09.2024 PASSED IN A.S.NO.25003/2023 ON
THE FILE OF 74TH ADDITIONAL CITY CIVIL AND SESSIONS
JUDGE, MAYOHALL UNIT, BENGALURU (CCH-75), DISMISSING
THE PETITION FILED UNDER SECTION 34 OF THE ARBITRATION
AND CONCILIATION ACT, 1996.
THIS MFA HAVING BEEN HEARD AND RESERVED FOR
JUDGMENT
ON
26.11.2025
AND
COMING
ON
FOR
PRONOUNCEMENT OF JUDGMENT THIS DAY, ANU SIVARAMAN
J., PRONOUNCED THE FOLLOWING:
CORAM:
HON'BLE MRS. JUSTICE ANU SIVARAMAN
and
HON'BLE MR. JUSTICE VIJAYKUMAR A. PATIL
CAV JUDGMENT
(PER: HON'BLE MRS. JUSTICE ANU SIVARAMAN)
This Miscellaneous First Appeal is filed under Section
37(1)(c) of the Arbitration and Conciliation Act, 1996, ('the
Arbitration Act' for short) against the judgment dated
21.09.2024 passed by the LXXIV Additional City Civil and
Sessions Judge, Mayohall Unit, Bengaluru, (CCH-75) ('the
trial Court' for short) in A.S. No.25003/2023.
2.
We have heard Shri Mithun S.K., learned counsel
appearing for the appellant and Shri. Udaya Holla, learned
Senior Counsel as instructed by Shri. Sanjay H. Sethiya,
learned Advocate appearing for caveator/respondent No.1.
3.
The
A.C.No.134/2022.
appellant
The
claim
was
was
the
claimant
based
on
a
in
Joint
Development Agreement dated 22.10.2012. The claim raised
was that respondent No.1 herein/developer had to pay an
amount of Rs.47,46,17,454/- as compensation and in the
alternative, to direct the developer to hand over 39,551
square feet of Super Built-Up area in the Schedule Property.
The project in question was the construction of a multistoried residential complex in property bearing No.98, Bull
Temple Road, Basavanagudi, Bengaluru.
The respondents
being put on notice had submitted their objections to the
claim statement and had also filed a counter claim as
follows:"a)
Declaring
that
the
Owner/Claimant/Petitioner's
share of Super Built up Area in the residential
project put up on the Schedule Property stands
reduced to 45,574.67 sq.ft., and 21,413.33 sq.ft.
sq.ft.
of
Owner/Claimant/Petitioner's
share
of
Super-Built up Area stands apportioned to the
Developer/Respondent's share,
b)
Directing the Owner/Claimant/Petitioner to execute
fresh
Sharing
Agreement,
incorporating
the
reduction of the Owner/Claimant/Petitioner's share
to
45,754.67 sq.ft.
Super-Built up Area, and
apportioning 21,413.33 sq.ft. sq.ft. of Super-Built
up Area, to the share of the Respondent, in relation
to the residential project put up on the Schedule
Property.
c)
Directing the Owner/Claimant/Petitioner to pay a
sum of Rs.4,72,80,130/- (Rupees Four Crores
Seventy Two Lakhs Eighty Thousand One Hundred
& Thirty only), to the Respondent towards GST,
Deposits/Pro-rata Charges, Maintenance Charges
and Electricity Charges,
d)
Directing the Owner/Claimant/Petitioner to pay
charges towards DG installation at the rate of
Rs.75/sq.ft. of his reduced SBA,
e)
Directing the Owner/Claimant/Petitioner to pay the
club
membership
charges
at
the
rate
of
Rs.5,00,000/- (Rupees Five Lakhs only) per flat,
and Rs.10,00,000/- (Rupees Ten Lakhs only) per
penthouse, as per the revised sharing agreement to
be
executed,
after
reduction
of
Owner/Claimant/Petitioner's share of SBA,
f)
Directing the Owner/Claimant/Petitioner to pay a
sum of Rs.10,00,00,000/- (Rupees Ten Crores
only)
to
indemnify
the
Respondent
for
the
violations committed by the Claimant/Petitioner
and
g)
Pass such other order/s as this Hon'ble Tribunal
deems fit, in the facts and circumstances of the
instant case."
4.
The learned sole arbitrator had considered the
contentions advanced on both sides and had rejected the
claim. The counter claim of the respondent was allowed in
part and a total amount of Rs.18,31,82,187/- was directed
to be paid by the claimant to the developer with 12%
interest
per
annum
from
date
of
claim
petition
till
realization. The said award was challenged by the appellant
by filing an application under Section 34 of the Arbitration
Act which also came to be dismissed after considering the
contentions elaborately.
5.
The present appeal is preferred challenging the
order of the trial Court dismissing Section 34 application.
6.
The learned counsel appearing for the appellant
submits that the order of the Trial Court is completely
erroneous and the Trial Court had not considered the serious
contentions raised by the appellant.
It is contended that
Section 34 application was dismissed without considering
the
valid
contentions
raised
by
the
appellant.
The
submissions of the appellant were not considered and the
errors committed by the learned Arbitrator which were
pointed out, were not taken note of.
It is contended that
the Trial Court disregarded the conspicuous absence of
substantive reasoning in the arbitrator's decision and the
lack of reasoning amounted to a patent illegality, which
vitiated
the award.
It is contended that Section 34 of
Arbitration Act permits the Competent Court to scrutinize
whether the award is vitiated by patent illegality or is
opposed to public policy. Since the present case comes
under the said category, the refusal to interfere was
completely unwarranted.
7.
It is further contended that the refusal on the
part of the trial Court to consider the contentions raised by
the appellant that the arbitrator has failed to apply the Real
Estate (Regulation and Development) Act, 2016 ('RERA' for
short) provisions and to impose penalties on respondent
No.1 for its delay amounts to a patent illegality that vitiates
the award. It is contended that despite the clear admission
that the developer had committed undue delay in obtaining
land sanction and in completion of the construction, the
claim was rejected without any proper reasoning.
8.
Further, it is contended that the action of the
learned arbitrator in allowing the unsubstantiated counter
claims raised by the developer was completely illegal and
unwarranted. It is submitted that these aspects of the
matter have also not been considered by the trial Court.
The finding of the arbitrator that time was not the essence
of the contract is clearly contrary to the express terms of
contract and though this aspect was specifically raised
before the trial Court, the same is completely ignored.
It is further contended that the trial Court has failed to
consider the appellant's status as an 'allottee' under Section
2(d) of the RERA Act and the said oversight being corrected,
the appellant would have been entitled to compensation
applying the provisions of the RERA Act.
9.
The learned counsel appearing for the appellant
has relied on the following decisions:•
Priyanka Taksh Sood And Ors. v. Sunworld
Residency Pvt. Ltd. and Anr., reported in 2022 SCC
OnLine Del 4717;
•
Experion Developers Pvt. Ltd. v. Sushma Ashok
Shiroor, reported in AIR 2022 SC 1824;
•
M/s. Imperia Structures Ltd. v. Anil Patni & Anr.,
reported in AIR 2021 SC 70;
•
Projector Director, National Highways No.45E &
220, National Highways Authority of India v.
M.Hakeem & Anr., reported in (2021) 9 SCC 1;
•
Skandia
Insurance
Co.
Ltd.,
v.
Kokilaben
Chandravadan & Ors., reported in (1987) 2 SCC
654;
•
Modern Hotel v. Commissioner of Central Excise
and Ors., reported in (2016) 15 SCC 620, and
•
Gayatri Balasamy v. ISG Novasoft Technologies
Ltd., reported in 2025 INSC 605.
10.
The
learned
senior
counsel
appearing
for
respondent No.1, on the other hand, submits that this Court,
considering
an
appeal
under
Section
37(1)(c)
of
the
Arbitration Act is not empowered to go into the merits of the
claim and to re-appreciate the evidence. It is further
contended that under Section 37 of the Arbitration Act, this
Court cannot travel beyond the restrictions laid down under
Section 34 of the Arbitration Act and cannot undertake an
independent assessment of the merits of the award.
11.
It is further contended that the grounds not
raised in a petition under Section 34 of the Arbitration Act
cannot be raised at the stage of appeal under Section 37 of
the Arbitration Act. Further, relying on the Circulars dated
31.10.2019 and 6.11.2019 issued by the RERA, it is
contended that individuals/organizations like landowners fall
within the term 'Promoter' or 'Promoters' under the RERA
Act and cannot claim the status of 'allottees'.
12.
It is further contended that an elaborate and in-
depth examination of the findings in the award is completely
unwarranted in an application under Section 37 of the
Arbitration Act and only patent illegalities that are apparent
in the award or in the proceedings under Section 34 of the
Arbitration Act can be corrected in Section 37 application as
well.
13.
The
learned
senior
counsel
appearing
for
respondent No.1 has placed reliance on the following
decisions:• Larsen & Toubro Ltd. v. Puri Construction Pvt.
Ltd. & Ors., reported in 2025 SCC OnLine SC 830;
• Haryana Tourism Ltd. v. Kandhari Beverages
Ltd., reported in (2022) 3 SCC 237;
• Delhi Airport Metro Express Pvt. Ltd. v. Delhi
Metro Rail Corporation Ltd., reported in (2022) 1
SCC 131;
• UHL Power Co. Ltd. v. State of Himachal Pradesh,
reported in (2022) 4 SCC 116;
• S.V.Samudram v. State of Karnataka & Anr.,
reported in (2024) 3 SCC 623;
• Somdatt Builders - NCC - NEC (JV) v. National
Highways Authority of India & Ors., reported in
2025 SCC OnLine SC 170;
• Gopal Krishan Rathi v. Dr. R.Palani, reported in
2025 SCC OnLine Mad 481;
• International Seaport Dredging Pvt. Ltd. v.
Kamarajar Port Ltd., reported in 2024 SCC OnLine
SC 3112;
• Shri. Lachoo Mal v. Shri. Radhey Shyam, reported
in 1971(1) SCC 619;
• The Director of Inspection of Income Tax
(Investigation), New Delhi & Anr. v. M/s. Pooran
Mal & Sons and Anr., reported in (1975) 4 SCC
568;
• H.R.Basavaraj & Anr. v. Canara Bank & Ors.,
reported in (2010) 12 SCC 458;
• Commissioner of Customs, Mumbai v. Virgo
Steels, Bombay & Anr., reported in (2002) 4 SCC
316;
• Sepco Electric Power Construction Corporation v.
Power Mech Projects Ltd., reported in 2022 SCC
OnLine SC 1243; and
• Manish v. Godawari Marathawada Irrigation
Development
Corporation,
reported
in
MANU/SCOR/30132/2018.;
14.
The case set up by the appellant in the claim
petition was that the appellant, who was the owner of the
scheduled property had entered into a Joint Development
Agreement with the respondent developer on 22.10.2012. A
Power of Attorney was also executed by the appellant in
favour of the respondent on 22.10.2012. A supplementary
agreement was also entered into on the same day, by which
an amount of Rs.10 Crores was paid as non-refundable
deposit and a further amount of Rs.15 Crores as refundable
deposit to the appellant.
However, it was contended that
the amounts stated in the supplementary agreement were
not paid.
15.
Later, a sharing agreement was entered into
between the parties on 01.07.2017. It was contended that
there was delay in commencement and completion of the
construction in terms of the Joint Development Agreement
dated 22.10.2012 and without completing the work, an
Occupancy Certificate was obtained by the developer on
05.12.2020.
appellant
to
Thereafter,
make
the
the
developer
refund
of
an
required
the
amount
of
Rs.11,12,90,253/-.
16.
The appellant claimed that there was an undue
delay in completing the project and loss caused to the
appellant by the respondent failing to achieve the maximum
Floor Area Ratio. It is contended that a Floor Area Ratio of
4.8 could have been achieved, but only a Floor Area Ratio of
4.19 was achieved by the respondent which resulted in loss
of Rs.10,05,48,000 /- to the appellant. Further, huge loss
was caused due to delay in completion of the project and
deducting the refundable deposit of Rs.7,50,00,000/- an
amount of Rs.47,46,17,454/- was claimed.
17.
The respondents, on the other hand, contended
that there were legal issues with regard to ownership and
possession of the land and there were outstanding liabilities
on the property which could not be cleared by the appellant.
It is submitted that the property was mortgaged to the IDBI
Bank
and
on
installments,
account
action
of
had
non-payment
been
of
initiated
the
loan
under
the
Securitisation and Reconstruction of Financial Assets and
Enforcement of Security Interest Act, 2002 ('SARFAESI Act'
for short) against the appellant.
The said amounts had to
be cleared and the documents released from the mortgagor
before possession could be taken by the developer and
further steps taken. It was contended that the original title
deeds and documents of the schedule property together with
possession of substantial portion of the property, was
handed over only on 20.07.2013 and the title deeds were
released
on
22.07.2013.
The
appellant
had
retained
possession of the old existing house in the schedule
property. Thereafter also, the suits filed before the City Civil
Court by M/s. Unishire Builtech LLP was withdrawn only on
16.10.2015. The necessary permissions for construction
were obtained and a revised plan for construction of two
levels
of
sanctioned
basement
on
with
11.01.2016.
ground
plus
floors
was
Thereafter,
the
respondent
requested the appellant to execute the sharing agreement
as per the Joint Development Agreement; but the appellant
refused and disputes arose between the parties.
18.
It
commenced
Certificate
is
submitted
only
was
in
issued
the
on
that
the
construction
was
year
and
Completion
10.10.2019
and
Occupancy
Certificate was issued in the year 2020. It was therefore
contended that there was no delay on the part of the
developer
in
either
commencing
or
completing
the
construction and the delay, if any, was occasioned due to
the actions of the appellant himself. The respondent had
also filed a counter claim contending that the refundable
deposit as per the agreement between the parties was not
being refunded by the appellant.
19.
The learned Arbitrator considered the contentions
of the parties and came to the definite conclusion that there
was no inordinate delay occasioned on the part of the
developer. It was specifically found that there were valid
reasons for the delay in commencement and completion of
the project which were not referable to the developer. The
learned Arbitrator specifically found that the period for
completion of the project is 30 months plus 6 months from
the date of issuance of Commencement Certificate.
The
date of Commencement Certificate - Ex.R32 was found to be
19.01.2017. As such, it was found that the period of
completion as per the terms of the Development Agreement
will
be
18.01.2020.
Relying
on
Ex.R41
-
Completion
Certificate dated 10.10.2019, the learned Arbitrator came to
the conclusion that the project was completed well within
time and that there was no delay in construction on the part
of the developer.
20.
On the basis of the pleadings, the evidence
adduced and the elaborate arguments advanced on both
sides, the sole Arbitrator found at paragraph No.61 of the
arbitral award, which reads as follows:"61. The main questions which require to be
considered in the light of the material on record,
arguments advanced are;
(i)
Who is responsible for the delay in the
completion of the project, the owner or the
developer?
(ii)
Whether the Claimant has made out a case
for the claim towards delay compensation as
per Section 18 of RERA 2016?
(iii)
Whether the developer has failed to achieve
FAR of 4.8?
(iv)
Whether the Claimant is entitled to the
amounts claimed?
(v)
Whether the Respondent is entitled to the
counterclaim?"
Thereafter, each of the aspects raised was considered
elaborately on the basis of the evidence placed on record.
Thereafter, it was specifically found that the respondent developer cannot be held responsible for the delay in
completion of the project and that the claimant has by his
conduct contributed to the delay.
21. Further, the question of Floor Area Ratio was
specifically considered in the Award. It was found that the
Floor Area Ratio achieved was 4.256 and that it was not on
an account of any fault of the respondent - developer that
the Floor Area Ratio of 4.8 could not be achieved. Further,
the question whether the appellant was entitled to be
treated as an allottee for payment of compensation under
the RERA Act was also specifically considered and rejected
by the learned Arbitrator.
It was further found that though
claims for damages had been raised, no evidence was placed
by the claimant to support his contentions. It was therefore
found that without clear proof of the loss caused to the
claimant, he could not claim compensation or damages from
the developer in terms of the agreements entered into
between the parties.
It was also found that the claimant
had specifically agreed to refund of the security deposit and
he could not produce any evidence to show that he had
refunded the said amount. Accordingly, the claim was
rejected and counter claim was partly allowed.
22.
In the application under Section 34 of the
Arbitration Act, filed by the appellant also, the same
contentions were raised by the appellant. The District Court
considering
the
challenge
specifically
adverted
to
the
contentions raised by the appellant and found that there was
no patent illegality vitiating the award which justifies
interference in terms of Section 34 of the Arbitration Act.
The contention that the appellant is to be considered as an
allottee under the RERA Act was also specifically considered
by the District Court as well.
23.
Having considered the contentions advanced on
either side, we notice that the Arbitral Award was passed
after considering the voluminous documents produced by
the parties on either side. The contentions of the parties
have been specifically considered by the learned Arbitrator.
In Section 34 application before the District Court also, the
contentions raised have been considered and it has been
found that there is no patent illegality vitiating the award. It
is a trite law that an examination in an appeal under Section
37 of the Arbitration Act, cannot travel beyond the scope of
an application under Section 34 of the Arbitration Act.
24.
We have given our anxious consideration to the
pleadings and the materials on record in the instant case.
We have also taken note of the decisions relied on by both
sides. It is abundantly clear that in view of the provisions of
the Arbitration Act, specifically Sections 34 and 37 thereof,
this Court, or for that matter, the District Court under
Section 34 of the Arbitration Act can interfere with an award
only in case, the specific grounds provided under Section
34(2) of the Arbitration Act are available. In the instant
case, we find that the appellant has not been able to
substantiate that the award was vitiated by any patent
illegality or that any of the other grounds provided in
Section 34 were made out. It is therefore clear that there
can be no re-appreciation of evidence or independent
assessment of the disputes raised before the arbitrator by
this Court exercising power under Section 37 of the
Arbitration Act.
25.
After considering the pleadings of the parties, the
Arbitral Award, the order of the trial Court, on an earnest
appraisal of the pleadings and the materials on record, we
find no error or patent illegality which requires a correction
in the award of the learned Arbitrator. The appeal fails and
the same is accordingly dismissed.
All
pending
interlocutory
applications
shall
disposed of.
Sd/(ANU SIVARAMAN)
JUDGE
Sd/(VIJAYKUMAR A. PATIL)
JUDGE
cp*
stand
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review