[2026:RJ-JP:9066]
HIGH COURT OF JUDICATURE FOR RAJASTHAN
BENCH AT JAIPUR
S.B. Civil Writ Petition No. 16910/2010
Mahavir Prasad Gupta S/o Shri Gopilal Gupta Age 39 Years, R/o
Brahmapuri, Anta, District Bara Rajasthan
----Petitioner
Versus
Commissioner
Panchayati
Raj
and
Secretary,
Department,
Rural
Development
Government
of
and
Rajasthan,
Government Secretariat, Rajasthan, Jaipur, by the State of
Rajasthan.
2. Commissioner, Mahatma Gandhi National Rural Employment
Guarantee Programme (MGNREGA), Government Secretariat,
Jaipur, Rajasthan.
3.
District
Mahatma
Programme
Collector
Gandhi
and
District
Programme
Coordinator
National
Rural
Employment
Guarantee
(MGNREGA)
Collectorate,
Room
No.
104,
Collectorate Baran Rajasthan.
4. Zila Parishad Baran By Chief Executive Officer & Additional
District Programme Coordinator (MGNREGA) Zila Parishad Baran,
District Baran Rajasthan.
5. Panchayat Samiti Anta by Development Officer Panchayat
Samiti Anta District Bara Rajasthan.
6. Development Officer and Programme Officer Mahatma Gandhi
National Rural Employment Guarantee Programme (MGNREGA)
Panchayat Samiti Anta District, Baran Rajasthan.
7. Deputy District Collector and Block Coordinator (MGNREGA)
Anta District Baran Rajasthan.
----Respondents
For Petitioner(s)
:
Mr. Pranava Sharma, Adv. for
Mr. Satyavarat Sharma, Adv.
For Respondent(s)
:
Mr. Keshar Singh Shekhawat, Adv.
HON'BLE MR. JUSTICE PRAVEER BHATNAGAR
Judgment
1. Date of conclusion of arguments
2. Date on which the judgment was reserved
3. Whether the full judgment or only the operative
part is pronounced
24/02/2026
24/02/2026
Full Judgment
(2 of 8)
[2026:RJ-JP:9066]
[CW-16910/2010]
4. Date of pronouncement
1.
27/02/2026
The petitioner has approached this Court by way of the
present writ petition, assailing the order dated 11.11.2010 passed
by the District Collector and District Programme Coordinator,
MGNREGA, Baran, whereby his contractual services as Accounts
Assistant have been terminated with immediate effect and has
also laid challenge to consequential order dated 15.11.2010
passed by the Development Officer and Programme Officer,
Panchayat Samiti Anta, directing that the work of Accounts
Assistant be assigned to another person.
2.
The material facts giving rise to the present dispute is that
on 27.02.2008 interviews were conducted by the District Council
for appointment to the post of Accounts Assistant under the
Mahatma Gandhi National Rural Employment Guarantee Scheme
(in short, ‘MGNREGA’) on contractual
basis. The petitioner
participated in the selection process and his name was reflected in
the merit list dated 24.03.2008 and in pursuance thereto he was
allotted Panchayat Samiti Anta.
3.
Subsequently, a service agreement was executed between
the petitioner and the competent authority and he was appointed
on a consolidated honorarium of Rs. 8,000 per month. The
petitioner underwent training on 01.04.2008 and thereafter, by
order dated 13.02.2009, the charge of MNREGA accounts was
handed over to him.
4.
On
22.07.2010,
a
show
cause
notice
was
issued
by
respondent No.3 to several officers including the petitioner,
(3 of 8)
[2026:RJ-JP:9066]
[CW-16910/2010]
alleging that payment had been made for compaction of soil in
gravel road works without competent approval. The petitioner
submitted his reply on 30.07.2010 denying the allegations and
stating that he had merely processed bills after due certification
and approval by the competent authorities.
5.
It is the case of the petitioner that without conducting any
regular enquiry and without affording him opportunity of personal
hearing, the respondent No.3 passed the impugned order dated
11.11.2010 terminating his services with immediate effect, though
his contractual tenure was valid up to 28.02.2011. Consequently,
by order dated 15.11.2010, his duties were assigned to another
Accounts Assistant.
6.
Learned
counsel
for
the
petitioner
contends
that
the
impugned order is arbitrary and violative of the principles of
natural justice. It is submitted that though a show cause notice
was issued, no enquiry was conducted, no findings were recorded
after proper consideration of the reply and no opportunity of
personal hearing was granted prior to termination.
7.
It is further submitted that the petitioner was merely an
Accounts Assistant discharging ministerial and procedural duties.
The sanction of works, technical approval, certification in the
measurement book and approval of payment were within the
exclusive domain of the Junior Technical Assistant, Assistant
Engineer and Programme Officer and the petitioner had no
authority to sanction work or approve technical estimates.
8.
Learned counsel argues that payments were released strictly
after written approval by the Programme Officer and that cheques
(4 of 8)
[2026:RJ-JP:9066]
[CW-16910/2010]
were signed jointly with the competent authority. It is contended
that all documents on record demonstrate that the petitioner
acted strictly in accordance with established financial procedure.
9.
It is further argued that the allegations in the termination
order go beyond the scope of the show cause notice. While the
notice alleged absence of prior approval for compaction, the
termination order attributes misuse of government funds and
serious irregularity, which were never specifically put to the
petitioner.
10.
Learned counsel also submits that as per the contractual
terms, termination required one month’s notice or payment of
honorarium in lieu thereof. The services of the petitioner have
been terminated with immediate effect without compliance of the
said condition. Furthermore, the petitioner’s contractual tenure
was subsisting till 28.02.2011 and termination prior to expiry of
the
term,
without
due
process
and
without
adherence
to
contractual safeguards and the same is arbitrary and violative of
Articles 14 and 21 of the Constitution of India. Therefore, it is
prayed that the impugned order may be quashed and set aside
and petitioner be reinstated with continuity of service and all
consequential benefits.
11.
Per
contra,
learned
counsel
for
the
respondents
has
supported the impugned order and submitted that serious
financial irregularities were detected in the execution and payment
of compaction works under the scheme of MGNREGA. The
compaction work was undertaken without competent sanction and
payments were released in violation of financial norms.
[2026:RJ-JP:9066]
12.
(5 of 8)
[CW-16910/2010]
Learned counsel contends that the petitioner, being Accounts
Assistant and joint signatory to cheques, was under obligation to
ensure compliance with financial rules and to prevent illegal
disbursement of government funds. It is argued that he failed to
discharge his duties diligently and facilitated release of payments
despite lack of proper sanction.
13.
It is further submitted that a show cause notice was duly
issued to the petitioner and his reply was considered. Upon
consideration of the material available on record, the competent
authority found that irregular payments had been made and
thereafter contractual services of the petitioner were terminated.
14.
It is also contended that the petitioner was engaged purely
on contractual basis and had no vested right to continue till expiry
of the contractual term. It is urged that in contractual matters,
particularly in cases involving financial irregularity, the scope of
judicial review is limited and the Court ought not to interfere
unless the action is shown to be patently arbitrary or malafide.
Hence, it is prayed that the present writ petition deserves
dismissal.
15.
Heard and perused the material available on record.
16.
It is not in dispute that the present matter arises out of a
purely contractual relationship between the parties. The petitioner
was engaged on contractual basis under the scheme of MGNREGA
and his engagement was governed by a service agreement
executed between the parties.
17.
The scope of this Court while exercising its power under
Article 226 is limited when it comes to adjudication of contractual
[2026:RJ-JP:9066]
(6 of 8)
[CW-16910/2010]
claims. In this regard, the Hon’ble Apex Court in the case of Joshi
Technologies International Inc. v. Union of India, (2015) 7
SCC 728, has held as under:“55. Law in this aspect has developed through catena
of judgments of this Court and from the reading of
these judgments it would follow that in pure
contractual matters the extraordinary remedy of
writ under Article 226 or Article 32 of the
Constitution cannot be invoked. However, in a
limited sphere such remedies are available only
when the non-Government contracting party is
able to demonstrate that it is a public law remedy
which
such
party
seeks
to
invoke,
in
contradistinction to the private law remedy
simpliciter under the contract. Some of the case law
to bring home this cardinal principle is taken note of
hereinafter.
56. Significantly, in Andi Mukta Sadguru Shree
Muktajee
Vandas
Swami
Suvarna
Jayanti
Mahotsav Smarak Trust v. V.R. Rudani [(1989) 2
SCC 691] as well, this Court made it clear that if
the rights are purely of private character, no
mandamus can be issued. Thus, even if the
respondent is “State”, the other condition which
has to be satisfied for issuance of a writ of
mandamus is the public duty. In a matter of
private character or purely contractual field, no
such public duty element is involved and, thus,
mandamus will not lie.
69. The position thus summarised in the aforesaid
principles has to be understood in the context of
discussion that preceded which we have pointed out
above. As per this, no doubt, there is no absolute bar
to the maintainability of the writ petition even in
contractual matters or where there are disputed
questions of fact or even when monetary claim is
raised. At the same time, discretion lies with the
High Court which under certain circumstances, it
can refuse to exercise. It also follows that under
the following circumstances, “normally”, the
Court would not exercise such a discretion.”
[2026:RJ-JP:9066]
18.
(7 of 8)
[CW-16910/2010]
It is also well established that while exercising jurisdiction
under Article 226 of the Constitution of India, this Court does not
sit as an appellate authority over administrative or disciplinary
decisions. The scope of judicial review is confined to examining
the decision-making process and not the merits of the decision
itself. The Hon’ble Supreme Court in the case of Union of India
v. P. Gunasekaran, (2015) 2 SCC 610, held as under:“13. Under Articles 226/227 of the Constitution of
India, the High Court shall not:
(i) reappreciate the evidence;
(ii) interfere with the conclusions in the enquiry,
in case the same has been conducted in
accordance with law;
(iii) go into the adequacy of the evidence;
(iv) go into the reliability of the evidence;
(v) interfere, if there be some legal evidence on which
findings can be based.
(vi) correct the error of fact however grave it may
appear;
(vii) go into the proportionality of punishment unless it
shocks its conscience.”
(Emphasis Supplied)
19.
It is equally well settled that in matters of termination of
contractual engagement, the Court would interfere only if the
action is shown to be arbitrary, malafide or in violation of statutory
or constitutional provisions. In the present case, it is borne out
from the record that a show cause notice dated 22.07.2010 was
issued to the petitioner detailing the allegations relating to
irregular release of payments in respect of compaction works
under MGNREGA and the petitioner submitted his reply on
30.07.2010. The allegations against the petitioner pertained to
financial irregularities and improper release of government funds
in his capacity as Accounts Assistant and joint signatory to
[2026:RJ-JP:9066]
(8 of 8)
[CW-16910/2010]
cheques. The petitioner was put to notice of the allegations and
was afforded the opportunity to submit his explanation and the
competent authority, upon consideration of the material on record
and the reply submitted by the petitioner, formed its satisfaction
that the petitioner had failed to discharge his contractual
obligations diligently.
20.
Therefore, considering the peculiar facts of the present case
and the precedents laid down by the Hon’ble Apex Court, this
Court is of the considered opinion that no ground for interference
under Article 226 is made out.
21. Accordingly, the instant writ petition, being devoid of merit, is
hereby dismissed.
22.
All pending application(s), if any, also stand disposed of.
There shall be no order as to costs.
(PRAVEER BHATNAGAR),J
Ashwani Kr Srivastava /-215
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review