Result
Dismissed
Bench
Venkateswarlu Nimmagadda
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

12. By observing the same, the suit was dismissed. It is settled legal position that any aggrieved party cannot invoke simultaneous jurisdiction before the concerned authority/Court below and before the constitutional courts under the extraordinary jurisdiction. Moreover, the appeal filed by the petitioner before the respondent No.2 already disposed of and the same was recorded in proceedings of the suit itself. Therefore, the fact remains that the petitioner approached different forums, more particularly, the court below contrary to the scheme of the Act. In view of the same, the petitioner is not entitled for any consideration to grant any relief. Accordingly, the Issue No.II held against the petitioner

13. In view of the foregoing discussion and on perusal of the material placed record, this Court is of the view that there are no merits in the present writ petition and is liable to dismissed.

14. Accordingly, the present Writ Petition is dismissed. There shall be no order as to costs. As a sequel, miscellaneous applications pending, if any, shall also stand closed.

Filed under

Constitution of India Code of Civil Procedure, 1908 Electricity Act, 2003 Article 226, Constitution of India Section 151, Code of Civil Procedure, 1908 Section 126, Electricity Act, 2003

The sections, explained

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

HIGH COURT OF ANDHRA PRADESH **** WRIT PETITION NO: 20259/2013 Between: 1. M/S. YATI SOFTY, REP. BY ITS PARTNER Y.SRINIVAS S/O DORAYYA, AGED 48 YEARS, RIO D.NO.2-2-8, SRI NAGAR, KAKINADA, EAST GODAVARI DISTRICT. .....PETITIONER AND 1. THE ANDHRA PRADESH EASTERN POWER DISTRIBUTION COMPANY LTD, REP. BY ITS CHAIRMAN AND MANAGING DIRECTOR, VISAKHAPATNAM and 3 OTHERS. .....RESPONDENTS DATE OF JUDGMENT PRONOUNCED : DATE OF JUDGMENT UPLOADED : 09.07.2026 SUBMITTED FOR APPROVAL: THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA 1. Whether Reporters of Local newspapers may be allowed to see the Judgments? Yes/No 2. Whether the copies of judgment may be marked to Law Reporters/Journals Yes/No 3. Whether Your Lordships wish to see the fair copy of the Judgment? Yes/No _________________________________ VENKATESWARLU NIMMAGADDA, J * THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA + WRIT PETITION NO: 20259/2013 % 09.07.2026 Between: 1. M/S. YATI SOFTY, REP. BY ITS PARTNER Y.SRINIVAS S/O DORAYYA, AGED 48 YEARS, RIO D.NO.2-2-8, SRI NAGAR, KAKINADA, EAST GODAVARI DISTRICT. .....PETITIONER AND 1. THE ANDHRA PRADESH EASTERN POWER DISTRIBUTION COMPANY LTD, REP. BY ITS CHAIRMAN AND MANAGING DIRECTOR, VISAKHAPATNAM and 3 OTHERS. .....RESPONDENTS !Counsel for the petitioners : Sri P.Narasimha Rao ^Counsel for the respondents : Sri V.V.Satish (SC for APEPDCL) Sri Metta Chendra Sekhar Rao < Gist : > Head Note: ? Cases Referred: 1. 2009 (4) CCC 279 (Kar.) APHC010523352013 IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3329] THURSDAY, THE 9th DAY OF JULY 2026 PRESENT THE HONOURABLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 20259/2013 Between: 1. M/S. YATI SOFTY, REP. BY ITS PARTNER Y.SRINIVAS S/O DORAYYA, AGED 48 YEARS, RIO D.NO.2-2-8, SRI NAGAR, KAKINADA, EAST GODAVARI DISTRICT. ...PETITIONER AND 1. THE ANDHRA PRADESH EASTERN POWER DISTRIBUTION CO LTD, REP. BY ITS CHAIRMAN AND MANAGING DIRECTOR, VISAKHAPATNAM. 2. THE CHIEF GENERAL VISAKHAPATNAM. MANAGER, 3. THE SUPERINTENDENT VISAKHAPATNAM. O & CS ENGINEER, A.P.E.P.D.C.L, A.P.E.P.DE.L. 4. THE ASSISTANT DIVISIONAL ENGINEER, OPERATION, TOWN -1, A.P.E.P.D.C.L. KAKINADA, E.G.DISTRICT ...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue a Writ, order or direction, especially one in the nature of Writ of Certiorari calling for the records relating to proceedings vide No.CGM/O&Cs/EPDCLNSP/O&M-II/MP case/D.No. 1890/11 dated 27-6-2011 confirming the proceedings of the 3rd respondent vide Lr.No. SE/A/VSP/C.VSP/D.KDA/SD.T1-KDA/PF. 2927/D.No 1197/ dated 24-3-2011 as illegal, arbitrary, violative of Sec 126 of the I.E.Act 2003 and General Terms and Conditions made thereunder and consequently set aside the proceedings of the 2nd respondent No.CGMIO&Cs/EPDCL/VSP/O&M-II /MP case/ D.No. 1890/11 dated 27-6-2011 and pass. IA NO: 1 OF 2013(WVMP 2960 OF 2013 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to vacate the interim Orders passed on 12-07-2013 W.P.M.P.No. 24857 of 2013 in W.P No. 20259 of 2013 IA NO: 2 OF 2013(WPMP 24459 OF 2013 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to dispense with the filing of original proceedings No. CGM/O&Cs/EPDCL/ VSP/O&M-II/MP case/D.No. 1890/11 dated 27-06-2011 and pass. IA NO: 3 OF 2013(WPMP 24857 OF 2013 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to direct the respondents not to disconnect the power supply to S.C.No. 505029828 of M/s Yati Softy pending disposal of the above writ petition and pass. Counsel for the Petitioner: 1. P NARASIMHA RAO Counsel for the Respondent(S): 1. V V SATISH (SC for APEPDCL) 2. METTA CHENDRA SEKHAR RAO The Court made the following: THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 20259 OF 2013 ORDER:This writ petition is filed under Article 226 of the Constitution of the India seeking the following reliefs:“to issue a Writ, order or direction, especially one in the nature of Writ of Certiorari calling for the records relating to proceedings vide No.CGM/O&Cs/EPDCL/VSP/O&M-II/MP case/D.No.1890/11 dated 27.6.2011 confirming the proceedings of the 3rd respondent vide Lr.No. SE/A/VSP/C. VSP/D.KDA/SD.T1-KDA/PF.2927/D.No.1197/dated 24.3.2011 as illegal, arbitrary, violative of Sec 126 of the I.E.Act, 2003 and General Terms and Conditions made thereunder and consequently set aside the proceedings of the 2 nd respondent No.CGM/O&Cs/EPDCL/VSP/O&M-II /MP case/ D.No.1890/11 dated 27.6.2011 and pass such other order or orders….” 2. Heard learned counsel for the petitioner and the learned Standing Counsel for the respondents. 3. The case of the petitioner herein is that the respondent No.3 passed final assessment order dated 24.03.2011 pursuant to the provisional assessment order passed by the respondent No.4 without providing an opportunity of hearing and without following the due procedure as contemplated under Section 126(3) of the Electricity Act, 2003, which is contrary to the scheme of the Act. 4. Learned counsel for the petitioner submits that in similar circumstances, the Hon’ble High Court of Karnataka in M.P.Sreenath Gupta v. The Assistant Executive Engineer (EI), Bangalore Electricity Supply Company TRD, W3 Sub-Division, Bangalore and Anr.1, held as follows: “When once an opportunity is accorded to the consumer to respond to the provisional assessment order, it is very necessary that the order should be one which gives all details about the manner of arriving at the demanded amount and not a cryptic or non-speaking order without reasons which the consumer will not be able to respond. The requirement of providing opportunity to the consumer to offer his explanation and thereafter the authority to hear the petitioner, consider the objections and then to pass order cannot be empty formality as unless a provisional order indicates the reasons and circumstances under which the amount is demanded and arrived at, it will not be possible for the consumer to respond to the provisional demand.” 5. He further submits that in the instant case, the respondents not followed the procedure of providing opportunity to the petitioner to submit his explanation and opportunity of hearing pursuant to the orders passed by the Hon’ble High Court of Karnataka as referred supra. Therefore, the impugned order/final assessment order dated 24.03.2011 passed by the respondent No.3 and the order dated 27.06.2011 passed in appeal filed by the petitioner confirming the order of the respondent No.3 dated 24.03.2011 are liable to be set aside. 6. On the other hand, learned Standing Counsel for the respondents filed counter affidavit, wherein, the relevant portion of the said counter-affidavit is extracted hereunder: 2009 (4) CCC 279 (kar.) “It is to submit that the 4th Respondent on the strength of the findings recorded by him during the course of inspection and by virtue of powers vested in him made a provisional assessment of malpractice charges under Cat II as per the provisions of Sec 126 of Electricity Act, 2003 in a sum of Rs.3,93,220/- and demanded payment of the same providing an option to the Petitioner to pay 50% of the same i.e., Rs.1,96,610/- + Rs.150/- towards supervision charges if the Petitioner was desirous of continuity of supply. The Petitioner was also provided to make a representation before the competent authority within 15 days on receipt of the P.A notice if he was not agreeable with the assessment. The Petitioner paid 50% of the P.A notice amount and availed continuity of supply pending enquiry of the competent authority. 5. It is to submit that the 3rd Respondent after providing a full and fair opportunity to the petitioner passed his Final assessment Order dated 24.03.2011 finally assessing the final liability at Rs.4,25,021/- further providing an opportunity to the petitioner to prefer an appeal to the 2nd Respondent. 6. It is to submitted that the 2nd Respondent after giving a personal hearing to the Petitioner and his Counsel and on consideration of entire material placed before him, passed his appellate order dated 27.06.2011 modifying the final assessment order. It is submitted that the 2nd Respondent passed a speaking order on 27.06.2011 finally assessing the malpractice charges. The allegations that the Respondents 2 & 3 have passed their respective Orders without providing any opportunity is untrue and untenable. It is submitted that the Petitioner filed O.S No.1/2011 on the file of the Special Court namely the 1st Addl. District Court:: East Godavari for a declaration that the final assessment order dated 24.03.2011 and the appellate order dated 27.06.2011 are illegal and arbitrary and for permanent injunction restraining the Respondents from disconnecting the service. It is submitted that on the contentions raised by the Respondents, among others that the Petitioner is not entitle to invoke the Special Court's jurisdiction in relation to the malpractice of energy and that that suit is barred under Sec 126 & 127 and 145 of Electricity Act, 2003, the Special Court decided the issue relating to the jurisdiction vide its Order made in I.A No. 3027/2012 and rejected the suit as not maintainable. Heard both the learned counsels and perused the material placed on 7. record. The issues fell for consideration before this Court are as follows: I. Whether the respondents herein followed due procedure as contemplated under Section 126(3) of the Electricity Act, 2003 or not? II. Whether the petitioner can invoke simultaneous jurisdiction challenging the same impugned proceedings under the scheme of the Act or not? Issue No.I: 8. For determination of Issue No.I, it is appropriate to extract Section 126(3) of the Electricity Act, 2003, which reads as follows: 126.Assessment:3) The person, on whom an order has been served under subsection (2), shall be entitled to file objections, if any, against the provisional assessment before the assessing officer, who shall, after affording a reasonable opportunity of hearing to such person, pass a final order of assessment within thirty days from the date of service of such order of provisional assessment, of the electricity charges payable by such person. (4) Any person served with the order of provisional assessment may, accept such assessment and deposit the assessed amount with the licensee within seven days of service of such provisional assessment order upon him.” 9. On perusal of the section 126(3) of the Act, 2003, it is evident that after issuance of provisional assessment order by the authority, the petitioner should be provided an opportunity of hearing or for submission of objections. After such submission, the same would be considered and a final assessment order shall be passed by the authority concerned. In the instant case, the facts placed before this Court appears that the provisional assessment order was issued on 23.09.2010 while assessing provisional unauthorized drawing of electricity by the petitioner. It is also observed that the petitioner was specifically called for submission of objections/representations to the final assessment of the liability within a period of 15 days. It seems that the petitioner availed the same and submitted his objections and also provided with opportunity of hearing by way of letter dated 31.01.2011. After considering the objections as well as provisional assessment order, the authority passed his final assessment order dated 24.03.2011 increasing the amount payable by the petitioner from the provisional assessment amount is of Rs.3,93,370/- to Rs.4,25,021/-. While passing the final assessment order, the petitioner was also informed that it is an appealable order and the appeal lies to the Chief General Manager, Visakhapatnam. It is further observed that the appeal also filed before the respondent No.2 herein and petitioner was issued notice and contested in the appeal. After hearing both the parties, the appellate authority passed final orders dated 27.06.2011 revising the final assessment orders and directed the petitioner to pay the total amount of Rs.3,91,480/- . As such, the petitioner is liable to pay an amount of Rs.3,91,480/-. 10. On perusal of the entire proceedings as filed before the Court, it indicates the petitioner was provided an opportunity not only for submission of objections and representation but also provided opportunity of hearing and the same was considered and the amount was assessed by the authority and was revised in the final assessment order. The amount in the final assessment order was revised in the order of the appeal after considering the objections of the petitioner. Therefore, all these facts and proceedings indicates that the respondents observed Section 126(3) of the Electricity Act, 2003. Hence, the Issue No.1 is held against the petitioner. Issue No.II 11. For determination of Issue No.II, it is observed that the petitioner invoked the jurisdiction of the trial Court by way of O.S.No.1 of 2011 on the file of Special Court namely I Additional District Judge, East Godavari, Rajahmundry. The suit was dismissed by holding as under: “The cause of action for the suit arose on 21st September 2010 when the Assistant Divisional Engineer Operation Town-1 Kakinada of the defendant company inspected the schedule property and alleging that the plaintiff misused the electrical service connection from industrial load the commercial load and thereafter on 23rd September, 2010 made a provisional order and thereafter on 24th March, 2011 when the Superintendent Engineer made final order and thereafter when the plaintiff preferred an appeal before Chief General Manager, Visakhapatnam and on 27th May, 2011 when the Chief General Manager passed orders dismissing the appeal and now when the defendants are trying to collect the amount from the plaintiff under threat of disconnecting the supply to the plaint schedule property at Kakinada where the plaint schedule property is situated within the jurisdiction of this Court.” 12. By observing the same, the suit was dismissed. It is settled legal position that any aggrieved party cannot invoke simultaneous jurisdiction before the concerned authority/Court below and before the constitutional courts under the extraordinary jurisdiction. Moreover, the appeal filed by the petitioner before the respondent No.2 already disposed of and the same was recorded in proceedings of the suit itself. Therefore, the fact remains that the petitioner approached different forums, more particularly, the court below contrary to the scheme of the Act. In view of the same, the petitioner is not entitled for any consideration to grant any relief. Accordingly, the Issue No.II held against the petitioner 13. In view of the foregoing discussion and on perusal of the material placed record, this Court is of the view that there are no merits in the present writ petition and is liable to dismissed. 14. Accordingly, the present Writ Petition is dismissed. There shall be no order as to costs. As a sequel, miscellaneous applications pending, if any, shall also stand closed. ________________________________ VENKATESWARLU NIMMAGADDA, J Date:09.07.2026 Note: L.R. copy be marked (B/o) BSP THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA WRIT PETITION NO: 20259 OF 2013 Date:09.07.2026 Note: L.R. copy be marked (B/o) BSP