Serial No. 23
Regular List
HIGH COURT OF MEGHALAYA
AT SHILLONG
WP(C) No. 10 of 2019
Date of Decision : 09.09.2019
Vs.
M/S T.K. Engineering
Consortium Pvt. Ltd.,
The Union of India & 6 Ors.
Coram:
Hon’ble Mr. Justice H. S. Thangkhiew, Judge
Appearance:
For the Petitioner(s)
:
Mr. S.S. Dey, Sr. Adv. with
Ms. T. Yangkyi, Adv.
For the Respondent(s)
:
Ms. A. Paul, ASG with
Ms. R. Dutta, Adv.
i)
Whether approved for reporting in
Law journals etc.
ii)
Whether approved for publication
in press:
1.
Yes/No
Yes/No
The petitioner has filed the instant writ petition challenging the
termination letter dated 17.01.2019 issued by the General Manager
(Airports), RITES Ltd. whereby the Contract Agreement No.
RITES/AP/ICP/DAWKI/2016/10150 dated 30.09.2016 for the work of
“Development of Integrated Check Post at Dawki (Meghalaya) along
Indo-Bangladesh Border” is sought to be terminated by the respondents.
2.
The brief facts of the case are that the petitioner was awarded the
work of “Development of Integrated Check Post at Dawki (Meghalaya)
along
Indo-Bangladesh Border” vide Contract Agreement No.
RITES/AP/ICP/DAWKI/2016/10150 dated 30.09.2016. The duration of
the project was 2 years and the site was handed over to the petitioner
contractor on 18.11.2016. It is the case of the petitioner that the cause of
WP(C) No. 10 of 2019
delay are attributable to respondents, inasmuch as, part of the project site
where the main check gate and where the major part of the construction
is to be carried out, was not handed over to the petitioner. The other
contention of the petitioner is that there were changes in revised
architectural drawings and designs of the integrated check post, lay out
plan and also that there was delayed clearances from Forest Department
and Mining Departments, apart from the obstruction to construction due
to some land disputes of the local people. In spite of the hurdles, the
petitioner contends that more than 52-53% of the work as stipulated in
the contract has been completed.
It is the further case of the petitioner that the respondents are
trying to allot the remaining work to other contractors in a nontransparent manner, at the risk and cost of the petitioner and even the
bank guarantee of Rs. 3,31,34,743/- (Rupees Three Crore Thirty One
Lakh Thirty Four Thousand Seven Hundred Forty Three) only, has
already been encashed and the petitioner served with impugned
cancellation order dated 17.01.2019.
3.
The respondents No. 3 to 6 had filed an affidavit dated 11.02.2019
questioning the maintainability of the writ petition on the following
counts: (a) That there is an arbitration clause in the agreement, (b) That
as per Clause 46.17 of the contract agreement, the Courts in the City as
specified in Schedule „F‟ alone shall have the jurisdiction, and on
account of the jurisdiction ouster clause, only the Courts in New Delhi
would have jurisdiction; and (c) That the present writ petition involves
complex disputed questions of fact and the same cannot be decided in a
writ proceeding.
4.
This Court has however looking into the urgency and nature of the
matter and on being prima facie satisfied had ruled by order dated
02.04.2019 that the writ was maintainable and as such this matter has
come to be finally heard on merits.
5.
However, a most pertinent fact that is noted at this juncture, is that
the contractual period by the efflux of time including even the extended
period, that had been allowed to the writ petitioner, that is till
WP(C) No. 10 of 2019
28.05.2019, has since lapsed. This being the situation as it pertains,
together with the fact that there has been no further extension of the
contract, the scope of deliberation and consideration of the instant case,
will essentially be limited to the point as to whether the term of contract
can be held to have expired and the effect it will have on the competing
rights and claims of the parties.
6.
Heard Mr. S.S. Dey, learned Senior Counsel assisted by
Ms. T. Yangkyi, learned counsel for the petitioner, on the main question
of the time period for execution of the work. In this regard written
arguments has been filed in support of his contentions, that the period of
24 months as referred in the Work Order dated 30.09.2016 is to be
counted with effect from the Date of Start which he submits is the date
of handing over site, and not 15 days from date of the Letter of
Acceptance. The points as put forward in the written argument is
reproduced herein below :(a) That as per Work Order dated 30.09.2016 (Annexure-2 Page 25
of writ petition) “the time of 24 (Twenty Four) months allowed
for execution of the work will be reckoned from the date of start
as defined in Schedule „F‟ or from the first day of the handing
over of site, whichever is later ..”
(b)
That further as per definition of „Date of Commencement of the
Work‟ (Section 7 Conditions of Contract at Page 50 of writ
petition) “it will be the date arrived at after providing for the
Mobilization period as stipulated in Schedule F or the first date
of handing over of site whichever is later. Time allowed for
execution of the work will be reckoned from the date of
commencement of works”.
(c) That Schedule „F‟ as referred to above is at Page 109 of the
Contract Agreement filed separately. Clause 2 (xiii) stipulates
Date of commencement of work as “15 days from the date of
issue of LOA or the first date of handing over of site whichever
is later.” Clause 5.1 (a) stipulates Time allowed for execution of
work as “24 months (Twenty Four Months)” and Date of start as
WP(C) No. 10 of 2019
“15 days from the date of issue of Letter of Acceptance or the
first date of handing over of site whichever is later”.
(d) That Clause 1.5 under Section 1 of the Contract Agreement at
Page 55 the Availability of Site is stipulated as “the complete
land for ICP construction site shall be handed over to contractor
in one go at the beginning of the project itself”. The option given
in the porfoma for handing over of sites in parts has been
consciously struck out.
7.
Learned counsel submits that, a conjoint reading of the
aforesaid provisions of the bipartite Contract between the parties
unambiguously provides that the period of „24 months‟ as referred to in
the Work Order dated 30.09.2016 has to be counted and reckoned with
effect from the Date of Start, which is the first date of handing over of
site (not 15 days from the date of Letter of Acceptance as the Contract
stipulates execution of work after handing over of the Site). He submits
that the ambit of the term „handing over of site‟ has to be read
meaningfully in terms of Clause 1.5, meaning thereby, that „handing
over‟ will mean de facto completion of the process of handing over of
the „complete land for ICP construction site‟ to the contractor in one go
at the beginning of the project itself. He submits once the „complete
land‟ as stipulated in Clause 1.5 has been totally handed over, then the
first date of such process of handing over, will be reckoned to be the
Date of Start for counting the period of 24 months.
8.
The learned senior counsel then refers to the letter dated
30.05.2017 issued by the respondent No. 5, which had informed the
petitioner that the issues with regard to the work beyond 40 meters of
zero line, had been resolved, and the petitioner instructed to increase
work mobilization accordingly. He submits that this letter signifies that
the project site, which was to be handed over to the petitioner for
construction included the 40 meters from the zero line was yet to be
handed over, and as such, he submits that even on the date of the letter,
the complete land for ICP construction site, had not been handed over.
He further submits that as the process of handing over was not complete,
WP(C) No. 10 of 2019
no first date can positively be fixed to signify as „Date of Start‟ so as to
start counting of the 24 months period.
9.
The learned Senior counsel also submits that the averments
made at Para-7 of the affidavit-in-opposition were to be noted, inasmuch
as, he contends that the respondents had themselves stated that there is
no due date of handing over of site, mentioned in the agreement. The
learned senior counsel further submits that, time being the essence of the
contract, the provisions of the contract are to be rigidly applied. He
submits that on a plain reading of the provisions thereof, it would reflect
that the terms contained therein, are clear and unambiguous and cannot
be interpreted differently. The learned senior counsel then reiterates the
other points as raised, with regard to the late change of drawing, design,
layout plan and also other factors which he contends have attributed to
the undue delay of the project, which cannot be attributed to the writ
petitioner. He lastly submits that the contract is subsisting in view of the
submissions so placed, and also taking into consideration the delay
caused by the respondents, the letter of termination is arbitrary and not
maintainable.
10.
Ms. A. Paul, learned ASG for the respondents opens her
submissions by submitting that as the contract between the parties had
expired on 28.05.2019, the instant writ petition has become infructuous.
However, in reply to the submissions of the learned senior counsel for
the petitioner, she submits that the Letter of Acceptance (LOA) for the
subject contract, was issued to the petitioner on 30.09.2016 at a value of
Rs. 66.27 crores. She then draws the attention of this Court to the Clause
2 (xiii) of Section 4, Schedule F of the Agreement at Page 109, which
provides that the date for commencement of work shall be 15 days from
the date of issue of LOA, or the „first date of handing over of the site‟
whichever is later.
11.
The learned ASG further submits that after issuance of the
LOA on 30.09.2016, the writ petitioner failed to report to take over the
site, and it was only on 18.11.2016, that the same could be done. She
further submits that since the delay was caused by the contractor, the
date of commencement therefore, will have to be taken to be from
WP(C) No. 10 of 2019
15.10.2016, which is 15 days from issuance of LOA, as was agreed upon
by both the parties. She also submits that the culpability of the petitioner
in the delay is illustrated by letter dated 27.09.2016, whereby the
petitioner had requested the respondents for the postponement of
issuance of the LOA, on the ground the it was not in a position to furnish
the Performance Guarantee as per the contract agreement.
12.
The learned ASG then refers to Annexure-21 at page 104 of
the writ application, and submits that the writ petitioner never disputed
that the date of commencement of the work was 15.10.2016, inasmuch
as, the said document recording the same, has been countersigned by the
authorized representative of the writ petitioner. She also submits that as
per the LOA, the contract period for the work was 24 months from the
date of commencement as defined in Schedule F of the contract
agreement, and therefore, the contract would have terminated on
24.10.2018 after 24 months. However, she submits, as the writ petitioner
had sought extension for another 264 days, the respondents by letter
dated 27.06.2018 (Annexure 7 of the affidavit-in-opposition) had
extended the time for completion of the work up to 28.05.2019, without
any levy of liquidated damages in terms of Clause 5 of the agreement
dated 30.09.2016. She further submits that thereafter the writ petitioner
never sought further extension and as such, this being the situation, the
contract did not subsist thereafter and stood automatically terminated.
13.
With regard to the other contentions of the writ petitioner
that the architectural drawings had been changed by the respondents on
16.01.2019 and termination issued on 17.01.2019, the learned ASG
submits that the same was of no consequence or relevance, inasmuch as,
it pertained to only one Guard Room and its attached toilet in the
Entrance Gate No. 2 of the Integrated Check Post. She submits it was not
as if the entire dimension and location of the project was changed. She
further submits that the miniscule revision had no impact in the progress
of the work, as the petitioner had done the work only up to the
foundation, and that work on the super structure had not even been
started by the petitioner.
WP(C) No. 10 of 2019
14.
The learned ASG then submits that another aspect that
clearly portrays the laches of the contractor/writ petitioner insofar as
timely execution of the work concerned, is borne out by the fact that
though the total value of the contract is Rs. 66.26 crores as on
14.01.2019, the writ petitioner had submitted a third running account bill
for a sum of Rs. 6,29,78,848.46p (6.29 crores) which is only about 1/10th
of the project cost. She further submits that such delay in such type of
projects which is for the development of the Integrated Check Post at
Dawki (Meghalaya) along the Indo-Bangladesh Border, which involves
public interest, as well as security concerns, cannot be held up or
relegated to a slow pace due to the petitioner. To conclude her
submissions, the learned ASG submits that entering into any other
dispute as raised by the writ petitioner, will be a futile exercise at this
stage, more so when Clause 25 of the contract agreement provides for
settlement of all disputes arrived at by the contractual agreement through
arbitration. She further submits that the contract had since been expired
and the writ petitioner having recourse to other remedy, the writ petition
should be dismissed.
15.
In support of her submissions, the learned ASG has relied on the
following:i)
WP(C) No. 127 of 2018 (Arunnachala Impex Pvt. Ltd vs.
Union of India & Ors.) Para 3
ii)
OMP 523 of 2008 (Lt. Col. (retd.) K.S. Ahluwalia vs.
Indraprastha Gas Ltd.) Para 3 & 4
iii)
(1994) 2 SCC 70, Union of Territory of Pondicherry & Ors.
vs. P.V. Suresh & Ors. Para 11 & 12
16.
I have heard learned counsel for the parties and given my
thoughtful consideration to the respective submissions and the materials
on record.
17.
The law of contract, is governed by the principle of
autonomy of the parties. In this scenario, the conduct of the parties has
more bearing in interpreting the terms of the contract. This observation is
made in view of the fact that the entire dispute which is to be adjudicated
by this Court is now condensed to the fact, as to whether, there still
WP(C) No. 10 of 2019
subsists a contractual relationship between the petitioner and the
respondents. The case as put up by the petitioner is that Clause 5.1 (a)
provides that “time allowed for execution of work will be counted from
the Date of Start which is to be reckoned from 15 days from the date of
issue of the Letter of Acceptance or the first date of handing over of site
whichever is later”. Relying on this, the petitioner has argued that since
the site was not fully handed over as per the stipulation of Clause 1.5,
under the caption “availability of site” the date of start to reckon 24
months was not fixed, and therefore the contract would be said to be still
subsisting. The other facets as can be seen from the contract is that at
Clause 2(xiii) under the caption “date of commencement of work”
speaks of the date to be reckoned 15 days from the date of issue of LOA
or first date of handing over of site whichever is later. For ready
reference the relevant Clauses of the contract agreement are reproduced
herein below:SECTION 1
1.5 Availability of Site
The complete land for ICP construction site shall be handed over to
contractor in one go at the beginning of the project itself.
SECTION 4
PROFORMA OF SCHEDULES
Schedule ‘F’
2(xiii) Date of commencement of work
15 days from the date of issue
of LOA or the first of handing
over of site whichever is later
5.1 (a) Time allowed for execution
of work
24 months (Twenty Four
Months) from the date of start
Date of Start
18.
15 days from the date of issue
of Letter of Acceptance or the
first date of handing over of
site whichever is later.
On perusal of the conditions of the contract agreement as
reproduced above, the same will go to show that the time allowed for
execution of work was originally 24 months, and that the date of
commencement of work was to be 15 days from the date of issue of
WP(C) No. 10 of 2019
LOA, or the first date of handing over of site whichever is later. The date
of start, would mean the first date of handing over of site whichever is
later. To interpret the above conditions of the agreement, the factual
matrix and the relevant background circumstances, must be seen and
appreciated, in context to the facts to which they pertain to.
Interpretation of such contract agreements should be reasonable, keeping
in mind good sense, that should result in a fair result. In this backdrop,
firstly it is to be noted that it is not disputed that after issuance of LOA
on 30.09.2016, the writ petitioner took over nearly a month and half i.e.
till 18.11.2016 to take over the site. Secondly, the writ petitioner by
letter dated 27.09.2016, had also requested the respondents for
postponement of issuance of LOA as the petitioner was not in a position
to deposit performance guarantee. Thirdly, as the 24 months were close
to being over, extension was requested by the writ petitioner which was
granted by the respondents till 28.05.2019. Lastly, the fact that only
1/10th of the project cost had been accounted for by the petitioner
through the running bills also indicates the progress of the work.
19.
The contract document in this regard should be read as a
whole, taking into consideration the clauses governing the conditions
and stipulations and cannot be read in isolation in order to arrive at a
reasonable and harmonious interpretation. In the instant case, keeping in
mind the objectives of the project and attendant facts, the conduct of the
writ petitioner undoubtedly reflects the laches of the petitioner in
discharging its liability as per the contract agreement. The materials as
placed, also reveal that it cannot be said that the site was not handed over
to prevent the commencement of work, which would not qualify as a
„date of start’. The writ petitioner was not diligent in discharging his
obligations judging by the quantum of work completed and therefore
cannot take the plea that it was prevented in any manner from
commencing the work due to the non handing over of the site.
20.
Another pertinent fact that has also been highlighted by the
respondents is that the date of commencement of work was 15.10.2016
i.e. 15 days after issuance of LOA and that the same had been accepted
by the petitioner to be the date of commencement in view of the fact that
WP(C) No. 10 of 2019
the document dated 17.08.2017 recording the same had been
countersigned by the authorized representative of the writ petitioner
itself.
21.
As discussed above, and taking into account the entire
factual matrix, background circumstances and giving a reasonable
interpretation to the clauses of the agreement, the inescapable conclusion
will necessarily be that the date of commencement of work, as also
acknowledged by the petitioner, is 15.10.2016. The contentions of the
writ petitioner that the contract still subsists cannot therefore be
accepted, more so, in view of the fact that extension had been granted by
the respondents specifically upto 28.05.2019. The petitioner in fact, it
can be said is also precluded from taking this plea, and if really
aggrieved with the fixation of „date of start’
or „date of
commencement of work’ should have raised the same at the time when
request for extension was made and not at this stage. In view of these
findings, the writ petition deserves no further consideration, and the fact
that no contract is subsisting presently, is affirmed. The judgments
placed by learned counsel for the respondents have been considered but
as they are of limited application to the instant case, they have not been
relied upon.
22.
Accordingly, the instant writ petition stands dismissed. The
writ petitioner will be at liberty to take recourse to other remedies as
provided in the contractual agreement.
23.
No order as to costs.
JUDGE
Meghalaya
09.09.2019
“V. Lyndem PS”
WP(C) No. 10 of 2019
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.